Category:PRELIMINARY NOTIFICATION OF EVENT OR OCCURRENCE (PNO
MONTHYEARPNO-I-99-043, on 990916,Hurricane Floyd Was Approaching Ccnpp,Sgs,Hcgs & Ocnpp.Hurricane Was Centered at Latitude 36.0 North & Longitude 76.6 West & Moving north-northeast at Approx 25 Mph.Plants Remain at Power1999-09-16016 September 1999
[Table view]PNO-I-99-043:on 990916,Hurricane Floyd Was Approaching Ccnpp,Sgs,Hcgs & Ocnpp.Hurricane Was Centered at Latitude 36.0 North & Longitude 76.6 West & Moving north-northeast at Approx 25 Mph.Plants Remain at Power PNO-I-99-039, on 990831,Haddam Neck Plant CR Was Notified by Transportation Contractor,Hittman Transportation Svcs,That Driver of Truck,Left Plant Earlier in Day Noticed Water Leakage from from sea-land Container He Was Transporting1999-09-0101 September 1999 PNO-I-99-039:on 990831,Haddam Neck Plant CR Was Notified by Transportation Contractor,Hittman Transportation Svcs,That Driver of Truck,Left Plant Earlier in Day Noticed Water Leakage from from sea-land Container He Was Transporting PNO-I-99-022, on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions1999-05-11011 May 1999 PNO-I-99-022:on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions PNO-I-99-016, on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve1999-04-0707 April 1999 PNO-I-99-016:on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve PNO-I-99-006, on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys1999-01-29029 January 1999 PNO-I-99-006:on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys PNO-I-99-004, on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review1999-01-20020 January 1999 PNO-I-99-004:on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review PNO-I-99-001, on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power1999-01-0404 January 1999 PNO-I-99-001:on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power PNO-I-98-062, on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch1998-12-15015 December 1998 PNO-I-98-062:on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch PNO-I-98-039, 980812,Millstone Unit 3 Was Shutdown to Repair Small Leak on Afws Discharge Noted.Current Leakage Does Not Exceed Regulatory Requirements & Shutdown Not Required by Tech Specs.Licensee Issued Press Release on 9808111998-08-12012 August 1998 PNO-I-98-039:980812,Millstone Unit 3 Was Shutdown to Repair Small Leak on Afws Discharge Noted.Current Leakage Does Not Exceed Regulatory Requirements & Shutdown Not Required by Tech Specs.Licensee Issued Press Release on 980811 PNO-I-98-033, on 980728,licensee Identified Leak of Approximately 1,000 Gallons of Demineralized Water & Chemical Agents Used for Decontamination of Plant Sys.Region I Radiation Specialist Will Be Onsite to Review Licensee1998-07-28028 July 1998 PNO-I-98-033:on 980728,licensee Identified Leak of Approximately 1,000 Gallons of Demineralized Water & Chemical Agents Used for Decontamination of Plant Sys.Region I Radiation Specialist Will Be Onsite to Review Licensee PNO-I-98-026, on 980701,Millstone Unit 3 Criticality Update Made.Nrc Staff Continues to Provide Augmented Insp of Unit 3 Restart Activities,Including round-the-clock Coverage of Key Operational.Licensee Plans No Press Release1998-07-0101 July 1998 PNO-I-98-026:on 980701,Millstone Unit 3 Criticality Update Made.Nrc Staff Continues to Provide Augmented Insp of Unit 3 Restart Activities,Including round-the-clock Coverage of Key Operational.Licensee Plans No Press Release PNO-I-98-025, on 980630,unit 3 Established Reactor Criticality,However Reactor Was Shut Down When Control Room Operator Noticed Spiking Intermediate Range Monitor.Licensee Troubleshooting1998-06-30030 June 1998 PNO-I-98-025:on 980630,unit 3 Established Reactor Criticality,However Reactor Was Shut Down When Control Room Operator Noticed Spiking Intermediate Range Monitor.Licensee Troubleshooting PNO-I-97-073A, on 971210,update of Offsite Surveys for Contaminated Blocks Made.Total of 114 Blocks Out of 3032 Indicated Radioactive Contamination at Greater than Two Times Background Levels.Licensee Plans to Return to Sites1997-12-11011 December 1997 PNO-I-97-073A:on 971210,update of Offsite Surveys for Contaminated Blocks Made.Total of 114 Blocks Out of 3032 Indicated Radioactive Contamination at Greater than Two Times Background Levels.Licensee Plans to Return to Sites PNO-I-97-074, on 971203,licensee Announced Senior Mgt Restructuring,Which Included Naming New Chairman,President, Chief Executive Officer,Chief Financial Officer & Promotion of Director of Site Operations1997-12-0404 December 1997 PNO-I-97-074:on 971203,licensee Announced Senior Mgt Restructuring,Which Included Naming New Chairman,President, Chief Executive Officer,Chief Financial Officer & Promotion of Director of Site Operations PNO-I-97-073, survey Identified Former Cask Wash Down Area Needing Further Characterization & Remediation within Licensee Control Area.Concrete Blocks Used for Temporary Shield Wall Was Used by 15 Households as of 9711301997-12-0101 December 1997 PNO-I-97-073:survey Identified Former Cask Wash Down Area Needing Further Characterization & Remediation within Licensee Control Area.Concrete Blocks Used for Temporary Shield Wall Was Used by 15 Households as of 971130 PNO-I-97-071, on 971124,licensee Announced Some Senior Level Mgt Changes.Ns Carns Resigned as Chief Nuclear Officer of Northeast Nuclear Energy Co,Effective 971201.Press Release Was Issued1997-11-24024 November 1997 PNO-I-97-071:on 971124,licensee Announced Some Senior Level Mgt Changes.Ns Carns Resigned as Chief Nuclear Officer of Northeast Nuclear Energy Co,Effective 971201.Press Release Was Issued PNO-I-97-053, on 970826,special Security Insp Will Be Performed,That Will Examine Security Activities at Vermont Yankee,Pilgrim & Indian Point 3.Team Will Include Security Specialists from Region I & NRR1997-08-22022 August 1997 PNO-I-97-053:on 970826,special Security Insp Will Be Performed,That Will Examine Security Activities at Vermont Yankee,Pilgrim & Indian Point 3.Team Will Include Security Specialists from Region I & NRR PNO-I-97-049, on 970807,inadvertent Actuation of Halon Sys Occurred Affecting CR & Adjacent Central Alarm Station. Personnel Took Photographs of Panel of Halon Actuation Panel,Prior to Actuation.Root Cause of Actuation Evaluated1997-08-0808 August 1997 PNO-I-97-049:on 970807,inadvertent Actuation of Halon Sys Occurred Affecting CR & Adjacent Central Alarm Station. Personnel Took Photographs of Panel of Halon Actuation Panel,Prior to Actuation.Root Cause of Actuation Evaluated PNO-I-97-045, on 970801,electricians Restoring One Set of Main Generator Exciter Brushes,Following Routine Surveillance,When One of Brushes Sparked Excessively & Disintegrated.Electricians Exited Area & Notified CR1997-08-0404 August 1997 PNO-I-97-045:on 970801,electricians Restoring One Set of Main Generator Exciter Brushes,Following Routine Surveillance,When One of Brushes Sparked Excessively & Disintegrated.Electricians Exited Area & Notified CR PNO-I-97-024, on 970422,Oyster Creek Nuclear Generating Station Commenced Controlled Shutdown of Unit Due to Equipment Problems.Unit Expected to Be Shut Down for Six Days for Correction of Diaphram Problem1997-04-23023 April 1997 PNO-I-97-024:on 970422,Oyster Creek Nuclear Generating Station Commenced Controlled Shutdown of Unit Due to Equipment Problems.Unit Expected to Be Shut Down for Six Days for Correction of Diaphram Problem PNO-I-97-022, on 970410,GPU,Inc Announced,Addition to Continued Operation of Oyster Creek & Also Exploring Options of Sale.Util Will Begin Next Wk to Develop Plans to Support Sale of Plant,Decommissioning & Personnel Retention1997-04-10010 April 1997 PNO-I-97-022:on 970410,GPU,Inc Announced,Addition to Continued Operation of Oyster Creek & Also Exploring Options of Sale.Util Will Begin Next Wk to Develop Plans to Support Sale of Plant,Decommissioning & Personnel Retention PNO-I-97-014, on 970227,retrieval of Contaminated Matl at Vendor Facility Made.Licensee Dispatched Survey Team, Consisting of HP Supervisor,Hp Technician & Radioactive Matl Handler to Vendor Facility to Survey & Retrieve Matl1997-02-28028 February 1997 PNO-I-97-014:on 970227,retrieval of Contaminated Matl at Vendor Facility Made.Licensee Dispatched Survey Team, Consisting of HP Supervisor,Hp Technician & Radioactive Matl Handler to Vendor Facility to Survey & Retrieve Matl PNO-I-96-085, on 961204,board of Directors of Connecticut Yankee Atomic Power Co Voted to Retire Haddam Neck Nuclear Power Generating Station,After Nearly 29 Yrs of Svc.Nrc Responding to Media Inquires & Present at Press Conference1996-12-0505 December 1996 PNO-I-96-085:on 961204,board of Directors of Connecticut Yankee Atomic Power Co Voted to Retire Haddam Neck Nuclear Power Generating Station,After Nearly 29 Yrs of Svc.Nrc Responding to Media Inquires & Present at Press Conference PNO-I-96-080, on 961102,two Radiation Workers Entered Reactor Cavity & Fuel Transfer Canal Area to Inspect & Collect Debris in Preparation for Flooding Cavity to Accomplish Defueling Operation Causing Airborne Contamination1996-11-0808 November 1996 PNO-I-96-080:on 961102,two Radiation Workers Entered Reactor Cavity & Fuel Transfer Canal Area to Inspect & Collect Debris in Preparation for Flooding Cavity to Accomplish Defueling Operation Causing Airborne Contamination PNO-I-96-078, on 961025,licensee Manually Scrammed Reactor Due to Turbine Runback,Resulted from Problem in Stator Cooling Sys.Resident Will Continue to Follow Event1996-10-29029 October 1996 PNO-I-96-078:on 961025,licensee Manually Scrammed Reactor Due to Turbine Runback,Resulted from Problem in Stator Cooling Sys.Resident Will Continue to Follow Event PNO-I-94-005, ;on 940113,util Declared & Terminated Unusual Event Due to TS Required Shutdown Due to Three Rods Being Declared Inoperable Based on Position Indication.Senior Resident Inspector,State of CT & Media Advised of Event1994-01-13013 January 1994 PNO-I-94-005;on 940113,util Declared & Terminated Unusual Event Due to TS Required Shutdown Due to Three Rods Being Declared Inoperable Based on Position Indication.Senior Resident Inspector,State of CT & Media Advised of Event PNO-I-93-075, on 931228,personnel at Plant Observed Smoke Emanating from Area Between Remaining Lower Portion of Reactor Vessel & Biological Shield at About 78' Elevation1993-12-29029 December 1993 PNO-I-93-075:on 931228,personnel at Plant Observed Smoke Emanating from Area Between Remaining Lower Portion of Reactor Vessel & Biological Shield at About 78' Elevation PNO-I-93-054, on 930925,initial Shipment of Shoreham Slightly Irradiated Fuel to Limerick Nuclear Generating Station Begun.Shipment Found to Be in Compliance W/Applicable NRC & DOT Regulations1993-09-27027 September 1993 PNO-I-93-054:on 930925,initial Shipment of Shoreham Slightly Irradiated Fuel to Limerick Nuclear Generating Station Begun.Shipment Found to Be in Compliance W/Applicable NRC & DOT Regulations PNO-I-93-053, on 930922,State of Nj Will Make Public Intent to Request Restraining Order Prohibiting Util from Shipping Irradiated Fuel from Plant to Limerick Station.State Arguments Will Address Environmental Issues1993-09-21021 September 1993 PNO-I-93-053:on 930922,State of Nj Will Make Public Intent to Request Restraining Order Prohibiting Util from Shipping Irradiated Fuel from Plant to Limerick Station.State Arguments Will Address Environmental Issues ML20059K9751993-06-29029 June 1993 PNO-1-93-033:on 930622,26 & 27,util Declared Ue as Result of Problems During Electrical Sys Testing.Caused by Loss of Offsite Power Event During Performance of TS a Train Partial Loss of Power Surveillance Testing PNO-I-93-006, on 930125,licensee Notified NRC That Reactor Vessel Core Temp Exceeded 212 Degrees F During Shutdown Cooling Operations.No Core Damage or Radioactive Release Occurred.Inspectors Reviewing Event.State of Nj Notified1993-01-26026 January 1993 PNO-I-93-006:on 930125,licensee Notified NRC That Reactor Vessel Core Temp Exceeded 212 Degrees F During Shutdown Cooling Operations.No Core Damage or Radioactive Release Occurred.Inspectors Reviewing Event.State of Nj Notified PNO-I-90-094, on 901016,transfer of Fuel Assemblies Stuck in Upper Core Internals.No Apparent Damage to Dropped Fuel Assembly Occurred.Recovery Operations Secured1990-10-17017 October 1990 PNO-I-90-094:on 901016,transfer of Fuel Assemblies Stuck in Upper Core Internals.No Apparent Damage to Dropped Fuel Assembly Occurred.Recovery Operations Secured PNO-I-90-077, on 900906,unplanned Shutdown Greater than 48 H Occurred Due to RCS Packing Leak from Pressurizer Spray Valve.Plant Placed in Hot & Cold Shutdown.Licensee Activities Monitored & State of Ny Informed1990-09-0707 September 1990 PNO-I-90-077:on 900906,unplanned Shutdown Greater than 48 H Occurred Due to RCS Packing Leak from Pressurizer Spray Valve.Plant Placed in Hot & Cold Shutdown.Licensee Activities Monitored & State of Ny Informed PNO-I-90-065, on 900814,licensee Reported That Licensed Reactor Operator Tested Positive for Marijuana as Result of Random Fitness for Duty Test.Operator Unescorted Site Access Suspended for 14 Days1990-08-15015 August 1990 PNO-I-90-065:on 900814,licensee Reported That Licensed Reactor Operator Tested Positive for Marijuana as Result of Random Fitness for Duty Test.Operator Unescorted Site Access Suspended for 14 Days PNO-I-90-063, on 900809,plant Shutdown Due to Potential Loss of Three Emergency Diesel Generators.Caused by Blown Control Power Fuse.Fuse Replaced1990-08-0909 August 1990 PNO-I-90-063:on 900809,plant Shutdown Due to Potential Loss of Three Emergency Diesel Generators.Caused by Blown Control Power Fuse.Fuse Replaced PNO-I-90-062, on 900806,containment Unidentified Leak Rate Exceeded Tech Spec Limit.Caused by Water Introduction Into Drywell.Licensee Began Plant Shutdown,Vented Drywell & Evaluated Plant Conditions1990-08-0707 August 1990 PNO-I-90-062:on 900806,containment Unidentified Leak Rate Exceeded Tech Spec Limit.Caused by Water Introduction Into Drywell.Licensee Began Plant Shutdown,Vented Drywell & Evaluated Plant Conditions PNO-I-90-041A, on 900509,75 Gallons of Contaminated Water Spilled Out of TN-RAM Cask & Into Trench.Cask Should Contain No free-standing Liquid.Cask Placed in Secured Parking Area within Burial Site.State of CT Notified1990-04-10010 April 1990 PNO-I-90-041A:on 900509,75 Gallons of Contaminated Water Spilled Out of TN-RAM Cask & Into Trench.Cask Should Contain No free-standing Liquid.Cask Placed in Secured Parking Area within Burial Site.State of CT Notified PNO-I-89-080, on 890922,NRC Presented Preliminary Results of Requalification Exams Indicating Failure of Two Crews. Licensee Preparing Justification for Continued Operation for Region I Mgt Review1989-09-22022 September 1989 PNO-I-89-080:on 890922,NRC Presented Preliminary Results of Requalification Exams Indicating Failure of Two Crews. Licensee Preparing Justification for Continued Operation for Region I Mgt Review PNO-II-89-066A, updates Status of Hurricane Hugo for Nuclear Facilities in Southeast.Manning of Incident Response Ctr by Region II Continuing1989-09-21021 September 1989 PNO-II-89-066A:updates Status of Hurricane Hugo for Nuclear Facilities in Southeast.Manning of Incident Response Ctr by Region II Continuing PNO-II-89-066, licensees Prepared for Adverse Weather Conditions Due to Hurricane.Briefings Held W/Key Managers on Responsibilities to Check All Trailers,Secure Crane Hooks & Increase Emergency Food Supplies1989-09-21021 September 1989 PNO-II-89-066:licensees Prepared for Adverse Weather Conditions Due to Hurricane.Briefings Held W/Key Managers on Responsibilities to Check All Trailers,Secure Crane Hooks & Increase Emergency Food Supplies PNO-I-89-079, on 890911,unplanned Reactor Shutdown for Greater than 48 H Due to Problems W/Emergency Diesel Generator.Drywell Entered,Leaking Feedwater Check Valve Repaired & Minor Maint Performed1989-09-12012 September 1989 PNO-I-89-079:on 890911,unplanned Reactor Shutdown for Greater than 48 H Due to Problems W/Emergency Diesel Generator.Drywell Entered,Leaking Feedwater Check Valve Repaired & Minor Maint Performed ML20247N0071989-09-11011 September 1989 PNS-I-89-015:revised Notification of Telephone Threat, Correcting Event Date from 890909 to 890911.Call, Originating from Limerick or Peach Bottom,Received at Corporate Ofc.On 890525,threat Received at Peach Bottom PNO-I-89-078, notifies of Potential Strike by Svcs Personnel on Weekend of 890909-10.Personnel from Bargaining Unit Will Assist Util Staff in Certain Maint & Const Activities & Util Developed Contingency Plan1989-09-0808 September 1989 PNO-I-89-078:notifies of Potential Strike by Svcs Personnel on Weekend of 890909-10.Personnel from Bargaining Unit Will Assist Util Staff in Certain Maint & Const Activities & Util Developed Contingency Plan PNO-I-89-076, on 890906,contaminated Equipment Located in Unrestricted Areas.Equipment Included Hydrolaze Unit & Tools.Licensee Initiated Survey as Result of Ongoing Internal Assessment1989-09-0707 September 1989 PNO-I-89-076:on 890906,contaminated Equipment Located in Unrestricted Areas.Equipment Included Hydrolaze Unit & Tools.Licensee Initiated Survey as Result of Ongoing Internal Assessment PNO-V-89-047, on 890808,earthquake & Aftershock of 5.1 & 4.2 Magnitudes,Respectively,Occurred Approx 15 Miles Southwest of San Jose,Ca.Reactors Shutdown During Earthquake.Tour of GE Reactor Disclosed No Damage1989-08-0808 August 1989 PNO-V-89-047:on 890808,earthquake & Aftershock of 5.1 & 4.2 Magnitudes,Respectively,Occurred Approx 15 Miles Southwest of San Jose,Ca.Reactors Shutdown During Earthquake.Tour of GE Reactor Disclosed No Damage PNO-I-89-063, on 890721,NRC Team Insp of Allegations Re Facility Completed.Insp Dealt W/Approx 120 Concerns from Three Allegers.Preliminary Results Indicate 44 Allegations Unsubstantiated & 19 Not within Charter of Insp Team1989-07-26026 July 1989 PNO-I-89-063:on 890721,NRC Team Insp of Allegations Re Facility Completed.Insp Dealt W/Approx 120 Concerns from Three Allegers.Preliminary Results Indicate 44 Allegations Unsubstantiated & 19 Not within Charter of Insp Team PNO-I-89-058, on 890713,licensee Commenced Defueling of Facility.Defueling Scheduled to Be Completed in Approx 3 Wks.Following Completion of Core Offload,Reactor Vessel Will Be Reassembled & Normal Water Level Restored1989-07-14014 July 1989 PNO-I-89-058:on 890713,licensee Commenced Defueling of Facility.Defueling Scheduled to Be Completed in Approx 3 Wks.Following Completion of Core Offload,Reactor Vessel Will Be Reassembled & Normal Water Level Restored PNO-I-89-057, on 890711,plant Scram & Generator/Turbine Trip Caused by Fault in One Operable Main Transformer.Other Main Transformer Failed on 890625.Licensee Has One Replacement Transformer Onsite & Expects Installation by 8907141989-07-12012 July 1989 PNO-I-89-057:on 890711,plant Scram & Generator/Turbine Trip Caused by Fault in One Operable Main Transformer.Other Main Transformer Failed on 890625.Licensee Has One Replacement Transformer Onsite & Expects Installation by 890714 PNO-IV-89-045, on 890703,earthquake Near Tremonton,Ut Occurred.Earthquake Safety Interlocks Did Not Trip & No Damage Occurred1989-07-0505 July 1989 PNO-IV-89-045:on 890703,earthquake Near Tremonton,Ut Occurred.Earthquake Safety Interlocks Did Not Trip & No Damage Occurred PNO-I-89-053, on 890628,about 95% of Lilco Shareholders Voted to Approve Settlement Agreement Which Will Transfer Shoreham to Long Island Power Authority for Decommissioning1989-06-29029 June 1989 PNO-I-89-053:on 890628,about 95% of Lilco Shareholders Voted to Approve Settlement Agreement Which Will Transfer Shoreham to Long Island Power Authority for Decommissioning 1999-09-16 Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS MONTHYEARPNO-I-99-043, on 990916,Hurricane Floyd Was Approaching Ccnpp,Sgs,Hcgs & Ocnpp.Hurricane Was Centered at Latitude 36.0 North & Longitude 76.6 West & Moving north-northeast at Approx 25 Mph.Plants Remain at Power1999-09-16016 September 1999
[Table view]PNO-I-99-043:on 990916,Hurricane Floyd Was Approaching Ccnpp,Sgs,Hcgs & Ocnpp.Hurricane Was Centered at Latitude 36.0 North & Longitude 76.6 West & Moving north-northeast at Approx 25 Mph.Plants Remain at Power IR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support PNO-I-99-039, on 990831,Haddam Neck Plant CR Was Notified by Transportation Contractor,Hittman Transportation Svcs,That Driver of Truck,Left Plant Earlier in Day Noticed Water Leakage from from sea-land Container He Was Transporting1999-09-0101 September 1999 PNO-I-99-039:on 990831,Haddam Neck Plant CR Was Notified by Transportation Contractor,Hittman Transportation Svcs,That Driver of Truck,Left Plant Earlier in Day Noticed Water Leakage from from sea-land Container He Was Transporting IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000213/19990021999-08-20020 August 1999 Insp Rept 50-213/99-02 on 990420-0719.No Violations Noted. Major Areas Inspected:Decommissioning Operations & Sf Safety Maint & Surveillance,Plant Support & Rediological Controls IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20207F1521999-05-25025 May 1999 Notice of Violation from Investigation Rept 1-94-021 on 940506-960329.Violation Noted:Between 740831-910407,licensee Made Changes to Facility Described in Safety Analysis Rept for Refueling Core Offloads Without Performing Evaluation ML20196K2621999-05-24024 May 1999 EN-99-020:on 980525,notice of Violation & Exercise of Enforcement Discretion Will Be Issued to Licensee.Action Based on Severity Level III Problem Consisting of Four Individual Violations Involving Refueling Outage IR 05000213/19990011999-05-21021 May 1999 Insp Rept 50-213/99-01 on 980119-990419.No Violations Noted. Major Areas Inspected:Aspects of Licensee Activities in Preparation for Dismantlement & Decommissioning of Facility ML20206R7141999-05-12012 May 1999 Notice of Violation from Investigation on 970314-0722. Violation Noted:M Thomas Engaged in Deliberate Misconduct on 970227,that But for Detection,Would Have Caused Licensee to Be in Violation of 10CFR20.1802 ML20206R7391999-05-12012 May 1999 Notice of Violation from Investigation on 970616-0718. Violations Noted:On 961209 & 10,J Foley Deliberately Caused Util to Be in Violation of 10CFR50.9 & TS 6.11 & in June 1997 Provided Inaccurate Info to NRC Inspector PNO-I-99-022, on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions1999-05-11011 May 1999 PNO-I-99-022:on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours PNO-I-99-016, on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve1999-04-0707 April 1999 PNO-I-99-016:on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve ML20205M7201999-04-0606 April 1999 Notice of Violation from NRC OI Case 1-96-002 & Conclusions of Millstone Independent Review Team.Violation Noted. E Debarba,Deliberately Discriminated Against Supervisor in Performance Engineering Group at Millstone Station ML20205M7351999-04-0606 April 1999 Notice of Violation from Investigation in Case Numbers 1-96-002 & 1-97-007.Violation Noted:Licensee Discriminated Against Supervisor in Performance Engineering Group at Plant Due to Involvement in Protected Activities ML20205J8031999-04-0505 April 1999 Notice of Violation from Insp on 961102-27.Violation Noted:Licensee Failed to Adequately Instruct Workers & Failed to Perform Adequate Radiological Surveys in Reactor Cavity & Fuel Transfer Cavity IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems ML20206B3801999-03-29029 March 1999 EN-99-015:informs Commission That Staff Intends to Exercise Discretion Pursuant to Section VII.B.6 of Enforcement Policy & Not Propose Civil Penalty for Severity Level III Problem That Occurred in Nov 1996,prior to Licensee Decision ML20205J0941999-03-12012 March 1999 Rept of Review of Millstone Units 1,2 & 3:Allegations of Discrimination in NRC Ofc of Investigations Cases 1-96-002, 1-96-007,1-97-007 & Associated Lessons Learned ML20207M1131999-03-0909 March 1999 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:Employment of Two Contractor Employees Terminated in Aug 1997,in Part Because Individuals Raised Concerns Re MOV Program Manual IR 05000003/19980191999-03-0909 March 1999 Insp Rept 50-003/98-19 on 981130-990222.No Violation Noted. Major Areas Inspected:Review of Facility Mgt & Control ML20205G6161999-03-0909 March 1999 EN-99-010:on 990309,notice of Proposed Imposition of Civil Penalty in Amount of $88,000 Issued to Licensee.Action Based Upon Severity Level II Problem Involving Discrimination Against Two Contractor Employees at Millstone MOV Dept IR 05000219/19980121999-03-0404 March 1999 Insp Rept 50-219/98-12 During Periods 981214-18,990106-07 & 20-22.No Violations Identified.Major Areas Inspected: Review of Licensee self-assessment of Plant Environ Qualification Program & Corrective Actions for Open Items IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20207B7041999-02-26026 February 1999 Notice of Violation from Insp on 981103-990118.Violations Noted:Two Different Locked High Radiation Area Doors in Containment Builiding Found Unlocked & Unattended IR 05000213/19980061999-02-26026 February 1999 Insp Rept 50-213/98-06 on 981103-990118.Violations Noted. Major Areas Inspected:Aspects of Licensee Activities in Preparation for Dismantlement & Decommissioning of Facility. Security Program Was Also Inspected PNO-I-99-006, on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys1999-01-29029 January 1999 PNO-I-99-006:on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ PNO-I-99-004, on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review1999-01-20020 January 1999 PNO-I-99-004:on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20199C6381999-01-0707 January 1999 Notice of Violation from Insp on 981006-1123.Violation Noted:On or Before 981120,conduit 9-15,in Fire Area A-24,not Sealed & Tested in Accordance with Astme E-119,fire Endurance Test PNO-I-99-001, on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power1999-01-0404 January 1999 PNO-I-99-001:on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power IR 05000213/19980051998-12-21021 December 1998 Insp Rept 50-213/98-05 on 980720-1102.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support PNO-I-98-062, on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch1998-12-15015 December 1998 PNO-I-98-062:on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch IR 05000219/19980091998-11-25025 November 1998 Insp Rept 50-219/98-09 on 980914-1025.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20196C6071998-11-25025 November 1998 Notice of Violation from Insp on 980914-1025.Violation Noted:On 981014,security Force Vehicle Escort Left Non licensee-designated Vehicle Unattended in Protected Area & Failed to Ensure That Vehicle Ignition Locked & Key Removed IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20195H6901998-11-18018 November 1998 Notice of Violation from Insp on 980818-1005.Violation Noted:Engineering Evaluations Not Performed When RCS Heatup Rate Limit Exceeded on 951217 & When RCS Cooldown Rate Limit Exceeded on Three occasions,940424,0728 & 951215 IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan ML20155F8511998-10-29029 October 1998 Insp Rept 50-213/98-04 on 980720-0911.Violations Noted. Major Areas Inspected:Aspects of Licensee Preparations, Planning & Implementation of RCS Chemical Decontamination, Operations,Engineering,Maint & Plant Support IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys ML20155B1521998-10-23023 October 1998 Notice of Violation from Insp on 980810-0903.Violation Noted:Design Basis,As Described in FSAR Chapter 14,Accident Analyses Had Not Been Correctly Translated Into Plant Procedures & Acceptance Criteria IR 05000219/19980081998-10-20020 October 1998 Insp Rept 50-219/98-08 on 980727-0913.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ 1999-09-16 |
-. . _ . . . . .
DCS No:
Date: September 27, 1985 PREllMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE--PNO-I-85-71
.This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. The information is as initially received without verification or evaluation, and is basically all that is known by the Region I staff on this date.
Facility: Various Region I Plants Licensee Emergency Classification:
Notification of Unusual Event Alert Site Area Emergency General Emergency Not Applicable X NONE
Subject:
. ACTIONS IN RESPONSE TO HURRICA.NE GLORIA As of 10:00 a.m. today, Gloria was located about 50 miles east of Cape May, New Jersey and moving in a northerly direction at a speed of 30 miles per hour. Reactor facili-ties located along the coast have been implementing procedures in accordance with their emergency ' pl an s . A consolidated status report for potentially affected Region I
' facilities has been provided to the HQ IRC and is being periodically updated.
The 0yster Creek facility has reduced power levels (to 35%) commensurate with their plan and the hurricane is expected to move past the plant within the next two hours (i.e. by noon). The Indian Point and Shoreham units are shutdown. Millstone Units 1 and 2, and Haddam Neck are shutting down. Unusual event declarations have been made at
-these and several other plants further inland. Emergency response facilities have been
. staffed.
Region I has been tracking the progress of the hurricane and the status of the plants
-on a-con _tinuing basis by continuous manning of the regional IRC and 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> coverage at'the sites. Extensive communications with State governments continues and the consolidated status report is being shared with emergency response officials.
This-information is current as of 10:00 a.m.
CONTACT: 'R. Starost'ecki
.488-1229 DISTRIBUTION:
H. St. MNBB Phillips E/W Willste Mail: ADM:DMB Chairman Palladino EDO NRR IE NMSS DOT:Trans only-Comm. Zech- PA OIA RES Comm. Bernthal ELD AE00 'i Comm. Roberts.
Comm. Asselstine-lACRS Air Rights' INPO----
SECY SP NSAC----
CA f POR Regional Offices TMI Resident Section p RI Resident Office l
8509300364 850927 Licensee:
h-I -071 PDR (Reactor Licensees)
Region I' Form 83 .
'(Rev. ' July,1984)
I
[D M ,I l