PN-75-110:on 751016,unplanned Shutdown Instituted,Due to Electrical Fault in Main Generator.Short Found in C Phase, Apparently Caused by Metal Cylinder Found Lodged in Windings.Duration of Shutdown Not Yet Established
ML20236V105
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 10/20/1975
From: Bidinger G, Jennifer Davis, Thornburg H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To:
References
PN-75-110, NUDOCS 9807310304
Download: ML20236V105 (1)


Text

P _o r. d du C /

PRELIMINARY NOTIFICATION - NOT FOR PUBLIC DISCLOSURE f^G October 20, 1975 PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE --PN-75-110 i

.+ This preliminary notification constitutes EARLY notice of events of )

POSSIBLE safety or public interest significance. The information l presented is as initially received without verification or evaluation )

and is basically all that is known by OIE staff as of 10:15 a.m. on the I dat'e of this notification. IT SHOULD BE SPECIFICALLY NOTED THAT THIS NOTIFICATION MAY CONTAIN INFORMATION TIAT.LATER MAY BE DETERMINED TO BE INACCURATE OR INCONSISTENT. AN OFFICE OF INSPECTION AND ENFORCEMENT ,

~ NOTIFICATION OF AN INCIDENT OR OCCURRENCE (BLUE SHEET) SUBSEQUENTLY WILL BE ISSUED IF WARRANTED.

. . a. - .. .. ,

Facility: Indian Point 2 (DN 50-247)

Consolidated Edison Company of New York, Inc.

Subject:

UNSCHEDULED SHUTDOWN An unplanned shutdown was instituted at 1:15 p.m., October 16, 1975, due to an electrical fault in the main generator. A short was found in the C phase, apparently caused by a metal cylinder found lodged in the wind-  !

ings. The source of the cylinder is unknown. ,

u=-= l

~ Duration of the shutdown is not yet established. It will be a minimum of l one week for correction of this problem. Stator rework, which could j

-"= take an additional four to five weeks, is being considered. ,

'- i j Media interest is expected because of close attention paid to nuclear '

facility availability. The State of New York has been and is being kept informed. A press release is planned by the licensee.

OIE received notification of this occurrence by telephone from Mr. Makepiece, Director of Technical Engineering, at 9:00 a.m., October 20, 1975.

Contact:

GHBidinger, IE x7261 HDThornburg, IE x7358 JGDavis, IE x7541 Distribution:

, Chairman Anders Commissioner Mason S. J. Chilk, SECY l

Commissioner Gilinsky Commissioner Rowden G. F. Murphy, JCAE Commissioner Kennedy C. C. Kammerer, CA

- {

D. F. Knuth, IE J. A. Harris, PA I L. V. Gossick, EDO T. J. McTiernan, AIA l B. C. R,u. sche, NRR ,, J. La Fleur, ISP K. R. " Chapman, NMSS H. K. Shapar, ELD ..

Transmitted: P Bldg ,2 4 ; E St1 ,/  ; MNBB 3  ; Luge , [

PRELIMINARY NOTIFICATION - NOT FOR PUBLIC DISCLOSURE

- Oi V N= <y 9807310304 751020 mE 9 PDR I&E V' 4

PN-75-110 PDR

__ . _ . _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ . . . . . . . . . . . . . _ _ . . . . . . - . . . . . . . . . . . . . . I