IR 05000482/2024014
| ML24341A034 | |
| Person / Time | |
|---|---|
| Site: | Wolf Creek |
| Issue date: | 12/17/2024 |
| From: | Vincent Gaddy NRC/RGN-IV/DORS/EB1 |
| To: | Reasoner C Wolf Creek |
| References | |
| IR 2024014 | |
| Download: ML24341A034 (18) | |
Text
December 17, 2024
SUBJECT:
WOLF CREEK GENERATING STATION - COMPREHENSIVE ENGINEERING TEAM INSPECTION REPORT 05000482/2024014
Dear Cleve Reasoner:
On November 13, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Wolf Creek Generating Station and discussed the results of this inspection with Jamie McCoy, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.
One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements and was determined to be Severity Level IV. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:
Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Wolf Creek Generating Station.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Wolf Creek Generating Station. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Vincent G. Gaddy, Chief Engineering Branch 1 Division of Operating Reactor Safety Docket No. 05000482 License No. NPF-42
Enclosure:
As stated
Inspection Report
Docket Number:
05000482
License Number:
Report Number:
Enterprise Identifier:
I-2024-014-0002
Licensee:
Wolf Creek Nuclear Operating Corp.
Facility:
Wolf Creek Generating Station
Location:
Burlington, KS
Inspection Dates:
October 21, 2024, to November 13, 2024
Inspectors:
C. Baron, Contractor
D. Bryen, Reactor Inspector
W. Cullum, Senior Reactor Inspector
S. Graves, Senior Reactor Inspector
R. Kumana, Senior Reactor Inspector
D. Reinert, Senior Reactor Analyst
F. Thomas, Reactor Inspector
Approved By:
Vincent G. Gaddy, Chief
Engineering Branch 1
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a comprehensive engineering team inspection at Wolf Creek Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
Failure to Perform an Evaluation Pursuant to 10 CFR 50.59 for Adding Operator Actions to Mitigate a Chemical Volume and Control System (CVCS) Rupture Cornerstone Significance/Severity Cross-Cutting Aspect Report Section Mitigating Systems Green Severity Level IV NCV 05000482/2024014-01 Open/Closed
[H.4] -
Teamwork 71111.21M The inspectors identified a Green finding of 10 CFR 50, Appendix B, Criterion III, Design Control when the licensee added additional equipment, which was not previously relied upon, to mitigate a Chemical Volume and Control System (CVCS) rupture in the Auxiliary Building, and an associated Severity Level IV Non-cited Violation (NCV) of 10 CFR 50.59, Changes,
Tests, and Experiments, when the licensee did not perform a written evaluation which provides the bases for the determination that the change, test, or experiment does not require a license amendment pursuant to paragraph 50.59(c)(2).
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
===71111.21M - Comprehensive Engineering Team Inspection The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:
Structures, Systems, and Components (SSCs) (IP section 03.01)===
- (1) NK44, 125VDC Panel DP-NK44
- Updated Safety Analysis Report (USAR), technical specifications (TS), and TS bases document
- Visual inspection of bus for as-built configuration and material condition
- Environmental conditions
- Short circuit and equipment protection
- Load voltage
- Component maintenance history
- System Health Report
- (2) EEJ01A, Residual Heat Removal Heat Exchanger 1A
- Residual heat removal system piping and instrumentation diagram
- Vendor manual for installation, operation, and maintenance of the heat exchanger
- System operating procedures
- Corrective action program documents
- Visual inspection of the as-built configuration and material condition
- (3) EJFCV0618, Residual Heat Removal Heat Exchanger Bypass Valve 618
- Calculations for required thrust, actuator capability, and available margin
- Valve and actuator vendor manuals for installation, operation, and
- maintenance
- Inservice and diagnostic testing records including procedures and results for position
- Indication and stroke time testing
- Maintenance work order history records of visual inspections, lubrications, and elastomer replacement
- Corrective action program documents
- Visual inspection of the as-built configuration and material condition (4)480V Bus NG01/Transformer XNG01
- Updated final safety analysis report, technical specifications, and technical specifications bases document.
- Electrical drawings
- Component maintenance history and corrective action program documents
- Procedures for transformer inspection, maintenance, and testing
- Voltage analysis and short circuit calculations
- Visual inspection of switchgear for as-built configuration and material condition
- Environmental conditions for equipment
- System health report
- Vendor manual and plant design drawings
- (5) EFHV0051, Train A Component Cooling Water Heat Exchanger Essential Service Water Inlet Valve
- Piping and instrumentation drawings
- Vendor documentation
- Calculations for torque and thrust
- Visual inspection of the component
- Corrective actions related to the component
- Preventative maintenance history
- System operating procedures and emergency operation
- (6) SGL10A, Residual Heat Removal Room Cooler
- Piping and instrumentation drawings
- Room heat load calculations
- Tube plugging limit calculation
- Vendor documentation
- Visual inspection of the component
- Corrective actions related to the component
- Preventative maintenance history
- (7) Essential Service Water Train B HVAC Fan CGD01B
- Design requirements within purchase specifications
- Functionality tests of the essential service water pumphouse ventilation system
- Room heat load calculations
- Component maintenance history and corrective action program reports
- Essential service water pumphouse ventilation system piping and instrumentation diagram
- Vendor manual for installation, operation, and maintenance of the essential service water pumphouse ventilation fans
- Visual inspection of the as-built configuration and material condition
- (8) NK13, 125VDC Battery
- Updated Safety Analysis Report (USAR), technical specifications (TS), and TS bases document
- Visual inspection of battery cells, support structure, conductors, and material condition
- Environmental conditions
- Maintenance and testing history
- Cell temperature calculation
- System Health Report
- Evaluation of Operator Actions to Locally Align Swing Charger (OPA-NK025)
- (9) AFW Motor-Driven Pump, PAL01B
- Pump Head and Flow Requirements
- NPSH Requirements
- Minimum Recirculation Flow Requirements
- Basis for Inservice Testing Acceptance Criteria
- Evaluation of Recent Inservice Testing Results
- Evaluation of Limiting Runout Flow Conditions
- Evaluation of Operator Actions to Terminate Flow to Faulted Steam Generator (OPA-SLB)
- Testing Requirements for Manual Valves Credited with Isolating Flow
- Evaluation of Seismic Hazards in AF Pump Room
- (10) Condensate Storage Tank, TAP01
- Evaluation of Tanks Capacity Requirements
- Evaluation of Protection of Tank from External Hazards
- Evaluation of Freeze Protection of Tank and Associated Piping
- Evaluation of Level Setpoints for Automatic Transfer of AF Pumps and Alarms
- Evaluation of Tank Floating Barrier and Associated Vents
Modifications (IP section 03.02) (5 Samples)
- (1) Change Package 20007, 7300 Controls Upgrade - Protection Set
- (2) Change Package 20500, Component Cooling Water Heat Exchanger EEG01A Pitting Repair
- (3) Change Package 20394, Emergency Diesel Generator Jacket Water Bleeder Vent Valves
- (4) Change Package 14726, AKR-30 Battery Charger Supply Breaker Setting Changes
- (5) Change Package 20082, Replace Check Valves ALV0030 and ALV0042 with New Design 10 CFR 50.59 Evaluations/Screening (IP section 03.03) (20 Samples)
- (1) GS-M-005, Aluminum in Containment
- (2) GS-M-006, Zinc in Containment
- (3) CP 20734, Replacement of Post Accident PR/SR Recorder with Yokogawa
- (4) AN-07-009, GOTHIC Model for Component Cooling Water Pump Room Temperature
- (5) GK-M-014, Cooling and Heating Load Calculation Control Building Class 1E Electrical Equipment Areas During Accident Conditions - Train A
- (6) SYS-EP-200, Safety Injection Accumulator Operation
- (7) YY-49, High Energy Line Break in the Auxiliary Building (8)
===020663, Main Feedwater Regulating Valve Body to Bonnet Stud Repair (9)020616, BBPV8702B Motor rotor change - magnesium to aluminum (10)020631, System Descriptions M-10B and M-10EN Update
- (11) STS KJ-005B, Manual/Auto Start Sync & Loading of EDG NE02 (12)020535.11.01-C-035, Essential Service Water System Train B Room Coolers - Auxiliary Building (P-287 Parts 2 - 6)
(13)020292, Substation Transformers No. 8,9,10 & 11 and Breakers Replacement R25 (14)020538, PFSSD Modification to Address IN 92-18 for Multiple 'A' Train MOVS-Refuel (15)020551, Cyber Security Equipment Upgrade (16)020671, Containment WI-FI Upgrade
- (18) AL-16-W, Determine the Available NPSH for the Auxiliary Feedwater Pumps, with Dissolved Nitrogen in the Condensate Storage Tank
- (20) EMG E-0 REV. 48, EMG Procedure Revision Screen Operating Experience Samples (IP section 03.04)===
- (1) CR 10017549, IRIS Event 475377 Callaway Emergency Exhaust Fan
- (2) CR 10015425, Part 21 on NPS Part Number 16-AAT907B, 48 VDC Power Supplies
- (3) CR 10020756, RCP ESBU-TB-91-04 Revision in M-712-00202
INSPECTION RESULTS
Failure to Perform an Evaluation Pursuant to 10 CFR 50.59 for Adding Operator Actions to Mitigate a Chemical Volume and Control System (CVCS) Rupture Cornerstone Significance/Severity Cross-Cutting Aspect Report Section Mitigating Systems Green Severity Level IV NCV 05000482/2024014-01 Open/Closed
[H.4] -
Teamwork 71111.21M The inspectors identified a Green finding of 10 CFR 50, Appendix B, Criterion III, Design Control when the licensee added additional equipment, which was not previously relied upon, to mitigate a Chemical Volume and Control System (CVCS) rupture in the Auxiliary Building, and an associated Severity Level IV Non-cited Violation (NCV) of 10 CFR 50.59, Changes, Tests, and Experiments, when the licensee did not perform a written evaluation which provides the bases for the determination that the change, test, or experiment does not require a license amendment pursuant to paragraph 50.59(c)(2).
Description:
The inspectors reviewed a change to calculation YY-49, High Energy Line Breaks in the Auxiliary Building, and the associated 10CFR50.59 screening. The calculation change resulted in a reduction in time for time-critical operator actions that were already in place to isolate the rupture, and an addition of new time-sensitive operator actions required to mitigate a rupture in the Chemical Volume and Control System (CVCS) in the Auxiliary Building. The new operator actions were associated with initiating the Emergency Exhaust System (EES) within one hour to improve the atmospheric conditions in the Auxiliary Building.
Procedure AI 21-016, Operator Time Critical Actions Validation, which included the reduction in time to isolate the CVCS rupture and the new time sensitive actions to initiate EES, was released prematurely on 3/15/2022 before the change to calculation YY-49 was issued. The 50.59 screening for the change to calculation YY-49 was performed on 6/1/2022.
Since the procedure change to AI 21-016 was already issued which established the new operator actions, the plant staff performing the 50.59 review did not realize that new operator actions were being established since they already appeared in the procedure. As a result, the 50.59 review incorrectly established that the change to calculation YY-49 screened out and a 50.59 evaluation was not performed.
Corrective Actions: The licensee entered the issue into the corrective action program.
Corrective Action References: CR 10037557
Performance Assessment:
Performance Deficiency: The licensee failed to establish measures that assure the design basis is correctly translated in specifications, drawings, and procedures as required by 10 CFR 50, Appendix B, Criterion III, Design Control. Specifically, the licensee issued a procedure change notice prior to a formal design change which resulted in additional operator actions during a CVCS rupture.
Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the licensee added manual actions to initiate the Emergency Exhaust System (EES) within one hour following a Chemical Volume and Control System (CVCS) rupture. There was no technical evaluation for these additional operator actions or the use of EES following a CVCS rupture. The EES was previously not relied upon for the mitigation of a CVCS rupture.
Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power.
Inspectors used Exhibit 2, Mitigating Systems Screening Questions, to evaluate the significance. The finding screened to Green because the finding is a deficiency affecting the design or qualification of a mitigating SSC, and the SSC maintained its operability or PRA functionality. Specifically, the new time sensitive operator actions were validated and the operability of the EES was not called into question.
Cross-Cutting Aspect: H.4 - Teamwork: Individuals and work groups communicate and coordinate their activities within and across organizational boundaries to ensure nuclear safety is maintained. The inspectors determined that the performance deficiency was reflective of current performance since the issue occurred within the nominal three year period. The cross-cutting aspect of Teamwork was chosen because there was a breakdown in communication between the individual who issued the procedure change ahead of the revision to the calculation.
Enforcement:
The ROPs significance determination process does not specifically consider the regulatory process impact in its assessment of licensee performance. Therefore, it is necessary to address this violation which impedes the NRCs ability to regulate using traditional enforcement to adequately deter non-compliance.
Severity: The inspectors used guidance in Enforcement Manual Section 2.1.3, Enforcement of 10 CFR 50.59 and Related FSAR Violations, along with Enforcement Policy Section 6.1, and Enforcement Manual Appendix E, Examples of Minor Violations. Inspectors determined that the significance of the issue is consistent with Severity Level IV. Specifically, the associated finding screened as Very Low Safety Significance using the Significance Determination Process.
Violation: Title 10 of the Code of Federal Regulations Part 50.59(d)(1) states that, The licensee shall maintain records of changes in the facility, of changes in procedures, and of tests and experiments made pursuant to 50.59(c). These records must include a written evaluation which provides the bases for the determination that the change, test, or experiment does not require a license amendment pursuant to 50.59(c)(2).
Contrary to this requirement, from August 22, 2022 to November 13, 2024, the licensee did not include a written evaluation which provides the bases for the determination that the change, test, or written experiment does not require a license amendment pursuant to 50.59(c)(2). Specifically, the licensee did not perform an evaluation for the addition of a time sensitive operator action to operate the EES within one hour following a CVCS rupture in the Auxiliary Building. The EES is a system that was not previously relied upon to mitigate this event.
Title 10 of the Code of Federal Regulations Part 50, Appendix B, Criterion III, Design Control, requires in part that, Measures shall be established that assure the design basis is correctly translated in specifications, drawings, and procedures.
Contrary to this requirement, the licensee did not establish measures to assure that the design basis is correctly translated in specification, drawings, and procedures. Specifically, the licensee released a procedure change which incorporated new operator actions prior to a change in calculation that required those additional operator actions.
Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On November 13, 2024, the inspectors presented the comprehensive engineering team inspection results to Jamie McCoy, Site Vice President and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Calculations
20535.11.01-C-
035
Essential Service Water System Train B Room Coolers -
Auxiliary Building (P-287, Parts 2 - 6)
Calculations
20535.11.01-C-
035
Essential Service Water System Train B Room Coolers -
Auxiliary Building (P-287, Parts 2 - 6)
Calculations
AL-02-W
AFW System - Minimum Allowable Recirculation
Calculations
AL-12
Auxiliary Feedwater System
Calculations
AL-16
Determine the Available NPSH for the Auxiliary Feedwater
Pumps, with Dissolved Nitrogen in the Condensate Storage
Tank
Calculations
AL-21
Auxiliary Feedwater Pumps
Calculations
AL-23
Auxiliary Feedwater Pumps
Calculations
AL-30-WC
AFW System Setpoints
Calculations
AL-32
Steady State Performance of Auxiliary Feedwater System
Calculations
AL-M-017
Hydraulic Calculation for Addition of Turbine Driven Auxiliary
Feedwater Pump Standby Tanks (TAL01A, TAL01B, &
TAL01C)
Calculations
AL-M-021
Establishment of the Auxiliary Feedwater (AFW) Pump
Comprehensive Test Error Allowances and Minimum
Operability Limit Curves
Calculations
AN-07-009
GOTHIC Model for CCW Pump Room Temperature
Calculations
AN-97-003
Evaluation of the Motor Driven Auxiliary Feedwater Pump
Performance
Calculations
E-020
Distribution Switchboards
Calculations
EJ-28
RHR Heat Exchanger Nozzle Thermal Growth
Calculations
EJ-M-034
KVAP Analysis for 8" Air-Operated Butterfly Valves
EJFCV0618/0619
Calculations
GD-234
Essential Service Water Pumphouse - Determine the
Cooling and Heating Requirements of the Site Related
Pumphouses
Calculations
GK-M-014
Cooling and Heating Load for Control Building Class 1E
Electrical Equipment Areas During Accident Conditions -
Train A
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Calculations
GL-04-W
RHR Pump Rooms 1109 and 1111 Heat Loads
Calculations
GL-454
Minimum Coil Design Pressure
Calculations
GS-M-004
Hydrogen Generation Analysis
Calculations
NE-E-001
Emergency Diesel Transient Loading Analysis
001
Calculations
NG-E-004
Class 1E 120 VAC MCC Power Distribution System
Calculations
NK-E-001
25 VDC Class 1E Battery System Sizing, Voltage Drop and
Short Circuit Studies
Calculations
XX-E-006
AC System Analysis
Calculations
XX-E-042
Class 1E 480VAC and 208/120VAC System Coordination
Calculations
XX-M-052
Partial/total volumes for the new turbine driven auxiliary feed
water condensate tanks TAL01A, TAL01B and TAL01C
Calculations
XX-M-070
FAC Program Minimum Wall Thickness Calculation for Small
Bore Piping and Components
Corrective Action
Documents
CR-
10007289, 10007290, 10031120, 10031864, 10017549,
10024005, 20036994, 20036992, 10021612, 10017218,
10027276, 10029488, 10031043, 00076014, 10012960,
10013314, 10015425, 10030450, 10030455, 10012293,
00145506
Corrective Action
Documents
Resulting from
Inspection
CR-
10037457, 10037467, 10037531, 10037749, 10037753,
10037822, 10037850, 10037855, 10037856, 10037858,
10037860, 10037916, 10037917
Drawings
E-050A-00002
Wolf Creek Nuclear Operating Corporation Layout for NK
Batteries
W08
Drawings
E-11NG20
Low Voltage System Class 1E Motor Control Center
Summary
21
Drawings
E-11NK01
Class 1E 125V DC System Meter & Relay Diagram
Drawings
E-K3GD01
Schematic Diagram ESW Pump Room Supply Fan A
Drawings
E-K3GD01A
Schematic Diagram ESW Pump Room Supply Fan B
Drawings
J-K2GD01 (Q)
Control Logic Diagram - Essential Service Water Pump
House HVAC Supply Fans
Drawings
KD-7496
One Line Diagram
Drawings
M-12AB02
P&ID - Main Steam System
Drawings
M-12AE02
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Drawings
M-12AL01
P&ID - Auxiliary Feedwater System
Drawings
M-12AP01
P&ID - Condensate Storage and Transfer System
Drawings
M-12EJ01
Piping and Instrumentation Diagram Residual Heat Removal
System
Drawings
M-12FC02
P&ID - Auxiliary Turbines - Auxiliary Feedwater Pump
Turbine
Drawings
M-K2GD01
Piping & Instrumentation Diagram Essential Service Water
Pump House HVAC
Drawings
MD32520
Nozzle Check Valve
D
Drawings
WIP-E-11NG01-
011-C-1
Low Voltage System Class 1E 480V Single Line Meter &
Relay Diagram
Drawings
WIP-E-11NG02-
011-C-1
Low Voltage System Class 1E 480V Single Line Meter &
Relay Diagram
Engineering
Changes
20292
Substation Transformers No. 8,9,10 & 11 and Breakers
Replacement R25
Engineering
Changes
CP 012858
Westinghouse 7300 Lead / Lag Card Deletions
Engineering
Changes
CP 20082
Replace AFW check valve
11/1/2021
Engineering
Changes
DCP 020292 -
Substation
Transformers No.
8, 9, 10 & 11 and
Breakers
Replacement R25
50.59 Applicability Determination
Engineering
Changes
DCP 020292 -
Substation
Transformers No.
8, 9, 10 & 11 and
Breakers
Replacement R25
50.59 Applicability Determination
Engineering
Changes
DEC-020500
A CCW Heat Exchanger EEG01A Pitting Repair
Engineering
Engineering
AKR-30 Battery Charger Supply Breaker Setting Changes
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Changes
Disposition -
Change Package
014726
Engineering
Changes
Engineering
Disposition -
Change Package
014726
AKR-30 Battery Charger Supply Breaker Setting Changes
Engineering
Changes
Engineering
Disposition -
Change Package
014726
AKR-30 Battery Charger Supply Breaker Setting Changes
Miscellaneous
Whitepaper - CETI-2024 for CP14726-11-04-2024 - Final
11/04/2024
Miscellaneous
1-GD-21
Startup Field Report - G-D/ESW Pumphouse HVAC
08/26/1983
Miscellaneous
2-0956
Document Revision Request - STS KJ-005B, Manual/Auto
Start, Sync & Loading of EDG NE02
Miscellaneous
APF 29B-004-01
Inservice Testing Program for Pumps and Valves - Change
Notice
Miscellaneous
Protection of cables shown on drawings E-11NG01 and E-
11NG02
06/18/2013
Miscellaneous
BD-EMG E-3
Basis - STEAM GENERATOR TUBE RUPTURE
Miscellaneous
E-017-00628
Summary of Switchgear Equipment NG01 NG02 NG03 &
NG04
W13
Miscellaneous
E-050A-00011
Product Manual - Lucent Technologies Lineage 2000 Round
Cell Battery
09/01/1996
Miscellaneous
INC S-0502
Wire Wrap Standards and Practices
7A
Miscellaneous
KMS-4
Mechanical Standard for Bolting
Miscellaneous
M -712-00202-
0001
RCP Main Flange Joint Integrity
Miscellaneous
M-109-00104
ULTRAFLOTE Cover Operating Manual
W03
Miscellaneous
M-10AL
System Description - AUXILIARY FEEDWATER SYSTEM
Miscellaneous
M-10AP
System Description - CONDENSATE STORAGE AND
TRANSFER SYSTEM
Miscellaneous
M-612
Design Specification for the Room Coolers for the Wolf
Creek Generating Station
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Miscellaneous
M-612-00062
Instruction Manual for Air Handling Units
Miscellaneous
M-722-00052
Instruction Manual for Auxiliary Heat Exchangers
W12
Miscellaneous
M-724-00424
Instruction Manual for Butterfly Valves Fisher/Continental
Westinghouse Electric
W08
Miscellaneous
MEC-016
Main Flange Elongation Verification on the RCPs
Miscellaneous
OPA-NK025
Failure To Locally Align Train A Swing Charger
10/18/2022
Miscellaneous
PIR 2002-0242
PIR to document the recent events at the Callaway Plant
01/29/2002
Miscellaneous
Specification No.
E-050A
Technical Specification for The Class 1E Batteries
Miscellaneous
System Health
Report - 2023 Q4
NK System
2/20/2024
Procedures
AI 21-016
Operator Time Critical Actions Validation
Procedures
ALR 00-025C
NK01 TROUBLE
Procedures
ALR 00-055F
Frz Prot Trouble
Procedures
ALR 00-127A
AFP Suct Press Lo
Procedures
ALR 301
25 VDC Class IE Switchboard NK01
Procedures
Scaffold Construction
26A
Procedures
Industry Operating Experience Program
Procedures
CFR 50.59 Reviews
Procedures
CKL ZL-004
Turbine Building Reading Sheets
183
Procedures
E-10NK
System Description For 125-Volt DC System (Class 1E
Power System)
Procedures
EMG E-0
Reactor Trip or Safety Injection
Procedures
EMG E-2
Faulted Steam Generator Isolation
Procedures
EMG E-2
Faulted Steam Generator Isolation
Procedures
EMG E-3
Steam Generator Tube Rupture
Procedures
IP-ENG-001
Standard Design Process
Procedures
MGM MOOP-012
Crane/Hoist Inspections
Procedures
MPE BA-014
Battery Impedance Testing
4B
Procedures
MPE E017AQ-01
Test Masterpact 480V Circuit Breaker
1A
Procedures
MPE E017Q-07
Load Center Transformer Inspection
17A
Procedures
STN AL-201
Auxiliary Feedwater System Valve Test
Procedures
STN IC-466
ESW Pump Room B Temperature and Ventilation Control
13A
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Calibration
Procedures
STN PE-068
Periodic Testing of Air-Operated Valves
Procedures
STS AL-100B
MDAFW Pump B Five Point Reference Pump Curve
Determination
5A
Procedures
STS AL-102
MDAFW Pump B Inservice Pump Test
Procedures
STS AL-105B
MD AFP B Flow Path Verification
Procedures
STS AL-106B
Motor Driven AFW Pump B Discharge Check Valve Closed
Test
Procedures
STS AL-210D
AFW Inservice Check Valve Test
Procedures
STS AL-212
MD AFP Comprehensive Pump Testing, Flow Path
Verification & CV Testing
Procedures
STS EF-100A
ESW System Inservice Pump A & ESW A Check Valve Test
050
Procedures
STS EF-100B
ESW System Inservice Pump B & ESW B Check Valve Test
2
Procedures
STS EJ-209A
Train A RHR System Inservice Valve Test
Procedures
STS KJ-005B
Manual/Auto Start, Sync & Loading of EDG NE02
Procedures
STS MT-019A
25 Vdc Class 1E Quarterly Inspection for NK11 And NK13
Batteries
Procedures
STS MT-058
Modified Performance Test For 125 Vdc Class 1E Batteries
Procedures
STS MT-080
25 Volt DC Battery Inspection
Procedures
STS PE-043A
RHR Train A Normal Operation Pressure Test
Procedures
SYS NK-131
Energizing NK Buses
Procedures
SYS OPS-008
Cold Weather Operations
13A
Work Orders
2426, 77096, 17374, 63232, 23-488476-000, 23-488405-
000, 23-487248-000, 23-485630-000, 23-485631-000, 23-
485656-000, 23-485656-002, 23-483676-000, 22-482213-
000, 22-480900-000, 22-480695-000, 22-480547-000, 22-
479189-000, 21-469969-000, 21-475350-000, 19-452308-
000, 19-452215-000, 18-437213-000, 18-435426-000, 13-
380152-018, 16-415412-000, 16-411777-000, 18-445218-
001, 18-445218-002, 22-478403-000