IR 05000482/2024014

From kanterella
Jump to navigation Jump to search
Comprehensive Engineering Team Inspection Report 05000482/2024014
ML24341A034
Person / Time
Site: Wolf Creek 
Issue date: 12/17/2024
From: Vincent Gaddy
NRC/RGN-IV/DORS/EB1
To: Reasoner C
Wolf Creek
References
IR 2024014
Download: ML24341A034 (18)


Text

December 17, 2024

SUBJECT:

WOLF CREEK GENERATING STATION - COMPREHENSIVE ENGINEERING TEAM INSPECTION REPORT 05000482/2024014

Dear Cleve Reasoner:

On November 13, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Wolf Creek Generating Station and discussed the results of this inspection with Jamie McCoy, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements and was determined to be Severity Level IV. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Wolf Creek Generating Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Wolf Creek Generating Station. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Vincent G. Gaddy, Chief Engineering Branch 1 Division of Operating Reactor Safety Docket No. 05000482 License No. NPF-42

Enclosure:

As stated

Inspection Report

Docket Number:

05000482

License Number:

NPF-42

Report Number:

05000482/2024014

Enterprise Identifier:

I-2024-014-0002

Licensee:

Wolf Creek Nuclear Operating Corp.

Facility:

Wolf Creek Generating Station

Location:

Burlington, KS

Inspection Dates:

October 21, 2024, to November 13, 2024

Inspectors:

C. Baron, Contractor

D. Bryen, Reactor Inspector

W. Cullum, Senior Reactor Inspector

S. Graves, Senior Reactor Inspector

R. Kumana, Senior Reactor Inspector

D. Reinert, Senior Reactor Analyst

F. Thomas, Reactor Inspector

Approved By:

Vincent G. Gaddy, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a comprehensive engineering team inspection at Wolf Creek Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Perform an Evaluation Pursuant to 10 CFR 50.59 for Adding Operator Actions to Mitigate a Chemical Volume and Control System (CVCS) Rupture Cornerstone Significance/Severity Cross-Cutting Aspect Report Section Mitigating Systems Green Severity Level IV NCV 05000482/2024014-01 Open/Closed

[H.4] -

Teamwork 71111.21M The inspectors identified a Green finding of 10 CFR 50, Appendix B, Criterion III, Design Control when the licensee added additional equipment, which was not previously relied upon, to mitigate a Chemical Volume and Control System (CVCS) rupture in the Auxiliary Building, and an associated Severity Level IV Non-cited Violation (NCV) of 10 CFR 50.59, Changes,

Tests, and Experiments, when the licensee did not perform a written evaluation which provides the bases for the determination that the change, test, or experiment does not require a license amendment pursuant to paragraph 50.59(c)(2).

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Comprehensive Engineering Team Inspection The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Structures, Systems, and Components (SSCs) (IP section 03.01)===

(1) NK44, 125VDC Panel DP-NK44
  • Updated Safety Analysis Report (USAR), technical specifications (TS), and TS bases document
  • Visual inspection of bus for as-built configuration and material condition
  • Environmental conditions
  • Short circuit and equipment protection
  • Load voltage
  • Component maintenance history
  • System Health Report
(2) EEJ01A, Residual Heat Removal Heat Exchanger 1A
  • Vendor manual for installation, operation, and maintenance of the heat exchanger
  • System operating procedures
  • Corrective action program documents
  • Visual inspection of the as-built configuration and material condition
(3) EJFCV0618, Residual Heat Removal Heat Exchanger Bypass Valve 618
  • Calculations for required thrust, actuator capability, and available margin
  • Valve and actuator vendor manuals for installation, operation, and
  • maintenance
  • Inservice and diagnostic testing records including procedures and results for position
  • Maintenance work order history records of visual inspections, lubrications, and elastomer replacement
  • Corrective action program documents
  • Visual inspection of the as-built configuration and material condition (4)480V Bus NG01/Transformer XNG01
  • Electrical drawings
  • Component maintenance history and corrective action program documents
  • Procedures for transformer inspection, maintenance, and testing
  • Voltage analysis and short circuit calculations
  • Visual inspection of switchgear for as-built configuration and material condition
  • Environmental conditions for equipment
  • System health report
  • Vendor manual and plant design drawings
(5) EFHV0051, Train A Component Cooling Water Heat Exchanger Essential Service Water Inlet Valve
  • Piping and instrumentation drawings
  • Vendor documentation
  • Calculations for torque and thrust
  • Visual inspection of the component
  • Corrective actions related to the component
  • Preventative maintenance history
  • System operating procedures and emergency operation
(6) SGL10A, Residual Heat Removal Room Cooler
  • Piping and instrumentation drawings
  • Room heat load calculations
  • Tube plugging limit calculation
  • Vendor documentation
  • Visual inspection of the component
  • Corrective actions related to the component
  • Preventative maintenance history
(7) Essential Service Water Train B HVAC Fan CGD01B
  • Design requirements within purchase specifications
  • Functionality tests of the essential service water pumphouse ventilation system
  • Room heat load calculations
  • Component maintenance history and corrective action program reports
  • Essential service water pumphouse ventilation system piping and instrumentation diagram
  • Vendor manual for installation, operation, and maintenance of the essential service water pumphouse ventilation fans
  • Visual inspection of the as-built configuration and material condition
(8) NK13, 125VDC Battery
  • Updated Safety Analysis Report (USAR), technical specifications (TS), and TS bases document
  • Visual inspection of battery cells, support structure, conductors, and material condition
  • Environmental conditions
  • Maintenance and testing history
  • Cell temperature calculation
  • System Health Report
  • Evaluation of Operator Actions to Locally Align Swing Charger (OPA-NK025)
(9) AFW Motor-Driven Pump, PAL01B
  • Pump Head and Flow Requirements
  • Minimum Recirculation Flow Requirements
  • Basis for Inservice Testing Acceptance Criteria
  • Evaluation of Recent Inservice Testing Results
  • Evaluation of Limiting Runout Flow Conditions
  • Evaluation of Operator Actions to Terminate Flow to Faulted Steam Generator (OPA-SLB)
  • Testing Requirements for Manual Valves Credited with Isolating Flow
  • Evaluation of Seismic Hazards in AF Pump Room
  • Evaluation of Automatic Transfer of Pump Suction from CST to ESW
(10) Condensate Storage Tank, TAP01
  • Evaluation of Tanks Capacity Requirements
  • Evaluation of Protection of Tank from External Hazards
  • Evaluation of Freeze Protection of Tank and Associated Piping
  • Evaluation of Level Setpoints for Automatic Transfer of AF Pumps and Alarms
  • Evaluation of Tank Floating Barrier and Associated Vents

Modifications (IP section 03.02) (5 Samples)

(1) Change Package 20007, 7300 Controls Upgrade - Protection Set
(2) Change Package 20500, Component Cooling Water Heat Exchanger EEG01A Pitting Repair
(3) Change Package 20394, Emergency Diesel Generator Jacket Water Bleeder Vent Valves
(4) Change Package 14726, AKR-30 Battery Charger Supply Breaker Setting Changes
(5) Change Package 20082, Replace Check Valves ALV0030 and ALV0042 with New Design 10 CFR 50.59 Evaluations/Screening (IP section 03.03) (20 Samples)
(1) GS-M-005, Aluminum in Containment
(2) GS-M-006, Zinc in Containment
(3) CP 20734, Replacement of Post Accident PR/SR Recorder with Yokogawa
(4) AN-07-009, GOTHIC Model for Component Cooling Water Pump Room Temperature
(5) GK-M-014, Cooling and Heating Load Calculation Control Building Class 1E Electrical Equipment Areas During Accident Conditions - Train A
(6) SYS-EP-200, Safety Injection Accumulator Operation
(7) YY-49, High Energy Line Break in the Auxiliary Building (8)

===020663, Main Feedwater Regulating Valve Body to Bonnet Stud Repair (9)020616, BBPV8702B Motor rotor change - magnesium to aluminum (10)020631, System Descriptions M-10B and M-10EN Update

(11) STS KJ-005B, Manual/Auto Start Sync & Loading of EDG NE02 (12)020535.11.01-C-035, Essential Service Water System Train B Room Coolers - Auxiliary Building (P-287 Parts 2 - 6)

(13)020292, Substation Transformers No. 8,9,10 & 11 and Breakers Replacement R25 (14)020538, PFSSD Modification to Address IN 92-18 for Multiple 'A' Train MOVS-Refuel (15)020551, Cyber Security Equipment Upgrade (16)020671, Containment WI-FI Upgrade

(17) XX-M-070, FAC Program Minimum Wall Thickness Calculation for Small Bore Piping and Components
(18) AL-16-W, Determine the Available NPSH for the Auxiliary Feedwater Pumps, with Dissolved Nitrogen in the Condensate Storage Tank
(19) CP 020624, TDAFW Sprinkler Main Drain Addition
(20) EMG E-0 REV. 48, EMG Procedure Revision Screen Operating Experience Samples (IP section 03.04)===
(1) CR 10017549, IRIS Event 475377 Callaway Emergency Exhaust Fan
(2) CR 10015425, Part 21 on NPS Part Number 16-AAT907B, 48 VDC Power Supplies
(3) CR 10020756, RCP ESBU-TB-91-04 Revision in M-712-00202

INSPECTION RESULTS

Failure to Perform an Evaluation Pursuant to 10 CFR 50.59 for Adding Operator Actions to Mitigate a Chemical Volume and Control System (CVCS) Rupture Cornerstone Significance/Severity Cross-Cutting Aspect Report Section Mitigating Systems Green Severity Level IV NCV 05000482/2024014-01 Open/Closed

[H.4] -

Teamwork 71111.21M The inspectors identified a Green finding of 10 CFR 50, Appendix B, Criterion III, Design Control when the licensee added additional equipment, which was not previously relied upon, to mitigate a Chemical Volume and Control System (CVCS) rupture in the Auxiliary Building, and an associated Severity Level IV Non-cited Violation (NCV) of 10 CFR 50.59, Changes, Tests, and Experiments, when the licensee did not perform a written evaluation which provides the bases for the determination that the change, test, or experiment does not require a license amendment pursuant to paragraph 50.59(c)(2).

Description:

The inspectors reviewed a change to calculation YY-49, High Energy Line Breaks in the Auxiliary Building, and the associated 10CFR50.59 screening. The calculation change resulted in a reduction in time for time-critical operator actions that were already in place to isolate the rupture, and an addition of new time-sensitive operator actions required to mitigate a rupture in the Chemical Volume and Control System (CVCS) in the Auxiliary Building. The new operator actions were associated with initiating the Emergency Exhaust System (EES) within one hour to improve the atmospheric conditions in the Auxiliary Building.

Procedure AI 21-016, Operator Time Critical Actions Validation, which included the reduction in time to isolate the CVCS rupture and the new time sensitive actions to initiate EES, was released prematurely on 3/15/2022 before the change to calculation YY-49 was issued. The 50.59 screening for the change to calculation YY-49 was performed on 6/1/2022.

Since the procedure change to AI 21-016 was already issued which established the new operator actions, the plant staff performing the 50.59 review did not realize that new operator actions were being established since they already appeared in the procedure. As a result, the 50.59 review incorrectly established that the change to calculation YY-49 screened out and a 50.59 evaluation was not performed.

Corrective Actions: The licensee entered the issue into the corrective action program.

Corrective Action References: CR 10037557

Performance Assessment:

Performance Deficiency: The licensee failed to establish measures that assure the design basis is correctly translated in specifications, drawings, and procedures as required by 10 CFR 50, Appendix B, Criterion III, Design Control. Specifically, the licensee issued a procedure change notice prior to a formal design change which resulted in additional operator actions during a CVCS rupture.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the licensee added manual actions to initiate the Emergency Exhaust System (EES) within one hour following a Chemical Volume and Control System (CVCS) rupture. There was no technical evaluation for these additional operator actions or the use of EES following a CVCS rupture. The EES was previously not relied upon for the mitigation of a CVCS rupture.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power.

Inspectors used Exhibit 2, Mitigating Systems Screening Questions, to evaluate the significance. The finding screened to Green because the finding is a deficiency affecting the design or qualification of a mitigating SSC, and the SSC maintained its operability or PRA functionality. Specifically, the new time sensitive operator actions were validated and the operability of the EES was not called into question.

Cross-Cutting Aspect: H.4 - Teamwork: Individuals and work groups communicate and coordinate their activities within and across organizational boundaries to ensure nuclear safety is maintained. The inspectors determined that the performance deficiency was reflective of current performance since the issue occurred within the nominal three year period. The cross-cutting aspect of Teamwork was chosen because there was a breakdown in communication between the individual who issued the procedure change ahead of the revision to the calculation.

Enforcement:

The ROPs significance determination process does not specifically consider the regulatory process impact in its assessment of licensee performance. Therefore, it is necessary to address this violation which impedes the NRCs ability to regulate using traditional enforcement to adequately deter non-compliance.

Severity: The inspectors used guidance in Enforcement Manual Section 2.1.3, Enforcement of 10 CFR 50.59 and Related FSAR Violations, along with Enforcement Policy Section 6.1, and Enforcement Manual Appendix E, Examples of Minor Violations. Inspectors determined that the significance of the issue is consistent with Severity Level IV. Specifically, the associated finding screened as Very Low Safety Significance using the Significance Determination Process.

Violation: Title 10 of the Code of Federal Regulations Part 50.59(d)(1) states that, The licensee shall maintain records of changes in the facility, of changes in procedures, and of tests and experiments made pursuant to 50.59(c). These records must include a written evaluation which provides the bases for the determination that the change, test, or experiment does not require a license amendment pursuant to 50.59(c)(2).

Contrary to this requirement, from August 22, 2022 to November 13, 2024, the licensee did not include a written evaluation which provides the bases for the determination that the change, test, or written experiment does not require a license amendment pursuant to 50.59(c)(2). Specifically, the licensee did not perform an evaluation for the addition of a time sensitive operator action to operate the EES within one hour following a CVCS rupture in the Auxiliary Building. The EES is a system that was not previously relied upon to mitigate this event.

Title 10 of the Code of Federal Regulations Part 50, Appendix B, Criterion III, Design Control, requires in part that, Measures shall be established that assure the design basis is correctly translated in specifications, drawings, and procedures.

Contrary to this requirement, the licensee did not establish measures to assure that the design basis is correctly translated in specification, drawings, and procedures. Specifically, the licensee released a procedure change which incorporated new operator actions prior to a change in calculation that required those additional operator actions.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On November 13, 2024, the inspectors presented the comprehensive engineering team inspection results to Jamie McCoy, Site Vice President and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Calculations

20535.11.01-C-

035

Essential Service Water System Train B Room Coolers -

Auxiliary Building (P-287, Parts 2 - 6)

71111.21M

Calculations

20535.11.01-C-

035

Essential Service Water System Train B Room Coolers -

Auxiliary Building (P-287, Parts 2 - 6)

71111.21M

Calculations

AL-02-W

AFW System - Minimum Allowable Recirculation

71111.21M

Calculations

AL-12

Auxiliary Feedwater System

71111.21M

Calculations

AL-16

Determine the Available NPSH for the Auxiliary Feedwater

Pumps, with Dissolved Nitrogen in the Condensate Storage

Tank

71111.21M

Calculations

AL-21

Auxiliary Feedwater Pumps

71111.21M

Calculations

AL-23

Auxiliary Feedwater Pumps

71111.21M

Calculations

AL-30-WC

AFW System Setpoints

71111.21M

Calculations

AL-32

Steady State Performance of Auxiliary Feedwater System

71111.21M

Calculations

AL-M-017

Hydraulic Calculation for Addition of Turbine Driven Auxiliary

Feedwater Pump Standby Tanks (TAL01A, TAL01B, &

TAL01C)

71111.21M

Calculations

AL-M-021

Establishment of the Auxiliary Feedwater (AFW) Pump

Comprehensive Test Error Allowances and Minimum

Operability Limit Curves

71111.21M

Calculations

AN-07-009

GOTHIC Model for CCW Pump Room Temperature

71111.21M

Calculations

AN-97-003

Evaluation of the Motor Driven Auxiliary Feedwater Pump

Performance

71111.21M

Calculations

E-020

Distribution Switchboards

71111.21M

Calculations

EJ-28

RHR Heat Exchanger Nozzle Thermal Growth

71111.21M

Calculations

EJ-M-034

KVAP Analysis for 8" Air-Operated Butterfly Valves

EJFCV0618/0619

71111.21M

Calculations

GD-234

Essential Service Water Pumphouse - Determine the

Cooling and Heating Requirements of the Site Related

Pumphouses

71111.21M

Calculations

GK-M-014

Cooling and Heating Load for Control Building Class 1E

Electrical Equipment Areas During Accident Conditions -

Train A

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Calculations

GL-04-W

RHR Pump Rooms 1109 and 1111 Heat Loads

71111.21M

Calculations

GL-454

Minimum Coil Design Pressure

71111.21M

Calculations

GS-M-004

Hydrogen Generation Analysis

71111.21M

Calculations

NE-E-001

Emergency Diesel Transient Loading Analysis

001

71111.21M

Calculations

NG-E-004

Class 1E 120 VAC MCC Power Distribution System

71111.21M

Calculations

NK-E-001

25 VDC Class 1E Battery System Sizing, Voltage Drop and

Short Circuit Studies

71111.21M

Calculations

XX-E-006

AC System Analysis

71111.21M

Calculations

XX-E-042

Class 1E 480VAC and 208/120VAC System Coordination

71111.21M

Calculations

XX-M-052

Partial/total volumes for the new turbine driven auxiliary feed

water condensate tanks TAL01A, TAL01B and TAL01C

71111.21M

Calculations

XX-M-070

FAC Program Minimum Wall Thickness Calculation for Small

Bore Piping and Components

71111.21M

Corrective Action

Documents

CR-

10007289, 10007290, 10031120, 10031864, 10017549,

10024005, 20036994, 20036992, 10021612, 10017218,

10027276, 10029488, 10031043, 00076014, 10012960,

10013314, 10015425, 10030450, 10030455, 10012293,

00145506

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR-

10037457, 10037467, 10037531, 10037749, 10037753,

10037822, 10037850, 10037855, 10037856, 10037858,

10037860, 10037916, 10037917

71111.21M

Drawings

E-050A-00002

Wolf Creek Nuclear Operating Corporation Layout for NK

Batteries

W08

71111.21M

Drawings

E-11NG20

Low Voltage System Class 1E Motor Control Center

Summary

21

71111.21M

Drawings

E-11NK01

Class 1E 125V DC System Meter & Relay Diagram

71111.21M

Drawings

E-K3GD01

Schematic Diagram ESW Pump Room Supply Fan A

71111.21M

Drawings

E-K3GD01A

Schematic Diagram ESW Pump Room Supply Fan B

71111.21M

Drawings

J-K2GD01 (Q)

Control Logic Diagram - Essential Service Water Pump

House HVAC Supply Fans

71111.21M

Drawings

KD-7496

One Line Diagram

71111.21M

Drawings

M-12AB02

P&ID - Main Steam System

71111.21M

Drawings

M-12AE02

P&ID - Feedwater System

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Drawings

M-12AL01

P&ID - Auxiliary Feedwater System

71111.21M

Drawings

M-12AP01

P&ID - Condensate Storage and Transfer System

71111.21M

Drawings

M-12EJ01

Piping and Instrumentation Diagram Residual Heat Removal

System

71111.21M

Drawings

M-12FC02

P&ID - Auxiliary Turbines - Auxiliary Feedwater Pump

Turbine

71111.21M

Drawings

M-K2GD01

Piping & Instrumentation Diagram Essential Service Water

Pump House HVAC

71111.21M

Drawings

MD32520

Nozzle Check Valve

D

71111.21M

Drawings

WIP-E-11NG01-

011-C-1

Low Voltage System Class 1E 480V Single Line Meter &

Relay Diagram

71111.21M

Drawings

WIP-E-11NG02-

011-C-1

Low Voltage System Class 1E 480V Single Line Meter &

Relay Diagram

71111.21M

Engineering

Changes

20292

Substation Transformers No. 8,9,10 & 11 and Breakers

Replacement R25

71111.21M

Engineering

Changes

CP 012858

Westinghouse 7300 Lead / Lag Card Deletions

71111.21M

Engineering

Changes

CP 20082

Replace AFW check valve

11/1/2021

71111.21M

Engineering

Changes

DCP 020292 -

Substation

Transformers No.

8, 9, 10 & 11 and

Breakers

Replacement R25

50.59 Applicability Determination

71111.21M

Engineering

Changes

DCP 020292 -

Substation

Transformers No.

8, 9, 10 & 11 and

Breakers

Replacement R25

50.59 Applicability Determination

71111.21M

Engineering

Changes

DEC-020500

A CCW Heat Exchanger EEG01A Pitting Repair

71111.21M

Engineering

Engineering

AKR-30 Battery Charger Supply Breaker Setting Changes

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Changes

Disposition -

Change Package

014726

71111.21M

Engineering

Changes

Engineering

Disposition -

Change Package

014726

AKR-30 Battery Charger Supply Breaker Setting Changes

71111.21M

Engineering

Changes

Engineering

Disposition -

Change Package

014726

AKR-30 Battery Charger Supply Breaker Setting Changes

71111.21M

Miscellaneous

Whitepaper - CETI-2024 for CP14726-11-04-2024 - Final

11/04/2024

71111.21M

Miscellaneous

1-GD-21

Startup Field Report - G-D/ESW Pumphouse HVAC

08/26/1983

71111.21M

Miscellaneous

2-0956

Document Revision Request - STS KJ-005B, Manual/Auto

Start, Sync & Loading of EDG NE02

71111.21M

Miscellaneous

APF 29B-004-01

Inservice Testing Program for Pumps and Valves - Change

Notice

71111.21M

Miscellaneous

AR 00070533

Protection of cables shown on drawings E-11NG01 and E-

11NG02

06/18/2013

71111.21M

Miscellaneous

BD-EMG E-3

Basis - STEAM GENERATOR TUBE RUPTURE

71111.21M

Miscellaneous

E-017-00628

Summary of Switchgear Equipment NG01 NG02 NG03 &

NG04

W13

71111.21M

Miscellaneous

E-050A-00011

Product Manual - Lucent Technologies Lineage 2000 Round

Cell Battery

09/01/1996

71111.21M

Miscellaneous

INC S-0502

Wire Wrap Standards and Practices

7A

71111.21M

Miscellaneous

KMS-4

Mechanical Standard for Bolting

71111.21M

Miscellaneous

M -712-00202-

0001

RCP Main Flange Joint Integrity

71111.21M

Miscellaneous

M-109-00104

ULTRAFLOTE Cover Operating Manual

W03

71111.21M

Miscellaneous

M-10AL

System Description - AUXILIARY FEEDWATER SYSTEM

71111.21M

Miscellaneous

M-10AP

System Description - CONDENSATE STORAGE AND

TRANSFER SYSTEM

71111.21M

Miscellaneous

M-612

Design Specification for the Room Coolers for the Wolf

Creek Generating Station

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Miscellaneous

M-612-00062

Instruction Manual for Air Handling Units

71111.21M

Miscellaneous

M-722-00052

Instruction Manual for Auxiliary Heat Exchangers

W12

71111.21M

Miscellaneous

M-724-00424

Instruction Manual for Butterfly Valves Fisher/Continental

Westinghouse Electric

W08

71111.21M

Miscellaneous

MEC-016

Main Flange Elongation Verification on the RCPs

71111.21M

Miscellaneous

OPA-NK025

Failure To Locally Align Train A Swing Charger

10/18/2022

71111.21M

Miscellaneous

PIR 2002-0242

PIR to document the recent events at the Callaway Plant

01/29/2002

71111.21M

Miscellaneous

Specification No.

E-050A

Technical Specification for The Class 1E Batteries

71111.21M

Miscellaneous

System Health

Report - 2023 Q4

NK System

2/20/2024

71111.21M

Procedures

AI 21-016

Operator Time Critical Actions Validation

71111.21M

Procedures

ALR 00-025C

NK01 TROUBLE

71111.21M

Procedures

ALR 00-055F

Frz Prot Trouble

71111.21M

Procedures

ALR 00-127A

AFP Suct Press Lo

71111.21M

Procedures

ALR 301

25 VDC Class IE Switchboard NK01

71111.21M

Procedures

AP 14A-003

Scaffold Construction

26A

71111.21M

Procedures

AP 20E-001

Industry Operating Experience Program

71111.21M

Procedures

AP 26A-003

CFR 50.59 Reviews

71111.21M

Procedures

CKL ZL-004

Turbine Building Reading Sheets

183

71111.21M

Procedures

E-10NK

System Description For 125-Volt DC System (Class 1E

Power System)

71111.21M

Procedures

EMG E-0

Reactor Trip or Safety Injection

71111.21M

Procedures

EMG E-2

Faulted Steam Generator Isolation

71111.21M

Procedures

EMG E-2

Faulted Steam Generator Isolation

71111.21M

Procedures

EMG E-3

Steam Generator Tube Rupture

71111.21M

Procedures

IP-ENG-001

Standard Design Process

71111.21M

Procedures

MGM MOOP-012

Crane/Hoist Inspections

71111.21M

Procedures

MPE BA-014

Battery Impedance Testing

4B

71111.21M

Procedures

MPE E017AQ-01

Test Masterpact 480V Circuit Breaker

1A

71111.21M

Procedures

MPE E017Q-07

Load Center Transformer Inspection

17A

71111.21M

Procedures

STN AL-201

Auxiliary Feedwater System Valve Test

71111.21M

Procedures

STN IC-466

ESW Pump Room B Temperature and Ventilation Control

13A

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Calibration

71111.21M

Procedures

STN PE-068

Periodic Testing of Air-Operated Valves

71111.21M

Procedures

STS AL-100B

MDAFW Pump B Five Point Reference Pump Curve

Determination

5A

71111.21M

Procedures

STS AL-102

MDAFW Pump B Inservice Pump Test

71111.21M

Procedures

STS AL-105B

MD AFP B Flow Path Verification

71111.21M

Procedures

STS AL-106B

Motor Driven AFW Pump B Discharge Check Valve Closed

Test

71111.21M

Procedures

STS AL-210D

AFW Inservice Check Valve Test

71111.21M

Procedures

STS AL-212

MD AFP Comprehensive Pump Testing, Flow Path

Verification & CV Testing

71111.21M

Procedures

STS EF-100A

ESW System Inservice Pump A & ESW A Check Valve Test

050

71111.21M

Procedures

STS EF-100B

ESW System Inservice Pump B & ESW B Check Valve Test

2

71111.21M

Procedures

STS EJ-209A

Train A RHR System Inservice Valve Test

71111.21M

Procedures

STS KJ-005B

Manual/Auto Start, Sync & Loading of EDG NE02

71111.21M

Procedures

STS MT-019A

25 Vdc Class 1E Quarterly Inspection for NK11 And NK13

Batteries

71111.21M

Procedures

STS MT-058

Modified Performance Test For 125 Vdc Class 1E Batteries

71111.21M

Procedures

STS MT-080

25 Volt DC Battery Inspection

71111.21M

Procedures

STS PE-043A

RHR Train A Normal Operation Pressure Test

71111.21M

Procedures

SYS NK-131

Energizing NK Buses

71111.21M

Procedures

SYS OPS-008

Cold Weather Operations

13A

71111.21M

Work Orders

2426, 77096, 17374, 63232, 23-488476-000, 23-488405-

000, 23-487248-000, 23-485630-000, 23-485631-000, 23-

485656-000, 23-485656-002, 23-483676-000, 22-482213-

000, 22-480900-000, 22-480695-000, 22-480547-000, 22-

479189-000, 21-469969-000, 21-475350-000, 19-452308-

000, 19-452215-000, 18-437213-000, 18-435426-000, 13-

380152-018, 16-415412-000, 16-411777-000, 18-445218-

001, 18-445218-002, 22-478403-000