ML20066A070

From kanterella
Jump to navigation Jump to search
Reissues Re Cancellation of CPPR-119.All Open & Closed Licensing Commitments Reviewed to Confirm That Cancellation Will in No Way Impact Safe Operation of Unit 1. Unit Approx 29% Complete
ML20066A070
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 12/27/1990
From: Cottle W
ENTERGY OPERATIONS, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
AECM-90-2-0004, AECM-90-2-4, NUDOCS 9101030001
Download: ML20066A070 (7)


Text

- _ _ _ - _ _ - _ -

i

. _.-. Entergy

""" o*"*"a u a"

] Operatons . ,; ,.

v q (NissueT withicorrec ted; subj ect 1; previously

~' ' * ) C""*

issued / dated (12/14/90[ j December 27, 1990 U.S. Nuclear Regulatory Commission Mall Station P1-137 Washington, D.C. 20555 Attention: Document Control Desk Gentlemen:

SUBJECT:

Grand Gulf Nuclear Station Unit 2 Docket No. 50-417 Construction Permit No. CPPR-119-Cancellation-of Unit 2 Construction Permit AECM-90/2-0004 On September 4,1974, the Atomic Energy Commission issued Construction

-Permit No CPPR-119 for the Grand Gulf Nuclear Station, Unit-No. 2-(Grand Gulf 2). Entergy Operations, Inc. (Entergy Operations), System Energy-_

Resources, Inc. (System Energy), Mississippi Power & Light Company and South Mississippi Electric Power Association (SMEPA) are licensees under the Permit.

For the reasons discussed below, Entergy Operations, on behalf :of itself.and the other licensees of Grand-Gulf 2, hereby requests the NRC to terminate the Construction Permit for the Unit.

The latest Completion Date for construction of Grand Gulf 2 in the Construction Permit is October 1,- 1984. - However, an application requesting an extension of the Latest Completion Date to January 1,1997 was submitted to the Staff in & letter dated April 23,1987-(AECM-87/2-0002). The NRC has not yet acted upon that-request._ Under NRC regulations, 10CFR2.109, the Construction

-the Permit is still in full force and ef fect until the NRC acts on-application.

Primarily because of financial limitations, the construction schedule -for Grand Gulf 2 was delayed several times in the latter part of_ the'1970's,-and from late 1979_until September-1985, only a_ limited amount of construction was performed on the Unit. Effective' September 18, 1985, all construction-activities on the Unit were suspended. A decision was made shortly thereaf ter to continue with full suspension of- construction until further evaluations were made regarding the future-of the Unit. Expenditures were: limited to those activities that were only' absolutely necessary for demobilization and suspension. As of March 1989, Grand Gulf was: approximately 29% complete based on the estimated man-hours needed.to complete the~UniL.

0 A9912041/SNLICFLR - 1 -

9101030001 901227

8) FDR ADOCK0500gf}7

AECM-90/2-0004 Page 2 In the Spring of 1989, a comprehensive report on alternatives regarding the future of Grand Gulf 2 was prepared. Based on this report and as part of a comprehensive settlement wi'.h federal, state and local regulators of outstanding issues and litigation surrounding System Energy and the Grand Gulf i

Nuclear Station, the Board of Directors of System Energy decided on June 1, 1989, to cancel and write off its investment in Grand Gulf 2. It was also decided at that time to allow the Construction Permit for Grand Gulf 2 to continue in ef fect for a period of time in order to allow Grand Gulf to sell as much eouipment and materiah from the Unit as possible while the NRC approved Quality Assurance Program was still in affect in accordance with the terms of the Construction Permit. This activity has now been completed as well as all other quality related Grand Gulf 2 demobilization activities.

Therefore, it is no longer necessary or desirable for the licensees of Grand-Gulf 2 to continue the Construction Permit in ef fect.

Cancellation of the Construction Permit for Grand Gulf 2 will not adversely impact the safe operation of Grand Gulf 1. Systems and equipment that were originally to be shared by both units, but are now used to support Grand Gulf 1 operations, will continue under the full control of Grand Gulf 1.

Also, activities at the Grand Gulf Nuclear Station site which would have been conducted under the authority of the Grand Gulf 2 Construction Permit are being addressed, as appropriate, in Grand Gulf 1 programs such as Physical Security Plan, QA Program, Ground Water Monitoring Program and the Hazardous Chemical Control Program.

All open and closed licensing commitments related to Grand Gulf 2 have been reviewed to confirm that cancellation of Grand Gulf 2 will in no way impact the safe operation of Grand Gulf 1. For commitments that were applicable to both units, the commitment was retained for Grand Gulf 1 to the extent it was still applicable. Any commitments unique to Grand Gulf 2 and which in no way af fect Grand Gulf 1 will be closed following cancellation of the Construction Permit. Commitments that were characterized as site related will be retained by Grand Gulf 1 to the extent applicable. Closed commitments were reviewed to ensure that cancellation of Grand Gulf 2 did not reopen a previously closed commitment and thus potentially impact Grand Gulf 1.

A review of Grand Gulf 1 Operating License Conditions was also done to assess any potential impact due to cancellation of Grand Gulf 2. Two license conditions of particular interest were noted: License Condition 2.c(27) and 2.c(38).

License Condition 2.c(27) was imposed to ensure that the construction and thus the filling of Grand Gulf 2 circulating water system would not present a potential flooding concern in Grand Gulf 1. The protection License Condition 2.c(27) provides will remain unchanged following cancellation of Grand Gulf 2 since there exist no plans to either complete or fill the Grand Gulf 2 circulating water system.

License Condition 2.c(38) was provided to allow control room boundary l penetrations to be open during construction of Grand Gulf 2 provided the inleakage did not exceed 760 CFM. At all other times, inleakage is limited to 590 CFM. The intent and requirement of this license condition will remain unchanged following cancellation of Grand Gulf 2. The applicable control room leakage will remain 590 cfm in accordance with present requirements.

A9012041/SNLICFLR - 2

AECM-90/2-0004 Page 3 Following cancellation of Grand Gulf 2, Entergy Operations plans to discuss further with the staf f the need for revision of License Conditions 2.c(27) and 2.c(38).

The Grand Gulf 2 site has been stabilized in accordance with all Construction Permit and UFSAR requirements. This includes the backfill of Grand Gulf 2 excavation site and the reseeding and turnover of formerly used construction sites to Grand Gulf 1 operations. Following complete turnover, which will occur by the end of 1990, Grand Gulf 1 operations will assume responsibility for maintenance and upkeep of the entire site. Final reclamation and restoration of the Grand Gulf Nuclear Station site will be addressed upon the decommissioning of Grand Gulf 1.

If you have any questions or would I;ke further information, p1<:4se let us know.

Yours truly, w '?~Csxa WTC/WKH:ams cc: Mr. D. C. Hintz Mr. R. B. McGehee Mr. N. S. Reynolds Mr. H. L. Thomas Mr. J. Mathis Mr. Stewart D. Ebneter Regional Administrator U.S. Nuclear Regulatory Commission l Region II 101 Marietta St., N.W., Suite 2900 Atlanta, Georgia 30323 Mr. L. L. Kintner, Project Manager Office of Nuclear Reactor Regulation

, U.S. Nuclear Regulatory Commission Mail Stop 11D21 Washington, D.C. 20555 l

A9012041/SNLICFLR - 3

ABCM-90/2-0004 Page 4 bec: Mr. M. A. Dietrich Mr. W. K. Hughey (2)

Mr. C. R. Hutchinson Ms. F. K. Mangan Mr. M. J. Meisner Mr. G. W. Muench Mr. T. E. Reaves Mr. F, W. Titus Mr. R. C. Townley Mr. G. A. Zinke File (LCTS)

File Hard Cony File (RPTS)

File (NL)

File (Central) ( 7)

A9012041/SNLICFLR - 4

CONCURRENCE. REVIEW FORM SECTION I g

RESPONSE DUE:

AECM 90/2-0004 Rev. 2 12/12/90 (NRC Required or Target)

SUBJECT:

Construction Permit No. CPPR-119 Cancellation of Unit 2 Construction Permit V. Y, Hughey N5 12////*?= W. Y. Hughey Sh _ fl ///jl f o NRC Document Preparer dat6 Responsible Section date' Managcr/ Superintendent Commitment Concurrence SECTION II Responsible Organization Locations Commitment Primary / Secondary Due Date None l

This letter contains commitments requiring procedural implementation YES ( ) NO (X)

A9012041/SNLICFLR - 5

SECTION 111 3

  1. T Concurrence

.Rhview Required Comments #

1 8

() (X)

VP, Engineering /Date (X) () MP W VP, Operations GGNS/DatyG'[./J iD

() (X)

Director, Nuclear Plant Engineering /Date

() (X)

CGN General Manager /Datn (X) () _

' '< - /2 /J fb D . tor, Nuclear '

L ensing/Date (X) () _ CH A N4e.14d C. R f f R. B. McGehee/Date*

I4(

sp' (X) () . -mya-}

' Director Plant hrojects &

Support *

  • Certification and concurrence per attached DOR.
  • OR;g:ss l AlCin ul4lt] /2/27lTo S y,,,j All C. o a c.a e tt ~ e cs [ c.u d;k(;w 6 p Qfc, . ,

gg,,9 ,4,g bA !2//y/ 9 o AcA I2/27/ 9 0 A9012041/SNLICFLR - 6

, i H OTION !!! _ddC/0-90[L CCO 4 4 316 G 99-l

=curat.

. Review Raquired y g Comments

'~

EP,T.ngineering/Date (X) ()

VP Operations 00N8/Date

()

(X) __

Oirector, Nuclear Plant Engineering /Date

() (X) 00H8 General Manager /Date _ _ _

(X) ()

Director, Nuclear Licensing /Date -

(X) () __

d6 _

m_; IB[12ho Tha tt,li Eit u$,h de,ew ene f R. B. McCahee/Date* vn T hi h e h h % u s; of % OQ Donne < inh W o o (X) () ,

Director, Planc Projecte &

Support *

  • Cartification and concurrence per-attached 00R.

A9012041/SNLICFLR - 6