ML20055G378

From kanterella
Jump to navigation Jump to search
Maint Team Insp Rept 50-333/90-80 on 900416-0511.Violation Noted But Not Cited.Major Areas Inspected:Overall Plant Performance,Mgt Support of Maint & Maint Implementation
ML20055G378
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 07/16/1990
From: Durr J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20055G377 List:
References
50-333-90-80, NUDOCS 9007230111
Download: ML20055G378 (54)


See also: IR 05000333/1990080

Text

\

,

Lp . *

'%

v

-

1.-

r U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report No. 50-333/90-80

License No. DPR-59

Licensee: Power Authority of the State of New York

P.O. Box 41

Lycoming, New York 13093

Facility: James A. FitzPatrick Nuclear Power Plant

Inspection at: Scriba, New York

Inspection conducted: April 16 - May 11, 1990

Inspectors: A. Delia Greca, Senior Reactor Engineer

E. H. Gray, Senior Reactor Engineer, Team Leader

G. K. Hunegs, Resident Inspector, IP3

R. Haroldsen, Consultant - Electrical

B. E. Martin, Consultant - Mechanical

R. McBrearty, Reactor Engineer

P. V. O'Connell, Radiation Specialist

'd.- Woody, Engineering Inspector, DOE

Approved by: 4%gre f /2. A /oM f f, a

acqud'P. Durr, Chief, Engineering Branch, d e

Division'of Reactor Safety

Summary: :See Executive . Summary

,

%'

h j

PDR

O

,

A

"

ds i.  ;

9
'* a

Cr u

kk .*

30

.l

ll i

pl'et

+

-s

& :i

N-

~

'

T

> TABLE OF' CONTENTS.

&, Tree .Page i

Designation. _N_o_. - .

,, -EXECUTIVE SUMMARY...................................... 4 I

+

?

);

-INTRODUCTION........................................... 7 o t

,

~

s I '0VERALL PLANT PERFORMANCE RELATED TO MAINTENANCE....... I 9  !

'

l .

.

1. 0 Di rec t ' Me a s u re s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1. 0 9

-

Historic Data ................................... 1.1' 9

Pl a ntl Wa l kdown In specti on ' . . . . . . . . . . . . . . . . . . . . . . . . '1. 2 9-

'

II MANAGEMENT- SUPPORT OF MAINTENANCE . . . . . . . . . . . . . . . . . . . . . II 12L .

2' 0 Management Commitment end Involvement ........... 2.0 12.

{

' Application of' Industry Initiatives .........-.... 2.1 12

j

.

g Management' Vigor and Example .

........ 2.2 13

3.-0 ' Management Organizationiand Administration

(Corporate and Plant)............................ 3.0 13

'

Program' Coverage for Maintenance ............,..., 3.1 L13  ;

~f;" Establish Pelicy, Goals, and Objectives ..........-3.2- 14

Resources A11ocation............................. 3.3 14

. Maintenance Requirements ...............-.........-. 3.4 1 41

Conduct Performance Measurements ~................. 3.5 15 ,

"'

, Document. Control-System ......................... 3.6- '16

Maintenance Decision Process .................... 3.7 17s

'

.o 4'0: Technical

, Support.................................-4.0 17 a

'

Establish Communication Chctnels ................ 4.1 17 .

-

. Engineer'ing Support'............................. 4.2 18

'

~ Role of PRA in-the Maintenance Process .......... 4;3 19

Quality Control.in the Maintenance Process ...... 4.-4 20- "

Radiological Controls in the Maintenance Process . 4.5 21-

'

,

Safety-Review of Maintenance Activities .......... 4.6- 23-

g -Regulatory Documents .in Maintenance . . . . . . . . . . . . . 4.7 24

,

LIIII MAINTENANCE IMP'LEMENTATION. . . . . . . . . . . . . . . . . . . . . . . . . . . . III 25

.

5.0L Work Contro1.......................... .......... 5.0 25 i

i

Maintenance in Progress .......................... 5.1 25-

Mechanical Maintenance ...... .............. 5.1.1 25

Electrical / Maintenance . . . . . . . . . . . . . . . . . . . . . 5.1.2 27

Instrumentation .& - Control s Maintenance . . . . . 5.1.3 28

4

1

'I

-

_ . - . . . . .

>- ,-

.: <-

, .-

'

,

. Table of Contents 3

Tree Page

Designation No.

Work Order Control .............................. 5.2 29

Equipment Records and History ................... 5.3 31

Work Planning ................................... 5.4 31

Work Priorities ................................. 5.5 32

Work Scheduling ................................. 5.6 33

Ba c kl og Control s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5. 7 34

Maintenance Procedures .......................... 5.8 34

Post Maintenance Testing ........................ 5.9 35

Review of Completed Work Documents .............. 5.10 36

6.0 Plant Maintenance Organization................... 6.0 37

Control of Plant Maintenance Activities ......... 6.1 37

Mechanical Maintenance .......................... 6.1.1 37

El ectri cal Mai ntenance . . . . . . . . . . . . . . . . . . . . . . . . . . 6.1.2 38

Instrumentation & Controls Maintenance ........... 6.1'.3 39

Control of Contracted Maintenance ............... 6.2 42-

Deficiency Identification and Control ........... 6.3 43

Maintenance Trending ............................ 6.4 44

Support Inte rf ace s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6. 5 45

7.0 Maintenance Facilities, Equipment, and

Ma te ri al s Con t rol . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7. 0 46

Maintenance Facilities and Equipment ............ 7.1 47

Material Controls ............................... 7.2 -47

Tool and Equipment Control . . . . . . . . . . . . . . . . . . . . . . 7. 3 48

Control and Calibration - M&TE................... 7.4 49

8.0 Personnel Contro1................................ 8.0 49

. Staffing Control ................................ 8.1 50

Personnel Training .............................. 8.2 50

Te st and Quali fication Process . . . . . . . . . . . . . . . . . . 8.3 51

Appendix 1 - Individuals Contacted

Appendix 2 - Summary of Weaknesses

Figure 1 - Maintenance Inspection Tree

,,- 1 ,

-,

%

. 4 '

EXECUTIVE SUMMARY

An in depth team inspection of the FitzPatrick maintenance program and its

implementation was performed on April 16 - May 11, 1990. The inspection

included a review of the maintenance program and observations of maintenance

work in progress. NRC Maintenance Inspection Guidance, dated September 1988,

and Temporary Instruction 2515/97, dated September 22, 1989 were used for this

inspection.

The inspection team evaluated three major areas: (1) overall plant performance

as related to maintenance (2) management support of maintenance; and (3)

maintenance implementation. For each element, the inspectors evaluated both

the program and the effectiveness of the implementation.- The inspection results

for each area are summarized in the following paragraphs and are discussed in

' detail in Sections I, II, and III in the body of the report.

I. OVERALL PLANT PERFORMANCE RELATED TO MAINTENANCE

From initial operation until the start of the current outage, the plant has

performed with high availability factors and minimal shutdowns resulting from

inadequate maintenance. Based on historic information, it may be concluded

that maintenance was effectively implemented during the first fifteen years of..

operation.

During plant walkdowns the team noted that, in general, all plant areas have

received adequate attention relative-to good housekeeping. However,- one

situation which could be improved is the identification of equipment and plant

areas. Equipment' tags were small or hard to find; sometimes no tags could be

found. Similarly, elevations and column locations were almost nonexisten'.. .

The only item of potential safety significance identified by the team is the

hanging of instrument calibration pots on cages around instrument racks

without seismic analysis. The pots were removed prior to completion of the

inspeccion.

II. MANAGEMENT SUPPORT OF MAINTENANCE

The maintenance program at JAF is based on a plan developed in late 1984.

Written policies and guidelines identify the responsibilities for developing "

the required procedures and for performing the work. Many of the work level

procedures were observed to be of recent origin or revision. This is indicative

o'f t program which is not fully mature but also undergoing an evolutionary

process' directed to improve maintenance.

The team found management to be generally supportive of improvements in the

maintenance program. This is primac 'y evident in the emphasis being given to

the training of all personnel involved in the plant's maintenance activities.

Noteworthy are the training ' laboratories which were found to be well equipped

p with mockup equipment and instruments. Some attention is being given to two

I

activities which enhance plant performance, Probability Risk Assessment (PRA)

. program and maintenance trending. However, the management goals for PRA have

not been established and maintenance trending is of limited scope.

y I  !

4

( .

$_

The-licensee has established systems to communicate between maintenance personnel

and other site organizations, including quality control, engineering and

operations. Good communication was observed in maintenance, modifications and

outage related activities. In addition, the daily interdepartmental meetings

were noted to be effective and productive and the organization and procedures

for engineering support appear to be working satisfactorily. However, a

formalization of interaction between performance engineers and systems engineers-

and a better uein,4;a of responsibilities, particularly in the failure

determination area, would be beneficial. '

t

Radiological controls to reduce exposure have been effectively integrated into

'

the JAF maintenance process. The program to ensure that modifications and

routine maintenance work receive an ALARA review is in place and workers were

observed to display good ALARA practices in the field.

III. MAINTENANCE IMPLEMENTATION

The licensee has developed an effective maintenance program which is efficiently

implemented and adequately controlled. Based upon the quality of work observed,

the experience level of the maintenance personnel is considered to be high. '

The mechanical maintenance staff was found to be knowledgeable and well trained

on all aspects of work performed, as were the electrical and I&C maintenance

s

groups. The-procedures for performing preventive and corrective maintenance

were considered to adequately support the individual programs. However, some

improvements could be achieved.by a better integration of the efforts of the

I&C and the electrical and mechanical maintenance departments.

'

The use of a work control center was found to be a good method for coordinating-

the activities of. the various departme ts involved and for authorizing work and-

tests. The method used by the licensee for documenting maintenance activities ,

and for maintaining equipment history and records appears to work well. However, t

the computer data base was not easily able to retrieve some records. In addition,

documentation of work control packages, post work reviews, and the program for

providing feedback to the various groups should be strengthened.

-The planning of scheduled and unscheduled work is generally wel'1 controlled

with knowledgeable planners directing the effort. Scheduling of preventive,

s corrective and predictive maintenance was determined to be adequate and

completed within the program guidelines. Adequate resources are allocated to.

manage and limit the work backlog.

-

The program elements for developing, approving and controlling maintenance

procedures were well documented. However, more attention should be placed in

ensuring consistency of format of the procedures.

'

, -.

,

'

.

6

Although the operations department's personnel responsible for post maintenance

testing-(PMT) are considered to be knowledgeable and experienced, the lack of

system engineer's input into the PMT determination and the use of generic in

lieu of more specific procedures are considered to be weaknesses in the PMT

program. The underlying concern is that PMT operational requirements may not

-

be recognized, particularly during periods of extensive maintenance activities.

The plant layout and personnel placement of the maintenance facilities were

determined to permit ef ficient operation of maintenance activities. Administra-

tive policies and procedures adequately control the specification, procurement

and receipt' inspection of maintenance related materials and equipment. Adequate

procedures also exist for the storage, tracking, accountability and issue of

safety related materials by-the warehouse. However, it was determined that a

large quantity of materials, including safety related components, after receipt

inspections, are turned over to the various maintenance groups, for unspecified

use. For uhese materials no specific procedures exist for their storage and

for tracking and controlling their use. This is a concern which requires

management attention. Identification , storage and issue of maintenance tools

and instruments were appropriately controlled.

Personnel performing calibrations were properly trained, and calibration

standards were ascertained to be traceable to the National Bureau of Standards.

Review of the licensee's personnel controls indicated that the maintenance

supervisory personnel receive periodic performance appraisals and that the

performance of bargaining unit personnel is informally assessed, on a continuous

basis, by supervisory personnel. Promotions are usually made.from within the

company with supervisory personnel advancing through various levels in the

department.

The testing and qualification of maintenance personnel were found to'be adequate,

as were the licensee's training and apprentice programs which are approved both

by INPO and the State of New York.

One non cited violation was identified with regard to the scheduling of EQ

related maintenance in the I&C area.

'

Appendix 2 contains a summary of identified weaknesses.

>

0

t

..

..

o ,

I

INTRODUCTION

Background

The Nuclear Regulatory Commission considers,the effective maintenance of

. equipment and components a major aspect of ensuring safe nuclear plant

operations and has made this objective one of the NRC's highest priorities.

To this end, the Commission issued a Policy Statement, dated March i

23, 1988, that states, "It is the objective of the Commission that all

components, systems, and structures of nuclear power plants be maintained

so that plant equipment will perform its intended function when required.

To accomplish this objective, each licensee should develop and implement a

maintenance program which provides for the periodic evaluation, and prompt

repair of plant components, systems, and structures to ensure their

availability".

.

This inspection was one of a series being performed by the NRC to evaluate

the effectiveness of maintenance activities at licensed power reactors.

The inspection was conducted in accordance with the guidanta provided in

,

NRC Temporary Instruction 2515/97 and the NRC Maintenance Inspection

Guidance. The v.mporary instruction includes a " Maintenance Inspection

Tree" that identifies for inspection the major elements associated with

effective plant maintenance.

,

l -Scope of Inspection

Site specific-information concerning the maintenance program was provided by

the licensee in. response to the letter' dated February 23, 1990. The team reviewed

.the information submitted by the licensee and planned for the inspection starting

, on April. 16,:1990. The team conducted the onsite. inspection at the FitzPatrick

. Plant from April'30 - May 11, 1990.

Daily meetings were held by the NRC team leader with plant management and

maintenance supervision to summarize the inspection team findings and identify

areas where additional information was required. On May 10 1990, an extended

meeting was held with responsible members of the licensee's organization. The

purpose of this meeting was to communicate the strengths, weaknesses, and

unresolved items identified by the team and to discuss the team's preliminary

findings. ' A summary of the inspection team's findings, including a presentation

of an evaluated maintenance inspection tree, was discussed with licensee

representatives including management, supervisors and engineers at the exit

,

meeting on May 11,1990 (see Appendix 1 for attendees).

, ^l

9

_. ,' 8

The Maintenance Inspection Tree

The inspection team's conclusions about the status of the plant's

maintenance program are indicated by colors (green, yellow, red or blue) on

the Maintenance Inspection Tree (Figure 1). For parts II and III of the

tree, the upper lef t portion of each block indicates how well the topic of

the block is described and documented in the plant maintenance program,

including the adequacy of procedures. The lower right portion of each

block indicates the team's conclusion as to the effectiveness of

implementation of the topic covered by that block. Green indicates that

the program is well documented or that the program implementation is

effective. However, even for blocks shaded green, some areas for

improvement may be indicated in the report. Yellow indicates e marginal

but acceptable condition and red indicates the topic is missing or the

intent of that portion of the tree is not being met by maintenance

activities. Blue indicates the item was not evalv:rrJ or could not be

properly evaluated due to recent changes.

Inspection Findings -

!

The inspection team's findings and conclusions regarding the FitzPatrick

Nuclear power Plant site maintenance program and its implementation are

documented in each section of the report. The weaknesses are listed in

Appendix 2.

,

i

i

I

I

_ _ _ _ . _ _ _ _ _ _ _ - _ _ . _ _ . _ _ _ . _ _ _ . - _ . _ _ _ _ _ . _ _ _ _ _ _ _ . _ _ _ . - _ _ _ _ _ _ _ _ _ _ . _ _ - - . _ _

.n - -

a

..

.

in: 'i

4

l

,, 9

3

I. OVERALL PLANT PERFORMANCE RELATED TO MAINTENANCE

~

1 .0- DIRECT MEASURES '

Scope

The scopt of this part of the inspection was to review the_ availability,

operability, and the material condition of the plant as it relates to the

implementation of an effective maintenance program.

Conclusions'

,

Overall, the condition of the plant, as observed during this maintenance

inspection, was found to be satisfactory. In general housekeeping was considered

good with all areas receiving adequate attention. Various conditions which

should be improved were, nonetheless, found. One such condition is the identifi-

cation of equipment and plant areas. Equipment tags were small or hard to find;-

sometimes no tags could be found. Similarly, elevations and column locations

were almost nonexistent.

The~ only item of potential safety significance identified by the team is the

hanging of instrument calibration pots on cages around instrument racks

without seismic analysis. The pots were removed prior to completion of-

inspection.

1.1 Historic Data

From initial operation until the start of the current outage, the plant has

performed with high availability factors and minimal shutdowns resulting from "

inadequate maintenance. Fuel integrity has remained high with resulting low

radiation contamination and health physics problems.

Based upon historic information, it may be concluded that maintenance was -;

effectively implemented during the first 15' years of operation.

11 . 2 Plant Walkdown Inspection

Scope i

The inspectors performed general plant, as well as selected system and component-

walk down to assess the general condition of the plant, including housekeeping.

Walkdowns included an evaluation of the buildings, components, and systems for

proper identification and tagging, accessibility, scaffolding, radiological

controls, and any unusual conditions. Unusual conditions included but were not-

limited to: water, oil, or other liquids on the floor or equipment; indications

of leakage through ceiling, walls or floors; loose insulation; corrosion;

unreasonable equipment vibration; excessive noise; unusual temperature; and

abnormal ventilation and lighting. Each time a team member was in the plant,

observations were made of these items and conditions.

l

l

If'

L ,

R

m 3 ,

..

I

.. 10

t

!

. Findings

'

In general, the plant appeared to be in good cc ditions and housekeeping appeared

to be adequate for a plant during an outage. However, the machine shop was

. observed to have trash and metal chips on the floor and tools and equipment

left.on work benches. Scaffolding in some areas did not have planking tied

down or' tags hung as required by P'. ant Standing Order PSC No. 51, " Erection of ,

Scaffolds Near Safety Related Equipment", Revision 4. A sheet of 1/16" asbestos-

gasket was found in the hall outside the north door of the maintenance office.

Further investigation into plant procedures revealed the licensee had no program i

in place for bagging / isolating or special handling of asbestos sheet gasket

material. The emergency diesel generator rooms were inspected and found to be

.in very good material condition.

One condition which requires management attention is the identification of

equipment rooms which was considered to be poor. Support columns did not have

plant location markings, and floor elevations were not marked. Also, equipment

and pipe systems exhibited token markings. This was considered to be a weakness

in the plant labelling program. The inspector also noted that PS0-60, Plant

Label Program procedure, was recently developed. The procedure describes a

program for labelling of system valves, major equipment, electrical distribution,

instrumentation, and plant areas. Labelling is scheduled for completion by the

end of 1992.

Equipment out of service was tagged. The tags referenced the correct equipment

I

and were filled out consistent with' established plant procedures.

Deficiency tags were attached to equipment needing corrective maintenance. Two

deficiency tags were observed to be several months old (Ref: (1) WRED 71-68366,

AC UPS Generator Breaker Pilot Light (will not light), dated September 28, 1989

and (2) WRED 10-69419, Liquid Sample Valve 10COV204 on RHR Pump B, (no closed

indication), dated June 21,1989). The inspector determined that in both cases

there had been a deliberate decision to postpone the corrective maintenance

until the refueling outage. The deficiencies were verified to pose no significant

risk to plant safety.

Generally, the condition of equipment and materials was considered satisfactory

to maintain operability of components at a level commensurate with the components'

function.

Motor control centers and electrical cabinets were found to be adequately clean.

Condu;ts penetrating fire barrier walls and floors were observed to have fire

stops in place. Some unused wires were observed in the Power Transformer No. 4

control junction box JB-NSS4 which were not tagged and not terminated on junction

blocks. These were verified to be spare wires that were shown as spare wires

on plant drawings. There is no requirement to label individual spare wires at

JAF.

Some dry boric acid crystals were observed at the base of one of the boric acid

injection pumps indicating that there had previously been some leakage at this

pump. This condition was called to the attention of plant personnel.

_ . . . _ _ . _ . _ _ _ . .

_ _ _ _ _

.

.

'

,

11

On the north end of the main steam tunnel, a main steam branch line 1" SDD-902-3C

was found to be bent. This bend was not shown in plant drawings FP-27C Revision 10

and 11825-6.25-18A. An Adverse Quality Condition Report (AQCR)90-090 was

subsequently written to remove insulation and investigate the bend.

During a review of the general condition of safety related instrumentation

within the reactor building, the inspector observed that instrument calibration

water pots, weighing approximately 15 pounds, had been mounted on the grating

of several rack enclosures. The . inspector also noted that some washers were

slightly larger than the grating holes and that the grating itself was rather

flimsy. In'one case ty-raps had been used for restraining the instrument.

Because damage could occur to safety related inttruments if the calibration

pots separated from their supports, during a seismic event, the inspector asked

the licensee if calculations existed which showed the ..ceptability of the

restraints used. By the end of the inspection, the licensee could neither

justify the installation nor satisfy the recommendations of Housekeeping and

Cleanliness Control Procedure WACP 10.1.7, Exhibit 9.2,5, dated March 1, 1990,

which requires the use of a " chain or wire of 1/4" size or larger." Therefore,

they removed the calibration pots and agreed to perform an engineering evaluation

prior to permanently reinstalling them.

Reactor water cleanup return line isolation valve 12MOV69 was observed to be

installed without T-drains. However, prior to the end of the inspection, the

licensee provided documentatton which showed that no T-drains were required-

for that specific application.

A walkdown was made to assess the plant's compliance to fire protection

requirements, All lumber located in the work areas was properly treated and

considered to be flame retardant. Accumulation of combustibles was kept to a

minimum with maintenance workers periodically collecting trash from their job.

Wherever welding was performed, a flame retardant material-made of fiberglass

was used to-surround the activity and control sparks. Fire extinguishers were

also on hand, in case they were needed. All fire extinguishers inspected had

been properly certified in accordance with plant procedures.

l

. . _ . . . _ _ _ _

_-_-_

'

,

.

, 12

11. MANAGEMENT SUPPORT OF MAINTENANCE

Scope

The scope of this part of the inspection was to determine through appropriate

examinations the degree of management support of the maintenance process.

Included in these examinations were the application of industry initiatives,

and participation of management in the maintenance process.

2.0 MANAGEMENT CNMITMENT AND INVOLVEMENT

SJL0 ele

The scope of this section is to determine management involvement in supporting

and using industry initiatives, and providing leadership in maintenance training,

self evaluation and use of historical plant data.

Conclusions

Licensee management has initiated several significant programs to optimize the

performance of plant maintenance. These include the 1984 planned maintenance

program, self assessments of maintenance, the corporate nuclear maintenance

program manual, an extensive training and qualification program, interaction

with nuclear industry groups and other nuclear utilities, the development of

systems engineering cap:bility and the formation of specialized task groups

including the planned maintenance task force (PMTF). On the basis of these

management initiatives, it is concluded that management has had a high level

of commitment to and involvement in the maintenance process.

2.1 Ayp11 cation ai industry Initiatives

The licensee is a participant in various nuclear industry groups that provide

a forum for interchange of plant maintenance experiences with other nuclear

utilities. Th3se industry groups include INPO, EPRI and NUMARC. The plant

uses the NPRDS data system for reporting and tracking plant problem components

and participates in the INPO nuclear network system.

The plant has a systems engineering program with assignments and responsibilities

defined in procedure PS0-1. The system engineer is the focal point for

information collection and assessment in regard to system design, operations

and maintenance.

On the basis of licensee involvement with industry groups, and its use of

information obtained through both formal and informal contacts with industry

committee memoers and those at similar nuclear plants, the maintenance

inspection team found that tut licensee has aggressively applied useful

industry initiatives.

I

_

'

.

.

.

,

,

13

1

2.2 Management Vigor and Example

Licensee management has demonstrated their interest in plant maintenance and

operations by several initiatives. These include issuance of the implementation

plan for the planned maintenance program by memorandum, dated November 9, 1984.

This maintenance plan included many of the attributes included in the NRC

maintenance inspection tree that are essential to a properly functioning

maintenance program. Progress in implementing the planned maintenance program

was monitored by various means including the conduct of a series of self assess-

ments, each of which identified actions aimed at improving plant maintenance.

The Corporate Nuclear Maintenance Program Manual, issued in February 1990, presents

the corporate policy on the nuclear plant maintenance program. This policy

manual states the background, policy, requirements, responsibilities, authority,

references and documentation needs for the primary areas of maintenance.

3.0 MANAGEMENT ORGANIZATION AND ADMINISTRATION (CORPORATE AND PLANT)

Scope

The objective of this section was to assess the effectiveness of the organization

and administration of the maintenance functions and the maintenance program.

The specific areas inspected to provide a broader perspective of maintenance

activities included: the existence, availability and scope of a formal mainten-

ante program; maintenance policy, goals and objectives; allocation of resources;

identification and definition of maintenance requirements; maisetenance

performance measurements, the documentation control system for maintenance;

and the maintenance decision process.

The maintenance program at JAF is based on a plan that was developed in 1984

(Ref: Memorandum, W. Fernandez to Distribution, J0PS-84-133 dated

Neve.tbcr 9, 1994;. Written administretion pnlicies and guidelines identify the

responsibilities for maintenance including the development of work level

procedures and schedules. Work level procedures have been developed that

control most scheduled and routine maintenance activities.

Many of the current work level procedures are of recent origin or have undergone

recent revision. This reflects the evolutionary process that has beer. followed

at JAF to improve the maintenance program. It also indicates that the maintenance

program is not fully mature.

3.1 Program Coverage for Maintenance

The maintenance program at JAF is described in a multi-level hierarchy of

documents. The corporate maintenance program is described in NUAP-5.10 and in

the Corporate Maintenance Program Manual (CMPM). Responsibilities for

administration, review and updating the program are described in administration

docume,,ts AP-1.1, 1.4 and 3.1. The program is further supported by Work

Activity Control Procedures (WACPs), Quality Assurance Procedures (QAPs), Plant

Standing Orders (PS0s), Maintenance Department Standing Orders (MD50s),

Instrumentation and Control Department Standing Orders (ICS0s), Operating

Department Standing Orders (OD50s), Technical Service Department Standing Orders

(TSS0s) and a group of radiation control documents.

,

--- ---mmmi-i----------is--e,

___-

5  !

.

'

, 14

Special training is necessary to make plant personnel knowledgeable in the ,

complex system for conducting work and of the relevant documents and procedures.

Coordination at the working level is the responsibility of the Work Control 7

i

Center (WCC). The inspector determined through interviews and observation that

individual workers had a good working knowledge of the procedures and documenta-

tion for conducting work tasks.

l

3.2 Establish Policy, Goals, and Objectives

l

Management goals and performance indicators are published in PS0-36. -This [

document is updated annually. Goals and commitments are tracked according to

PSO-35 and PSO-58. The inspector determined by interview of plant personnel

that supervisory personnel were aware of administrative policy, goals and.

objectives.

Weekly planning meetings are conducted by the WCC at the worker level. These

meetings are used to resolve conflicts and verify or assign priorities to work  :

tasks. The inspector observed that maintenance worker; utilized approved  ;

procedures for most tasks. Occasional deficiencies or ambigaities in the 3

procedures were observed. In these cases, the worker tended to make -

discretionary interpretations of the procedures. However, workers are trained

not to proceed on any work not specified in a work request.

3.3 Resource Allocation

Direct observation of maintenance activities, review of completed maintenance

actions,_and a review of selected performance indicators show that JAF management

has allocated sufficient resources to maintenance activities. Personnel are

generally available in sufficient number with satisfactory training and

qualifications.

'

During normal- plant operation, essentially all maintenance personnel are full

,

time employees. During refueling outage, the number of employees is approximately

l doubled by use of contract and temporary personnel and the standard work hours

are extended to 6 ten-hour days per week. Night shifts are added on an as-needed '

basis. Turn-over of permanent plant personnel has been low. Shop and tool *

areas are adequate. A new warehouse is under construction to provide better

parts control and'to alleviate some crowding in the administration and turbine

buildings.

3.4 Maintenance Requirements (Corporate and Plant)

The maintenance program at JAF includes surveillance, preventative and corrective

maintenance. The surveillance and preventative maintenance includes some of

the attributes of predictive maintenance.

Scme specific predictive maintenance activities are being routinely conducted

on pi e components. These include chemical analysis of oil samples from

selected electrical and mechanical equipment. 011 sample points are being

installed on some equipment to facilitate the sampling process. Vibration data

are being collected from some mechanical components and thrust, current and time

' data are being collected from motor operated valves.

<

. _ - _ _ _ _ - _ _ _

.

4 P

, 15

Baseline data have been collected and stored in computer data bases to permit '

trend analyses as data are accumulated. This program is formalized for some

plant components, but is presently limited by incomplete baseline data and data

base computer programs.

The Plant Maintenance Task Force (PMTF) was formed to provide continuing review .

and improvement in the plant maintenance program. The responsibilities of the

PMTF are described in plant maintenance document PM-01. It mandates an ongoing

program for implementing regulatory requirements, defining component maintenance

tasks and frequency and review of component maintenance history. The procedures

for implementing this program are described in plant documents PMTF-3, 5 and 6.

The inspector determi%d that there are 4 levels of priority for corrective ,

maintenance work:

'

1. Emergency - Requires immediate action.

2. Priority 1 - To be corrected within 1 week.

3. Priority 2 - To be corrected within 1 month.

4 Priority 3 - To be corrected when convenient. -

All plant personnel are encouraged to initiate corrective maintenance actions ,

by either filling out a maintenance request form (MR) and attaching appropriate ,

deficiency tags to the relevant components or by informing plant supervision of

a problem. The MR is then evaluated by the responsible group supervisor to

determine if action-is required. If action is required, a work request is

processed in accordance with established procedures.

3.5 Performance Measurement

T'e licensee conducts performance measurements in accordance with Performance

Engineering Procedure PEP 2.1.2, " Weekly Unit Performance $1onitoring",

Revision 0, dated Noved er W 9. This procedure addressr:$ a standardized method

for collecting, storing, analyzing, and reporting the data monitored, and

provides a means of early detection of degradation in the monitored system

parameters and equipment performance. Data acquisition is obtained from the

licensee's Emergency Plant Information Computer (EPIC) system printouts and

.

'

logs. Adverse conditions having a significant effect on the ef ficiency or '

availability of the plant are brought to the attention of the performance

engineering supervisor through this system.

The information is entered by the performance engineering group into various

,

computer programs which analyze the data, calculate correction factors and

variables and produce performance spreadsheets and graphic plots of the data.

The spreadsheets and graphs are examined for trends or v.11ues that affect plant *

performances, reliability or efficiency. Although the scope of monitoring is

limited, the licensee is making progress in this area, as evident by the reports

reviewed.

.

,

':

.

..

i

+ 16

,

'

In addition to the above, the licensee has instituted PSO No. 58, " Management

Observer Program", Revision 2, dated February 1990, which uses management ,

personnel to observe housekeeping, overall plant performance, and reliability. '

Management observers, as defined by the PSO, are the resident manager and his

staff down to the assistant department heads. Areas of observation are, to  ;

some extent, limited by the PSO, in that each observer will only observe tasks ,

in two of the eight departments identified in the PSO. Observations are

conducted on a designated time frame and, upon completion of the observation,

they are submitted through a Management Task Observation Report to the

Superintendent of Power. When reviewing the report file, the maintenance team ,

' inspector observed a number of missing reports from the last quarter of 1989. .

The licensee had previously. identified this concern in January of 1990; however, '

no corrective actions were taken. The file was not well maintained..  ;

3.6 Document Control System '

Th9 inspectors evaluated various procedures in place at JAF to ensure that

proper document control included establishment of accountability, authority,

documentation requirements, and responsibility. The inspectors also reviewed

the plant procedures to ensure that updating and traceability of plant i

documentation was addressed. A partial list of related procedures includes:

Administrative Procedure API.2, " Plant Operating and Review Committee" which

directs the periodic review of plant procedures; API.4, " Control of Plant

Procedures", which establishes requirements for initiation, review, approval,

revision, temporary changes, withdrawal, and control of plant procedures; AP3.1,

" Procedure for Maintenance Procedures", establishes a format for the procedures

and relative characteristics; Maintenance Department Standing Order, MD-50-16,

"Mair.tenance Work Planning and Routing of Work Requests", which establishes

controls for pre-job planning; Plant Standing Order, PS0 41, " Operation of

Archival Storage Facility", which establishes guidelines for operation of the

licensee's archiving process and storing of plant documents; PS0 46, " Procedure

for Control of Vendors Manuals", which establishes control and Ostribution of +

technical vendor manuals throughout the facility; and Work Activity Control

Procedure, WACP 10.1.1, " Procedure for Controls of Maintenance and Engineering  :

'

Assistance Requests", which describes program for reporting plant system material

deficiencies, for performance of corrective maintenance anc repair of equipment,

for controlling performance of equipment modifications, for initiating request

for work ' permits, and for initiating requests for engineering assistance or

plant modifications.

The majority of the documents reviewed for this element have been established

for some time and are being implemented.

1.

l

l

r

c- . . . . . - . . . . . . . . . . . .

-

. ..

. . , ,

.

.

.

17

3.7 Maintenance Decision Process

The inspectors reviewed the Corporate Nuclear Maintenance Program Manual,

various plant procedures, and engineering documents to determine the extent to

which JAF's management is directly involved with decisions regarding maintenance

activities. The inspectors concluded that the program for equipment upgrade,

for replacement of plant components and for evaluating effects of plant aging

could be strengthened. In the past, the licensee's management did not give

high priority to plant aging considerations, but they are aware of ongoing

discussions on this subject. Decisions for upgrading and replacing plant

equipment, in the past, were addressed on a case by case basis, depending on

necessity and system parameters. Corporate engineers as well as site system

engineers and equipment specialists take part in assessing the need for action.

Although the licensee's final maintenance goals are being achieved with good

results, the inspectors concluded that, due to the lack of guidance documentation,

the consistency of future program implementation could be at risk.

4.0 TECHNICAL SUPPORT

The inspector assessed the area of technical support by evaluating the extent

to which engineering principles have been factored into the maintenance process.

This was accomplished by evaluating the performance of the various engineering

organizations, studying plant procedures, sampling work packages, and observing

maintenance activities. Other organizations whose performance was evaluated

included Quality Control, Safety, and the Planned Maintenance Task Force (PMTF).

4.1 Engineering Comtaunication Channels

The inspector evaluated channels of communication throughout the course of the

entire inspection noting situations that required communication and evaluating

performance in this area.

The primary written method of communication between the plant organizations and

engineering is accomplished through a request for engineering assistance by

plant procedure WACP10.1.1. This procedure states that engineering assistance

can be requested "to perform evaluations, desire for mods, etc.", subjecting

the use of this procedure to wide interpretation by plant personnel. Therefore,

virtually any plant situation requiring engineering review compels the use of

WACP 10.1.1. Other instances which require maintenance personnel to communicate

with engineering are contained it. specific maintenance procedures. Certain

situations in these procedures specify that maintenance personnel are to consult

with the cognizant engineer, if unusual conditions exist. Engineers are also

kept apprised of maintenance concerns through their participation in the

maintenance daily planning meetings,

. .. .. .

- - - - - - - -

.

.

. _ .. . .. ..

l

'

o 3

.

, 18

The inspector found evidence of other forms of communication being carried out

between the various engineering organizations which are not covered by plant

procedures. The use of performance memoranda by performance engineers, to

convey adverse system / component failure trends to system engineers, is one

example. A similar situation was also noticed with the PMTF organization and

the system engineering group.

Conclusion

Formal and informal communication between the engineering organizations and the

maintenance department are effectively being accomplished. Engineering

participation in maintenance activities and mutual respect between these

organizations were both evident. However, some plant documentation covering

several key situations which require communication does not exist. Communication

at the plant would be enhanced by formalizing the interaction between the per-

formance engineers /PMTF and the system engineers. The licensee recognizes

this problem and has committed to formalize these lines of communication.

4.2 Engineering _ Support

The inspector examined the area of engineering support by evaluating the program

established for performing failure determination and analysis, assessing the

use of NPRDS data for identification of potential problems with systems / components,

and evaluating the effectiveness of the system engineering program.

Engineering responsibility for failure analysis is contained under the Technical

Services organization and within the maintenance organization. Both groups are

responsible for performing the analysis. However, the criteria for when either

group is responsible for performing it are vague. For example, MD-S0-16 requires

maintenance engineers to perform failure analysis of all Category 1 and M

components not already subject to engineering reviews, but the procedure doesn't

specify which type of failures are subject to engineering reviews by other

organizations. Involvement of system engineers was noted whan a system / component

failure was safety-related or involved a modification. Thit observation was

based on conversations with system / maintenance erpineers and not apparent in

plant procedures.

Failure analysis is also being performed by the Performance Engineering

organization for use in NPRDS. Performance engineers review all plant work

requests to search for failure data reportable to the NPRDS. If adverse trends

are noticed through excessive failures, a performance memorandum is written to

inform the system engineer. In addition, the Component Failure Analysis Report

(CFAR) compares plant component failure rates to industry averages. The

inspector determined that NPRDS data, including the CFAR, were being appropriately

used by system engineers. However, plant documentation related to CFAR's was not

in place.

l

_ _ _ _ _ _ _ _ _ - .

__ _ _ _ _ _ _ - _ - . . - .

'

, f

.

. 19

!

The effectiveness of the system engineering program was evaluated by the f

inspector. The general support for this program by management and other '

organizations was favorable. The system engineers are adequately involved in i

plant activities including: performing evaluations in conjunction with i

unusual occurrences; active participation in tests conducted for evaluating -

system performance; and appropriate review of outside operating experience. l

Initiatives have also been taken by the System Engineering Supervisor to improve ,

the effectiveness of the program such as documenting prioritized goals for the- >

program, and developing system reference books. Some inadequacies, however, '

,

were identified in the. System Engineering Program procedure, PS0-1. Most notable i

was a requirement for trending of system parameters. This was not being performed

by the system engineering program, nor was there evidence of developed plans to

do so. Other prob 1 cms included reference to the use of the PRA which doesn't

exist, and lack of guidance on when to use the System Engineering Memorandum.

The licensee recognized these procedural problems and is in the process of .

modifying PSO-1. i

Conclusions

The overall level of support from the engineering organizations to the maintenance

process was determined to be good with certain noted exceptions. Clarification

is needed in delineating responsibilities for failure determination and analysis.

Integration of plant procedures related to this area would be beneficial, A >

program to perform analysis of adverse failure data identified in the CFAR is

not documented. It was recognized that many of these programs are new and 4

that the licensee was evaluating the best method for conducting business prior

to documentation. The licensee is committed to correcting these problems through +

modifications to the plant procedures.

4.3 . Role of PRA in the Maintenance Process ,

The purpose of this section of the inspection was to determine the extent to #

which the Probabilistic Risk Analysis (PRA) or the risk. concept is ccnsidered ,

in all aspects of the maintenance process. This includes not only planning,  ;

scheduling, and prioritization of work, but also engineering evaluations, i

Risk based concepts are presently.not considered in the planning, scheduling,

and prioritization of maintenance activities at JAF, Discussions with the

licensee indicate they plan to have the PRA completed by the end of 1990.

However, there is no evidence of documented goals for the use of the PRA once

it it nmpleted. The fact was also noted in a memorandum from the QA Super--

.intendent, dated August 24, 1989, which notes there _is no program to assure

that the benefits of the PRA can be implemented in a timely manner. Despite .

the lack of a formal PkA and integration of its concepts into the maintenance

process, the inspector found that risk has been considered in various situations.

For instance, the inspector noted the use of fault tree analysis by Technical

Services to examine the need for an emergency diesel generator fuel cutoff valve.

Also, the Planned Maintenance Task Force used risk concepts to rank the importance

of JAF check valves to be inspected during the 1990 refueling outage.

, s

>

, _. _

. _. . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _

,. $-

,

,- 20

i

Conclusions ,

The use of risk assessment concepts was found in a few areas-of the maintenance

process. However, management goals have not been established to consider the ,

use of the PRA. This includes consideration of how it will be used in planning,

scheduling, and prioritization of maintenance activities.

4.4 quality Control in the Maintenance Process

f

The inspector evaluated the presence of Quality Control (QC) in the maintenance

'

process. _This was accomplished by looking at the involvement of QC inspectors  ;

and reviewing the systems which are in place for reporting and correcting

quality deficiencies. *

QC inspections are essentially established by the maintenance department, when

'

a maintenance procedure is initially written. These procedures are reviewed by f

the QC department for verification of proper inspection points. Several

completed work packages were reviewed by the inspector, and it was determined -

that QC inspection points were appropriately assigned and followed. Instructions '

for these inspections are contained within the maintenance procedures themselves,

and they were found to be generally adequate, with a few noted exceptions. In

work request #77288, involving maintenance of a motor operated valve (MP59.41), i

the procedure was unclear in a section requiring a QC inspection point. QC [

corrected-this inadequacy by using a temporary modification to the procedure.

Other cases have occurred due to the fact that many maintenance procedures are ,

new.

!

The lack of criteria to aid in the determination of appropriate QC inspection

' hold points was noted by the inspector. At present, the establishment of these

points is based on the discretion of the individual responsible for writing the

maintenance procedure, and subject to appropriate QC review. Plant wide

guidance in this area would ensure consistency of maintenance procedures. The ,

licensee noted this deficiency and plans to correct the problem through che -

development of guidelines for all plant inspections.  !

The QA department has an established program in place for the entification, I

documentation, and correction of quality deficiencies. The pro,eam was found

to be very comprehensive, covering deficiencies related to materials, equipment

malfunctions, procedures, and processes. A mechanism was in place for escalating-

Adverse Quality Condition Reports (AQCR's) to high levels of management for

resolution. The inspector found the escalation process was being actively used

with a few exceptions. One example was AQCR 88-017 which was not escalated

, properly and, as a result, has remained unresolved since 1988; this particular

example was determined to be an isolated case of inadequate escalation. i

l

,

,

-

-

.

.

--

_ _ _ . _ _ _ _ . _ _ _ _ . . . _ . . . . .. ..

2 .

t

=

,

' *

, 21

The procedure associated with corrective action of AQCR's requires that a root

cause analysis be performed by the responsible department. Guidance for

performing this analysis is not in place, and formal training for root cause

analysis is not available to plant personnel. The licensee has taken steps to

rectify this deficiency through the initiation of a plantwide Corrective Action

program. This program will integrate several plant procedures related to causal

analysis and provide training to employees in the recognition of adverse

conditions and performance of causal analysis.

Conclusions

The QC department is actively involved in maintenance activities and was

considered to be functioning well. It was determined that documented inspection

criteria guidelines would ensure that a consistent approach is taken with regard

to preparation of maintenance procedures. The quality deficiency program is

functioning well, but needs more concise guidance with regard to root cause

analysis.

4.5 Integration of Radiological Controls into the Maintenance Process

Scope

The purpose of the inspection was to determine the extent to which radiological

controls are integrated into the maintenance process. This area was reviewed by

observing ongoing maintenance activities, by reviewing Radiation Protection's

involvement in the planning and preparation for :upporting maintenance work,

-and by reviewing the licensee's program for maintaining exposures as low as

reasonably achievable.

Findings

For the 1990 refueling outage, the licensee set the As Low As Reasonably

Achievable (ALARA) exposure goal at 500 man-rem. This goal included 200 man-rem

for routine operations and 300 man-rem for outage related work. Previous annual

cumulative exposures for refueling outage years were 785 man-rem in 1988 and

940 man-rem in 1987. The licensee anticipated that, with the dose rate reductions

achieved with the recirculation system's decontamination effort, undertaken

during the 1988 out' ige, and with the initiation of the primary system's zinc

injection program, begun in 1989, the dose rates inside the drywell would be

significantly lower than those encountered in previous outages. Based on the

anticipated work a:tivities in 1990 and the historic exposure data, it appeared

that the licensee had set a reasonable 1990 ALARA goal.

As of the end of April 1990, the licensee's exposure reached was 425 man-rem,

which was 210 man-ree over the exposure goal for the period. The licensee stated

that this was primarily due to unanticipated high dose rates inside the drywell

end to the additional numuar of weld overlays required to be completed during to

current outage.

.

, t-

. i

.

22

At the beginning of the current outage, radiation surveys indicated that the

dose rates inside the drywell were significantly higher.than anticipated.

Therefore, during the inspection, the licensee's management met with the vendor

for the zine injection program to evaluate the effectiveness of the program in

reducing the source term. The licensee has decided to continue, at least for

'

the immediate future, with the zine injection program. Meanwhile, the licensee  :

is evaluating the possibility of another recirculation system's decontamination

effort during the next refueling outage.

In addition to the zine injection program . sed the recirculation system

decontomination, the licensee has in place other programs to reduce the source '

term at the facility. These include a cobalt reduction program and a hot spot

identification and abatement program. As part of the cobalt reduction program,

the licensee has replaced several control rod blades with cobalt free control

rod blades. Although the source term at the facility remains relatively high,

management appeared to be committed to reducing it and their involvement in ,

this matter was considered good.

The licensee has established criteria for determining which maintenance tasks

require an ALARA review. These criteria require an increase in the level of

ALARA review for maintenance activities involving higher man-rem exposures and

a follow-up review for those tasks that significantly exceed the ALARA estimate. ,

The team reviewed several ALARA reviews for radiologically significant maintenance '

work and found them to contain appropriate ALARA requirements such as increased

mock up training to reduce the individual's time in radiation areas and ensuring

that adequate shielding is in place. In general, the licensee's program to

ensure that outage maintenance work inside the radiologically controlled area 1

receives an ALARA review is adequate.

The tearr reviewed the licensee's mock up facilities. Mock up equipment includes

a rtcirculation pump seal cavity, control rod drives, weld overlay equipment,

hydraulic control units, as well as various valves and electrical breakers. The

licensee has also initiated the use of new valve actuation testing equipment i

which reduces the amount of time individuals must stay in radiation areas while

. conducting valve actuation tests, The vendor for the new equipment spent one

week onsite training licensee personnel on the proper use of the equipment.

Discussions with training supervisors, ALARA personnel, and maintenance workers

indicated that the licensee was making effective use of the mock up equipment

to minimize personnel exposures.

The team also noted that ALARA training is provided to workers in the General-

Employee Training. By direct observation and discussions with workers, the team

determined that workers are aware of the need to minimize exposures and do take

ALARA precautions while conducting work.

.

'

.

'

, 23

,

The team conducted several tours to assess the upkeep of the facility, including

housekeeping. In general, the housekeeping and material condition of the reactor

building appeared to be adequate. The team observed several areas of the turbine

building where improvement could be made in the general housekeeping and several

instances where used oily rags and protective clothing, including coveralls,

booties, cotton liners, and gloves, were left on top of equipment or on the

floor and not placed in containers, as required. The team also noted a mop,

labelled as contaminated, and oil from equipment, also labelled as internally

contaminated, which were left uncontained on the floor.

The team observed maintenance activities and reviewed Radiation Work Permits

(RWP) for work inside the drywell. The radiological coverage for maintenance

activities inside the drywell was generally good. The team reviewed several

RWPs for maintenance work in the reactor building and turbine building. The

team noted that several of the RWPs for High Radiation Area entries did not

require that the individuals making the entry be provided with a radiation

survey instrument, an alarming dosimeter, or be accompanied by an individual

qualified in radiation protection procedures and radiation survey instruments.

In addition, the RWP did not specify the frequency at which periodic radiation

surveillance was to be conducted. This matter is discussed in the report for

NRC Inspection No. 50-333/90-17 which was being conducted at the same time as

the Maintenance Team Inspection.

Conclusions

The licensee has implemented an adequate program to ensure that modification

and routine work inside the radiologically controlled area receive an ALARA

review to reduce cumulative annual personnel exposures. The licensee also has

made effective use of mock up facilities for training personnel; workers

demonstrated good ALARA practices in the field. Improvements need to be made in

the general housekeeping of the turbine building. Overall, the integration of

radiation protection into the maintenance process is considered good.

4.6 Safety Review of Maintenance Activities

This portion of the inspection focused on the consideration given to safety in

the performance of maintenance work. Safety at JAF is integrated into the

maintenance process in a number of ways.

The safety program at JAF has under gone recent improvements as a result of an

increasing number of work related injuries. The new program was implemented in

January,1990 and includes a list of initiatives primarily aimed at increased

Safety Supervisor responsibility. These initiatives include more participation

in Maintenance Department daily planning meetings, and a more proactive safety

violation program. The safety program has also attracted more management

involvement, and the inspector observed participation in safety meetings by the

Superintendent of Power. This new program, however, has not been integrated

into the plant procedures. Though no firm commitments were made, the licensee

indicated that this effort would be undertaken sometime in 1990. 1

,

a

i

.

., t

.- ,

. .

. 24  ?

During routine walkdowns, one team memoer. noted the presence of uncovered  :

asbestos containing gasket material outside the mechanical maintenance area.

Though asbestos handling procedures are ir. place, they are not informative of

this type-of plant situation. The licensee is presently reevaluating procedures ,

to determine proper storage and handling requirements for this type of material.

Conclusions .

The site safety _ program was only recently est0blished at JAF, and has generated. ,

renewed attention from management and plant workers through the effective use

of safety violations. Although too early to assess the impact to the number of '

work related injuries, there is evidence that the overall awareness of safety

has recently improved. In order to make this program more visible, plant -

procedures should be modified. In partic.ular, the plant procedure for the I

-storage and handling of asbestos 3hould be reevaluated to consider all possible  :

'

plant situations.

4.7 _ Regulatory Documents

-

The system in place to ensure that regulatory documents are factoried into the

maintenance _ process was examined. The inspector observed that management

controls are in place for controlling regulatory document.t. These controls ,

. include the establishment of_ focal points to ensure that changes to these

documents are properly administered. - Assistance is also gi/en in this area by

-system engineers, who are responsible for ensuring consistency of system ,

'

operating characteristics in documents such as technical. specifications and the

FSAR, The licensee has also established a computer tracking system, known as '

the Action Commitment Tracking System (ACTS), to track documents such as NRC

commitments.

The Planned Maintenance Task Force (PMTF) has a program in place to ensure that

regulatory documents are factored into the preventive maintenance program.

This. requirement is established through procedure PMTF-03. Accordingly, the

PMTF is required to search designated regulatory documents for applicability

prior to establishing equipment preventive maintenance. frequency.

Conclusions ,

The licensee has established adequate measures to ensure that changes to

regulatory documents are factored into the maintenance process. Both, plant

and corporate m agement have been helpful in giving regulatory documents the

proper attenti a.

i

w

_ _ .

'

,

t

"

.

.

, 25

III. MAINTENANCE IMPLEMENTATION

Scope

,

s

The purpose of this part of the inspection was to determine the effectiveness

of the established maintenance controls and, more importantly, the quality of l

work performed. The controls established in four areas were evaluated: work -

control; plant maintenance organization; maintenance facilities, equipment and

materials controls; and personnel control. The team evaluated the effectiveness

of these controls through observations of work in progress; through a review of

completed work orders, procedures, and other documentation associated with

maintenance, training of maintenance personnel, tools in stock, and spare parts;

and through discussions held with all levels of personnel.

>

'

5.0 WORK CONTROL

t

Scope

The purpose of this part of the inspection was to determine .ae effectiveness- '

of maintenance work controls, and the quality of work performed. The controls

established in the following areas were evaluated in determining the effective-

ness of the maintenance program: review of maintenance in progress, work order

control, equipment-records and history, job planning, work priorities, work

scheduling, backlog controls, maintenance procedures, port maintenance testing,

and review of completed work documents. The evaluation of the above sections

.

of the maintenance work control program included such areas as observation of l

maintenance in progress, review of completed M'/Rs, inspection of selected systems

and components and discussions with perse:inel.

Conclusions

The licensee.has tatablished an effective maintenance program which is

effectively implemented. Most work is of high quality and adequately controlled.

5,1 Maintenance in Progress

The review of maintenance in progress was evaluated by considering work

performance in accordance with procedures and station policies, goals and

objectives. *

5.1,1 Mechanical' Maintenance in Progress .

,

The inspector observed work in. progress in conjunction with snubber functional'

testing, snubber removal and replacement, and snubber overhaul / repair. Additional

work observed included the check valve In-Service Testing (IST) Program, repacking ,

of "B" condensate pump, replacement of main feed check valve 34NRV-111A, and.

repairing of various motor operated valves, including service water and emergency

service water system valves.

,

s

-_ --_ -_

,

.

.-

!

>

.

.

. 26

!

,

Positive interactions between maintenance personnel and various engineering '

groups was evident during the inspectors observation of check valve In-Service

Testing-(IST). Furthermore, maintenance personnel were observed assembling ,

various service water system check valves while the Quality Lontrol Department

was video taping the valve internals and adjacent piping utilizing state-of-the-art

fiber optic equipment. Additionally, the engineering technical staff was on-hand

to evaluate and to determine appropriate actions, as necessary. Procedures

were followed and steps were properly initialed and dated. QC personnel were 3

on-hand and available from job initiation to completion. The team work and ,

synergism observed during this maintenance activity was considered a strength. '

The snubber functional test program was observed to proceed well, despite the

number of functional tests- failures (5 hydraulic and 2 mechanical) recorded.

As a result, more than 160 snubbers were functionally tested or planned to be ,

functionally tested during this outage.

Three teams of qualified personnel performed within the frame work of this i

program: (1) Snubber test stand operator and QC technician; (2) Snubber repair

bench mechanic and QC technician; and (3) Snubber removel/ installation mechanical '

personnel and QC technicians. ,

After a snubber has passed the functional test, a QC accept tag is attached, i

and is made available to replace a designated snubber of the same size in the  ;

plant. QC ensures'that the specific plant location and the unique snubber *

. identifier number is recorded. Metal identification tags are also installed on

the snubber. If a snubber fails its functional test or an abnormal condition ,

exists, it is inspected and repaired. Newly tested and installed snubbers are

painted orange to aid in location identification. The. snubber program engineer i

is responsible for the selection of snubbers which need functionally testing, ~

as per Technical Specifications Section 3.6.1/4.6.I. The observation of the

overall implementation and operation of this program by the inspector was -

considered to be a strength.

The-inspector also observed maintenance work in progress concerning (1) The B

Emergency diesel generator (EDG) power assembly maintenance and preventive-

maintenance, (2) standby liquid control pump A discharge surge accumulator ,

repair, (3) installation of residual heat removal (RHR) and core spray (CS) .

pump motors.

Generally, the mechanics were knowledgeable, maintenance procedures were adequate.

and being followed, and good worker attitudes were observed. Good communication-

was observed between maintenance and quality control personnel. The inspector -

observed good interaction between first line supervisors and their mechanics. '

One problem was identified with the core spray pump maintenance. The inspector

observed that two openings in piping associated with the core spray pump were

not sealed to prevent intrusion of foreign objects; covers were promptly installed

once identified.

<

. . , .

.

y ,

.

c

, 27

,

Conclusions

The inspector concluded that mechanical maintenance activities were adequate

and were accomplished by skilled maintenance personnel. The maintenance

personnel appeared knowledgeable and well trained on all aspects of the work

performed. QC involvement was evident throughout the work observed and the >

overall organization of the maintenance activities was considered a strength, ,

5.1.2 Electrical Maintenance in Progress '

Findings $

The inspector observed the following work in progress:

--

Preventative maintenance on 600 volt, 23MOV31 Limitorque Motor Starter per

procedure MP 56.1

--

Preliminary functional test of RHR isolation Valve 10MOV17 (preliminary

VOTES test)

--

Replacement of brushes on UPS Motor Generator per procedure MP 58.2 1

--

Baseline test of RCIC Turbine Steam Valve 13MOV131 per procedures MP 59,38 '

and 59,40 (MOVATS test)

--

Annual service discharge test of 125 Volt Station Battery 71SB2 per

procedure MP 57,6

The inspector observed that the technicians appeared knowledgeable in the plant -

requirements and of the work being performed. A spot check of the training

records of the participating technicians showed that each had received training

for the task being performed.

With the exception of the functional test of the RHR valve 10MOV17, all work

was conducted according to written procedure. The inspector was told that this

valve had been recently overhauled and that new baseline test data would be

taken according to approved procedures following the preliminary functional

. test being observed,

The inspector noted that preparation for the observed work was adequate, with-

-consideration given to proper approvals, use of calibrated test equipment,

tagging procedures, quality control and safety. The work requests forms

indicated the safety category (1, 2 or 3) of the applicable components. However,

work procedures at JAF are the same for all safety categories. Quality control

and supervisory personnel were observed to be present for most safety category

1 work. Except for the preliminary functional test of the 10MOV17 valve,

appropriate as-found and as-left parameters were recorded. Post maintenance

testing was also included in the procedures when applicable.

_ _ _ _ _ .

!

'

'

.  :

.

A

, 28

l

The procedures used in the observed work were all revised just prior to the i

refueling outage. The procedures were found to be sufficiently clear and easy i

to follow by reasonably trained personnel. However, some instances of ambiguity

or deficiencies were observed. For example, in procedure MP 56.1, there is an l

implied requirement (on page 24) that the technician'should verify that the  ;

motor starter overload heaters are rated a minimum of 300*4 of full load amps,

for safety-related MOVs and 100's for non-safety-related motor loads. Since the

motors are remote from the motor starter and often inaccessible the technician

does not have any simple method for making this verification.

This concern was submitted to the licensee who responded that the maintenance

procedure would be revised to require that the technician verify overload heater .

ratings, as found in the field, against plant drawings. Current plant drawings

do not include this information but are being revised to include it.

,

Conclusions  :

Field observations indicate that maintenance work performed by electrical

personnel at JAF is reasonably well managed and that the written procedures are

generally acceptable. Where procedures are lacking, improvements are being

made and the ingenuity and good training of technicians has been sufficient to

overcome imperfections in the present system.

5.1.3 Instrumentation & Control Maintenance in Progress

Findings

The inspector observed work being performed by several technicians in the

Instrument & Control (I&J) group. The work primarily consisted of instrument

. calibrations which are periodically performed to ensure system performance

within design specifications. The inspector also witnessed work in progress

associated with a High Pressure Core Injection (HPCI) modification and a post

modification test associated with Scram Discharge Instrument Volume. +

While witnessing the above work, the-inspector noted that good maintenance

practices were employed and that quality control check points were employed.

The quality of work observed and discussions with supervisors and technicians

involved indicate that I&C personnel are generally knowledgeable in the plant

, requirements and in the tests being performed. The-inspector also reviewed

l training records of representative technicians and found them to be appropriate

- for the tasks being performed. In all but one case, test' equipment and tools

were adequate and used within the calibration period. The exception observed

involved a current generator requiring weekly calibration and being used to

test the accuracy of some ammeters. In this case, the calibration period had

expired. However, the technician was using a calibrated ammeter in series with

the output which assured the required accuracy.

- - _ - _ . _ _

,  : .e

o o

O'

._

. 29

Revii., cf work packages of activities being observed revealed that approval

signatures and authorizations had been obtained and that the latest-documentation,

.

'

including vendor manuals, was being used. Tagging of equipment out of service

was adequate as well as housekeeping and cleanliness. Supervisory personnel

were observed to provide adequate oversight and, for safety related work which

required Quality Control (QC) approval, a QC person was available. Also, general

i safety and ALARA rules were observed and technicians were noted taking radiativn

exposure readings in the area of the work activities.

Within-the scope of the inspection, only two minor deficiencies were observed.

In one case, where an HGA relay was being calibrated, the procedure followed

pertained to the calibration of a similar relay, type HMA. In addition, the

training module for relay calibration pertained to yet another relay, type

HFA. Discussions with the technician and his supervisor revealed that, though

inappropriate, the procedure did permit its use for HGA relays and that the

latest vendor manual did not specify calibration requirements.

The other case involved the post modification testing of the Scram Discharge

Instrument Volume instrumentation. The test required recording the as-found

calibration of the transmitter and recalibrating the loop according to the

applicable procedure. -It was determined later, a leaky-instrument isolation

valve prevented the technicians from maintaining the system at the required

pressure for a period of time long enough to take accurate readings. As a

result, the recording of as-found readings was not considered to be very

accurate by.the inspector. However, for.the recalibration effort, the

responsible technician, after various unsuccessful attempts to stabilize the

output, decided to stop the test and evaluate the appropriate course of action, j

Conclusions

Field observations of 1&C personnel performing maintenance activities indicated

that good maintenance practices were employed and that technicians were generally

knowledgeable of work assigned to them, However, some minor deficiencies were

observed which could be resolved with more attention to details.

5.2 Work Order Control

Scope

-The. inspector's objective in this area was to evaluate the effectiveness of the

maintenance work control process to ensure that plant safety, operability and

reliability are maintained, The following areas were evaluated:

l

--

Maintenance in Progress

---

-Work order control

l

--

Equipment records history

1

,

I

l

1

'!

. _ _ -

. ,  !

<

,

.

. 30 J

--

Work prioritization and backlog control

--

Maintenance procedures I

--

Review of completed work and post maintenance testing

Findings

The inspector reviewed the licensees method of work control. WACP 10.1.1, J

Procedure for Control of Maintenance and Engineering Assistance Requests is  ;

described in the administrative program for work control. This procedure

provides for reporting plant system material deficiencies; performing corrective  ;

maintenance and repair of equipment at the plant; controlling the performance

of equipment modifications; initiating requests for various work permits; and.

initiating requests for engineering assistance or plant modifications. It

includes the administrative procedures for initiation, minimum planning,

authorization, testing and documentation of work. WACP 10.1.1 is implemented  ;

by the work control center. During outages, the work control center (WCC) is  :

operated by two senior reactor operators and two clerks. The,e persons are '

knowledgeable and well qualified for these positions. However, one area which

was considered to be inadequate was the method for identification cf rework in

.

'

that it relies on the memory of personnel staffing the WCC. )

1

WACP 10.1.2, Equipment and Personnel Protective Tagging, is tr.3 procedure that

sets the requirements to ensure protection of equipment and personnel from

injury or damage during operation, test or repair . The inspector reviewed the

PTR-files and determined that work is being accomplished in accordance with

procedures. However, one problem was identified with the conduct of the D'

emergency diesel generator (EDG) idle speed inspection. The emergency service .

water (ESW) strainer ~ and supply header drains were inadvertently left open,

after moving-the boundaries on the equipment tagout for the ESW system. It

appears that the review performed to ensure that the new boundaries were adequate

to conduct maintenance and lack of a system lineup contributed to the problem.

The licensee made an operations department night order book entry and conducted

a formal critique ~concerning the problem. '

Conclusions

The use of a WCC appears to be a good method for coordinating work between

various. departments and for authorizing work and testing. Work is effectively

identified, prioritized and tracked.- Effectiveness is, in part, due to

significant. verbal interaction between various groups rather than to the

organization. Some problems have occurred due to the large volume of work ,

centrally ca irnlied and due to lack of attention to details. *

.

f

.

4.

,

-. :

.

.

..

31

5.3 E

3 uipment Records and History

Scope

The inspection objective was to assess maintenance history for plant components

and to determine the extent to which equipment records are used for trending,

planning and scheduling maintenance activities. Plant history records, NPRDS

data,

area.

and root cause analysis reports were elements used in evaluating this

Findings

Equipment history and records are accessed through a number of computers located

throughout the plant- .

These records are also available on microfiche. The

computer database can be accessed through a number of different files such as

component, system, or activity codes. The information from the various work

control forms is entered into the computer database by the WCC clerks. The

database appears to be accurate and up-to-date. However, the inspector had the

following two concerns in the maintenance history record area: a)-The nature

of the computer database is such that the plant's maintenance history records

may not be easily retrievable or in sufficient details to be of any value, b)

-Failure analysis and root cause evaluation are a recent program and not fully

implemented.

Procedure WACP 10.1.18, Control of the Plant Master Equipment List,-has been in

place for approximately two years. The master equipment list (MEL) is a computer

based file designed to be an unambiguous source for QA classification. The ,l

engineering information group updates the MEL The data, after entry, is

verified and second checked. Access- to the MEL database is through computer

terminals assigned to the various user groups.

Conclusions

The licensee has an effective method of maintaining equipment history and

records,. however the computer database may not be easily retrievable and some *

records contain minimal information. Failure analysis and root cause evaluation

programs are not fully implemented.

5.4 Work Planning

Scope

-The inspector observed maintenance activities to determine the adequacy of the

planning function in providing guidance in the areas of safety, coordination of

activities, technical accuracy, completeness of data packages, scheduling,.

special instructions, and exposure controls.

,

w

h

i

(l j 'S

.

im . ,

I . t

[ , 32

'

E

Findinas

-

The inspector reviewed various aspects of work planning in use by the licensee  !

ano discussed the planning process.with work planners. Some considerations j

used for planning include the assigned work priority, work that can be efficiently  :

performed with other scheduled work, and conditions that will deteriorate with l

time. A maintenance plenning checklist is provided with key attributes to assist

the planner in completing his task. The licensee currently has two mechanical

and two electrisal personnel performing the planning function. In general.  !

most planning was adequately performed with effective use of the maihtenance e

planning checklist. However, a few problems were identified with the planning '

for some work. For instance, the inspector observed one work order (WRED 71838,

replacement of brushes on the UPS MG) in which the planning was inccmplete,  ;

1.e., approved parts and not-applicable sections of the installation procedure ,

nad not been identified . Consequently, the work technician performed these-

elements of the planning task himself. In addition, several work request ,

packages in the mechanical maintenance area, ready for closure, were found to  !

contain no checklist. Maintenance planners are taking some good initiatives

which enhance the performance of maintenance activities. Examples of this are -

inclusion of system drawings and polaroid pictures of the work and work area to '

assist the mechanics in determining the component location in the system.

Conclusions

The planning for both scheduled and nonscheduled work is generally well controlled  ;

with bowledgeable planners directing the effert. A few examples of.in:omplete

or nonexistent planning were noted which appear to be due to inattention to

detail and the volume of work during the refueling outage.

5.5 Work Priorities

.

Scope

'The purpose of this inspection area was to evaluate the maintenance work

prioritization methods and criteria.

Findings

Priorities are assigned on the work request form using guidance provided in '

WACP 10.1.1, Procedure for Control of Maintenance and Engineering Assistance

Requests. Four levels of priority are used. The levels are designated as >

emergency, priority 1, 2, and 3. The guidance for determination of priority is '

adequate and useful to those individuals who make the determination. Review of

several work requests showed that the level of priority is being accurately 3

assigned using the guidance provided.

Work priorities are used in the work scheduling process to ensure that work

with higher priority receives the necessary level of attention.

!

,

y

_

. 1

, 33

!

!

!

One weakness identified was the lack of use of probabilistic risk analysis (PRA) l

in determining work priorities. This is further di> cussed in section 4.3, Role

.of PRA in the Maintenance Process. -1

!

Conclusions l

Work prioritization is performed by knowledgeable personnel, and is. adequately  ;

determined. The program could be enhanced by including risk evaluation or PRA  ;

factors in the process.  ;

5.6 Work Scheduling

S_CPlle j

The purpose of this inspection area was to determine if maintenance scheduling l

and backlog controls are established and to evaluate the methods used to  !

identify and control preventive, corrective and predictive maintenance.

Findings

Scheduling of maintenance during plant operation is coordinated by the work

control center (WCC). The WCC supervisor compiles a list of work requests that

are considered to be most important to plant operation and that can be worked

during normal operation. This priority list is used by the maintenance and I&C ,

departments for planning and scheduling purposes. Routine maintenance tasks

are discussed, scheduled, and tracked by the WCC, in -conjunction-with other

departments, during daily and weekly scheduled meetings. The -weekly scheduled

meeting is chaired by the planning = superintendent. -The purpose of the weekly.

planning meeting is to establish the next week's work schedule, discuss-upcoming ,

work, coordinate activities between departments, arrange limiting conditions ,

for operation (LCOs), and general problem solving discussion. Special. conditions

are applied prior to. entering an LC0 to better control,the maintenance activity, i

A list of high priority work items to be performed during short forced outages.

is also maintained for planning purposes. Maintenance and refueling outage  ;

activities are' determined by the planning superintendent. A system window

. concept is used for scheduling maintenance activities. Periods of time are

determined for systems- during which all maintenance activities for that system

, are to be scheduled. it appears that this method-provides good administrative

? controls to prevent necessary redundant equipment-from being taken out'of

service. l

Conclusions

Maintenance scheduling for preventive, corrective and predictive maintenance = is "

identified and completed within the program guidelines. The WCC, during

operation, and the planning superintendent, during outages, adequately schedule

work activities. ,

,

___-

,

.* ,

-.

C

'

.. 34

5.7 Backlog Controls

Scope i

The purpose of this inspection area was to determine the effectiveness of

backlog controls and the adequacy of the bases for deferral of maintenance

activities.

,

Findings

i

The licensee's backlog and monitoring system was reviewed. Important parameters -

related to maintenance are measured and tracked on a monthly report. These  !

parameters are used to manage the maintenance department workload. Some of the

items tracked include non-outage corrective maintenance backlog greater than 3 .

months old, out of service control room instruments, preventive maintenance

items overdue, total number of work requests open and items awaiting final ,

administrative close out. Review of tracked data for the past year showed that

the maintenance backlog was being appropriately managed.

Conclusions ,

The licensee has a backlog monitoring system that includes a monthly trend I

report. The maintenance superintendent has been actively involved in monitoring

the status of backlog items and has the necessary resources to adequately manage

the backlog of maintenance items.

5.8 Maintenance Procedures *

1

Scope .

The inspection objective was to assess the development and approval process,

the technical content, the method of control, and the periodic review process ,

of maintenance procedures.

Findings

,

The inspector reviewed the licensee process for maintenance procedure development  ;

and implementation. Procedure development, control, review and use is controlled

by a number of- different utility procedures. AP-1.11, Procedure Writers Guide,

provides detailed guidance-for preparation of procedures. -AP-1.4, Control of. .

Plant Procedures, provides guidance for procedure initiation, review, approval,

and revision. A checklist is- also provided to aid the reviewer in completing

the procedure reviews. Other procedures provide guidance for special processes,

instrument maintenance, and surveillance tests.

The-inspector reviewed several preventive and corrective maintenance procedures.

.The procedures were technically correct and capable of being used. However,

'

several procedures were not consistent with AP-1.11. For example, " cautions"

are used where a " warning" should be used, prerequisites and notes contain

action steps, signature blocks are not provided for QC, and some procedures do >

not have an expiration date assigned. The nature of these errors is such that '

they should not adversely affect the conduct of maintenance.

,

, _ . , _ . .

_ _ . . . . . . . . . . . .. .

,

.'

'

.

. 35

- Computer programs are used to assist in tracking biennial procedure reviews.

The program to complete biennsal procedure review was judged to be functioning

well.

Conclusions

The maintenance procedure development, approval and control program elements

were well documented. More attention needs to be placed in ensuring consistent

procedure format.

5,9 Post Maintenance Testing

Scope

The inspection objective was to determine whether post maintenance testing

criteria were established, documented and implemented. The effectiveness of

the post maintenance testing program was assessed based on operational readiness

and evaluation of established acceptance criteria.

Findings

The Corporate Nuclear Maintenance Program, Chapter 11, Post Maintenance Testing,

describes the policy which is to ensure that plant equipment or systems are

capable of performing its intended function af ter corrective,. preventive or

predictive maintenance or af ter modifications are performed on that equipment

or system. Various procedures implement the policy and guidelines. NYPA

classifies post maintenance testing (PMT) as post-work testing (PWT). These

terms are considered equivalent for the purpose of this inspection report. The

post-work testing program is controlled by WACP 10.1.1, Procedure for Control

of Maintenance and Engineering Assistance Requests. This procedure includes

Addendum 9.4 which provides generic guidelines for determination of PWT recuire-

ments. The inspector was concerned that the use of generic guidelines incead

of a more specific procedure may result in inadequate PWT determination. Other

procedures discuss system engineer interaction and PWT scheduling.

The inspector reviewed several work request packages, located in the PWT pending

file, to determine the adequacy of PWT. In general, existing instrument surveil-

lance and operations surveillance procedures are used to verify operability of

safety-related equipment. No specific discrepancies were identified with the

-adequacy of PWT. The filing system currently suffers from a lack of space.

The licensee is addressing this issue in the form of plans to enlarge the WCC.

PWT requirements are determined by a senior reactor operator (SRO) and checked

by a second SRO. The shift supervisor (SS) verifies satisfactory completion of

tests and restoration of the component to service. The determination of PWT

relies upon the knowledge and personal skills of the SS and of the SR0s who

work in the work control center. System engineers are minimally involved in

the PWT program. Procedure PSO-1, System Engineer Program, formally empowers

the System engineer to assist in PWT determination, but, in practice, PWT is

primarily determined by operations personnel.

'

4

,

c.. l

. .

[ - .. 36 j

'

'

Conclusions

The lack of system engineer input into the PWT determination and use of generic

PWT guidance instead of more specific procedures are considered to be a weaknesses

l- in the PWT program. The concern is that some PWT operational requirements may

not be recognized, especially during periods of extensive maintenance activities.

Nonetheless, the inspector recognizes that the operations department's personnel

which are responsible for the PWT program are knowledgeable and experienced and

, perform this function well. However, the success of this system is mainly

dependent upon personnel skills who are currently assigned to the task.

5.10 Review of Completed Work Documents

S.cgge

The objectives of this inspection area were to assess the process for licensee's

.

'

review of work documents, general completeness of work documents, ard feedback

from review of the maintenance process.

Findings

WACP 10.1.1, Procedure for Control of Maintenance and Engineering Assistance

Requests, describes the administrative program for work control documentation.

This and various other procedures provide for review, storage and tracking of

records. A checklist detailing the documentation requirements is provided to

assist the responsible departments' administrative efforts. Although there are

several mechanisms to pr^ vide feedback to various groups, the feedback process,

. in practice, is usually accomplished through the morning planning meeting or

other informal methods,

A weakness was noted in the program, in that work packana dor mentetivt is it

tiaies incumplete. Some specific examples include: the final work package

review was not completed on PMWR 09137 and many procedure steps were not signed

off in the supporting procedure, MP-56.1, 600V Motor Control Center Maintenancs

and; Testing; WR 70568, CRD water pump A casing leak repair, was a rework but

was not identified on the computer list as such; not all work requests have the.

activity code number in block 6 of the work request form indicated; and the

e time required-to complete the work is not usually documented.

Conclusions

. The review of completed work control documents shows that additional attention

needs to be placed in completing the required work control packags documentation

and for conducting post work reviews. The program for providing feedback to j

various groups needs to be strengthened.  ;

!

'I

, ._ -.

, e +

'

'

'

.. 37

6.0 PLANT MAINTENANCE ORGANIZATION

Scope i

The scope of this portion of the inspection was to determine the effectiveness  !

and extent of control exercised by the maintenance organization for: (a) main-

tenance activities -(b) contract maintenance personnel, (c) deficiency

identification and control, (d) maintenance trending, and (e) support interfaces.

6.1 Control of Plant Maintenance Activities

Scope

The inspection objective was to assess the extent that the mechanical,  ;

electrical, and instrumentation and control disciplines have established

controls for performing maintenance activities.

6.1.l~ Mechanical Maintenance

The inspectors interviewed personnel at various management levels and found -

them to be knowledgeable of their responsibilities. The staffing of the ,

mechanical section, in the maintenance department, appeared to be adequate for t

-an outage. They were sufficiently supplemented with contractor and temporary '

personnel and were adequately integrated into the department's work force. .The

inspectors reviewed the licensee's plant maintenance organization and the

maintenance and administrative procedures used to direct and control maintenance. -

Selected station maintenance procedures and work request packages were also

reviewed. Additionally, the inspectors observed work in progress on mechanical '

components, interviewed first line supervisors, and the maintenance mechanic

journeymen.

Specific observations are listad below:

'

l

During the installation of internal parts on main feed check valve 34NRV-11A, 4

work was required to be stopped. It was discovered that the shaft could not be

inserted into the valve body due to a bushing that had been lef t in place during

di sa s sembly. The valve.in question was new and was being installed with a newly

written procedure. The work was supervised by the Vendor's Technical

Representative (VTR). When the inspector asked why the bushing had not been

removed,-the VTR stated he was responsible for the oversight. Subsequently,

the bushing was removed and the internal parts were installed in proper order

without further incidence. Although this was an isolated event, it appears

,

t

that a firmer control of the VTR actions should be in place.

When observing the assembly of new interr.a1 parts for the outside main steam

isolation valve, 29A0V-868 a digital caliper (M-113), used for measuring the

dowel' pin in the assembly, was found to be without its proper identification

number attached, as required in Maintenance Department Standing Order MD-S0-04,

" Maintenance Department Measuring and Test Equipment Calibration Program",

' Revision 7, Section 7.'la. However, this digital caliper did have the proper

,_ ..-

I l

. 38

usage log card in its carrying case. Upon further investigation, the same

deficiency was observed with another digital caliper (M-116). The licensee

took.immediate corrective actions and provided proper markings on the calipers )

in question. l

The JAF main technical library was inspected by the maintenance team. This

area was found to be neat and well organized, and centrally located in the

administrative complex for easy access to plant publications. The techrical

manual update program was reviewed by the inspector and found to be satisfactory. '

These manuals are located in a controlled area, and may be checked out when

neeoed. Maintenance personnel are aware of the availability of these manuals.

The inspector reviewed various completed maintenance work packages with respect

.to use of qualified personnel, prioritization, quality control (QC) involvement,

quality of documentation, equipment history, description of problems and

resolutions, and post maintenance testing. The inspector concluded on the

basis of the documents examined, that the licensee, in general, had adequately 1

addressed these items. However, the team also found that the " Action Accom- '

plished" and "Cause" sections of the work tracking form were not always utilized

to their fullest extent. Additionally, in one case, some areas in the work

package procedure that asked for specific information were left blank.

Specifically, when an adverse condition was found, during a check valve

inspection, the spaces for comments and for apparent cause were left blank.

Also, the signature of the cognizant engineer was missing.

Conclusions

The mechanical maintenance personnel appeared to be knowledgeable, displayed a

positive attitude towards their assigned tasks and were observed to be well

trained. Gentrally, good communications existed between maintenance personnel

and other groups, First line supervisors conducted daily meetings with their

workers to discuss daily assignments and to receive craftsmen feedback. However,

the licensee's review for completeness of the work packages needs to be ,

strengthened.

6.1.2 Electrical Maintenance

Electrical maintenance at JAF is controlled by a complex system of formal

procedures. Numerous approvals are required on all work requests before work

can begin. Most of the required approvals are obtained by a single action

within the Work Control Center (WCC). The WCC provides an approval chain that

includes representation from the interfacing disciplines such as QC, Safety,

Radiation Control,.0perations and Planning. During normal plant operation, the

WCC operates under the jurisdiction of Operations. During plant outages, the

WCC operates under the direction of the Planning Department.

I

..

., 9

.

!

..

. 39

,

The Maintenance Department also has planners who review work requests and

perform preliminary work such as procurement of qualified parts. A properly

processed work request results in a work order with specific directions on work

to be done, procedures to be used, applicable sections or exceptions to the

procedures, and parts and tools necessary for the job. However, this procedure

is not rigorously followed. As an example, the inspector observed one work

order (WRED 71838, replacement of brushes on the UPS MG) in which the planning.

was incomplete, i.e., the approved parts had not been identified and the  :

not-applicable secti W of the installation procedure had not been identified.

Consequently, these elements of the planning task were performed by the work  !

te:hnician himself.

host of the written preventative maintenance work procedures cover a variety of

maintenance subtasks on a family of similar components. When a work request is  :

initiated, it is necessary to determine what written procedures are applicable

and what sections of the procedures are applicable. When this portion of 4

planning is' neglected at the supervisory level, it defaults to the work level

technician. While this process displays some weakness, no instances were

observed where it had safety significance.

The maintenance department at JAF maintains a log of scheduled preventative r

maintenance tasks that have been delayed beyond their due date. The inspector

reviewed this log and determined that some preventative maintenance tasks on

MOVs had been deferred for more than a year past their due date. The licensee

responded to this. concern by showing that there had been no deferments of -

technical specification required surveillance or EQ related maintenance. The

MOV preventative maintenance had been deferred because the MOV maintenance  ;

program was undergoing massive upgrade (as recommended by INPO) and the main-

'

tenance on most MOVb was limited to plant outage. Additional training was also

necessary to implement the new procedures. The inspector noted that the number

of deferred tasks is rapidly being reduced. At the beginning of the outage

there were a total of 73 deferred tasks. At the time of the inspection 18 had

been completed and 30 more were scheduled prior to startup. The remaining

twenty-five tasks were scheduled af ter startup.  ;

The inspector noted that the working interface between electr Nal maintenance

and I&C maintenance is not defined in any written document and that the interface

follows an unwritten general understanding between the persornel of the two

departments. Since I&C maintenance operates within a differtnt department there

is a possibility that some components could be overlooked by lack of a clear

jurisdictional definition. The inspector looked for evidenco of forgotten

components but found none. The missed annual maintenance of a 500 KW LPCI

inverter, which falls under I&C jurisaation, is discussed under Paragraph 6.1.3 y

below. The inter face between I&C and electrical maintenance is not a problem

for corrective maintenance since the WCC will assign the task to one organization

or the other.

,

+

>..

, .

.

4 40

The working relationship between I&C and electrical maintenance appears to be

excellent and no instances were observed where the interface between electrical

maintenance and I&C had created any problem. There was, however, one instance

observed where work was not coordinated within the maintenance department. As- r

a result, the floor of the 125 Volt station battery room was painted too soon

prior to the battery service test for the paint to dry.

Conclusions

The inspector concluded that the electrical maintenance staff had a well

developed program for performing corrective and preventive maintenance.

Instances of imperfection in the maintenance procedures were overcome by a

highly-trained and competent staff. Imperfections in the maintenance program

are recognized and there is a continuing trend toward improvement.

6.1.3 IJstrumentation & Controls

The inspector observed work in progress in the instrumentation and control (I&C)

discipline and interviewed various maintenance craft personnel that were

performing the work. The inspector found that the I&C activities witnessed

were well planned, the craft personnel were knowledgeable of their required

tasks, and the steps outlined in their maintenance procedure were followed.

The I&C maintenance organization is a-separate group <hich operates outside the ,

maintenance organization, with its own Superintendent snd procedures. Some of

these are parallel to the procedures developed for the (electrical and mechanical)

maintenance department. Although the boundaries of jurisdiction between I&C

and the maintenance department, especially electrical, are not clearly defined,

the two organizations. appear to operate well and without confusion as to the

areas of responsibility. However, the annual preventive maintenance for the

LpCI inverter was not included in the I&C maintenance data base. In addition,

one requirement was. found to be implemented differently by the two organizations.

While reviewing the I&C computer printout of maintensnce required to maintain

qualification, the inspector found that a 10*4 time margin had been used to

perform that activity. The method-used to develop the schedule was consistent

with the I&C applicable procedure. However, the margin had been added to,

rather than. subtracted from the expiration date of the equipment's qualified

life but no components had passed the correct expiration date. Upon identifica-

tion, the licensee immediately initiated corrective actions. These included:

(1) revision of computer schedule; (2) review of schedule to identify overdue

maintenance, if any; (3) scheduling repl cement of 12 pressure switches prior

to refueling outage (only items with overdue date but already scheduled for

replacement per Modification No. MI-89-038); and validation of EQ schedule.

The inadequate scheduling of required maintenance constitutes a violation of

10CFR 50.49, Section (e)(5) which states that " Equipment qualified by test must

be preconditioned by natural or artificial (accelerated) aging to its end of

installed life condition... If preconditioning to an end of installed life

condition is not practicable,... The equipment must be replaced or refurbished

at the end of its designated life..."

- - - -

,__

,

e

,-

,' 41

_

In accordance with the NRC Enforcement Policy, 10CFR Pa~t ? Am adix C, the

violation is a severity level V (Supplement I). Howevei, occaua the safety

significance of the violation is minor, corrective actions wa - initiated prior

'

to the end of the inspection period, and the criteria specified in Section V. A

- of 10CFR Part 2, Appendix C, were satisfied, the violation is not being cited.

. (50-333/90-80-01)

--

The primary mechanism for identifying I&C corrective maintenance is the work

request which is submitted to the work control center for evaluation and

scheduling. The procedure that controls the process for identifying, scheduling,

and tracking to completion of I&C maintenance activities, as in the case of

mechanical and electrical maintenance, is WACP-10.1.1. Evaluation of this and

other procedures relating to the performance of I&C maintenance activities

identified no programmatic concerns. Mxchanisms are in place for oversight of

in process activities by supervisory and management personnel; training and

periodic evaluation of technicians; periodic review of technical and

-= administrative procedures; ensuring that feedback from technicians and

supervisory personnel is obtained and factored in the preparation and the

revision of the procedures; ensuring that appropriate procedures, materials,

instruments and tools are used for the activity on hand. However, one area

which was found to be lacking and which needs management attention is the

control of materials. In this area, two observations illustrate the inspector's

concern.

In the first example one relay, which had been obtained from stock to replace

another damaged safety related relay, was returned to stock with a " Hot Used"

blue tag without appropriate recertification for use in safety related circuits.

The_ problem here was that the relay had been opened and used to recalibrate the

damaged relay- . Therefore, verification of its characteristics was necessary

prior to-its return to stock, as indicated by the responsible supervisor.

Discussions with QC personnel indicated that the tag would have not been

=

questioned and that the relay would have been recertified for use.

The second observation relates to some gaskets used in conjunction with two

-safety related diesel generator pressure switches. While reviewing the work

package, the inspector observed that the gaskets were part of a larger shipment

(report of material received RMR #43808) which included 25 of those gaskets,

five seals and'three more types of gaskets. Since the material identified on

the RMR appeared to exceed the scope of the repair job, the inspector asked the

entire scope of work. The inspector determined that the gasket had been obtained

from a maintenance supervisor, rather than from the warehouse. Further

investigation revealed that a large quantity of materials, including materials

used in safety related applications, are purchased for Direct Turnover, i. e.,

materials are procured and, after receipt inspection, are turned over to the

requesting organization, rather than stored in the warehouse until needed. The

major concern here is that the procedures that control the storage, distribution,

and restocking of safety related materials no longer apply. While it is true

,

. . _ . . _ , . . . . . _ _ _

_ . . . .

,.

,

. 42

that no limitations are imposed on the usage and handling of materials, once

they are released from the warehouse, in general, the probability of damage is

minimal if used within a reasonable amount of time. The same cannot be assumed

when stored for relatively long periods in a desk drawer, Storage time is

particularly important for those materials which have a limited shelf life.

Conclusions

The I&C organization has a well developed program for performing preventive

and corrective maintenance. The program also appears to be parallel to that

of the maintenance organization. However, the use of independent procedures

and data base can lead to inconsistent results as evidenced by the findings

identified. Control of materia's for safety related applications is a concern

which needs management's attention. The problem is particularly noteworthy for

materials purchased for direct turnover.

6.2 Control of Contracted Maintenance

Scope

The objective of this part of the inspection was to assess contractor support

to maintenance activities. Specifically, the assessment included selection and

training, monitoring of performance, accountability, and quality control.

Findings

At the time of the inspection, the facility was shutdown with extensive main-

tenance and modification work scheduled for completion during that period. For

this purpose the licensee had secured the support of approximately 90 temporary

and contractor personnel. Discussions with personnel from the various mainten-

ance organizations, Quality Control, and 'Iraining revealed that the licensee,

during normal plant operation, utilizes permanent JAF employees for the every

day maintenance activities. During periods of heavy work load, such as refueling

shutdowns, it does resort to contractors and temporary help. However, these

personnel are generally used in a support capacity, as-part of a maintenance

team, where continuous supervision is exercised. One exception to this was

found in the Quality Control organization, where contractors work independently,

and in one case a contractor was performing supervisory duties.

As a result of the licensee's general policy, except for general training,

contractors and temporary employees receive little or no training, prior to

their assignment to the group for which they were hired. With respect to the

effective utilization of contractors and temporary personnel, the licensee

relies heavily on previous experience and training from other employers and

organizations. In the case of the quality control supervisor, he is a regular

hire and has performed quality control functions at JAF for many years.

Observations of I&C work in progress confirmed the statements by the interviewed

personnel. In general, contractors and temporary technicians were used in teams

of at least two persons, with the permanent JAF employee responsible for

directing and signing the activities prescribed by the particular procedure

being used, j

l

_..____ _ ._

,.

,

... 43

Conclusions

,

The licensee appears to make effective use of contractors and temporary personnel.

While there may be some concern about quality of work performed or accepted, as

in the case of QC personnel, because of their unfamiliarity with plant specific

procedures, no examples of adverse quality maintenance work were observed.

'

!

6.3 Deficiency Identification and Control System

Scope =

The objectives of this portion of the inspection were to determine the licensee's

process for deficiency identification, the personnel's understanding of this

process, and the ease for effectively reporting deficiencies. .

Findings

The deficiency identification system consists primarily of two mechanisms: the

work request (WR) and the adverse quality condition report ( AQCR). The work

request, governed by Work Activity Control Procedure WACP-10.1.1, is used for

reporting plant system material deficiencies and for performing corrective

maintenance and repair of equipment. Quality Assurance Procedures QAP-15.2 and

QAP-16.1 provide.the mechanism for identifying, reporting, evaluating and

dispositioning of non-conformances and adverse quality conditions.

All licensee.and contractor . personnel involved in work activities related to

operation, maintenance and modifications at the facility are responsible for

identifying ~ deficiencies and conditions which are adverse to quality and to the

safe operation of the plant. However, while all maintenance personnel were

familiar with the work request process and satisfactorily implemented WRs for

equipment deficiencies, they' expressed confusion on the initiation and

implementation of the AQCR process.

l

~0bservations of maintenance activities and discussions with maintenance craft

indicate that, in practice, deficiencies, including nonconformances, when

identified, are reported.to the supervisor verbally and/or by means of work

request *, Although examples of AQCRs prepared by engineering were found, AQCRs

- are nomily prepared by the Quality Control organization which is responsible

.for the monitoring and dispositioning of nonconformances.

Once a deficiency has been identified, regardless of the method used for

reporting it, if it does constitute a nonconformance, an AQCR is ultimately

written. At that point, the mechanisms which are in place for evaluating and

. tracking to resolution of nonconformances and which are contained in the

applicable Quality Assurance procedures come into action, The reasons for the

I

above are that: (1) all work requests are routed through the work control center,

the staff of which includes a quality control person; and (2) a copy of the

work request is always sent to Quality Control for evaluation and scheduling of

required monitoring Activities. However, the weakness in understanding non-

conformances could impair their recognition.

l

1

l

t,

_ . _ _ _ _ _ _ _ . . _ _ _ _ _ _ _ _ _ . . _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ . . _ . _ _ . . _ _ _ _ _ _ _ . _ . _ _

i ,-

,

$

~*

, .

4- 44

Conclusions

The program, as described in the procedures, for identifying and reporting

deficiencies and nonconformances and for requesting maintenance, was adequately

implemented. Implementation of the mechanisms for resolving deficiencies also

was found to be adequate. However, some weakness appears to exist in the

identification of nonconformances. This may be primarily due to a lack of

understanding of the difference between a deficiency and a nonconformance, and

inadequate training of all plant personnel in the Quality Assurance procedures.

6.4 Maintenance Trending

Scope

The objectives of this part of the inspection were the review of the maintenance

trending program procedure development, of systemic versus specific corrective

actions, of root cause analyses, and rework evaluation.

Findings

Plant Standing Order PS0-1 requires that a system engineer be responsible for

collecting and evaluating data relative to the design,' operation and maintenance

of the systems assigned to him. The intent of the requirement is to make the

system engineer the focal point for particular systems and components to

ultimately improve the overall performance and reliability of the plant.

Accordingly, one of the responsibilities of the system engineer is to trend

-important system parameters so that he can evaluate system performance and

identify early stages of deterioration in components and systems. The

engineering department also includes a performance group with specific project

responsibilities. In addition to the above, approximately three years ago, the

licensee initiated a program to track failures of systems and components. The

program utilizes a computer based data bank, which includes industry as well

as plant specific failure reports, to analyze the component failures and'

. establish, among other things, the adequacy of the preventive maintenance

procedure.

Although programs have been established for early warning and prevention of

system and component- failures, their implementation appears to be lacking

somewhat. As a result, maintenance activities tend primarily to fall within

the area of corrective maintenance work. Some of-the reasons for this are, the >

limited scope of the various programs which are in place, the newness of some

programs, and the lack of coordination between various groups, programs, and

data bases. For instance, the program initiated three years ago te analyze

component history and adequacy of maintenance procedures is limited to critical

systems and components. As a result, although 22 " critical systems" were

analyzed, not all of the safety related equipment is addressed. In addition,

this program is not-tied in any way to the Master Equipment List (which has its

own data base) and has a limited life. Therefore, when the program is completed

and its objectives are attained, no further trending is planned to verify

assumptions and ensure acceptability of results.

- - - - - - - - - - - - - - -

_ _ _ . . . . . _ . - - .

_ _ _

,

..

, 45

Root causs inalysis is addressed in Administrative Procedure AP-8.1 and Quality

Assurance i rocedure QAP-16.1. Both procedures identify the need for such

analysis, e pecially in the case where significant adverse quality conditions

are identifi$d, as specified by the latter procedure. With respect to corrective

maintenance, iiscussions with system engineers indicate that, within the scope

of this portit', of the inspection, root cause analyses are appropriately

conducted to p,svent recurrence and corrective actions are followed to ensure

correctness of .nalysis results. One example of properly conducted roct cause

analysis is the ,ngoing evaluation, including laboratory tests, to resolve

problems _experien ed with the instrument air system. However, with respect to

preventive mainte ince, root cause analyses appeared to be minimal and limited'

to the cataloging sf components' failure modes in computerized data bases.

Conclusions

Programs are in place for performance of maintenance trending and root cause

analysis. However, the implementation of these programs is somewhat lacking

because of the limited scope of the current efforts. As a result the licensee

is tending more toward reactive fixes.

6.5 Support Interfaces

The inspector examined and reviewed the licensee's interface between the

maintenance organizations and other departments, inc.uding Operations, Quality

' Control, and Engineering.

The focal point for all maintenance and modification work is the work control

center (WCC) where all work requests, regardless of the originating organization,

are funnelled. The WCC, which falls under the responsibility of Operations,

reviews all work requests and assigns primary responsibility for execution of

the task. The procedure which governs the activities is WACP-10.1.1, titled

Procedure for Control of Maintenance and Engineering Assistance Requests.

Besides the WCC formal as well as practical lines of communication between

various organization are established through the daily and weekly schedule

meetings. These meetings involve supervisory personnel from the various plant

organizations.

Through the observation of in process maintenance activities, attendance morning

and scheduling meetings, and discussions with personnel in the various organiza-

tions, the inspector concluded that effective. communication exists among the

maintenance crganizations (I&C, Electrical and Mechanical) and between these-

and.the support organizations. Communications appear to work in both directions

with maintenance being used,- for instance, by engineering for data collection

and transfer; engineering being used for problem solving. Quality Control (QC)

is involved in all activities, in that a member of that department is part of

the WCC staff and reviews all work requests. In addition, a copy of all work

requests is sent to QC for scheduling its activities.

..

m*

  • l

. 46

The only example iJentified by the team where effective communication was not

used was work reglest No. 70213. In this case, the originator reported that

loose screws had been observed on an EQ junction box. The work request was

marked to'be minor and added to the list of minor maintenance work whh;h is

tracked separately. Since the deficiency involved a Class 1E junction box in

the. reactor building and, therefore, exposed to moisture, engineering should

have baen consulted for proper scheduling of the required maintenance.

Conversely, good communication was observed between engineering and maintenance,

as in the case of the HPCI modification being performed, during the current

outage. The modification involved Engineering, I&C and Mechanical maintenance.

Since the work being performed was in a high radiation area, prior to the

execution of the various tasks, the technicians and engineers met to discuss

problems encountered and their resolution.

7.0 MAINTENANCE FACILITIES, EQUIPMENT AND MATERIAL CONTROL

Scope

The objective of this portion of the inspection was to assess the plant's

maintenance facilities and controls over maintenance equipment, tools and -

materials to determine how well they support the maintenance activities. The

I

following areas were examined during this inspection:

-

Maintenance facilities and equipment

-

Materials controls

-

Maintenance tool and equipment controls ,

-

Control and calibration of meter and test equipment

The objective was attained by plant walkdowns, document reviews, and interviews

conducted with. supervisors and personnel in associated areas.

Conclusions

The plant layout and personnel placement of the maintenance facilities were

determined to permit efficient operation of maintenance activities, The layout

-of the maintonance facilities and space utilization were organized and

controlled, and the flow of material and equipment throughout the plant was

accommodated by the facilities.

Administrative policies and procedures adequately control the specification,

procurement and receipt inspection of maintenance related materials ind

equipment. Except as described in Section 6.1.3, safety related materials are

adequately identified to ensure proper procurement, storage and issue for its

intended use. The warehouse material tracking system is adequate for maintaining

inventory and for accountability of materials received, stored and issued from

the warehouse. The procurement program is implemented to ensure that materials

intended for maintenance activities are correctly specified and received in a

manner which support established maintenance work schedules.

- - ---

. .. ..

.. .

.

. ..

_ _ . .. . ..

g ..-

a e

, 47

Maintenance tool and equipment identification, storage, and issue were

controlled. Personnel performing calibrations were properly trained, and

calibration standards were ascertained to be traceable to the National Bureau

of Standards.

7.1 Maintenance Facility And Equipment

A tour of the I&C and Maintenance facilities was conducted.to assess the degree

to which the facility layout and its accessibility provided for_ efficient

i

maintenance operations.

The offices of the I&C Superintendent and Supervisors are located in the

administration building,- as are the I&C main tool room and the electrical

storage room. The I&C hot shop, where potentially contaminated equipment is

stored, is in the turbine building. The maintenance tool room is in the turbine

building within easy access to the maintenance Supervisors' offices in the same

building. The office of the Maintenance Superintendent is located in an annex

to the administration building, but in proximity to the maintenance facilities.

Support organizations work areas, including health physics and quality assurance,

are close by or easily contacted by telephone or by the facility's page system.

Areas are established as needed to-support specific maintenance and modification

activities, such as the turbine maintenance project and the emergency diesel

generator maintenance project which were conducted during the current refueling

outage. The inspector observed that the space provided for these projects was

adequate to accommodate the associated activities. The inspector also noted

that specific areas were allocated for the storage of scaffolding in the plant.

7.2 Materials Controls

The adequacy of administrative policies and procedures were reviewed with

respect to the effective control of material (components, spare parts, and

consumables) used in maintenance, beginning with material requisition and

extending through material -installation or use.

The inspector determined that adequate guidelines have been established for

ensuring that appropriate specifications are identified in the procurement of

materials, and that the required certificates are provided with material that

is delivered to the site receiving area. Procurement documents, including

,

- . . . _ . _ . . . .

__

,

..-

q.

. 48

Procurement Requisition #018858 for replacement seal set #0701-217 used for 23

MOV-16, were reviewed to ascertain that administrative policies and procedures-

are being complied with. The Procurement Document Technical Review Summary

confirmed that applicable requirements are addressed by the purchase documents

including receipt inspection, testing, design requirements, applicable

specification, seismic and environmental qualification.

A walkdown of the site warehouse was conducted and warehouse and quality control

(QC) personnel were interviewed to assess the adequacy of the facility regarding

support of the maintenance effort. The warehouse provides an ANSI N45.2.2 Level

B storage capability for parts and consumables. The licensee stated that, at

present, there is no Level A storage capability and that no present need exists

for that type of storage. However, the new warehouse, currently under

construction, will provide space for Level A storage. An area of the existing

warehouse is allocated to quality control personnel for the performance of their-

receipt inspections prior to placing the materials in the assigned warehouse

storage area. Materials are not placed in the general issue area until QC has

attached an inspection tag, indicating that receipt inspection requirements

have been complied with. Warehouse inventory'is controlled and tracked via a

computerized data base. Special storage requirements, such as shelf life and

EQ requirements, are identified, as are code class, maximum and minimum

inventory levels, and inventory on hand. Automatic reordering is initiated

' when inventory drops below an established minimum level. Material issued from

the warehouse is controlled by identifying the individual to whom the material

is issued and the work request number to which the material is to be applied.

7.3- Maintenance Tool and Equipment Controls

A tour of the maintenance tool room was conducted to assess the adequacy of the

control maintained by the licensee over tools and equipment stored in the tool

room. Tools and equipment are controlled by means of a computer based tracking

system which identifies the equipment by a unique number, the calibration

frequency, calibration date, and calibration due date. The majority of

calibrations are performed by a vendor who picks up and returns the tools on a

scheduled frequency. The tool room attendant is qualified to perform specific-

tests, such as load tests of rigging equipment. He is also responsible for

maintaining all records of vendor calibrated and internally calibrated equipment.

The inspector reviewed the data base for selected equipment and found that the

records were complete and that they identified the current status of that equipment.

.The inspector observed that the data base regarding rigging equipment, ID# 00167,

was updated at the time the equipment was returned to the tool room and that

the current status of the equipment, including its availability for use and its

current storage location, was identified. Additionally, the inspector observed

the performance of load testing of a new chainfall, rigging ID# 00255,

S/N CB-1279 DBW. The test was performed by the tool room attendant who, sub-

sequent to the testing operation, identified the equipment with permanent marking

and +.ntered the appropriate information into the computerized tracking system

data base. The dynamometer used to perfort the load test, M&TE #M-155,

S/N AP 29841, was used within its calibration period and the equipment used to

calibrate the dynamometer was determined to be traceable to the National Bureau

of Standards.

- _ -_ - __ _ _ .

yo

1

..

"

L:

. 49

7.4 Control and Calibration of Meter and Test., Equipment

A tour of the I&C main tool room, relay room and hot shop was conducted to

assess the adequacy of the control and calibration system incorporated by.the

licensee for the equipment stored in those areas,

' The inspector determined that- a color coded tagging system is in place which

identifies the calibration. status of each piece of test equipment. Additionally,

a control' usage log for each piece of equipment identifies each job on which

the equipment is used. Test equipment is identified with a unique number which

is also used on the associated tag and control log. The information is included

i

in the equipment computerized tracking system.

Test equipment calibration is performed both in-house and by a vendor. In-house

calibration is performed by the I&C tool room attendant who is qualified to

perform specific calibrations. Calibrations for which the attendant has received

no training are done by the licensee's vendor. Calibration equipment used for

both in-house-and vendor calibrations was determined to be traceable to the

National Bureau of Standards. Calibration records of selected I&C_ equipment

were reviewed and found to be complete. In addition, usage logs indicated that

the equipment had been used within its current calibration period. Issuance of-

test equipment is the responsibility of the shift tool room attendant.

8.0 PERSONNEL CONTROL

Scope

The objective of this portion of the inspection was to determine the extent to

which personnel are trained and qualified to perform maintenance activities.

To make the asse'$nrnt the following areas were examined:

-

Staffing control

-

Training

-

Testing and qualification

-

Current status

The assessment was based on interviews, observations at the training facilities,

observations of field activities, and review of training records.

Conclusions

The licensee's training program is approved by INP0 and the apprentice program-

is also approved by the State of New York. Personnel training records are

arranged in a manner that permits a reviewer to quickly determine an individual's

current training status and are maintained in a dedicated area of the trait 'ng

facility. The training laboratories (mechanical, electrical and I&C) were very

well equipped and included appropriate mock-ups. The instructors were

knowledgeable in their respective discipline.

.. .. .__.___. _ __ _

. - - _ _ _ - - _ _ -

_ _ _ _ _ _ _ _ _ _ _ _ _ _ - - _ . . . . . . . - . . ._

..

,

,.g

. 50

8.1 Staffing Control

Assessment of this area was based on interviews with the instrument and controls

(I&C)'Superint'endent and the Assistant to the Maintenance superintendent.

promotion is done from within the company and, when'possible, within the depart-

ment. All of the I&C supervisors have advanced through various levels in the

department and 3 of E maintenance supervisors were promoted from-the bargaining

'

unit. The turnover race is very low, less than 1*4 per year, and has resulted

in an experienced group. The average years of experience are approximately

8 1/2 years and 9 1/2 years, for the mechanical and electrical maintenance

departments, respectively, and approximately 7 years, for the I&C department.

During outages, a 60. hour per week work schedule is followed. However, the

schedule reverts back to 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> per week during periods of normal operation.

8.2 Personnel Training

The licensee's training program is divided into two parts, an apprentice program

and a continuing training program which applies when the apprentice program is

completed. The training follows the INP0 guidelines and is approved by INPO.

Additionally, the apprentice program is approved by the State of New York.

The apprentice program requires approximately 26 to 28 weeks to complete. The

licensee requires that it be completed in 4 years, but it can be completed in

less than 4 years. For this purpose, individuals are scheduled for the training

approximately 1 week in each 6 week period, or approximately 6 to 8 weeks per

year. The program includes fundamental courses of basic theory in the various

disciplines and BWR Technology, theory in a specific discipline, oracticed skills

which include laboratory work and/or sessions in the plant, plant specific

systems, and un-the-job training.

A " Jury of Experts", made up of a minimum of three members, establishes the

program and updates it as it deems necessary, based on plant experience and

needs. The jury is comprised of members in each of the following categories:

- '

Supervisor

-

. Training Instructor

-

Plant Worker

The committee must meet at least once a year, but it may convene more often, if

the need arises.

Progress of individuals is documented and tracked by the training department's

computerized tracking system. A training tracking matrix is generated every 6

weeks (each training cycle) by the training department who distributes copies

to thel departments supervisors. The matrix lists the individual's records and

is used to determine their current status in the program (apprentice, journeyman,

etc.). . Specialized training is provided by in-house training instructors and

by vendors, who are expert on the specific subject, on an as-needed bases.

......_.__._ _

-

- --

- - - - -

.. - -

..,,..... .. ,. . . . . . . . . . . .

-

,

b' , .a

. ,/

.

. 51

Selected records of NYPA employees and maintenance contractor employees were

reviewed and were determined to be complete and current. The records showed

that those individuals had received training in specific activities being

performed during the outage.

The inspection included a tour of the three training laboratories (Mecha* ical,

Electrical and I&C) in the facility. The laboratories are used to pro,ide

general, hands-on training and, additionally, training for more comp'.icated,

non-routine maintenance projects. The' laboratories were observed to be well

stocked with mockups and equipment to simulate plant conditions.

8.3 Testing and Qualification

Training.and qualification of- Power Authority employees,. including instruction,

testing and documentation of each individual's training status, is administered

by the licensee's training department. The course content is defined by the

apprentice and the continuing training programs, as established by the " Jury of -

Experts."

Training of contractor maintenance personnel is administered by the Contract

Services group, but the licensee's training department provides specialized

training in selected cases,

On-the-job monitoring and supervision by licensee staff are the methods used-

by the 1icensee to assure that the desired level of contractor performance is

achieved.

" - - - -

. . - - . . - . . . . . . . . . . , . . , . .

_________

, .

.4

. . I'

.

APPENDIX 1

INDIVIDUALS CONTACTED

New York Power Authority

R,-Archer I&C Tool Room Attendant

  • R. Baker Maintenance Superintendent

A. Brais Procurement Engineer

  • P. Brozenich Waste Management General Supv.

B. Carlson Preventive Maintenance Supervisor

P. Clements Contract Services - Civil /Struc Supv.

E. Conger Warehouse Supervisor

J. Conroy Quality Assurance Supervisor

  • J. DeRoy Assistant to Maintenance Supt.

- *'P. J. Donahue PMTF Manager

  • W. Fernandez Resident Manager
  • T. J. Herrman Systems Engineering Supervisor

E..Hyne Shift Supervisor

J. Johnson Quality Assurance Specialist

N. Johnson Mechanical Maintenance Planner'

S. Juravich I&C Surveillance Coordinator

  • H. N, Keith I&C Superintendent
  • R. Lallman Director BWR Operations & Maintenance
  • T. Landers Superintendent Material Control

J. Leach Maintenance Tool Room Attendant

  • D. Lindsey Planning Superintendent
  • R. Liseno Superintendent of Power
  • R. A. Locy Operations Superintendent

J. Lyons Performance Engineer

D. Maclean. Journeyman Electrician

R. Maki Work Control Center Supervisor

J. Marris I&C' Lead Technician

K. Moody Equipment Qualification Supervisor

  • E. Mulcaney Sr Technical Advisor

D. Nacamuli I&C Maintenance Supervisor

  • R. A. Patch Sr. Quality Assurance Specialist

M. Reno I&C Maintenance Supervisor

  • 'G Tasick Quality Assurance Superintendent
  • G. J. Vargo Rad. & Env. Services Superintendent
  • V, M. Walz Technical Services Superintendent
  • J. Wierowski Technical Training Supervisor

. . - - - - - -

~

1l , i .!c ,

~ ~ ~

-

- -

<

,

q

%dugj ,~Je .

s' d

k,wl,W?

a .

N

. ,

JW m a s.

.e

1 Appen'dixL S '21 i

-i

(i! if l

Q, , % % - _;

. --

1

-  % ited States Nuclear' Regulatory Commission. .i

,.

.; t , .t ~

ii

'{ ,* ALL.DellaGreca

. Sr. Reactor Engineer- 1

lL4 ,

^*'H.!Graye Sr. Reactor: Engineer-; *

J

m.g

'

  • :- Haroldsen- Inspector - EGG-

yw c..'R. .G; K~.~;Hunegs .

.-

- Resident Inspectn. t

, . - * J.1CL Linv111e= Project Branch Chief- _l

P4J '*'R. X McBrearty; . Reactor Engineer . l

M * B. G MartinL Inspector AMSEC ~

M  :*LP. 0'*onnel1 Radiation' Special.1 st'

p: ,

  • 1RL-Platse.. ResidentfInspector= j

o, -

  • W' Schmidt; ' Sr. Resident Inspector- i
  • '

- -

Indicat$s personne11 present,at the exit' mee' ting'

>

l-

) ', I_

l. *

J. ,

l

\- .

L

!

+l

l' l

l1 lL. y

.-3

--

g

il

f i .' , -

r. ', )

' '

,

r 3

Ar ._

<

k

?.

>M

s

t

t ..

.

..#

)

i

p

-

,h

, s.

+

f,

,

y

s

F

x ~I

, _ V! lI

[-? -

'

,

l.

l' ,

ir (I'

v' ..

\

. , < g#,

h s

r_  ;

s' h k. , . 4 ,. .= ; . . . . . .l _J . _

,-

,

f,c a .

e-

APPENDIX 2

,

SUMMARY OF WEAKNESSES

-Weakness - A potential problem or condition presented to the licensee for

evaluation and corrective action as appropriate.

--

Plant walkdowns indicate that there are areas in the plant where house-

keeping and handling of hazardous materials and should be improved.

(1,2, 4.5 & 4.6) *

--

Identification of equipment and plant locations is lacking. (1.2)

--

Vie of equipment restraints.without seismic analysis may be indicative of

patentially inadequate design reviews. (1.2) ,

--

A -)redictive maintenance program is partially developed and implemented.

(3.4 & 6.4)

--

The program for equipment upgrade, for replacement of plant components and

for evaluating effects of plant aging could be strengthened. (3.7)

--

Interaction between performance and system engineering is not described

by procedure. (4.1)

--

Definition of responsibilities for engineering support of maintenance is

not well documented in some cases. (4.2)

--

Risk based concepts or PRA are not presently considered in the planning,

scheduling, and prioritization of the maintenance process. Management

goals _in the use of PRA have not been established. (4.3 & 5.5)'

!

--

Criteria-for establishing QC inspection hold points in work packages are

not defined by procedures. (4.4)

--

The method for identification of rework, particularly during periods of

~ heavy work load is not under documented control. (5.2)

--

Equipment maintenance history could be enhanced by more attention to

details, by a more detailed data base, and by full implementation of

failure and root cause evaluations. (5.3 & 5.10)

--

Several examples of maintenance activities wi a incomplete or no planning

were identified. (5.4)

i

m

r:

-v ,/'-

. Appendix 2 2

(

->

Guidelines for procedure development could be improved to ensure a

consistent format. (5.8)

--

More specific procedures, which include the system engineer's input, should

be considered for post maintenance testing. (5.9)

<--

Parallel procedures and data bases for the electrical and I&C departments l

were noted to be inconsistent in approach or definition of-boundaries of  !

responsibility (6.1.3) i

.I

--

The direct turnover of safety related materials to supervisors presents

the situation where the material is no longer under warehouse control

(6.1.3).

- - . Not all personnel have a' clear understanding of the difference between

deficiency and nonconformance. (6.3)  !

!

-f

  • Numbers between parentheses refer to report sections,

i

-!

!

'

,

.

!

!

,

!

'

i

!

l

i

I-

i