ML20010A279

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept Re Containment Internal Structures Coating Deficiency,Initially Reported on 791213. Nonconforming Coatings Are Being Removed.Statistical Testing Program Initiated for Remaining Coating
ML20010A279
Person / Time
Site: Midland
Issue date: 07/31/1981
From: Jackie Cook
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, 79-12, 79-12-#9, NUDOCS 8108110273
Download: ML20010A279 (2)


Text

-

&ffG66(s Consumers power m.

C0mpany via na,uant - n+ta.s.,a, and Constmetion o.n.r.1 ofta : 194s weet Pernesi need, Jeckson. Mi 49201 + (si7) 7sso4ss 79-12 #9 July 31, 1981 k? I

\  ;

Mr J G Keppler, Regional Director Office of Inspection and Enforcement d~ g\)G #g# 7) .8 p

US Huclear Regulatory Commission s Region III ' Os,N

')

799 Roosevelt Road Glen Ellyn, IL 60137

\h3p '

MIDLAND PROJECT -

DOCKET NOS 50-329, 50-330 COIt"aINMENT INTERNAL STRUCTURES COATING DEFICIENCY FILE: 0.h.9 37 SERIAL: 12068

Reference:

CPC0 letters to J G Keppler; Same

Subject:

1) Serial Hove-309-79; dated December 13, 1979
2) Serial Hove-26-80; dated February 7, 1980
3) Serial Hove-75-80; dated April 15, 1980 h) Serial 9125; dated June 11, 1980
5) Serial 8823; dated September 9, 1980
6) Serial 10051; dated October 31, 1980
7) Serial 11199; dated February 23, 1981
8) Serial 12009; dated May 29, 1981 This letter, as were the referenced letters, is an interim 50.55(e) report on the containment internal structures coating deficiency.Section V(a)(2) of the enclosure to Reference 8 provided the testing program to evaluate the previously applied System 9 coating. The coatings that have been identified to be nonconforming are presently beira removed. The statistical testing program to do the testing of the remaining coating is being initiated.

Specification 7220-A-56(Q) (Reference 8,Section V(b)) for the System 9 g y/

coating repair has not been issued pending review of the requirement for a maximum allowable humidity level at the time of application. A testing program is being developed to define this parameter. 3 l I 8100110273 810731 PDR ADOCK 05000329 S PDR AU6! 5 1981

e

  • Serial 12068 2 79-12 #9 Another report, either interin or final, vill be sent on or before October 30, 1981.

3,g /A4 /F/L WRB/1r CC: Director of Office of Inspection & Enforcement Att Mr Victor Stello, USNRC (15)

Director, Office of Management Information & Program Control, USNRC (1) l RJCook, USNRC Resident Inspector, Midland (1)

CBechhoefer, ASLB Panel RSDecker, ASLB Panel FPCowan, ASLB Panel AS&L Appeal Panel MMCherry, Esq MSinclair BStamiris CRStephens, USNRC WDPaton, Esq, USNBC FJKelly, Zsq, Attorney General SHFreeman, Esq, Asst Attorney General WHMarshall CJMerritt, TNK&J

- . . , - . _ . . , _ _ _ _ _ . , _ . _ _ _ . _ _ - - _ . . _ _