Forwards List of Shielding Mods Being Incorporated in Plant Design.Completion of Mods Will Be Made Prior to Issuance of OL or by 820101
ML19345B083
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 11/21/1980
From: Nichols T
SOUTH CAROLINA ELECTRIC & GAS CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 8011260092
Download: ML19345B083 (2)


Text

/

- : st:ns

-e- ,e

""" ""3, '**'

SOUTH CAROLINA ELECTRIC a gas COMPANY POST OF FICE SQR 764 CcLUMBIA. SOUTH CAROLINA P 9 218

,,xS G, J ,C.> f8 2uT 7t T. C. NicMots' Jn.

vu r.. .u .. ... c.%. o.m . Novembec 21, 1980

%ca., c .m U.' 2 Y' l'.:s SEilyicE3

' C!!

Mr. liarold R. Denton, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission

Washington, D. C. 20555

Subject:

Virgil C. Summer Nuclear Station Docket No. 50/395 Shielding Modifications

Dear Mr. Denton:

As requested by Mr. John Minns of the Radiation trotection Branch, South Carolina Electric and Gas Company, acting for itsalf and agent for South Carolina Public Service Authority, provides forty-five (45) copies of a list of shielding modifications being incorporated in the design of the Virgil C. Summer Nuclear Station. The shielding study will be com-pleted by the end of this year and all modifications will be completed prior to the issuance of an operating license or before January 1, 1982, whichever is earlier.

If you have any questions, please let us know.

Very truly yours, ,

, /

I T. C. Nichols, Jr.

RBC:TCN:rh cc: V. C. Summer G.11. Fist her T. C. Nicnols, Jr.

E. 11. Crews , Jr.

D. A. Nauman O. W. Dixon, Jr.

O. S. Bradham R. B. Clary W. A. Williams, Jr.

B. A. Bursey J. L. Skolds J. B. Knotts, Jr.

11. E. Yocom NPCF/Whitaker File l l

1 801320009#- 4  !

l l

SHIELDING MODIFICATIONS VIRGIL C. SUF0fER NUCLEAR STATION, Intermediate Building Pipe Chase The height and thickness of the chase curbs have been increased to provided adequate pest-accident shielding of the pipe shine. A personnel ladder has been relocated to eliminate a concrete cutout from permitting radiation shine to elevation 412'0".

Boron Injection Tank A two-foot concrete wall has been placed across the doorway to reduce direct radiation shine into the adjoining auxiliary building area. To climinate potentially high level scattering the wall was extended northward to the cubicle wall.

Auxiliary Building Elevation 425' 6" Pipe Chase Placement of 8-inch concrete wall and additional chase curb shielding were used to eliminate direct shine to auxiliary building elevation 436' 0". - -

Charging Pump Cooling Units Installation of lead and concrete shiciding will shield personnel from the piping located in the cubicle.

Cubicle 12-09 of Auxiliary Building Placement of lead and steel shadow shield will provide radiation protection of the cubicle floor area required for personnel access travel routes.

RHR/ Spray Pump Rooms and Cooling Units The sump line from the RHR/ Spray Pump Room to the waste holdup tank has been re-routed to provide sufficient slope with a high point within the pump cubicle and a vacuum breaking vent Jine. This will allow the line to be emptied by. gravity draining into the waste holdup tank upon shutoff of the sump pump.

Sampling System Additional shielding will be added in the area of the sampling system upon com-pletion of the design.