ML20210R550
| ML20210R550 | |
| Person / Time | |
|---|---|
| Site: | Summer |
| Issue date: | 08/05/1999 |
| From: | Plisco L NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Gabe Taylor SOUTH CAROLINA ELECTRIC & GAS CO. |
| References | |
| 50-395-99-03, EA-99-204, NUDOCS 9908170138 | |
| Download: ML20210R550 (10) | |
See also: IR 05000395/1999003
Text
,./_
August 5, 1999
EA 99-204
South Carolina Electric & Gas Company
ATTN: Mr. Gary J. Taylor
Vice President, Nuclear Operations
Virgil C. Summer Nuclear Station
P. O. Box 88 -
- Jenkinsville, SC 29065
Dear Mr. Taylor:
SUBJECT: NRC INTEGRATED INSPECTION REPORT NO. 50-395/99-03
Thank you for your response of July 7,1999, to our Non-Cited Violations (NCVs) identified on
. June 7,1999, concoming activities conducted at your facility, in your response, you denied
NCV 50-395/99003-01, " failure to remove loose debris from the reactor building," and requested
reclassification of NCV 50-395/99003-06, " failure to properly control access to a high radiation
area."
After careful consideration of the basis for your denial of NCV 50-395/99003-01, we have
concluded, for the reasons presented in the enclosure to this letter, that the NCV occurred as
stated in NRC Integrated Inspection Report No. 50-395/99-03.
NCV 50-395/99003-06 stated that you failed to properly control access to a high radiation area
in accordance with 10 CFR 20.1601, " Control of access to high radiation areas." You did not
deny the violation, but rather stated that the violation should be cited against 10 CFR 20.1501
since Health Physics did not perform surveys, reasonable under the circumstances, to evaluate
the extent of radiation levels and the potential radiological hazards that could be present during
fuel movement.
We carefully reviewed the material you provided in support of your request for reclassification
and material that was gathered during the onsite inspection. The reviewed material included
Condition Evaluation Report (CER) 99-0520, the Regulatory Assessment of CER 99-0520, and
Technical Specification 6.12, "High Radiation Areas." We agree that failure to do an adequate
-
survey was an issue in this event; however, we have elected to focus on the control of the high
radiation area in our regulatory action because that control represents a more direct risk for an
individual.
We disagree with your position that extreme measures would have been needed to access the
drained pit area.' ' A Radiation Work Permit already existed for entry into the pit and it would not
have been difficult for Health Physics Technicians and other workers to utilize it again.
. Additionally, we do not view a ladder located just a few feet below the accessible floor level as a
\\
OFFICIAL COPY
i
9908170138 990805
"
ADOCK 05000395
G
~
-
,
__
'
,
SCE&G
2
situation requiring extreme measures to gain access to the drained pit. An extreme measure
could have existed if the ladder had not been in the pit.
Therefore, it is our conclusion that your request for reclassification was not supported and that
NCV 50-395/99003-06 will remain as stated in NRC Integrated Inspection Report No.
50-395/99-03.
We appreciate your cooperation in this matter.
Sincerely,
Orig signed by Charles A. Casto for
Loren R. Plisco, Director
Division of Reactor Projects
Docket No.: 50-395
License No.: NPF-12
Enclosure:
Evaluations and Conclusion (NCV 50-395/99003-01)
'
.
SCE&G:
3
cc w/ encl:
R. J. White
Nuclear Coordinator (Mail Code 802)
' S.C. Public Service Authority
Virgil C. Summer Nuclear Station
-
P. O. Box 88
Jenkinsville, SC 29065
' J. B. Knotts, Jr., Esq.
Winston and Strawn
1400 L Street, NW
Washington, D. C. 20005-3502
Chairman
Fairfield County Council
P. O. Box 60
-
Winnsboro, SC 29180
.
Virgil R. Autry,' Director
Radioactive Waste Management
l
Bureau of Solid and Hazardous
Waste Management -
S, C. Department of Health
.
and Environmental Control-
2600 Bull Street
Columbia, SC 29201
- R. M, Fowlkes, Manager
Operations (Mail Code 303)
South Carolina Electric & Gas Company
Virgil C. Summer Nuclear Station
P-. O. Box 88
Jenkinsville, SC 20065
April Rice, Manager
Nuclear Licensing & Operating
Experience (Mail Code 830)
j
Virgil C. Summer Nuclear Station
P. O. Box 88
Jenkinsville;SC 29065
3
4
,
<
)
.,
. .
.
.
..
.. .. ..
.
..
.
. .
.
.
- - .
e
SCE&G'
4-
Distnbution w/enci
L. Plisco, Ril
K. Cotton, NRR
~ R. Aiello, Rll
L. Hayes,Ril
G. Kuzo, Ril
,
R. Gibbs, Ril
P. Fillion, Ril
S. Sparks, Ril
R. Borchardt, OE
B. Summens, OE (Letterhead copie) -
PUBLIC
NRC Resident inspector
. U.S. Nuclear Regulatory Commission
Route 1, Box 64 .
Jenkinsville, SC 29065
0FOR PREVIOUS CONCUR 0ENCES SEE ATTACHED
wrNE
RH:usw
RH:Unr
RH;pnr
RII:Una
RII:Una
RH:una
RII;tNa
asusuATURE
NAM _
KCayne *
._ ZZ:nn *
RHaag *
ETesta '
KBarF
BManett"
55 parks *
DATE
W 199
W . 19 9
W 199
.W.
199
91 199
W 199
91 199
wur v r
Ysa
NO
YE5
NO
YE5
NO
YE5
NO
YE5
NO
YE5
NO
YE5
NO
wrmt
FBI.1JRA
esuvuATURE
CEvans *
DATE.
W 199
W 199
W 199
91 199
91 199
91 199
W 199
wuryr
YE5
NO
YE5
NO
YE5
NO
YE5
NO
YE5
NO
YE5
NO
YE5
NO
OFFICIAL RECORD COPY
DOCUMENT NAIAE: G:WUM_ Denial.r2
.
<
.
s
\\ SCE&G
4
pi ribution w/ encl:
L. P '
o, Ril
K.Co
n, NRR -
R. Aiell Ril
,
L. Hayes, il
G. Kuzo, RI
R. Gibbs, Ril
P. Fillion, Ril
S. Sparks, Ril
J. Lieberman, OE
PUBLIC
1
NRC Resident inspector
U.S. Nuclear Regulatory Com
sion
Route 1, Box 64
Jenkinsville, SC 29065
.
OFFICE
Ril:DRP_
RII;DRP
Ril:DRP
Ril:DR5
ITl[:_DR5
RH0R5
RJi/JC5 g
f
W
WRE gL,
gg
7,g, f
, gg
/g gg
gp
l
NAME
%Coyne'
MWidmann
RNeag
ETesta
itBatt
BMellety
SSpdrks
'
DATE
7/24/99
7/ /99
7/2.7/99
7/ AT /99
,7/% /99
,7/ 2/)/99
9 T/4 /99
COFW
r vaur/ NO
YES
NO
MS) NO
TES) NO
/YES,
NO
/TEJ
NO
Y55 ) NO
I
lvrrms
RII: ORA
PSIGNATURE yg ,y
NAME
CEvanay
DATE
g'y /99
7/ /99
7/ /99
7/ /99
7/ /99
7/ /99
7/ /99
COPY't
{ YEW
NO
YES
NO
YES
NO
YES
NO
YES
NO
YES
NO
YES
NO
OPlilSIAL RECORD COPY
DOCUMENT NAME: G:MBUM_ Denial.r2
JM.-29-1999 11:25
USNRC U.C. SUMMER
803 345 5837
P.02
.
SCE&G
4
Distributg Wenci:
. L P!seco, Ril
K. Cotlon, NRR
R. AleNo, Ril
L Hayes, Rif
G. Kuzo, Ril
R. Gibbs, Rll
P. FiDion, Ril
S. Sparks, Ril
J. Lieberman, OE
PUBUC
NRC Residentinspector
U.S. Nuclear Regulatory Commission
Route 1, Box 64
Jenkinsville,SC 29066
.
I
__
_
m . _ , _
sre
--
_ - - - - - -
- - - -
=_ -N
_.
- ' ' "
'EGN
~
__
M
RDayne
- ]__
M
N _
fWerr
WMellutt
6
-.
w m
L_
rpm
_
n M
-- a m
n m
n m
n
m-
- _ , , _
=
no
_mn
vus
no
vus
no
vus . no ---
m - no
vus
no
..
_
- --
_ . . = _ .
. _ _ _ _ _ _ _
_
_
__
_
_
_
--
_ _ -
-
__
_
-
__
_
DATE
n M
N M
n M
11
m-
n ~~ M
~ 11 M
11 m
wur1r
~M
NO
M
mp_
r-
_ No
_ 735
NU
YE5_
80 0
_ VES
Mp
_Ves_
soo
OFFICIAL MOORD COPY
aG Mla4ME: kWhat.Desslutst
-
_
TOTAL P.02
.-
,
,
EVALUATIONS AND CONCLUSION (NCV 50-395/99003-01)
On June 7,1999, a Non-Cited Violation (NCV) was identified during a routine NRC inspection for
failure to adequately remove loose debris from the reactor building in accordance with Technical
Specification surveillance requirement 4.5.3.1.1 South Carolina Electric & Gas Company
responded to the NCV on July 7,1999. The licensee contends that the amount of debris found
by the inspectors represented a negligible challenge to Emergency Core Cooling System
(ECCS) sump performance and therefore performance of the surveillance requirement was
ac; equate. The NRC's evaluations and conclusion regarding the licensee's arguments are as
follows:
.
Restatement of NCV 50-395/99003-01
On May 7, the inspectors conducted an inspection of containment to assess mMerial
condition and general area housekeeping prior to reactor startup. At the time of this
inspection the licensee had completed a reactor building closeout visual inspection per
Quality Systems Procedure (QSP)-208, ' Inspection of Housekeeping and items in
,
Storage," Revision 9 and had entered Mode 4. In general, the material condition of the -
containment was satisfactory. However, the inspectors identified debris and tools, such
!
as a rubber shoe, a plastic bag, a cloth booty and other small items within accessible
areas of containment. The debris identified by the inspectors was subsequently
removed from the reactor building. The inspectors estimated the total amount of debris
to be approximately two square feet. The inspectors were informed by engineering
personnel that the transportable debris could block approximately two percent of one
train's sump suction screen and therefore this debris represented a negligible challenge
j
to sump performance. The inspectors agreed with this assessment.
'
TS Surveillance Requirement 4.5.3.1, " Emergency Core Cooling Systems," which is
, applicable for Mode 4, requires that the licensee perform a visual inspection per TS , 4.5.2.c, to verify that no loose debris is present in the reactor building. Section 8.2.1.B of
QSP-208, which implements the requirements of surveillance requirement 4.5.2.c,
'
requires, in part, that the licensee identify and correct reactor building housekeeping
discrepancies prior to reactor building closeout. The failure to adequately remove loose
debris from the reactor building is a violation of TS 4.5.3.1. This Severity Level IV
violation is being treated as a Non-Cited Violation (NCV), consistent with Appendix C of
-
the NRC Enforcement Policy. This violation is in the licensee's corrective action program
as CER 99-0748 and is identified as NCV 50-395/99003-01.
1
Summary of Licensee's Response to NCV 50-395/99003-01
4
.
The licensee contends the following:
i
The purpose of surveillance requirement 4.5.2.c is to ensure that the required number of
,
trains of the Emergency Core Cooling System (ECCS) are operable and that there is not
sufficient debris inside the reactor building that can be transported to the sumps and
-
Enclosure
i
F
.-
,
2
degrade ECCS performance to a level that its design basis functions can no longer be
performed.
The design of the ECCS sumps complies with the recommendations of Regulatory Guide
-
(RG) 1.82, " Water Sources for Long-Term Recirculation Cooling Following a Loss of
Coolant Accident," Revision 0, dated 6/74. Under the recommendations of this RG,
cump blockage from debris up to 50% is assumed. The design of the Virgil C. Summer
. Nuclear Station (VCSNS) sumps was verified as adequate for the 50% blockage criteria
by scale model testing conducted at the Alden Research Laboratory during the initial
plant licensing phase.
-
The potential sources of LOCA generated debris were also investigated during the
-
original plant licensing phase. Section 6.3.2.6.1 of the VCSNS FSAR describes the
potential sources of LOCA generated and other types of debris present inside the reactor
building. The NRC reviewed this investigation and concluded that the sumps could
perform their design function considering the debris blockage criteria of RG 1.82.
.
Subsequent to the NRC inspection of the reactor building, Engineering personnel
-
performed an evaluation and determined that the transportable debris found inside the
j
reactor building could block approximately two percent of one train's sump suction
screen and that this represented a negligible challenge to ECCS sump performance.
The inspectors agreed with this assessment. Therefore, it is SCE&G's position that the
- Technical Specification surveillance was adequate.
During conversations between plant staff and the inspectors, it was inferred that the ease
-
in which the debris was found was a contributing factor to issuance of the violation. It is
SCE&G's position that, although the presence of debris in the reactor building after
establishment of containment integrity was undesirable and showed lack of attention to
detail, the ease with which the debris was located is not a valid basis for a violation.
NRC Evaluation of Licensee's Response
The NRC staff has carefully reviewed your response and considered the following items:
1
Technical Specification surveillance requirement (SR) 4.5.2.c, which is referenced by TS - 4.5.3.1, requires, in part, that the ECCS subsystem be demonstrated operable *by a
visual inspection which verifies that no loose debris (rags, trash, clothing, etc.) is present
j
in the reactor building which could be transported to the RHR [ residual heat removal] and
Spray Recirculation sumps and cause restriction of the pump suctions during LOCA
conditions." Contrary to your position that the purpose of SR 4.5.2.c is to ensure debris
'
is not present that could prevent the ECCS sumps from performing their design basis
function, the SR does not reference a quantity of debris relative to ECCS sumps being
able to perform their function. The NRC recognizes that minor debris such as tie wraps,
'
small pieces of paper, etc., which remained in the reactor building following the visual
inspection of SR 4.5.2.c would not necessarily cause the SR to be viewed as
inadequate. However, the NRC considers that the type ofloose debris found by the
inspectors (e.g. rubber shoe, plastic bag, and cloth booty) was not minor and could
,
4
-
,
e
3
reasonably be transported to the RHR and Spray Recirculation sumps and cause
restriction of the ECCS pump suctions.
_ Our interpretation of SR 4.5.2.c requirements is consistent with your response to NRC
Bulletin 93-02," Debris Plugging of Emergency Core Cooling Suction Strainers." In this
Bulletin, the NRC requested licensees to identify temporary sources of fibrous materials
which are installed or stored in containment. In your June 10,1993, response to Bulletin 93-02, you stated that "all temporary material used during an outage inside containment
is removed so as to not reduce the performance of the emergency sumps." Your letter
further stated that the " Quality Control organization performs a reactor building closeout
inspection (each outage) which assures miscellaneous equipment / debris is removed
from the building." We believe that your response to Bulletin 93-02 is consistent with our
interpretation that the intent of SR 4.5.2.c is to remove all loose debris from the reactor
building.
Your engineering evaluation concluded that the transportable debris found in the reactor
-
building could block approximately two percent of one train's sump suction screen.
Although the NRC agrees that a two percent blockage of the ECCS sump represents a
negligible challenge to sump performance, your response did not consider the aggregate
effects of the debris identified by the inspectors with other potential sources of debris in
the reactor building. VCSNS Final Safety Analysis Report (FSAR) section 6.3.2.6.1,
" Containment Sump and its Effect on Long Term Cooling Following a LOCA," discusses
other potential sources of debris within the reactor building. FSAR section 6.3.2.6.1
does not identify loose debris of the type identified by the inspectors as potential
blockage sources for the ECCS sumps. Therefore, this debris represents an additional
two percent blockage beyond the sump debris loading assumed in the safety analysis.
The NRC considered the quantity of loose debris in the reactor building, including the
-
potential for ECCS sump screen blockage, when evaluating the severity level of the
violation. Although you failed to comply with TS 4.5.2.c, the NRC agrees that the
additional challenge created by the loose debris would not result in the ECCS system
being unable to perform its intended function. Therefore, based on guidance contained
in NUREG-1600, Rev.1, " General Statement of Policy and Procedure for NRC
Enforcement Actions," the NRC characterized the violation at a Severity Level IV.
Violations at Severity Level IV, the least significant of the four severity levels established
in the NRC Enforcement Policy, involve noncompliances with NRC requirements for
which the associated risks are not significant. Consistent with Appendix C of the
Enforcement Policy, the NRC treated this Severity Level IV violation as an NCV.
With regard to your comment concerning the ease in which the debris was found and the
inference that this was'a contributing factor to the issuance of the violation, the NRC did
consider the fact that the debris was located within readily accessible areas of the
reactor building. Based on the type of debris and its location in readily accessible areas,
it is reasonable to believe that the debris could have been transported to the reactor
building sump. In dispositioning this violation, the NRC considered the ease of the
inspectors' identification in the evaluation of the accessibility and transportability of the
1
loose debris.'
I
r
-
p
,.
4
NRC Conclusion
For the above reasons, the NRC staff concludes that the NCV 50-396/99003-01, " failure to
remove loose debris from the reactor building," occurred as stated,
'..
.
N
O
I
.