MONTHYEARML20217J3141999-10-15015 October 1999 Requests Emergency Publication of Document Entitled South Carolina Electric & Gas Co;Vc Summer Nuclear Station,Environ Assessment Transmitted on 991015 to Ofc of Fr for Publication ML20217J3281999-10-15015 October 1999 Forwards Copy of Environ Assessment & Finding of No Significant Impact Re Application for Exemption from Requiremets of 10CFR50,Section 50.60(a) for VC Summer Nuclear Station ML20217F8851999-10-0808 October 1999 Forwards Insp Rept 50-395/99-06 on 990801-0911.One Violation Occurred Being Treated as NCV RC-99-0192, Forwards Updated 1999 ECCS Evaluation Model Revs Rept for VC Summer Nuclear Station.Rept Is Being Submitted Pursuant to 10CFR50.46,which Requires Licensees to Notify NRC of Corrections to or Changes in ECCS Evaluation Models1999-09-28028 September 1999 Forwards Updated 1999 ECCS Evaluation Model Revs Rept for VC Summer Nuclear Station.Rept Is Being Submitted Pursuant to 10CFR50.46,which Requires Licensees to Notify NRC of Corrections to or Changes in ECCS Evaluation Models RC-99-0181, Forwards Anticipated Schedule for Operator Licensing Examinations.Sce&G Requests That NRC Prepare Examinations Stated on Attachment1999-09-21021 September 1999 Forwards Anticipated Schedule for Operator Licensing Examinations.Sce&G Requests That NRC Prepare Examinations Stated on Attachment ML20212C5091999-09-15015 September 1999 Forwards Anticipated Schedule for Operator Licensing Exams for Sce&G.Util Requests That NRC Prepare Exams on Encl RC-99-0184, Submits Seven Requests for Using Alternatives to Requirements of ASME Code,Section XI Re Subsection IWE & Iwl Insps to Be Performed at Vsns.Proposed Alternatives Will Provide Acceptable Level of Quality & Safety1999-09-15015 September 1999 Submits Seven Requests for Using Alternatives to Requirements of ASME Code,Section XI Re Subsection IWE & Iwl Insps to Be Performed at Vsns.Proposed Alternatives Will Provide Acceptable Level of Quality & Safety ML20212A8341999-09-0909 September 1999 Requests That Licensees Affected by Kaowool Fire Barriers Take Issue on Voluntary Initiative & Propose Approach for Resolving Subj Issues.Staff Plans to Meet with Licensees to Discuss Listed Topics ML20212A6951999-09-0909 September 1999 Requests That Licensees Affected by Kaowool Fire Barriers Take Issue on Voluntary Initiative & Propose Approach for Resolving Subj Issues.Staff Plans to Meet with Licensees to Discuss Listed Topics ML20211N4301999-09-0808 September 1999 Discusses Proposed Meeting to Discuss Kaowool Fire Barriers. Staff Requesting That Affected Licensees Take Issue on Voluntary Initative & Propose Approach for Resolving Issues ML20211Q8911999-09-0101 September 1999 Sumbits Summary of Training Managers Conference on Recent Changes to Operator Licensing Program.Meeting Covered Changes to Regulations,Exam Stds,New Insp Program & Other Training Issues.List of Attendees Encl RC-99-0177, Forwards Rev 2 to VC Summer Nuclear Station,Colr for Cycle 12, IAW Section 6.9.1.111999-08-31031 August 1999 Forwards Rev 2 to VC Summer Nuclear Station,Colr for Cycle 12, IAW Section 6.9.1.11 RC-99-0173, Requests That Info Listed in Rvid,Version 2,be Amended to Reflect Date for VC Summer Nuclear Station,As Marked in Encl to Ltr1999-08-31031 August 1999 Requests That Info Listed in Rvid,Version 2,be Amended to Reflect Date for VC Summer Nuclear Station,As Marked in Encl to Ltr ML20211L5181999-08-30030 August 1999 Forwards Insp Rept 50-395/99-05 on 990620-0731.One Violation Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20211H2481999-08-25025 August 1999 Forwards Four Controlled Copies of Amend 43 to Physcial Security Plan. Summary of Plan Changes, Are Included as Part of Each Controlled Copy.Encls Withheld Per 10CFR73.21 05000395/LER-1999-004, Submits Suppl 1 to LER 99-004-00 Re Discovery of Several Fuel Assembly Top Nozzle Holdown Screws Which Had Failed. Root Cause Will Not Be Completed by 990829,as Committed.W Analysis Will Be Issued After Fall Outages Are Complet1999-08-24024 August 1999 Submits Suppl 1 to LER 99-004-00 Re Discovery of Several Fuel Assembly Top Nozzle Holdown Screws Which Had Failed. Root Cause Will Not Be Completed by 990829,as Committed.W Analysis Will Be Issued After Fall Outages Are Completed RC-99-0171, Notifies NRC of Intent Re Submittal of Application to Renew OL of Vcs.Preparatory Work Has Begun to Develop Application for License Renewal to Be Submitted After 020806 Contingent Upon Final Approval of Board of Directors1999-08-23023 August 1999 Notifies NRC of Intent Re Submittal of Application to Renew OL of Vcs.Preparatory Work Has Begun to Develop Application for License Renewal to Be Submitted After 020806 Contingent Upon Final Approval of Board of Directors RC-99-0152, Seeks Exemption Under 10CFR0.12a(2)ii from 10CFR50,App G Requirements to Establish pressure-temperature Limits Curves Using Methodology Presented in 1989 ASME Section Xi,App G1999-08-19019 August 1999 Seeks Exemption Under 10CFR0.12a(2)ii from 10CFR50,App G Requirements to Establish pressure-temperature Limits Curves Using Methodology Presented in 1989 ASME Section Xi,App G RC-99-0164, Forwards semi-annual Fitness for Duty Rept from 990101 to 990630 for VC Summer Nuclear Station,Iaw 10CFR26.71(d)1999-08-17017 August 1999 Forwards semi-annual Fitness for Duty Rept from 990101 to 990630 for VC Summer Nuclear Station,Iaw 10CFR26.71(d) ML20210Q4851999-08-0505 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006 at VC Summer.Requests Info Re Individuals Who Will Take Exam,Personnel Who Will Have Access to Exam.Sample Registration Ltr Encl ML20210R5501999-08-0505 August 1999 Ack Receipt of 990707 Response to NCVs Identified on 990607 Re Activities Conducted at VC Summer.Informs That After Consideration of Basis for Denial of NCV 50-395/99-03, Concluded,For Reasons Stated,That NCV Occurred RC-99-0156, Forwards Rev 1 to VC Summer Nuclear Station COLR for Cycle 12, IAW TS Section 6.9.1.11.Sections 2.1 & 3.0 Were Added to Include Beacon Tsm1999-08-0404 August 1999 Forwards Rev 1 to VC Summer Nuclear Station COLR for Cycle 12, IAW TS Section 6.9.1.11.Sections 2.1 & 3.0 Were Added to Include Beacon Tsm RC-99-0147, Submits Attached Request for Relief from Performing SG PORV Strike Time Testing to Acceptance Criteria of Asme/Ansi OMa-19881999-07-26026 July 1999 Submits Attached Request for Relief from Performing SG PORV Strike Time Testing to Acceptance Criteria of Asme/Ansi OMa-1988 ML20210B7451999-07-22022 July 1999 Informs That as Result of Staff Review of Licensee Responses to GL 92-01,rev 1 & Rev 1,suppl 1,staff Revised Info in Reactor Vessel Integrity Database & Releasing Database as Rvid Version 2 ML20210E3771999-07-16016 July 1999 Forwards Insp Rept 50-395/99-04 on 990509-0619.One Violation Being Treated as Noncited Violation RC-99-0127, Estimates Submittal of Eleven Licensing Actions in Fy 2000. Based on Statistical Estimates of Past Licensing Actions, Number of Licensing Actions in Fy 2001 Should Be Approx Ten, in Response to AL 99-021999-07-0707 July 1999 Estimates Submittal of Eleven Licensing Actions in Fy 2000. Based on Statistical Estimates of Past Licensing Actions, Number of Licensing Actions in Fy 2001 Should Be Approx Ten, in Response to AL 99-02 RC-99-0129, Provides Response to non-cited Violations Noted in Insp Rept 50-395/99-03.C/As:concluded That Cask Loading Pit Inaccessible & Duration of Dose Rates on Operating Floor of Fhb So Short That High Radiation Area Did Not Exist1999-07-0707 July 1999 Provides Response to non-cited Violations Noted in Insp Rept 50-395/99-03.C/As:concluded That Cask Loading Pit Inaccessible & Duration of Dose Rates on Operating Floor of Fhb So Short That High Radiation Area Did Not Exist RC-99-0131, Forwards Rev 9 to VC Summer Nuclear Station Safeguards Contingency Plan,Per 10CFR50.54(p).Encl Withheld1999-07-0707 July 1999 Forwards Rev 9 to VC Summer Nuclear Station Safeguards Contingency Plan,Per 10CFR50.54(p).Encl Withheld ML20210B7111999-07-0606 July 1999 Provides Summary of 990701 Meeting with Sce&G in Atlanta, Georgia Re Recent Virgil C Summer Refueling Outage & Other Items of Interest.List of Meeting Attendees & Licensee Presentation Handouts Encl RC-99-0114, Submits Response to GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps, Under Oath or Affirmation1999-06-30030 June 1999 Submits Response to GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps, Under Oath or Affirmation ML20195H5861999-06-0707 June 1999 Confirms 990604 Telcon Between J Proper & R Haag Re Meeting Scheduled for 990701 in Atlanta,Ga,To Discuss Plant Refueling Outage & Items of Interest ML20207H5241999-06-0707 June 1999 Forwards Insp Rept 50-395/99-03 on 990328-0508.Six Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML20207D1881999-05-28028 May 1999 Informs That Effective 990524,K Cotton Assigned as Project Manager,Project Directorate II-1,for Virgil C Summer Nuclear Station 05000395/LER-1999-006, Forwards LER 99-006-00,describing Identified Safety Hazard with GE 7.2kV Magne-Blast Circuit Breakers.Event Is Being Reported Per 10CFR21.21a(1)1999-05-17017 May 1999 Forwards LER 99-006-00,describing Identified Safety Hazard with GE 7.2kV Magne-Blast Circuit Breakers.Event Is Being Reported Per 10CFR21.21a(1) RC-99-0104, Forwards Amend 17 to Training & Qualification Plan, Under Provisions of 10CFR50.54(p).Summary of Plan Changes Is Included as Part of Controlled Copy1999-05-13013 May 1999 Forwards Amend 17 to Training & Qualification Plan, Under Provisions of 10CFR50.54(p).Summary of Plan Changes Is Included as Part of Controlled Copy RC-99-0105, Forwards Copy of Sce&G Co 1998 Annual Financial Rept & Sc Public Service Authority 1998 Annual Financial Rept, for VC Summer Nuclear Station1999-05-13013 May 1999 Forwards Copy of Sce&G Co 1998 Annual Financial Rept & Sc Public Service Authority 1998 Annual Financial Rept, for VC Summer Nuclear Station 05000395/LER-1999-005, Forwards LER 99-005-00 for VC Summer Nuclear Station.Rept Describes Potential Condition for Exceeding Vsns Plant Design Basis Due to Submergence Qualification Issues for Certain ESF Components1999-05-12012 May 1999 Forwards LER 99-005-00 for VC Summer Nuclear Station.Rept Describes Potential Condition for Exceeding Vsns Plant Design Basis Due to Submergence Qualification Issues for Certain ESF Components ML20206L5121999-05-11011 May 1999 Informs That NRC Reorganized,Effective 990328.Reorganization Chart Encl ML20206P5771999-05-0707 May 1999 Informs That During 980519 Telcon Between T Matlosz & G Hopper,Arrangements Were Made for Administration of Licensing Exam at Virgil C Summer Nuclear Station During Wk of 990927 RC-99-0080, Submits Supplemental Info Re 970128 Response to NRC GL 96-06 Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions. Addl Analysis & Manpower Expenditure Involved Not Cost Effective1999-05-0606 May 1999 Submits Supplemental Info Re 970128 Response to NRC GL 96-06 Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions. Addl Analysis & Manpower Expenditure Involved Not Cost Effective RC-99-0097, Forwards Sce&G Cycle 12 COLR, IAW TS Section 6.9.1.111999-05-0606 May 1999 Forwards Sce&G Cycle 12 COLR, IAW TS Section 6.9.1.11 RC-99-0092, Informs That Util Has Reviewed Proposed Notice of Rulemaking & Fully Endorse Comments Prepared & Submitted on Behalf of Commercial Nuclear Power Industry by NEI1999-05-0303 May 1999 Informs That Util Has Reviewed Proposed Notice of Rulemaking & Fully Endorse Comments Prepared & Submitted on Behalf of Commercial Nuclear Power Industry by NEI RC-99-0090, Submits Special Rept (Spr 1999-003) Re Completion of ISI of SG Tubes,Indicating Number of Tubes Plugged or Repaired in Each Generator,Per TS 4.4.5.5.a & Section 4.4.5.5.b1999-04-29029 April 1999 Submits Special Rept (Spr 1999-003) Re Completion of ISI of SG Tubes,Indicating Number of Tubes Plugged or Repaired in Each Generator,Per TS 4.4.5.5.a & Section 4.4.5.5.b ML20206E1681999-04-29029 April 1999 Informs That FERC & NRC Will Conduct Category I Svc Water Pond (Swp) Dam Insp at Facility on 990610 ML20206P5021999-04-26026 April 1999 Forwards Insp Rept 50-395/99-02 on 990214-0327.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation,Consistent with App C of Enforcement Policy ML20205M0431999-04-13013 April 1999 Eighth Partial Response to FOIA Request for Records.App Q & R Records Encl & Being Made Available in PDR 05000395/LER-1999-002, Forwards LER 99-002-00 Re Condition for Exceeding Vsns Design Basis During Surveillance Testing Utilizing Certain ECCS Valves.Simplified Flow Diagram Included to Identify Configurations Discussed by Rept Encl1999-04-12012 April 1999 Forwards LER 99-002-00 Re Condition for Exceeding Vsns Design Basis During Surveillance Testing Utilizing Certain ECCS Valves.Simplified Flow Diagram Included to Identify Configurations Discussed by Rept Encl ML20205T2311999-04-0909 April 1999 Informs That on 990318,A Koon & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Date Schedules for Wk of 000807 for Approx Eight Candidates ML20205G4181999-04-0101 April 1999 Advises That 970725 Application & Affidavit Which Submitted, WCAP-14932, Probabilistic & Economic Evaluation of Reactor Vessel Closure Head Penetration Integrity for Plant, Will Be Withheld from Public Disclosure,Per 10CFR2.790(a)(4) RC-99-0078, Submits Summary of Present Levels of Property Insurance & Cash Flow Statement for VC Summer Nuclear Station,Per 10CFR50.54(w)(3) & 10CFR140.21(e)1999-04-0101 April 1999 Submits Summary of Present Levels of Property Insurance & Cash Flow Statement for VC Summer Nuclear Station,Per 10CFR50.54(w)(3) & 10CFR140.21(e) 1999-09-09
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARRC-99-0192, Forwards Updated 1999 ECCS Evaluation Model Revs Rept for VC Summer Nuclear Station.Rept Is Being Submitted Pursuant to 10CFR50.46,which Requires Licensees to Notify NRC of Corrections to or Changes in ECCS Evaluation Models1999-09-28028 September 1999 Forwards Updated 1999 ECCS Evaluation Model Revs Rept for VC Summer Nuclear Station.Rept Is Being Submitted Pursuant to 10CFR50.46,which Requires Licensees to Notify NRC of Corrections to or Changes in ECCS Evaluation Models RC-99-0181, Forwards Anticipated Schedule for Operator Licensing Examinations.Sce&G Requests That NRC Prepare Examinations Stated on Attachment1999-09-21021 September 1999 Forwards Anticipated Schedule for Operator Licensing Examinations.Sce&G Requests That NRC Prepare Examinations Stated on Attachment ML20212C5091999-09-15015 September 1999 Forwards Anticipated Schedule for Operator Licensing Exams for Sce&G.Util Requests That NRC Prepare Exams on Encl RC-99-0184, Submits Seven Requests for Using Alternatives to Requirements of ASME Code,Section XI Re Subsection IWE & Iwl Insps to Be Performed at Vsns.Proposed Alternatives Will Provide Acceptable Level of Quality & Safety1999-09-15015 September 1999 Submits Seven Requests for Using Alternatives to Requirements of ASME Code,Section XI Re Subsection IWE & Iwl Insps to Be Performed at Vsns.Proposed Alternatives Will Provide Acceptable Level of Quality & Safety RC-99-0177, Forwards Rev 2 to VC Summer Nuclear Station,Colr for Cycle 12, IAW Section 6.9.1.111999-08-31031 August 1999 Forwards Rev 2 to VC Summer Nuclear Station,Colr for Cycle 12, IAW Section 6.9.1.11 RC-99-0173, Requests That Info Listed in Rvid,Version 2,be Amended to Reflect Date for VC Summer Nuclear Station,As Marked in Encl to Ltr1999-08-31031 August 1999 Requests That Info Listed in Rvid,Version 2,be Amended to Reflect Date for VC Summer Nuclear Station,As Marked in Encl to Ltr ML20211H2481999-08-25025 August 1999 Forwards Four Controlled Copies of Amend 43 to Physcial Security Plan. Summary of Plan Changes, Are Included as Part of Each Controlled Copy.Encls Withheld Per 10CFR73.21 05000395/LER-1999-004, Submits Suppl 1 to LER 99-004-00 Re Discovery of Several Fuel Assembly Top Nozzle Holdown Screws Which Had Failed. Root Cause Will Not Be Completed by 990829,as Committed.W Analysis Will Be Issued After Fall Outages Are Complet1999-08-24024 August 1999 Submits Suppl 1 to LER 99-004-00 Re Discovery of Several Fuel Assembly Top Nozzle Holdown Screws Which Had Failed. Root Cause Will Not Be Completed by 990829,as Committed.W Analysis Will Be Issued After Fall Outages Are Completed RC-99-0171, Notifies NRC of Intent Re Submittal of Application to Renew OL of Vcs.Preparatory Work Has Begun to Develop Application for License Renewal to Be Submitted After 020806 Contingent Upon Final Approval of Board of Directors1999-08-23023 August 1999 Notifies NRC of Intent Re Submittal of Application to Renew OL of Vcs.Preparatory Work Has Begun to Develop Application for License Renewal to Be Submitted After 020806 Contingent Upon Final Approval of Board of Directors RC-99-0152, Seeks Exemption Under 10CFR0.12a(2)ii from 10CFR50,App G Requirements to Establish pressure-temperature Limits Curves Using Methodology Presented in 1989 ASME Section Xi,App G1999-08-19019 August 1999 Seeks Exemption Under 10CFR0.12a(2)ii from 10CFR50,App G Requirements to Establish pressure-temperature Limits Curves Using Methodology Presented in 1989 ASME Section Xi,App G RC-99-0164, Forwards semi-annual Fitness for Duty Rept from 990101 to 990630 for VC Summer Nuclear Station,Iaw 10CFR26.71(d)1999-08-17017 August 1999 Forwards semi-annual Fitness for Duty Rept from 990101 to 990630 for VC Summer Nuclear Station,Iaw 10CFR26.71(d) RC-99-0156, Forwards Rev 1 to VC Summer Nuclear Station COLR for Cycle 12, IAW TS Section 6.9.1.11.Sections 2.1 & 3.0 Were Added to Include Beacon Tsm1999-08-0404 August 1999 Forwards Rev 1 to VC Summer Nuclear Station COLR for Cycle 12, IAW TS Section 6.9.1.11.Sections 2.1 & 3.0 Were Added to Include Beacon Tsm RC-99-0147, Submits Attached Request for Relief from Performing SG PORV Strike Time Testing to Acceptance Criteria of Asme/Ansi OMa-19881999-07-26026 July 1999 Submits Attached Request for Relief from Performing SG PORV Strike Time Testing to Acceptance Criteria of Asme/Ansi OMa-1988 RC-99-0129, Provides Response to non-cited Violations Noted in Insp Rept 50-395/99-03.C/As:concluded That Cask Loading Pit Inaccessible & Duration of Dose Rates on Operating Floor of Fhb So Short That High Radiation Area Did Not Exist1999-07-0707 July 1999 Provides Response to non-cited Violations Noted in Insp Rept 50-395/99-03.C/As:concluded That Cask Loading Pit Inaccessible & Duration of Dose Rates on Operating Floor of Fhb So Short That High Radiation Area Did Not Exist RC-99-0131, Forwards Rev 9 to VC Summer Nuclear Station Safeguards Contingency Plan,Per 10CFR50.54(p).Encl Withheld1999-07-0707 July 1999 Forwards Rev 9 to VC Summer Nuclear Station Safeguards Contingency Plan,Per 10CFR50.54(p).Encl Withheld RC-99-0127, Estimates Submittal of Eleven Licensing Actions in Fy 2000. Based on Statistical Estimates of Past Licensing Actions, Number of Licensing Actions in Fy 2001 Should Be Approx Ten, in Response to AL 99-021999-07-0707 July 1999 Estimates Submittal of Eleven Licensing Actions in Fy 2000. Based on Statistical Estimates of Past Licensing Actions, Number of Licensing Actions in Fy 2001 Should Be Approx Ten, in Response to AL 99-02 RC-99-0114, Submits Response to GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps, Under Oath or Affirmation1999-06-30030 June 1999 Submits Response to GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps, Under Oath or Affirmation 05000395/LER-1999-006, Forwards LER 99-006-00,describing Identified Safety Hazard with GE 7.2kV Magne-Blast Circuit Breakers.Event Is Being Reported Per 10CFR21.21a(1)1999-05-17017 May 1999 Forwards LER 99-006-00,describing Identified Safety Hazard with GE 7.2kV Magne-Blast Circuit Breakers.Event Is Being Reported Per 10CFR21.21a(1) RC-99-0104, Forwards Amend 17 to Training & Qualification Plan, Under Provisions of 10CFR50.54(p).Summary of Plan Changes Is Included as Part of Controlled Copy1999-05-13013 May 1999 Forwards Amend 17 to Training & Qualification Plan, Under Provisions of 10CFR50.54(p).Summary of Plan Changes Is Included as Part of Controlled Copy RC-99-0105, Forwards Copy of Sce&G Co 1998 Annual Financial Rept & Sc Public Service Authority 1998 Annual Financial Rept, for VC Summer Nuclear Station1999-05-13013 May 1999 Forwards Copy of Sce&G Co 1998 Annual Financial Rept & Sc Public Service Authority 1998 Annual Financial Rept, for VC Summer Nuclear Station 05000395/LER-1999-005, Forwards LER 99-005-00 for VC Summer Nuclear Station.Rept Describes Potential Condition for Exceeding Vsns Plant Design Basis Due to Submergence Qualification Issues for Certain ESF Components1999-05-12012 May 1999 Forwards LER 99-005-00 for VC Summer Nuclear Station.Rept Describes Potential Condition for Exceeding Vsns Plant Design Basis Due to Submergence Qualification Issues for Certain ESF Components RC-99-0097, Forwards Sce&G Cycle 12 COLR, IAW TS Section 6.9.1.111999-05-0606 May 1999 Forwards Sce&G Cycle 12 COLR, IAW TS Section 6.9.1.11 RC-99-0080, Submits Supplemental Info Re 970128 Response to NRC GL 96-06 Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions. Addl Analysis & Manpower Expenditure Involved Not Cost Effective1999-05-0606 May 1999 Submits Supplemental Info Re 970128 Response to NRC GL 96-06 Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions. Addl Analysis & Manpower Expenditure Involved Not Cost Effective RC-99-0092, Informs That Util Has Reviewed Proposed Notice of Rulemaking & Fully Endorse Comments Prepared & Submitted on Behalf of Commercial Nuclear Power Industry by NEI1999-05-0303 May 1999 Informs That Util Has Reviewed Proposed Notice of Rulemaking & Fully Endorse Comments Prepared & Submitted on Behalf of Commercial Nuclear Power Industry by NEI RC-99-0090, Submits Special Rept (Spr 1999-003) Re Completion of ISI of SG Tubes,Indicating Number of Tubes Plugged or Repaired in Each Generator,Per TS 4.4.5.5.a & Section 4.4.5.5.b1999-04-29029 April 1999 Submits Special Rept (Spr 1999-003) Re Completion of ISI of SG Tubes,Indicating Number of Tubes Plugged or Repaired in Each Generator,Per TS 4.4.5.5.a & Section 4.4.5.5.b 05000395/LER-1999-002, Forwards LER 99-002-00 Re Condition for Exceeding Vsns Design Basis During Surveillance Testing Utilizing Certain ECCS Valves.Simplified Flow Diagram Included to Identify Configurations Discussed by Rept Encl1999-04-12012 April 1999 Forwards LER 99-002-00 Re Condition for Exceeding Vsns Design Basis During Surveillance Testing Utilizing Certain ECCS Valves.Simplified Flow Diagram Included to Identify Configurations Discussed by Rept Encl RC-99-0078, Submits Summary of Present Levels of Property Insurance & Cash Flow Statement for VC Summer Nuclear Station,Per 10CFR50.54(w)(3) & 10CFR140.21(e)1999-04-0101 April 1999 Submits Summary of Present Levels of Property Insurance & Cash Flow Statement for VC Summer Nuclear Station,Per 10CFR50.54(w)(3) & 10CFR140.21(e) RC-99-0066, Submits Rept of Status of Decommissioning Funding (RR-1950), for Vsns Per 10CFR50.751999-03-31031 March 1999 Submits Rept of Status of Decommissioning Funding (RR-1950), for Vsns Per 10CFR50.75 ML20205B9981999-03-29029 March 1999 Informs That Authority & Sce&G Has Ownership Interests of one-third & two-thirds,respectively in VC Summer Nuclear Station.Operating License Scheduled to Expire in 2022.Rept Addresses Decommissioning Cost Estimates & Financing RC-99-0054, Forwards Rev 2 to VC Summer Nuclear Station Training Simulator Quadrennial Certification Rept,1996-99, Per 10CFR55.45(b)(5)(ii)1999-03-22022 March 1999 Forwards Rev 2 to VC Summer Nuclear Station Training Simulator Quadrennial Certification Rept,1996-99, Per 10CFR55.45(b)(5)(ii) RC-99-0053, Requests That Implementation Date of Proposed TS Change Request Re Best Estimate Analyzer for Core Operations - Nuclear (Beacon) Be Extended. Util Requests 120 Day Time Frame to Perform Initial Beacon Calibrs During Cycle 121999-03-22022 March 1999 Requests That Implementation Date of Proposed TS Change Request Re Best Estimate Analyzer for Core Operations - Nuclear (Beacon) Be Extended. Util Requests 120 Day Time Frame to Perform Initial Beacon Calibrs During Cycle 12 RC-99-0048, Informs That Util Has Implemented Policy That Requires All Personnel Granted Unescorted Access to Vsns Satisfactorily Complete Test on Site Specific Info1999-03-10010 March 1999 Informs That Util Has Implemented Policy That Requires All Personnel Granted Unescorted Access to Vsns Satisfactorily Complete Test on Site Specific Info ML20207J5661999-02-16016 February 1999 Requests That Proprietary Rev 1 to WCAP-14932 Re Rv Closure Head Penetrations Integrity for VC Summer Nuclear Plant,Be Withheld from Public Disclosure,Per 10CFR2.790(b)(4) RC-99-0026, Provides Response to NRC RAI Re TS Change Request Re Best Estimate Analyzer for Core Operations - Nuclear1999-02-0505 February 1999 Provides Response to NRC RAI Re TS Change Request Re Best Estimate Analyzer for Core Operations - Nuclear RC-99-0023, Informs That in Response to GL 97-06,SCE&G Informed NRC of Plan to Perform Secondary Side Examination Scheduled for Refueling Outage RF-11.SCE&G Has Decided to Defer Secondary Side Insp of Sg.Reasons for Change of Plan Listed1999-02-0101 February 1999 Informs That in Response to GL 97-06,SCE&G Informed NRC of Plan to Perform Secondary Side Examination Scheduled for Refueling Outage RF-11.SCE&G Has Decided to Defer Secondary Side Insp of Sg.Reasons for Change of Plan Listed 05000395/LER-1998-009, Forwards LER 98-009-01 for VC Summer Nuclear Station.Rept Describes Unanalyzed Condition for non-safety Related Component for Which All Failure Mechanisms Had Not Been Evaluated1999-01-28028 January 1999 Forwards LER 98-009-01 for VC Summer Nuclear Station.Rept Describes Unanalyzed Condition for non-safety Related Component for Which All Failure Mechanisms Had Not Been Evaluated RC-99-0015, Forwards Amend 16 to Training & Qualification Plan,Per 10CFR50.54(p).Summary of Changes,Encl1999-01-22022 January 1999 Forwards Amend 16 to Training & Qualification Plan,Per 10CFR50.54(p).Summary of Changes,Encl RC-99-0005, Responds to 980908 RAI Re GL 97-01, Degradation of Control Rod Drive Mechanism Nozzle & Other Vessel Closure Head Penetrations1999-01-15015 January 1999 Responds to 980908 RAI Re GL 97-01, Degradation of Control Rod Drive Mechanism Nozzle & Other Vessel Closure Head Penetrations RC-98-0225, Forwards Rev 41 to EP-100, Radiation Emergency Plan. List of Changes by Page Number Affected by Rev 41 Also Encl1998-12-14014 December 1998 Forwards Rev 41 to EP-100, Radiation Emergency Plan. List of Changes by Page Number Affected by Rev 41 Also Encl RC-98-0226, Forwards Amend 42 to Psp.Changes Do Not Degrade Safeguards Effectiveness in PSP or Safeguards Contingency Plan,As Described in 10CFR50.54(p).Without Encl1998-12-14014 December 1998 Forwards Amend 42 to Psp.Changes Do Not Degrade Safeguards Effectiveness in PSP or Safeguards Contingency Plan,As Described in 10CFR50.54(p).Without Encl RC-98-0216, Requests Extension of Response Period to 990115 to Respond to NRC 980908 RAI Re GL 97-01, Degradation of CRDM Nozzle & Other Vessel Closure Head Penetrations. Util Intends to Utilize Industry Generic RAI Response1998-12-0404 December 1998 Requests Extension of Response Period to 990115 to Respond to NRC 980908 RAI Re GL 97-01, Degradation of CRDM Nozzle & Other Vessel Closure Head Penetrations. Util Intends to Utilize Industry Generic RAI Response RC-98-0189, Provides Assessment Results of GL 98-02, Loss of Rc Inventory & Associated Potential for Loss of Emergency Mitigation Functions While in Shutdown Condition, Per 10CFR50.54f1998-11-24024 November 1998 Provides Assessment Results of GL 98-02, Loss of Rc Inventory & Associated Potential for Loss of Emergency Mitigation Functions While in Shutdown Condition, Per 10CFR50.54f RC-98-0207, Forwards 120-day Response to NRC GL 98-04, Potential for Degradation of ECCS & CSS After LOCA Because of Construction & Protective Coating Deficiencies & Foreign Matl in Containment1998-11-11011 November 1998 Forwards 120-day Response to NRC GL 98-04, Potential for Degradation of ECCS & CSS After LOCA Because of Construction & Protective Coating Deficiencies & Foreign Matl in Containment RC-98-0177, Informs That Sce&G Will Classify as Moderate Any Stratification Condition That Results in Total Cuf,Based on Design Basis Values Plus Any Contribution from Stratification,Of Between 0.1 & 0.71998-11-0909 November 1998 Informs That Sce&G Will Classify as Moderate Any Stratification Condition That Results in Total Cuf,Based on Design Basis Values Plus Any Contribution from Stratification,Of Between 0.1 & 0.7 RC-98-0194, Provides Response to RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of SR Movs1998-11-0202 November 1998 Provides Response to RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of SR Movs RC-98-0202, Forwards Response to RAI Re Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions1998-10-30030 October 1998 Forwards Response to RAI Re Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions RC-98-0186, Expresses Appreciation for Opportunity to Present Topical Rept TR-104965, On-Line Monitoring of Instrument Channel Performance1998-10-26026 October 1998 Expresses Appreciation for Opportunity to Present Topical Rept TR-104965, On-Line Monitoring of Instrument Channel Performance RC-98-0185, Forwards non-proprietary Trs,Including Rev 0 to WCAP-15101, Analysis of Capsule W from Sce&G VC Summer Unit 1 Rv Radiation Surveillance Program & Rev 0 to WCAP-15103, Evaluation of PTS for VC Summer Unit 11998-10-0909 October 1998 Forwards non-proprietary Trs,Including Rev 0 to WCAP-15101, Analysis of Capsule W from Sce&G VC Summer Unit 1 Rv Radiation Surveillance Program & Rev 0 to WCAP-15103, Evaluation of PTS for VC Summer Unit 1 RC-98-0182, Responds to 980402 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs1998-10-0808 October 1998 Responds to 980402 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs RC-98-0178, Provides Comments on SALP Insp Rept 50-395/98-99.Util Ack That Station Can Enhance Future Performance Further with More Focus & Attention on Change Mgt Practices Re Plant & Procedure Changes1998-10-0505 October 1998 Provides Comments on SALP Insp Rept 50-395/98-99.Util Ack That Station Can Enhance Future Performance Further with More Focus & Attention on Change Mgt Practices Re Plant & Procedure Changes 1999-09-28
[Table view] |
Text
wy
g
" ) . . .
- L Q,
, ; . / .s October 8,1998 1; ^
@Edd 4 1
. A SCANA COMPANY RC-98-0182 rip Document Control Desk
> 7 '
U. S. Nuclear Regulatory Commission
>, i Washington, DC 20555 '
a= .n
,f A, Attention: Mr. L. M. Padovan j
fn ' q~ .
N Gentlemen: '
...jE l
Subject:
VIRGIL C. SUMMER NUCLEAR STATION '
A Gary N.! -
DOCKET NO. 50/395 Jiiehesikaf M.j$
4dktoparas ~ - OPERATING LICENSE NO. NPF-12
., J REQUEST FOR ADDITIONAL INFORMATION -
d@t M ..
- 3 GENERIC LETTER 96-05, (TAC NO. M97106) l I' , .'I " PERIODIC VERIFICATION OF DESIGN BASIS CAPABILITY !
i OF SAFETY-RELATED MOTOR-OPERATED VALVES" w
'-~,.e' c
,3
_..l..
i
, @ Roerence: Stephen A. Byrne letter RC-98-0070 to the Document Control
' bg% ' ] Desk dated April 2,1998;" Response to Safety Evaluation for the
<jg. j Joint Group Program on Periodic Verification of Motor Operated J swhculineDeM& Gas Co y Valves" i VirgilC Samer_kles StpN
'Nahauthbdi[% Pursuant to your request for additional information, South Carolina Electric & ;
43j J Gas Compar.y (SCE&G) is submitting the attached documentation under oath ,
_, of affirmation.
.S(803345A344!. .
+'
y j803.345S09; -
' ' Should you have any questions, please call Mr.Jeffrey W. Pease, at (803) 345- ,
jf, i$]"" ,
4124, at your convenience. !
3
,m _a n.g ~
Very truly yours,
$n1 - ,
. g
- j (//(AA*c4 j;
, 9s Yrjr s 3 Gary J. Taylor l pWM M JWP/GJT/dr }
lg_dMDT' j j& a -
Attachment
'g i@p,p.g P Te g ,y + -- 2 hO
.c "~79g'101303o5 991000 f 4
h
, d, . . d PDR P
ADOCK 05000395 PDR[
, , yw ny -
\
w 3, %cp, %~ ' l3 NUCl. EAR EXCELLENCE- A SUMMER TRADITION!
l! y }f q
- p. mn
j; i '
1 -
Docum:;nt Control Desk LTR 960005 '
RC-98-0182 P' age 2 of 2 I i L i l c: J. L. Skolds W. F. Conway R. R. Mahan (w/o Attachment)
R. J. White L.A.Reyes L M. Padovan
- s. NRC Resident inspector P
J. B. Knotts, Jr. i NSRC RTS (LTR 960005)
File (815.14) _
l DMS (RC-98-0182) l l
l I
i l STATE OF SOUTH CAROLINA :
- TO WIT :
COUNTY OF FAIRFIELD :
l hereby certify that on the M day of (AfoAre l 191 before me, the subscriber, L a Notary Pubhc of the State of South Carolina personally appeared Bruce C. Williams, I being duly sworn, and states that he has signature authonty for the Vice President, Nuclear Operations of the South Carolina Electric & Gas Company, a corporation of tbs State of South Carolina, that he provides the foregoing response for the purposes therein set forth, that the statements made are true anc correct to the best of his knowledge, information, and belief, and that he was authorized to provide the response on behalf of said Corporation.
WITNESS my Hand and Notarial Seal Ad/
/ Notary Public L
- My Commission Expires 7t 4 / 3 . 2. ,e r Date e
i
,- '7-1, I
' h! ,y*$~ ,
- t. l U l
Document Control Desk Attachment LTR 960005 RC-98-O'182 Page 1 of 8 Per your Request for Additional Information on Generic Letter 96-05, dated August 6, 1998, VCSNS submits the following response. The questions are restated below followed by the VCSNS response.
As background to the specific responses provided, the following information should be noted. SCE&G has an established plant specific MOV periodic verification (PV) program as described in our response to GL 96 05 (Reference letter RC-97-0052, dated March 13,1997). SCE&G considers plant-specific data to be the best source of information for our long-term PV Prc7 ram. SCE&G is participating in the Joint Owners Group (JOG) PV Program to enhe' 4 our own program and make our test data available to the industry. SCE&G .. supporting the JOG initiative by providing information on safety-related MOV performance from our site specjfic periodic verification program. SCE&G was the first utsty to complete both the first and second dynamic test for our two assigned JOG valves and the third and final JOG dynamic test is scheduled for RF 12 (Fall 2000). As stated in our letter RC-98-0070, dated 4/2/98.
SCE&G will review the data received from the JOG MOV PV Program and will incorporate the data into our plant specific program as applicable. The SCE&G PV program requirements are consistent with the JOG PV Program requirements as identified in MPR-1807, ' Joint BWR, Westinghouse and Combustion Engineering Owners' Group Program on Motor-Operated Valve (MOV) Periodic Verification',
Revision 2, dated July 1997 and the Westinghouse Risk Ranking Methodology as identified in ,W report V-EC-1658-A, Revision 2. The SCE&G PV program is a living program and will be modified, as necessary, based on plant specific and applicable
, industry information.
Question 1 Your March 13,1997, letter states that the scope of the motor-operated valve (MOV) program at the V. C. Summer Nuclear Station in response to Generic Letter (GL) 96-05 is the same as your station program in response to GL 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance. Your MOV periodic verification program should cover all GL 89-10 MOVs. In addition, GL 96-05 Indicated you should also consider safety-related MOVs assumed to be capable of returning to their safety position when placed in a position that prevents their safety system (or train) from performing its safety function.
This applies if you do not declare the system (or train) Inoperable when the MOVs are in their non-sarety position. Describe how you considered any such MOVs with respect to your GL 96-05 program at V. C. Summer.
Documsnt Control Desk Attachment LTR 960005 RD '98-01'82 Page 2 of 8 i
j Response 1 !
VCSNS has 18 Safety-Related MOVs that are not within the GL 89-10 scope.
4 Review of the non-GL 89-10 MOVs indicates that none of the valves are placed in a i position that would prevent their safety system (or train) from performing its safety
[ function within the design basis of the plant without declaring the associated system
- (or train) inoperable. VCSNS reconvened the MOV Expert Panel to review the SR MOVs outside the GL 89-10 scope to determine if any additional valves needed to i be added due to GL 96-05 requirements. GL 96-05 states that "The program should 1 include Safety-Related MOVs that are assumed to be capable of returning to their safety position when placed in a position that prevents their safety system (or train)
- from performing its safety function" within the current licensing basis of the plant.
i The Expert Panel provided the interdisciplinary input necessary to ensure that all valves required to be within the GL 96-05 scope are identified and properly included
) in the GL 89-10/96-05 scope. VCSNS has made licensing commitments that take a
credit for the Reactor Vessel Head Vent Valves (NUREG-0578). The Export Panel j concluded that the Reactor Vessel Head Vent Valves were the only additional valves that should be included in the GL 89-10/96-05 program based on the GL 96- 1 j 05 requirements. The Reactor Vessel Head Vent valves have been added to the j GL 89-10/96-05 scope due to GL 96-05 requirements only.
Question 2 i You state in your letter that six valves will undergo two additional dynamic tests by July 27,2005. Describe the evaluation performed to confirm that i information from tests of these six valves !s sufficient to determine the i degradation rate for the potential increase in thrust (torque) requirements for l all GL 96-05 MOVs at V. C. Summer.
j Resoonse 2 3
i VCSNS considers plant-specific test data to be the best source of information for i our long-term Periodic Verification (PV) program. The six valves were selected for
! additional dynamic testing based on rist, significance, testability, and applicability to i other GL 89-10/96-05 MOVs. The most risk significant valves (category 1) were then ranked for testing based on a quantitative estimate of the overall benefit of periodic dynamic testing. The six valves include butterfly and gate valves, and represent a cross-section of the three major valve suppliers for VCSNS. The six valves have also been evaluated for valve age degradation grouping based on ]
Docum::nt Control D sk Attachment LTR 9S0005 RD-98 0f82 Page 3 of 8 general similarities in valve design, materials, and application of the valves (especially the fluid environment). VCSNS is participating in the JOG PV program (Reference Letter #RC-98-0070, dated April 2,1998) and will utilize the results of the JOG PV program for specific applications / material pairs which are not fully represented by the valves being tested at VCSNS.
Question 3 In your letter, you do not discuss actuator output under dynamic conditions.
Describe your method for ensuring adequate actuator output, considering recent Limitorque guidance in Technical Update 98-01, and its Supplement 1.
Also, describe your method for determining the degradation rate associated with aging effects that could result in a potential decrease in actuator output.
Response 3 VCSNS has revised the design basis capabilities of all the station's GL 89-10/96-05 MOV actuators using information made available and documented in Commonwealth Edison White Paper 125. Implementing the Commonwealth Edison methodology in its entirety ensures adequate actuator output, considering the recent Limitorque guidance in Technical Update 98-01, and its Supplement 1. Five of the six valves slated for additional dynamic testing are rising stem flexible wedge gate valves. The stem-stem nut material pair is stainless steel-brass which is the same for all the station's GL 89-10/96-05 rising stem gate valves. The station's GL 89-10/96-05 MOVs use the same stem lubricant and have established lubrication frequencies. The sixth valve is a butterfly valve with a Limitorque actuator and a HBC gear box which is typical of all the station's GL 89-10/96-05 butterfly valves.
VCSNS has established a trending program to trend load sensitive behavior (LSB),
open/close stem friction coefficients and valve factor capability / margin under dynamic conditions. The periodic dynamic testing at VCSNS to date does not indicate any appreciable actuator degradation.
Question 4 Your letter indicated that you will perform periodic static diagnostic testing on your GL 96-05 MOVs. Describe the basis for your periodic test method to identify age-related degradation affecting thrust (torque) operating requirements and actuator output for all GL 96-05 MOVs.
u - . . _ _ - .
~
~
Document Control Desk Attachment LTR 960005 RC-98-0182 Page 4 of 8 Response 4 All the station's GL 89-10/96-05 MOVs will be diagnostically tested under static s
conditions at least once every 10 years. The static diagnostic testing is designed to provide information on the thrust and torque output of the motor-actuator and any changes to the motor-actuator as a rceult of aging offects such as increased stem
, friction coefficients or reduced thrust at Control Switch Trip (CST). VCSNS has l established a trending program to trend motor power / current, open/close stem friction coefficients, valve operating torque, running load / packing load, seating thrust and unseating thrust and valve factor capability / margin. The data used to trend MOV performance includes MOV failure and deficiency data, diagnostic test results, and industry data. The periodic reverification of MOV performance is intended to provide objective evidence of actuator capability and performance over l time. .
l Q,uestion 5 Justify any MOV grouping to share test Information or minimize testing.
Response 5 Valves in the GL 89-10/96-05 program are grouped by similarity of valve, actuator and application. Valves are grouped for age degradation based on similarities in I valve design, materials and application of the valve (especially the fluid environment). MOV equNalency is established consistent with the JOG periodic verification program (Reference MPR-1807 ' Joint BWR, Westinghouse and Combustion Engineering Owners' Group Program on Motor-Operated Valve Periodic Verification', Revision 2 dated July 1997, and JOG Position Paper PP-03,
' Scope of MOVs Covered by the JOG Program and Valve Grouping', Rev.0).
Actuator age degradation grouping is established with respect to actuator type, i control configuration and stem-stem nut material pair. The station's rising stem i MOVs are represented by two types of actuators (Limitorque and Rotork). The l stem-stem nut material pair for all tha station's rising stem MOVs is stainless steel-brass and the same stem lubricant is used on all valves. Periodic lubrication
- frequencies have been established for the actuator gearboxes and stem / stem nuts.
j The station's GL 89-10/96-05 quarter turn MOVs are all Henry Pratt butterfly valves
- with Limitorque actuators and HBC gear boxes.
]
l i
}
Document Control D:sk Attachment
)
LTR 960005 !
R'C '98-0182 I Page 5 of 8 1 Question 6 1
You state in ywr letter that you will place each MOV in the GL 96-05 program !
In a Probabilistic Risk Assessment (PRA) Group of high, medium or low risk. !
Describe the MOV risk-ranking methodology applied at V. C. Summer.
Response 6 I
VCSNS performed MOV risk ranking by a method similar to the WOG MOV risk i ranking methodology. The VCSNS MOV risk ranking was performed in July 1995, one year before revision 0 of the Westinghouse report V-EC-1658 was issued, and l
three years before the final revision was issued. The primary difference is the threshold for the different risk levels as described below. Both methods use the at-power PRA model supplemented by Expert Panel judgment for shutdown risk, external events, initiating events and containment performance. VCSNS is in the process of performing a data update to the PRA model. When this task is complete the MOV risk ranking may be revised. Consideration will be given at that time to adopting the WOG methodology for consistency with the industry.
The VCSNS MOV risk ranking methodology (for MOVs modeled in the PRA) is based on Risk Achievement Worth (RAW) and Risk Reduction Worth (RRW). A j and B train valves were grouped together and then a group importance value was l obtained based on Core Damage Frequency. The valves were then grouped in l
Risk Significance Categories of 1,2, and 3, similar to the High, Medium, and Low of the WOG methodology. The table below shows that the VCSNS thresholds for the various levels are more conservative than that shown for the WOG methodology.
While RRW was also calculated, it was found to be a subset of the RAW levels; i.e.
the RAW would escalate an MOV to a higher level before the RRW.
Westinghouse VCS Category WOG Criteria VCSNS Criteria Category H 1 RAW >10 RAW >1.99 M 2 10> RAW >2 1.99> RAW >1 L 3 RAW <2 RAW =1.0
- The Expert Panel reviewed MOVs categorized by the above criteria and then i revised the levels accordingly. For example, the Containment Spray System MOVs l were category 3 based on CDF but were increased to level 2 based on their j importance to containment performance. The Expert Panel also reviewed valves j that were not modeled in the at-power PRA, but were important from the standpoint j of shutdown, external events, or offsite dose.
i
Document Control Desk Att chm:nt LTR 960005 R'C:98-0182 Page 6 of 8 VCSNS has also performed a review of Table A.1 of V-EC-1658-A, Revision 2 which confirms that the VCSNS methodology is conservative in the ranking of MOVs when compared to other plants.
Question 7 You indicated in your letter that you will periodically test some MOVs at intervals longer than 5 years or three refueling outages. Describe your criteria for evaluating test data to justify these long test intervals.
Response 7 Each GL 89-10/96-05 MOV has been baseline static tested and most have been dynamically tested once and statically tested at least twice. To minimize the effects of diagnostic equipment error, direct stem thrust and torque measurements are taken wherever practicable. The static test results traces of each MOV are reviewed by MOV Component Engineers to ensure that the MOV is set up adequately and to validate the various design basis parameters. Each valve is setup above the minimum required values and below the maximum allowable values with diagnostic errors taken in the conservative direction. The new values are '
compared to the old values (LSB, stem friction coefficients, thrust at CST, operating torque, running load, etc.) and the data is inputted into the GL G3-10 MOV setup, test, and performance validation summary report (TRO1520-001) and MOV trend program. After each valve is setup and tested (statically or dynamically) an assessment of the capability of the actuator and existing setup is made. The assessment of capability is based on the minimum required thrust including margin allowances and is expressed as the " valve factor capability". The valve factor capability displays how sensitive the setup of a given valve is with respect to changes in valve performance. Any indication of degradation / anomalies that could affect the performance of the valve is evaluated for the individual valve as well as similar valves, as appropriate, and corrective actions are taken as necessary. The static testing intervals may be changed by the MOV Component Engineers based upon evaluation of the trending information, equipment performance, functional significance and operability concerns. Testing at VCSNS to date indicates that the station's MOV degradation rates are minimal.
Document Control D:sk l Attachment LTR 960005 R'C 98-0182 Page 7 of 8 Question 8 Your letter states that your GL 96-05 program will provide reasonable assurance that your GL 96-05 MOVs will remain operable until the next scheduled test. Describe your method for enouring that your periodic test interval (maximum of 10 years) provides continued design-basis capability of your GL 96-05 MOVs until the next scheduled test.
Response 8 The station's GL 89-10/96-05 periodic test intervals are based on the risk significance and safety function thrust capability margin of the specific MOV. All MOVs in PRA group 1 (high risk), as well as those MOVs in PRA group 2 (medium risk) with less than 100% safety function thrust capability margin, are statically tested once per five years or three refueling outages, whichever is longer. Those MOVs in PRA group 2 (medium risk) with safety function thrust capability margin equal to or greater than 100%, as well as all PRA group 3 (lower risk) MOVs, will be subject to static testing once per ten years or six refueling outages, whichever is j longer. Butterily MOVs which are not in PRA group 1 (high risk) will be subjected to static testing once per ten years or six refueling outages, whichever is longer. All MOVs are administratively required to have a 10% safety function thrust (torque for butterfly valves) capability margin to allow for potential age related degradation.
Any valve without at least a 10% safety function thrust capability margin will be evaluated for acceptability and will be tested at least every 5 five years or three refueling cutages, whichever is longer. MOV Component Engineers may change the testing intervals based upon evaluation of the trend data. Performance of both static and dynamic testing of similar MOVs yields objective evidence that similar valves will remain operable until the next scheduled test. The station performs additional motor power testing on each GL 89-10/96-05 on a frequency of approximately every 18 months. The motor power data is then trended with the rest of the MOV diagnostic, equipment performance and industry data.
A number of other different processes and activities in the plant provide evidence of valve performance. Normal plant operations periodically exercise a significant portion of the GL 89-10/96-05 valves. Periodic surveillance testing also gives information on valve operability along with valves which are part of the ASME Section XI Program. Any negative performance indicators discovered during the course of the above events or other events which could provide operational information would serve to alert the plant to a potential operational problem with the subject valve and the necessary corrective actions would be taken. The plant
, - . - - - -----=- -.- - - . . - -- . . . - - - - . - . _
Documsnt Control Desk Attachment LTR 960005 R'C-98-6162 Page 8 of 8 preventive maintenance activities also support the continued operability of the valves.
Question 9 in NRC Inspection Report 50-395/97-01 (dated April 17,1997), we closed our V.
C. Summer GL 89-10 program review based on your actions to verify safety-related MOV design-basis capability. In the Inspection report, we noted !
certain long-term actions that you were taking to address weaknesses in your l MOV program. For example, we noted weaknesses in your assumptions for valve factor, load sensitive behavior, and stem friction coefficient in your MOV calculations. Describe the actions taken to resolve these weaknesses, the results of those actions, and any future actions.
Response 9 The Inspector Follow-up items dealing with weaknesses in our assumptions for valve factors were closed by the NRC in NRC Integrated inspection Report No. 50-395/98-06, dated August 24,1998 (after issuance of this RAI). Station procedures are being revised to ensure the stem factor is stable during the seating portion of the dynamic test when determining the LSB values. The margins added to the minimum required thrust calculations remain in place and the LSB values are being l
monitored / trended per the station's GL 89-10/96-05 MOV PV program. The margin i added to the open direction minimum required thrust calculations remains in place l and the stem friction coefficients are being monitored / trended per the station's GL :
89-10/96-05 MOV PV program. :