ML19207A322

From kanterella
Jump to navigation Jump to search
Final Rept on Stop Work Order Issued to Bingham-Willamette Co on 790329.Vendor Failed to Demonstrate Compliance W/Spec Requirements for post-weld Repair Heat Treating. Vendor Will Correct Operational Defects
ML19207A322
Person / Time
Site: Beaver Valley
Issue date: 08/10/1979
From:
DUQUESNE LIGHT CO.
To:
Shared Package
ML19207A317 List:
References
NUDOCS 7908160443
Download: ML19207A322 (2)


Text

. .

FINAL REPORT ON STOP WORK ORDER ISSUED TO BINGHAM-WILLAMETTE COMPANY ON MARCH 29, 1979 1.0

SUMMARY

Quench spray, recircalation spray, and auxiliary feedwater pumps are being manufactured by Bingham-Willamette Company for the Beaver Valley Power Station - Unit No. 2. A stop work order was issued on March 29, 1979, because Bingham-Willamette Company was unable to demonstrate that it had performed welding and nondestructive testing to approved procedures. Bingham-Willamette had, in several cases, provided documenta-tion which failed to meet specification requirements. The pumps tested failed to meet the specification design operational requirements.

A joint Duquesne Light Company / Stone & Webster Quality Assurance audit was performed on May 7, 1979, to May 11, 1979, resulting in 13 findings and one observation. Bingham-Willamette has proposed corrective action for each finding. Stone & Webster has determined that the corrective actions are acceptable and satisfy the requirements of the pump specifications. On this basis, the stcp work order was removed on August 8, 1979.

2.0 IMMEDIATE ACTION TAKEN A "stop work" order was issued to Bingham-Willamette Company on March 29, 1979, for the Beaver Valley Power Station - Unit No. 2 pump orders only. This stop work order was issued because of Bingham-Willamette's inability to demonstrate that work had been done to approved procedures, to provide proper documentation for materials and NDT results, and to effect corrective action specified in the Nonconformance and Disposition Report.

3.0 DESCRIPTION

OF DEFICIENCY Bingham-Willamette failed to demonstrate compliance with specification requirements for post-weld repair heat treating, we1Jer qualification, welding proce'ure qualification, nondestructive testing procede;'s, material certitications, and pump operational test requirements.

Bingham-Willamette cantinued to manufacture the subject pumps for a period of l? to 15 months before taking exception to corrective a tion specified in the Nonconformance and Disposition Reports. This lack of confermance could have resulted in components which were technically unacceptable or whose quality could not be conclusively demonstrated.

4.0 ANALYSIS OF SAFETY IMPLICATION Pumps supplied by Bingham-Willamette include those in the containment quench spray and recirculation spray systems as well as auxiliary 798 339 g ( v) 2008160 t

feedwater systems. Failure of this equipment to perform to the specified requirements could impact the capabilities for containment and primary system heat removal.

5.0 CORRECTIVE ACTION TO REMEDY DEFICIENCY The Duquesne Light Company and Stone & Webster Engineering Corporation Quality Assurance Departments performed an in-depth audit of the Bingham-Willamette Quality Assurance program with respect to Beaver Valley Power Station - Unit No. 2 purchase orders on May 7 through May 11, 1979.

This audit resulted in 13 findings and one observation. Bingham-Willamette proposed corrective actions for each finding which are acceptable.

The corrective action regarding fabrication prchlcm is directed to areas of welder and weld procedure qualification, sensitization of austenitic stainless steel, non-destructive examination procedure approval and material documentation. In each case, Bingham-Willamette will provide or has performed corrective action to satisfy requirements of the specifications, codes, PSAR, and Appendix B to 10CFR50.

Quench pump testing performed to date has resulted in mechanical damage, rubbing, and excessive wear. Bingham-Willamette will correct, with the concurrence of Stone & Webster, the operational defects.

Pumps will be retested to assure that the mechanical defects are cor-rected. Pumps will only be shipped af ter satisfactory completion of operational and performance tests.

Based upon the above summary of Bingham-Willamette's corrective actions, it can be proved conclusively that the quench spray, recirculation spray, and auxiliary feedwater pumps are technically acceptable and that thei.r quality can be demonstrated to meet the requirements of 10CFR50, Appendix B. Thus, the stop work order issued to Bingham-Willamette on March 29, 1979, was removed on August 6, 1979.

., 798. 3410 2