ML16174A094

From kanterella
Jump to navigation Jump to search
NRC Component Design Bases Inspection Report 05000373/2016007; 05000346/2016007
ML16174A094
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 06/22/2016
From: Jeffers M
Division of Reactor Safety III
To: Bryan Hanson
Exelon Generation Co
References
IR 2016007
Download: ML16174A094 (47)


See also: IR 05000373/2016007

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE RD. SUITE 210

LISLE, IL 60532-4352

June 22, 2016

Mr. Bryan C. Hanson

Senior VP, Exelon Generation Company, LLC

President and CNO, Exelon Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT: LASALLE COUNTY STATION, UNITS 1 AND 2 - NRC COMPONENT

DESIGN BASES INSPECTION, INSPECTION REPORT 05000373/2016007;

05000374/2016007

Dear Mr. Hanson:

On May 13, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed a Component

Design Bases Inspection at your LaSalle County Station, Units 1 and 2. The enclosed report

documents the results of this inspection, which were discussed on May 13, 2016, with

Mr. Trafton, Site Vice President, and other members of your staff.

Based on the results of this inspection, four NRC-identified findings of very-low safety

significance were identified. The findings involved violations of NRC requirements. However,

because of their very-low safety significance, and because the issues were entered into your

Corrective Action Program, the NRC is treating the issues as Non-Cited Violations in

accordance with Section 2.3.2 of the NRC Enforcement Policy.

If you contest the subject or severity to any of these Non-Cited-Violations, you should provide

a response within 30 days of the date of this inspection report, with the basis for your denial,

to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington,

DC 20555-0001, with copies to the Regional Administrator, Region III; the Director, Office of

Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the

NRC Resident Inspector at the LaSalle County Station.

In addition, if you disagree with the cross-cutting aspect assigned to any finding in this report,

you should provide a response within 30 days of the date of this inspection report, with the

basis for your disagreement, to the Regional Administrator, Region III, and the NRC Resident

Inspector at the LaSalle County Station.

B. Hanson -2-

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public

Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy

of this letter, its enclosure, and your response (if any) will be available electronically for public

inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)

component of the NRC's Agencywide Documents Access and Management System (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html

(the Public Electronic Reading Room).

Sincerely,

/RA/

Mark T. Jeffers, Chief

Engineering Branch 2

Division of Reactor Safety

Docket Nos. 50-373; 50-374

License Nos. NPF-11; NPF-18

Enclosure:

IR 05000373/2016007; 05000374/2016007

cc: Distribution via LISTSERV

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket No: 50-373; 50-374

License No: NPF-11; NPF-18

Report No: 05000373/2016007; 05000374/2016007

Licensee: Exelon Generation Company, LLC

Facility: LaSalle County Station, Units 1 and 2

Location: Marseilles, IL

Dates: April 4, 2016 - May 13, 2016

Inspectors: N. Féliz Adorno, Senior Reactor Inspector, Lead

A Dahbur, Senior Reactor Inspector, Electrical

J. Corujo Sandín, Reactor Inspector, Mechanical

D. Reeser, Operations Inspector

J. Leivo, Electrical Contractor

C. Edwards, Mechanical Contractor

Approved by: M. Jeffers, Chief

Engineering Branch 2

Division of Reactor Safety

Enclosure

TABLE OF CONTENTS

SUMMARY ................................................................................................................................ 2

REPORT DETAILS .................................................................................................................... 5

1. REACTOR SAFETY ......................................................................................... 5

1R21 Component Design Bases Inspection (71111.21) ...................................... 5

4. OTHER ACTIVITIES .......................................................................................22

4OA2 Identification and Resolution of Problems.................................................22

4OA6 Management Meetings .............................................................................26

SUPPLEMENTAL INFORMATION............................................................................................. 1

KEY POINTS OF CONTACT .................................................................................................. 1

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED ....................................................... 1

LIST OF DOCUMENTS REVIEWED ...................................................................................... 2

LIST OF ACRONYMS USED.................................................................................................17

SUMMARY

Inspection Report 05000373/2016007; 05000374/2016007, 04/04/2016 - 05/13/2016; LaSalle

County Station, Units 1 and 2; Component Design Bases Inspection.

The inspection was a 3-week onsite baseline inspection that focused on the design

of components. The inspection was conducted by four regional engineering and

operations inspectors, and two consultants. Four Green findings were identified by the

team. These findings were considered Non-Cited Violations (NCVs) of U.S Nuclear Regulatory

Commission (NRC) regulations. The significance of inspection findings is indicated by their

color (i.e., greater than Green; or Green, White, Yellow, and Red) and determined using

Inspection Manual Chapter 0609, Significance Determination Process, dated April 29, 2015.

Cross-cutting aspects are determined using Inspection Manual Chapter 0310, Aspects Within

the Cross-Cutting Areas, dated December 4, 2014. All violations of NRC requirements are

dispositioned in accordance with the NRCs Enforcement Policy, dated February 4, 2015. The

NRCs program for overseeing the safe operation of commercial nuclear power reactors is

described in NUREG-1649, Reactor Oversight Process, Revision 5, dated February 2014.

NRC-Identified and Self-Revealed Findings

Cornerstone: Mitigating Systems

Green. The team identified a finding of very-low safety significance (Green) and an

associated NCV of Title 10, Code of Federal Regulations (CFR), Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings, for the failure to monitor the

fouling conditions of the core standby cooling system (CSCS) equipment area coolers.

Specifically, the licensee did not develop performance test procedures to assess the

fouling conditions of the safety-related CSCS equipment area coolers and did not

have acceptance criteria that delineate when to remove accumulations. The licensee

captured this issue in their Corrective Action Program (CAP) as Action Request

(AR) 02665463 and established a standing order for operations to impose more

restrictive service water temperature limits to reasonably assure the operability of

the affected coolers until long term corrective actions were implemented to restore

compliance.

The performance deficiency was determined to be more than minor because it was

associated with the Mitigating System cornerstone attribute of equipment performance

and adversely affected the cornerstone objective to ensure the availability, reliability,

and capability of systems that respond to initiating events to prevent undesirable

consequences. The finding screened as of very low safety significance (Green)

because it did not result in the loss of operability or functionality of mitigating systems.

Specifically, the licensee reviewed actual service water temperature values measured

during the last 12 months, performed an operability evaluation, and concluded that the

historical temperatures did not exceed the operability limits established by the operability

evaluation. The team did not identify a cross-cutting aspect associated with this finding

because it was not confirmed to reflect current performance. Specifically, the test

program for the CSCS equipment area coolers was developed in the decade of 1990s.

(Section 1R21.3.b(1))

2

Green. The team identified a finding of very-low safety significance (Green) and an

associated NCV of 10 CFR Part 50, Appendix B, Criterion III, Design Control, for the

failure to have the capability to verify the supply breakers of both reactor units feeding

the swing diesel generator (DG) components were closed during normal plant operation.

Specifically, the circuit design and procedures for the swing DG room fan, fuel oil

transfer pump, and fuel storage tank room exhaust fan did not ensure the detection of

the condition where one of these feeder breakers was tripped in the open position during

normal plant operation. The licensee captured this issue in their CAP as AR 02668759

and created a special log to monitor the associated breakers once per day.

The performance deficiency was determined to be more than minor because it was

associated with the Mitigating System cornerstone attribute of equipment performance

and adversely affected the cornerstone objective to ensure the availability, reliability,

and capability of systems that respond to initiating events to prevent undesirable

consequences. The finding screened as of very low safety significance (Green) because

it did not result in the loss of system and/or function, represent an actual loss of function

of at least a single train or two separate safety systems out-of-service for greater than its

Technical Specifications (TS) allowable outage time, and represent an actual loss of

function of one or more non-TS trains of equipment designated as high safety-significant

for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Specifically, a historical review did not find an example where

the swing DG was non-functional for a period greater than the applicable TS allowable

outage time as a result of this finding during the last year. The team did not identify a

cross-cutting aspect associated with this finding because it was not confirmed to reflect

current performance due to the age of the performance deficiency. Specifically, the

mean to detect an opened breaker associated with the affected loads was established

more than 3 years ago. (Section 1R21.3.b(2))

Green. The team identified a finding of very-low safety significance (Green) and an

associated NCV of 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures,

and Drawings, for the failure to establish procedures that were appropriate to manage

containment debris consistent with the emergency core cooling system strainer debris

loading design basis and supporting design information. Specifically, the procedures did

not contain instructions for evaluating containment debris sources consistent with the

associated analyses and other design documents. The licensee captured the team

concerns in their CAP as AR 02663076 and AR 02656299. The immediate corrective

actions included an operability evaluation that reasonably determined all of the affected

emergency core cooling system strainers remained operable.

The performance deficiency was determined to be more than minor because it was

associated with the procedure quality attribute of the Mitigating Systems cornerstone,

and adversely affected the cornerstone objective to ensure the availability, reliability,

and capability of systems that respond to initiating events to prevent undesirable

consequences. The finding screened as of very-low safety significance (Green)

because it did not result in the loss of operability or functionality of mitigating systems.

Specifically, the licensee performed an operability review and reasonably determined

that only a portion of the unqualified coatings would be available for transport to the

strainers and this quantity was bounded by the associated design basis analysis. In

addition, this review reasonably determined that sufficient analytical margin existed to

accommodate the quantities of the other debris types found during recent inspections.

The team did not identify a cross-cutting aspect associated with this finding because it

was not confirmed to reflect current performance due to the age of the performance

deficiency. Specifically, the associated procedures were established more than 3 years

ago. (Section 1R21.4.b(1))

3

Green. The team identified a finding of very-low safety significance (Green) and

associated NCV of the LaSalle County Station Operating License for the failure to

ensure that procedures were in effect to implement the alternate shutdown capability.

Specifically, the abnormal operating procedures (AOPs) established to respond to a fire

at the main control room did not include instructions for verifying that supply breakers for

three reactor core isolation cooling motor-operated valves (MOVs) were closed to

ensure they could be operated from the remote shutdown panel. Fire-induced failures

could result in tripping MOV power supply breakers prior to tripping the MOV control

power fuses. The licensee captured the team concerns in their CAP as AR 02668854

and established compensatory actions to reset the affected breakers, if required

The performance deficiency was determined to be more than minor because it was

associated with the Mitigating Systems Cornerstone attribute of protection against

external events (fire), and affected the cornerstone objective of ensuring the availability,

reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences. The finding screened as of very-low safety significance

(Green) because it was assigned a low degradation factor. Specifically, the procedural

deficiencies could be compensated by operator experience/familiarity and the fact that

the AOPs included steps to verify other breakers at the same locations were closed

would likely prompt operators to close the remaining breakers. The team determined

that this finding had a cross cutting aspect in the area of problem identification and

resolution because the licensee failed to take effective corrective actions for a similar

issue identified in 2014. Specifically, the resolution of this issue included actions to

revise the affected AOPs to include verifying all the reactor core isolation cooling MOVs

supplied breakers were closed. However, the licensee failed to include all of the MOVs

in the revised AOPs. [P.3] (Section 4OA2.b(1))

4

REPORT DETAILS

1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1R21 Component Design Bases Inspection (71111.21)

.1 Introduction

The objective of the Component Design Bases Inspection (CDBI) is to verify that design

bases have been correctly implemented for the selected risk-significant components

and that operating procedures and operator actions were consistent with design and

licensing bases. As plants age, their design bases may be difficult to determine and

an important design feature may be altered or disabled during a modification. The

Probabilistic Risk Assessment (PRA) Model assumes the capability of safety systems

and components to perform their intended safety function successfully. This inspectable

area verifies aspects of the Initiating Events, Mitigating Systems, and Barrier Integrity

cornerstones for which there are no indicators to measure performance.

Specific documents reviewed during the inspection are listed in the Attachment of this

report.

.2 Inspection Sample Selection Process

The team used information contained in the licensees PRA and the LaSalle County

Station, Unit 1 and 2, Standardized Plant Analysis Risk Model to identify one scenario to

use as the basis for component selection. The scenario selected was a loss of offsite

power (LOOP) event. Based on this scenario, a number of risk-significant components

were selected for the inspection. In addition, the team selected a risk-significant

component with Large Early Release Frequency (LERF) implications using information

contained in the licensees PRA and the LaSalle County Station, Units 1 and 2,

Standardized Plant Analysis Risk Model.

The team also used additional component information such as a margin assessment in

the selection process. This design margin assessment considered original design

reductions caused by design modifications, power uprates, or reductions due to

degraded material condition. Equipment reliability issues were also considered in the

selection of components for detailed review. These included items such as performance

test results, significant corrective actions, repeated maintenance activities, Maintenance

Rule (a)(1) status, components requiring an operability evaluation, system health

reports, and U.S. Nuclear Regulatory Commission (NRC) resident inspector input of

problem areas and/or equipment. Consideration was also given to the uniqueness and

complexity of the design, operating experience, and the available defense in depth

margins. A summary of the reviews performed and the specific inspection findings

identified are included in the following sections of this report.

The team also identified procedures and modifications for review that were associated

with the selected components. In addition, the team selected operating experience

issues associated with the selected components.

5

This inspection constituted 17 samples (i.e., 11 components, 1 component with

LERF implications, and 5 operating experiences) as defined in Inspection

Procedure 71111.21-05.

.3 Component Design

a. Inspection Scope

The team reviewed the Updated Final Safety Analysis Report (UFSAR), Technical

Specification (TS), Technical Requirements Manual, drawings, calculations, and other

available design and licensing basis information to determine the performance

requirements of the selected components. The team used applicable industry

standards, such as the American Society of Mechanical Engineers Code, Institute of

Electrical and Electronics Engineers Standards, and the National Electric Code, to

assess the systems design. The team also reviewed licensee actions, if any, taken in

response to NRC issued operating experience, such as Generic Letters (GL) and

Information Notices (INs). The team reviewed the selected components design to

assess their capability to perform their required functions and support proper operation

of the associated systems. The attributes that were needed for a component to perform

its required function included process medium, energy sources, control systems,

operator actions, and heat removal. The attributes that verified component condition

and tested component capability were appropriate and consistent with the design bases

may have included installed configuration, system operation, detailed design, system

testing, equipment and environmental qualification, equipment protection, component

inputs and outputs, operating experience, and component degradation.

For each of the components selected, the team reviewed the maintenance history,

preventive maintenance activities, system health reports, operating experience-related

information, vendor manuals, electrical and mechanical drawings, operating procedures,

and licensee Corrective Action Program (CAP) documents. Field walkdowns were

conducted for all accessible components selected to assess material condition,

including age-related degradation, configuration, potential vulnerabilities to hazards,

and consistency between the as-built condition and the design. In addition, the

team interviewed licensee personnel from multiple disciplines such as operations,

engineering, and maintenance. Other attributes reviewed are included as part of the

scope for each individual component.

The following 12 components (i.e., samples), including a component with LERF

implications, were reviewed:

Unit 2, Reactor Core Insolation Cooking (RCIC) Pump (2E51-C001): The team

reviewed the following hydraulic calculations to assess the pump capability to

perform its required mitigating functions: pump minimum required flow, runout

flow, flow capacity, and minimum required net positive suction head (NPSH). In

addition, the team reviewed analyses associated with water hammer and other

gas intrusion considerations, such as the condensate storage tank minimum

water level setpoint and instrument uncertainty calculations. The team also

reviewed test procedures and completed surveillance tests, including quarterly

and comprehensive in-service testing, to assess the associated methodology,

acceptance criteria, and test results. In addition, the team reviewed design

analyses and test documents of the equipment area cooler to assess its

6

capability to maintain room temperature below the maximum qualification

temperature value of the RCIC pump support components. The team also

assessed the pump protective measures against flooding, seismic, and

high-energy line break (HELB) effects.

Unit 2, RCIC Turbine (2E51-C002): The team reviewed analyses for turbine

minimum required steam flow, turbine required speed, and water hammer in the

steam exhaust line to assess the RCIC turbine capability to perform its required

mitigating functions. The team also reviewed turbine speed control and trip test

procedures, results, and trends, as well as vendor information, such as General

Electric Service Information Letters, to assess the turbine control system

capability to perform its function. In addition, the team reviewed design analyses

and test documents of the equipment area cooler to assess its capability to

maintain room temperature below the maximum qualification temperature value

of the RCIC turbine support components. The team also assessed the turbine

protective measures against flooding, seismic, and HELB effects.

Unit 2, RCIC Steam Supply MOV (2E51-F045): The team reviewed analyses for

maximum differential pressure, weak link, and minimum required thrust to assess

the valve capability to provide its required mitigating functions. In addition, the

team reviewed test procedures and recently completed surveillance tests to

assess the associated methodology, acceptance criteria, and test results. The

team also reviewed the valve seismic and HELB analyses to assess the

associated protective measures. In addition, the team reviewed electrical load

flow calculations to assess the motor capability to operate the valve under

degraded voltage conditions. The team also reviewed the protective relaying

scheme, including drawings, calculations and schematic diagrams, to assess its

capability to provide motor protection and to preclude spurious tripping under

accident conditions.

Unit 2, Drywell Purge Isolation Air-Operated Valve (2VQ-34): The team reviewed

analyses for maximum differential pressure, weak link, and minimum required

thrust to assess the valve capability to provide its function. The team reviewed

leak rate test procedures and recently completed surveillance tests to assess the

associated methodology, acceptance criteria, and test results, and ultimately

assess the valve capability to perform its containment barrier function. In

addition, the team reviewed the valve seismic and HELB analyses to assess the

associated protective measures. This review constituted one component sample

with LERF implications.

Swing Diesel Generator (DG) (0DG01K): The team reviewed the following

DG test procedures and completed surveillance tests to assess the associated

methodologies, acceptance criteria, and test results: single load rejection, full

load rejection, and capability to accept load within it design bases time. In

addition, the team reviewed tests and calculations associated with room heat up,

combustion air, and exhaust design. The team also reviewed the DG protective

measures against flooding, HELB, and tornado generated missiles. The

following loading calculations were reviewed to assess the DG capability to

perform its safety function: voltage, frequency, current, and loading sequences

during postulated LOOP and loss-of-coolant accident (LOCA) conditions. The

team also reviewed protective relay setpoint calculations and setpoint calibration

7

test results to assess the DG protection during testing and emergency

operations. A sample of TS surveillance results were reviewed to assess

compliance with the acceptance criteria and test frequency requirements.

In addition, the team reviewed the following DG auxiliary sub-components:

Air Start Receivers (0DG06TA/B) and Motors (0DG08KA/B/C/D): The

team reviewed the pre-operational test results of the air start receivers to

assess their capacity to support the minimum number of required DG

starts. In addition, test procedures and completed surveillance tests were

reviewed to assess the air start receivers and motors capability to start

the DG.

Jacket Water Cooler (0DG01A): The team reviewed the jacket water

cooler thermal analysis to assess its capability to maintain engine

temperature within design limits and verified that the licensee had

updated the analysis to reflect the latest design bases ultimate heat

sink temperature limit changes. In addition, the team reviewed the

implementation of the GL 89-13 Program and its commitments associated

with the jacket water cooler. Specifically, the team reviewed thermal

performance test and inspect-and-clean procedures and completed

surveillances to assess the associated methodologies, acceptance

criteria, and test results.

Fuel Oil Storage Tank (0DO2T): The team reviewed fuel oil consumption

calculations, and main storage and day tank capacity calculations,

including the associated level instrument setpoints and uncertainty

analyses, to assess the availability of the required DG fuel oil supply.

The team also reviewed test procedures for fuel oil quality. In addition,

the team reviewed the licensees evaluation and resolution of related

operating experiences and a Non-Cited Violation (NCV) identified in a

previous CDBI as discussed in Section 1R21.4.a and Section 4OA2.1.a

of this report.

Fuel Oil Transfer Pump (0DO01P): The team reviewed hydraulic

calculations to assess flow capacity, NPSH, and air-entraining vortices

preventive measures. The team also reviewed the control circuit design

and the pump protective devices.

Swing DG Room Fan (0VD01C) and Ventilation Balancing Dampers

(0VD01/2/3YA/B): The team reviewed air flow calculations to assess the fan

capability to maintain the swing DG room within its design bases temperature

limit. The team also reviewed design documentation and procedures associated

with the DG room temperature and fan intake filter differential pressure

instrumentation to assess the licensee capability to detect and address

degraded ventilation conditions. In addition, the team reviewed the preventative

maintenance documents for the fan and dampers, including sub-components

such as hydramotors and control logic circuitry, to assess their periodicity and

consistency with vendor information. The team also reviewed the protective

measures against flooding, seismic, and tornado generated missiles. The supply

fan maximum brake horsepower requirements were reviewed to assess the

motor capability to supply power during worse case design basis conditions.

8

The results of load flow and voltage regulation analyses were reviewed to assess

the motor capability to start and run during degraded offsite voltage conditions

coincident with a postulated design basis accident. The team also reviewed the

motor breaker settings to assess the motor overcurrent protection during the

most limiting design basis operating conditions. The DG operating and standby

readiness procedures were reviewed to assess the consistency between the DG

ventilation system operation and the design requirements. The team also

reviewed the design of the instrumentation relied upon for the automatic room

ventilation operation, including power supplies and setpoints, to assess the

system operation.

Unit 2, RCIC High-Temperature and High-Steam Flow Isolation Instrumentation

(TE-2E31-N004A/B, TE-2E31-N005A/B, TS-2E31-N602A/B, TS-2E31-N603A/B,

2E31-N013BA): The team reviewed schematic diagrams, instrument

specifications such as range and accuracy, setpoint and uncertainty calculations,

and the installation configuration to assess the temperature and flow

instrumentation capability to perform its function. In addition, the team reviewed

test and calibration procedures as well as recently completed surveillances to

assess the associated methodology, acceptance criteria, and test results. The

team also considered the protective measures against flooding, seismic, and

HELB when reviewing the described analyses and during field walkdowns.

Unit 2, Suppression Pool Water Temperature and Level Instrumentation

(2TE-CM-057/037, 2UY-CM037, 2LT-CM-030, 2LS-E22-N002): The team

reviewed schematic diagrams, instrument specifications such as range and

accuracy, margin and uncertainty calculations, and the installation configuration

to assess the capability of the temperature and level instrumentation to perform

its function. In addition, the team assessed the consistency between plant

surveillance procedures and the methodology for determining average water

temperature and data quality allowances described in vendor documentation.

The team also reviewed test and calibration procedures as well as recently

completed surveillances to assess the associated methodology, acceptance

criteria, and test results. In addition, the team considered the protective

measures against flooding, seismic, and HELB when reviewing the described

analyses and during field walkdowns.

Unit 2, 125 Volts Direct Current (Vdc) Distribution Panels 211Y/212Y

(2DC11E/13E): The team reviewed design calculations for the loading, short

circuit, voltage drop, ground detection/management, and electrical protection

for the distribution panels and a sample of loads to assess the ratings and

capability of the panels to serve the loads under design basis conditions, provide

coordinated protection, and to preclude premature tripping. In addition, the team

also reviewed the station blackout (SBO) load shedding procedures to assess

their consistency with the design margins established by the calculations and the

operators capability to perform the associated actions within the times assumed

in the calculations. The team also reviewed test procedures and recently

completed surveillances to assess the associated methodology, acceptance

criteria, and test results. In addition, the team considered the protective

measures against flooding and seismic when reviewing the described analyses

and during field walkdowns.

9

Unit 2, RCIC Instrumentation 125Vdc to 120 Volts Alternating Current (Vac)

Inverter (2E51-K603): The team reviewed the loading and protection

specifications and features for the inverter to assess its capability to serve the

instrument power supply loads under design basis conditions, including operation

under minimum direct current (DC) input voltage conditions. The team also

reviewed the basis for the inverter qualification, including surge protection and

electromagnetic compatibility. In addition, the team reviewed the modification

discussed in Section 1R21.5.a of this report. The team also reviewed test

procedures and recently completed surveillances to assess the associated

methodology, acceptance criteria, and test results. In addition, the team

considered the protective measures against flooding and seismic when

reviewing the described analyses and during field walkdowns.

Unit 2, 250Vdc Motor Control Center (MCC) 221Y (2DC06E): The team

reviewed the system short circuit and loading calculations to assess the available

short circuit current under faulted conditions and the capability to serve the

maximum anticipated bus load. The team also reviewed the bus, breaker, and

cable ratings to assess their capability to carry maximum loading and interrupt

maximum faulted conditions. In addition, the team reviewed cable separation

design to assess compliance with single failure and Title 10, Code of Federal

Regulations (CFR), Part 50, Appendix R criteria. Breaker coordination was also

reviewed to assess their capability to interrupt overloads and faulted conditions.

The team also reviewed recent engineering changes (ECs) to assess the bus

current capability to support design requirements. In addition, the team reviewed

test procedures and recently completed surveillances to assess the associated

methodology, acceptance criteria, and test results.

Unit 2, 4 Kilovolt (kV) Switchgear 241Y (2AP04E): The team reviewed the

design of the 4.16kV bus degraded voltage protection scheme, including

degraded voltage relay setpoint calculations, to assess its capability to supply

the required voltage to safety-related devices at all voltage distribution levels.

The team also reviewed 125Vdc system voltage drop calculations to assess

the 4.16kV bus circuit breakers control voltage. In addition, the team reviewed

supply breaker control logic and wiring diagrams to assess the capability to

automatically transfer between the normal and alternate sources under

postulated conditions as described in the UFSAR and in accordance with

operating procedures. This review included an assessment of the automatic and

manual transfer schemes between alternate offsite sources and the swing DG.

The team also reviewed the control circuit voltage to assess the circuit breakers

capability to close and trip. In addition, the team reviewed test procedures and

recently completed surveillances to assess the associated methodology,

acceptance criteria, and test results.

b. Findings

(1) Failure to Monitor the Fouling Conditions of the Core Standby Cooling System

Equipment Area Coolers

Introduction: The team identified a finding of very-low safety significance (Green)

and an associated NCV of 10 CFR Part 50, Appendix B, Criterion V, Instructions,

Procedures, and Drawings, for the failure to monitor the fouling conditions of the core

10

standby cooling system (CSCS) equipment area coolers. Specifically, the licensee

did not develop performance test procedures to assess the fouling conditions of the

safety-related CSCS equipment area coolers and did not have acceptance criteria

that delineate when to remove accumulations.

Description: On July 18, 1983, the NRC issued GL 89-13, Service Water System

Problems Affecting Safety-Related Equipment, to alert licensees about operating

experience and studies that raised concerns regarding service water systems in nuclear

power plants. The GL requested licensees, in part, to provide a response describing the

actions planned or taken to ensure that their service water systems were and will be

maintained in compliance with applicable regulatory requirements. The licensee

provided its response in a letter to the NRC titled Response to Generic Letter 89-13,

dated January 29, 1990. Subsequent reviews revealed weaknesses in the licensee

original GL 89-13 Program. As a result, the licensee re-baselined the program and

revised its original response in a letter to the NRC titled Generic Letter 89-13 Revised

Response, dated July 28, 1998. The revised response stated that the CSCS equipment

area cooler testing program would include tube-side (chemical) cleaning on condition,

air-side coil inspection, component flushing, air-side flow verification, cooling water

flow verification, and cooling water dP [differential pressure] monitoring.

During this inspection period, the licensee controlled the implementation of GL 89-13

activities with Revision 7 of Procedure ER-AA-340, GL 89-13 Program Implementing

Procedure. Step 4.2.3 stated Implement a heat exchanger performance-testing

program. It also stated Develop performance test procedures that will verify the

capabilities of the safety related heat exchangers, including test procedure and

instrument uncertainties, and contain acceptance criteria based on the design

requirements of the systems. In addition, Revision 9 of Procedure ER-AA-340-1001,

GL 89-13 Program Implementation Instructional Guide, provided detailed guidance for

the implementation of GL 89-13 activities. Step 4.1.1.1.C stated The program shall

inspect/test for macroscopic biological fouling organisms, sediment, corrosion and

general component condition. It also stated The inspection/test program shall have

acceptance criteria that delineate when to remove accumulations.

The team noted that the licensee developed a test procedure to measure flowrate and

dP for the CSCS cooler for the room containing the low pressure core spray and RCIC

systems (i.e., cooler 2VY04A) on a biennial basis and to evaluate the flowrate results

against an acceptance criterion. However, the dP results were only trended because an

associated acceptance criterion was not established. In addition, the team noted that

the cooler was cleaned four times since the GL 83-13 Program was established but was

unable to determine the trigger for these cleaning activities. The team was concerned

because flow verification by itself was insufficient to assess the cooler fouling condition.

Moreover, the team was concerned about the actual cooler fouling conditions because

the dP trend data since year 2010 showed a dP of approximately 8 times the dP

measured in the early 1990s when dP was first measured. A simplified calculation,

which assumed tube blockage was the cause for the increased dP results, determined

that approximately 60 percent of the tubes were completely blocked. In contrast, the

design basis analysis for the cooler only assumed 5 percent of the tubes were blocked.

11

The licensee captured the team concerns in their CAP as AR 2665463. The immediate

corrective actions included an extent of condition that determined this concern was

applicable to all four CSCS room coolers of each reactor unit. The other coolers

supported the residual heat removal (RHR) and high-pressure core spray systems.

The licensee also performed an operability evaluation that reasonably determined all

of the affected equipment were operable based, in part, on the actual service water

temperatures. In addition, because operability could not be supported at the service

water temperature TS limit, the licensee established a control room standing order to

declare some of the affected coolers inoperable at reduced service water temperature

limits until the coolers were cleaned. The licensee proposed plan to restore compliance

at the time of this inspection was to clean the affected coolers and revise the GL 89-13

Program documents to incorporate applicable Electric Power Research Institute

monitoring guidance.

Analysis: The team determined the failure to monitor the fouling conditions of the CSCS

room coolers was contrary to licensee Procedures ER-AA-340 and ER-AA-340-1001,

and was a performance deficiency. The performance deficiency was determined to be

more than minor because it was associated with the Mitigating System Cornerstone

attribute of equipment performance and adversely affected the cornerstone objective to

ensure the availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences. Specifically, the failure to verify that the

fouling conditions of the CSCS room coolers are consistent with the associated design

analysis does not ensure that these coolers would be capable of performing their

mitigating functions.

The team determined the finding could be evaluated using the Significance Determination

Process (SDP) in accordance with Inspection Manual Chapter (IMC) 0609, Significance

Determination Process, Attachment 0609.04, Initial Characterization of Findings,

issued on June 19, 2012. Because the finding impacted the Mitigating Systems

cornerstone, the team screened the finding through IMC 0609, Appendix A, The

Significance Determination Process for Findings At-Power, issued on June 19, 2012,

using Exhibit 2, Mitigating Systems Screening Questions. The finding screened as of

very-low safety significance (Green) because it did not result in the loss of operability or

functionality of mitigating systems. Specifically, the licensee reviewed actual service

water temperature values measured during the last 12 months and concluded that these

values did not exceed the operability limits established by the operability evaluation.

The team did not identify a cross-cutting aspect associated with this finding because it

was not confirmed to reflect current performance due to the age of the performance

deficiency. Specifically, the test program for the CSCS equipment area coolers was

developed in the decade of 1990s.

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion V, Instructions,

Procedures, and Drawings, requires, in part, that activities affecting quality be

prescribed by documented procedures of a type appropriate to the circumstances

and be accomplished in accordance with these procedures. The licensee established

Revision 7 of Procedure ER-AA-340 an Revision 9 of Procedure ER-AA-340-1001 as

the implementing procedures for monitoring, in part, CSCS room coolers capability to

perform their required safety functions, an activity affecting quality.

12

Procedure ER-AA-340, Step 4.2.3, stated Implement a heat exchanger

performance-testing program. It also stated Develop performance test procedures

that will verify the capabilities of the safety-related heat exchangers, including test

procedure and instrument uncertainties, and contain acceptance criteria based on

the design requirements of the systems. In addition, Procedure ER-AA-340-1001,

Step 4.1.1.1.C, stated The program shall inspect/test for macroscopic biological fouling

organisms, sediment, corrosion and general component condition. It also stated The

inspection/test program shall have acceptance criteria that delineate when to remove

accumulations.

Contrary to the above, as of May 4, 2016, the licensee failed to follow Step 4.2.3 of

Procedure ER-AA-340 and Step 4.1.1.1.C of Procedure ER-AA-340-1001. Specifically,

the licensee did not develop performance test procedures that verify the capabilities

of the safety-related CSCS room coolers because the test program did not inspect or

test for macroscopic biological fouling organisms, sediment, corrosion and general

component condition, and did not have acceptance criteria that delineate when to

remove accumulations.

The licensee is still evaluating its planned corrective actions. However, the team

determined that this issue does not present an immediate safety concern because the

licensee established a standing order for operations to impose more restrictive service

water temperature limits to reasonably assure the operability of the affected coolers.

Because this violation was of very-low safety significance (Green) and was entered into

the licensees CAP as AR 2665463, this violation is being treated as an NCV, consistent

with Section 2.3.2 of the NRC Enforcement Policy. (NCV 05000373/2016007-01;

05000374/2016007-01, Failure to Monitor the Fouling Conditions of the CSCS

Equipment Area Coolers)

(2) Failure to Ensure that Both Feed Supply Breakers for Swing Diesel Generator

Components Were Closed During Normal Plant Operation

Introduction: The team identified a finding of very-low safety significance (Green) and an

associated NCV of 10 CFR Part 50, Appendix B, Criterion III, Design Control, for the

failure to have the capability to verify the supply breakers of both reactor units feeding

the swing DG components were closed during normal plant operation. Specifically, the

circuit design and procedures for the swing DG room fan, fuel oil transfer pump, and fuel

storage tank room exhaust fan did not ensure the detection of the condition where one of

these feeder breakers was tripped in the open position during normal plant operation.

Description: Section 8.1.2.2 of the UFSAR, Unit Class 1E AC [Alternating Current]

Power System, stated that All of the ESF [engineered safety feature] equipment

required to shut down the reactor safely and to remove reactor decay heat for extended

periods of time following a LOOP and/or a LOCA are supplied with AC power from the

Class 1E AC power system. This UFSAR section defined Class 1E AC power systems

as that portion of the station auxiliary power system which supplies AC power to the

ESF and stated that The unit Class 1E AC power system is divided into three divisions

(Divisions 1, 2 and 3 for Unit 1; Divisions 1, 2, and 3 for Unit 2), each of which is

supplied from a 4160-volt bus (141Y, 142Y, and 143 for Unit 1 respectively) and (241Y,

242Y, and 243 for Unit 2 respectively). It also stated that Two ESF groups (Division 2

and 3) of each unit are supplied standby power from individual diesel-generator units,

while the third ESF group (Division 1) for each unit obtains its standby power from a

13

common diesel-generator unit, "0", which serves either of the corresponding switch

groups in each unit (Bus 141Y or 241Y). In addition, it stated that With this

arrangement, alternate or redundant components of all ESF systems are supplied

from separate switch groups so that no single failure can jeopardize the proper

functioning of redundant ESF.

Because the swing DG was designed to supply power to the division 1 ESF bus for

either reactor unit, several safety-related components that supported the swing DG

operation (i.e., room vent fan, fuel storage tank room exhaust fan, and fuel transfer

pump) were designed with one power supply from each reactor unit. As an example,

Unit 1 supplied power to the swing DG room fan (i.e., 0VD01C) via compartment B4 of

MCC135X-2 while Unit 2 supplied power to this component via compartment B4 of

MCC235X-2. Schematic diagram 1E-0-4433AA, Diesel Generator Room Ventilation

System, showed the following operational sequence for the associated control circuit

design:

If both MCCs were energized with no breaker or fuse failures during normal

operation, the fan would be powered from Unit 1. In addition, the plant process

computer (PPC) alarm contact from relay 74, Overload Relay, would be closed

causing the alarm to not be displayed at the Main Control Room (MCR). During

a LOOP event, the fan control circuit would connect to the MCC of the reactor

unit with a LOCA signal. Thus, the Units 1 and 2 MCCs were not considered

redundant or backup to each other.

If the Unit 1 MCC feed breaker tripped open and/or the Unit 1 control transformer

fuse opened during normal operation, relays AR1 and AR2 would de-energize

and power would automatically transfer to the Unit 2 MCC. At the same time, the

loss of power from Unit 1 would cause relay 74 to drop out until Unit 2 power

picked up. If the PPC alarm contact from relay 74 opened before relay 74 was

energized by Unit 2 power, the PPC alarm would appear on the ESF panel.

However, the team noted that the circuit design did not preclude a contact/relay

race between relays AR1/AR2 and relay 74 and, thus, the PPC alarm contact

from relay 74 was not assured to open before relay 74 was energized by Unit 2

power to provide the alarm function.

If the Unit 2 breaker tripped and/or the Unit 2 control transformer fuse opened

when the fan was powered from Unit 1 during normal operation, no PPC or

annunciator alarm would appear at the MCR.

If both Unit 1 and 2 MCCs de-energized during normal operation, relay 74

would dropout to activate the ESF display and overload alarm at the MCR

annunciator, which would prompt operators to respond in accordance with

Procedure LOR-0PL17J-2-1, Diesel Generator Ventilation Fan 0VD01C

Automatic Trip.

If either the Unit 1 MCC or the Unit 2 MCC thermal overload relays tripped during

normal operation, the fan control circuit would de-energize. The fan would not

run from either power source until the thermal overload relays was reset. In

addition, relay 74 would drop out to activate the ESF display and overload alarm

in the MCR.

14

The circuit designs for the swing DG fuel storage tank room exhaust fan and fuel oil

transfer pump were similar.

The team was concerned because the licensee had not assure that the failure of the

Unit 1 or Unit 2 feed breakers for these swing DG components during normal plant

operation would be detected. Specifically, the licensee relied on an alarm at the MCR to

detect a failure of either feed breaker during normal operation but the associated circuit

design did not assure an alarm signal would be generated by either of these conditions.

The team further noted that an undetected breaker failure during normal operations

would allow the swing DG to be and remain inoperable during normal operations,

which would result in the loss of total DG system given a postulated accident assuming

a single failure of the redundant DG train. In addition, the team noted that a failure of

either of these breakers during normal operations was credible given recent internal

operating experience. Specifically, on July 24, 2011, an equipment operator found

the Unit 1 swing DG room fan feed breaker (i.e., MCC 135X-2, B4) tripped during

an operator round. The licensee captured the discovery of this issue in their

CAP as AR 01243373, verified that the Unit 2 swing DG room fan feed breaker

(i.e., MCC 235X-2, B4) was closed, declared the swing DG inoperable for Unit 1,

and replaced the failed Unit 1 breaker. In addition, the licensee reviewed historical

PPC data and determined that the Unit 1 breaker tripped on July 22, 2011, during the

DG monthly surveillance run. Thus, the operators missed the PPC alarm and the

previous equipment operator rounds did not identified the condition.

The licensee capture the team concern in their CAP as AR 02668759. The immediate

corrective actions was to create a special log to monitor the associated breakers once

per day. At the time of this inspection, the licensee was still evaluating its planned

corrective actions to restore compliance.

Analysis: The team determined that the failure to have the capability to verify the supply

breakers of both reactor units feeding the swing DG components were closed during

normal plant operation was contrary to 10 CFR Part 50, Appendix B, Criterion III,

Design Control, and was a performance deficiency. The performance deficiency was

determined to be more than minor because it was associated with the Mitigating

Systems cornerstone attribute of equipment performance and affected the cornerstone

objective of ensuring the availability, reliability, and capability of systems that respond to

initiating events to prevent undesirable consequences. Specifically, the failure to have

the capability to verify the supply breakers of both reactor units feeding the swing DG

components were closed during normal plant operation would allow a condition where

one of the feeder breakers is in the open position during normal plant operation to go

undetected, which did not ensure power would be available to these components to

support the swing DG operability.

The team determined the finding could be evaluated using the SDP in accordance

with IMC 0609, Significance Determination Process, Attachment 0609.04, Initial

Characterization of Findings, issued on June 19, 2012. Because the finding impacted

the Mitigating Systems cornerstone, the team screened the finding through IMC 0609,

Appendix A, The Significance Determination Process for Findings At-Power, issued on

June 19, 2012, using Exhibit 2, Mitigating Systems Screening Questions. The finding

screened as of very-low safety significance (Green) because it did not result in the loss

of system and/or function, represent an actual loss of function of at least a single train or

two separate safety systems out-of-service for greater than its TS allowable outage time,

15

and represent an actual loss of function of one or more non-TS trains of equipment

designated as high safety-significant for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Specifically, a historical

review did not find an example where the swing DG was non-functional for a period

greater than the applicable TS allowable outage time as a result of this finding during the

last year.

The team did not identify a cross-cutting aspect associated with this finding because it

was not confirmed to reflect current performance due to the age of the performance

deficiency. Specifically, the means to detect an opened breaker associated with the

affected loads were established more than 3 years ago.

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, states, in

part, that measures be established to assure that applicable regulatory requirements and

the design basis are correctly translated into specifications, drawings, procedures, and

instructions. Section 7.3.6.2 of the UFSAR stated The diesel generators are applied to

the various plant buses so that the loss of any one diesel generators will not prevent the

safe shutdown of either unit. Further, it stated The total system satisfies single-failure

criteria.

Contrary to the above, as of May 13, 2016, the licensee failed to assure that

applicable regulatory requirements and the design basis were correctly translated into

specifications, drawings, procedures, and instructions. Specifically, the licensees

design control measures did not assure that the swing DG was applied to the buses

supplying power to its room fan, fuel oil transfer pump, and fuel storage tank room

exhaust fan such that the total DG system would be able to satisfy the single-failure

criteria. The associated circuit design and procedures did not ensure the detection of

a condition where the feeder breaker of one of the associated buses was tripped in the

open position during normal plant operation.

The licensee is still evaluating its planned corrective actions. However, the team

determined that the continued non-compliance does not present an immediate safety

concern because the licensee established a special log to monitor the associated

breakers once per day.

Because this violation was of very-low safety significance (Green) and was entered into

the licensees CAP as AR 02668759, this violation is being treated as an NCV, consistent

with Section 2.3.2 of the NRC Enforcement Policy. (NCV 05000373/2016007-02;

05000374/2016007-02, Failure to Ensure that Both Feed Supply Breakers for Swing

DG Components Were Closed During Normal Plant Operation)

.4 Operating Experience

a. Inspection Scope

The team reviewed five samples of operating experience issues to ensure that NRC

generic concerns had been adequately evaluated and addressed by the licensee. The

operating experience issues listed below were reviewed as part of this inspection:

IN 2006-22, New Ultra-Low-Sulfur Diesel Fuel Oil Could Adversely Impact

Diesel Engine Performance;

16

IN 2009-02, Biodiesel in Fuel Oil Could Adversely Impact Diesel Engine

Performance;

IN 2012-16, Preconditioning of Pressure Switches Before Surveillance Testing;

IN 2013-14, Potential Design Deficiency in MOV Control Circuitry; and

Bulletin 96-03, Potential Plugging of Emergency Core Cooling Suction Strainers

by Debris in Boiling-Water Reactors.

b. Findings

(1) Inadequate Procedures for Containment Debris Management

Introduction: The team identified a finding of very-low safety significance (Green) and an

associated NCV of 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures,

and Drawings, for the failure to establish procedures that were appropriate to manage

containment debris consistent with the emergency core cooling system (ECCS)

strainer debris loading design basis and supporting design information. Specifically,

the procedures did not contain instructions for evaluating containment debris sources

consistent with the associated analyses and other design documents.

Description: On May 6, 1996, the NRC issued Bulletin 96-03, Potential Plugging

of Emergency Core Cooling Suction Strainers by Debris in Boiling-Water Reactors,

to request addressees to implement appropriate procedural measures and plant

modifications to minimize the potential for clogging of ECCS suppression pool suction

strainers by debris generated during a LOCA and to provide a response describing

these actions. The licensee provided an initial response in a letter to the NRC titled

LaSalle County Station Unit 1 and 2 Response to the NRC Bulletin 96-03, dated

November 1, 1996. This response stated, in part, that the licensee planned to

install larger capacity passive strainers designed using the guidance contained in

NEDO-32686, Boiling Water Reactors Owners Group Utility Resolution Guidance for

ECCS Suction Strainer Blockage, which was endorsed with exceptions by the NRC.

By letter titled Completion Report for NRC Bulletin 96-03, dated April 28, 2000, the

licensee informed the NRC that all actions requested by the bulletin were completed,

including the implementation of procedures for periodic drywell and wetwell inspections

and periodic suppression chamber desludging. The NRC documented its review and

acceptance of the licensee responses in letter titled Completion of Actions for

Bulletin 96-03, LaSalle County Station, Units 1 and 2, dated June 2, 2000.

The licensee estimated the head loss across the debris bed formed on the strainers due

to accumulation of debris produced during a LOCA in calculation L-002051. This

calculation established separate design limits for different debris sources at specified

containment locations, such as unqualified coatings, rust flakes, and sludge. During this

inspection period, the licensee used Revision 9 of Procedure CC-AA-205, Control of

Undocumented/Unqualified Coatings inside the Containment, to control the amount of

undocumented/unqualified coatings within the design limits. In addition, Revision 8 of

Procedure LTS-600-41, Primary Containment Inspections for ECCS Suction Strainer

Debris Sources, was used to perform and document the periodic drywell and wetwell

inspections to identify and maintain containment debris quantities below their design

limits. Moreover, Revision 18 of Procedure OP-AA-108-108, Attachment 1, Engineering

Department Start-Up Checklist, step 24, required the licensee to verify that the

17

ECCS strainer debris loads were within design limits prior to unit startup. The

licensee completed this step by performing an evaluation using ECs.

However, the team noted that the procedures were inadequate to maintain containment

debris quantities consistent with the design basis and design supporting information.

Specifically,

Procedure CC-AA-205 did not contain instructions to ensure that the appropriate

coating supporting design information (i.e., thickness and density) was used

when evaluating degraded coatings that were originally considered as qualified

against the applicable strainer debris loading design basis limit. Specifically, the

licensee documented the identified areas of unqualified coatings in a log using

units of square feet. Because calculation L-002051 established a design limit of

328 pounds, the licensee converted the units from square feet to pounds.

However, the team noted that the licensee used the coating supporting design

information for the coating system that was originally installed as unqualified,

which had smaller thickness and density values than the originally qualified

coating system that was found degraded during the inspections and, thus, was

no longer qualified. As a result, the licensee underestimated the amount of

drywell unqualified coatings. Specifically, the incorrect logs showed an available

margin of about 16 percent and 44 percent for Units 1 and 2, respectively.

When the logs were corrected, the design basis limits were exceeded by about

20 percent and 7 percent for Units 1 and 2, respectively.

Procedure LTS-600-41 contained a sludge acceptance criterion that was

inconsistent with the applicable design basis limit and was non-conservative.

Specifically, calculation L-002051 established a sludge design limit of 750

pounds. However, procedure LTS-600-41 contained an acceptance criteria of

1000 pounds.

Procedure LTS-600-41 did not contain appropriate instructions to evaluate the

as-found conditions against the design basis limit for each debris type evaluated

by calculation L-002051. As a result, the licensee was not evaluating the as-

found conditions consistent with this calculation. For example, the diver

inspection report attached to Work Order 01317612 described the identified

sludge piles as The size of the material in these piles ranged from particulate to

3 [inches] long by 1 [inch] wide, but averaged in the dime to quarter size. In

contrast, the NEDO-32686 sludge particle maximum size was 0.003 inches.

Based on other documented inspection report descriptions, the team determined

that the likely debris type described by the diver was rust flakes, which had a

design basis limit of 100 pounds as opposed to 750 pounds for sludge. A second

example is documented in the next bullet.

Procedure LTS-600-41 did not contain appropriate instructions to evaluate the

aggregate effects of the debris found when performing different inspection

activities at different containment locations. Specifically, the team noted

instances when the inspection for the entire containment was not completed in a

single effort and the evaluation of the results for each inspection effort did not

account for the results for the other inspection activities when comparing the

identified condition against the design basis limits. For example, EC 392593,

which used the LTS-600-41 sludge results and was performed to meet Step 24

18

of Procedure OP-AA-108-108, Attachment 1, evaluated only the suppression

pool sludge against the design basis allowances of multiple debris sources.

Specifically, it stated Design Analysis L-002051 describes the following

suppression pool particulate matter debris assumed in the ECCS suction

strainer head loss analysis: 750 lbs. [pounds] of sludge, 300 lbs. [pounds]

of dirt/dust, 85 lbs. [pounds] of qualified paint debris, 328 lbs. [pounds] of

unqualified paint debris, and 100 lbs. [pounds] of rust flakes. It also concluded

that The estimated amount of sludge in the suppression pool at L2R14 (205 lbs.

[pounds]) and the predicated accumulation by L2R15 (365 lbs. [pounds]) are well

below the amount assumed in Design Analysis L-002051 (750 lbs. [pounds] plus

additional allowances for dust/dirt, paint, and rust. The team noted that

EC 392593 did not consider the amount of debris sources at both the drywell and

wetwell other than suppression pool sludge when crediting the design basis limits

for multiple drywell and wetwell debris sources. The team was concerned that

this licensee practice would allow a condition where the debris amount identified

in each inspection location is within the design basis limits but, in aggregate,

would exceed them. This example also illustrates the concern described in the

previous bullet. The team noted similar observations on other start-up ECs.

Overall, the team was concerned because the procedures were not adequate to ensure

that the containment debris quantities were consistent with the design basis analysis and

their relative distribution were consistent with the design information, including testing,

that supported the design basis analysis assumptions.

The licensee captured the team concerns in their CAP as AR 02663076 and

AR 02656299. The immediate corrective actions included an operability evaluation

that reasonably determined all of the affected ECCS strainers remained operable.

Specifically, the licensee reasonably concluded that only a fraction of the unqualified

coatings would be available for transport to the strainers during a LOCA and this amount

was bounded by the associated design basis limit. This determination was based, in

part, on unqualified coating testing and the documented condition of the unqualified

coatings. In addition, the licensee reviewed containment cleaning records and the

inspection results for the other debris sources and reasonably determined that the

associated design basis limits were met. The licensee proposed plan to restore

compliance at the time of this inspection was to revise the affected procedures and

the coating logs. In addition, the licensee planned to revise calculation L-002051

if additional margin is required to meet the corrected coating log values.

Analysis: The team determined the failure to establish procedures that were appropriate

to manage containment debris consistent with the ECCS strainer debris loading design

basis and supporting design information, was contrary to 10 CFR Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings, and was a performance

deficiency. The performance deficiency was determined to be more than minor

because it was associated with the procedure quality attribute of the Mitigating Systems

cornerstone, and adversely affected the cornerstone objective to ensure the availability,

reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences. Specifically, the failure to establish procedures that were

appropriate to manage containment debris does not ensure that the ECCS strainer

debris loading during a LOCA will be bounded by the associated design basis analysis.

19

The team determined the finding could be evaluated using the SDP in accordance with

IMC 0609, Significance Determination Process, Attachment 0609.04, Initial

Characterization of Findings, issued on June 19, 2012. Because the finding impacted

the Mitigating Systems cornerstone, the team screened the finding through IMC 0609,

Appendix A, The Significance Determination Process for Findings At-Power, issued on

June 19, 2012, using Exhibit 2, Mitigating Systems Screening Questions. The finding

screened as of very-low safety significance (Green) because it did not result in the loss

of operability or functionality of mitigating systems. Specifically, the licensee performed

an operability review and reasonably determined that only a portion of the unqualified

coatings would be available for transport to the strainers and this quantity was bounded

by the associated design basis analysis. In addition, this review reasonably determined

that sufficient analytical margin existed to accommodate the quantities of the other

debris types found during recent inspections.

The team did not identify a cross-cutting aspect associated with this finding because it

was not confirmed to reflect current performance due to the age of the performance

deficiency. Specifically, the associated procedures were established more than 3 years

ago.

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion V, Instructions,

Procedures, and Drawings, requires, in part, that activities affecting quality be

prescribed by documented procedures of a type appropriate to the circumstances

and be accomplished in accordance with these procedures. The licensee established

Revision 9 of Procedure CC-AA-205 and Revision 8 of Procedure LTS-600-41 as the

implementing procedures for containment debris management, an activity affecting

quality.

Contrary to the above, as of April 29, 2016, the licensee failed to have procedures of a

type appropriate to manage containment debris consistent with the ECCS strainer debris

loading design basis and supporting design information, as evidenced by the following

examples:

Procedure CC-AA-205 did not contain instructions to ensure that the appropriate

coating supporting design information (i.e., thickness and density) was used

when evaluating degraded coatings that were originally considered as qualified

against the applicable strainer debris loading design basis limit.

Procedure LTS-600-41 contained a sludge acceptance criterion that was

inconsistent with the applicable design basis limit and was non-conservative.

Procedure LTS-600-41 did not contain appropriate instructions to evaluate the

as-found conditions against the corresponding design basis debris type.

Procedure LTS-600-41 did not contain appropriate instructions to evaluate the

aggregate effects of the debris found when performing different inspection

activities at different containment locations.

The licensee is still evaluating its planned corrective actions. However, the team

determined that the continued non-compliance does not present an immediate safety

concern because the licensee performed an operability review and reasonably

determined that ECCS was operable based on the as-found conditions documented in

recent inspection reports.

20

Because this violation was of very-low safety significance (Green) and was entered

into the licensees CAP as AR 2656299 and AR 2663076, this violation is being

treated as an NCV, consistent with Section 2.3.2 of the NRC Enforcement Policy.

(NCV 05000373/2016007-03; 05000374/2016007-03, Inadequate Procedures for

Containment Debris Management)

.5 Modifications

a. Inspection Scope

The team reviewed two permanent plant modifications related to the selected risk

significant components to verify that the design bases, licensing bases, and performance

capability of the components had not been degraded through modifications. The

modifications listed below were reviewed as part of this inspection effort:

EC 396093, Install 125Vdc/120Vac Inverter to Power Existing 120Vac/24Vdc

Power Supply that Feeds Existing Containment Instrumentation; and

EC 395217, Unit 2 Division 1 and 2 DG Feed Breaker Logic Modification due to

C RHR and LPCS [Low-Pressure Core Spray] anti-Pump Logic.

b. Findings

No findings were identified.

.6 Operating Procedure Accident Scenarios

a. Inspection Scope

The team performed a detailed reviewed of the procedures listed below associated with

a loss of offsite power and a complete loss of AC power (i.e., SBO). The procedures

were compared to UFSAR, design assumptions, and training materials to asses for

constancy. The following operating procedures were reviewed in detail:

LOA-DG-101(201), DG Failure [Unit 1(2)], Revision 9(8);

LOA-FC-101(201), Unit 1(2) Fuel Pool Cooling System/Reactor Cavity Level

Abnormal, Revision 25(23);

LGA-RH-103(203), Unit 1(2) A/B RHR Operations in the LGAS/LSAMGS,

Revision 12(13);

LOP-RH-01, Filling and Venting the Residual Heat Removal System,

Revision 57;

LOP-RH-02, Venting the Residual Heat Removal System, Revision 9;

LOA-IN-101, Loss of Drywell Pneumatic Air Supply, Revision 9; and

LOP-IN 05, Replacing Nitrogen Bottles on Instrument Nitrogen System,

Revision 25.

21

For the procedures listed, time critical operator actions were reviewed for

reasonableness. This review included walkdowns of in-plant actions with a licensed

operator and the observation of licensed operator crews actions during the performance

of an SBO scenario on the station simulator to assess operator knowledge level,

procedure quality, availability of special equipment where required, and capability to

perform time critical operator actions within the required time. The simulated scenario

started with a dual unit loss of offsite power and then degraded, several minutes later,

into an SBO on Unit 1 with limited power available to Unit 2. In addition, the team

evaluated operations interfaces with other departments and the transition to beyond

licensing basis event procedures to assess the interface between licensing basis and

beyond licensing basis procedures. The following operator actions were reviewed:

establish automatic depressurization system control in the auxiliary electric

equipment room;

DC load shedding;

placement of RHR in the suppression pooling cooling mode following an SBO;

and

replacing drywell pneumatic air supply nitrogen bottles.

b. Findings

No findings of significance were identified.

4. OTHER ACTIVITIES

4OA2 Identification and Resolution of Problems

.1 Review of Items Entered Into the Corrective Action Program

a. Inspection Scope

The team reviewed a sample of problems identified by the licensee associated with

the selected components and that were entered into the CAP. In addition, the team

reviewed a sample of CAP documents for the last 3 years resulting from degraded

conditions. The team reviewed these issues to assess the licensees threshold for

identifying issues and the effectiveness of corrective actions related to design issues.

In addition, corrective action documents written on issues identified during the inspection

were reviewed to assess the incorporation of the problem into the CAP. The specific

corrective action documents sampled and reviewed by the team are listed in the

attachment to this report.

The team also selected three issues identified during previous CDBIs to assess the

associated licensees evaluation and resolution. The following issues were reviewed:

NCV 2007009-03, Lack of Station Blackout Analysis for Reactor Core Isolation

Cooling (RCIC);

NCV 2010006-02, DG Usable Fuel and RHR Pump NPSH Calculations Failed to

Consider Appropriate DG Frequency Variations; and

NCV 2010006-04, Fast Bus Transfer Analysis.

22

b. Findings

(1) Alternate Shutdown Procedures Failed to Ensure RCIC MOVs Supply Breakers Were

Closed

Introduction: The team identified a finding of very-low safety significance (Green) and

associated NCV of the LaSalle County Station Operating License for the failure to

ensure that procedures were in effect to implement the alternate shutdown capability.

Specifically, the AOPs established to respond to a fire at the MCR did not include

instructions for verifying that supply breakers for three RCIC MOVs were closed to

ensure they could be operated from the remote shutdown panel (RSP). Fire-induced

failures could result in tripping MOV power supply breakers prior to tripping the MOV

control power fuses.

Description: In the event of an MCR evacuation due to a fire, the safe shutdown

analysis credited the RCIC system for the alternate shutdown method from the RSP.

Specifically, RCIC was credited for reactor water makeup and decay heat removal.

During this event, the MCR control circuits for the RCIC MOVs needed to be transferred

from the MCR to the RSP. To accomplish this transfer, the licensee included

instructions to the operators for placing the RCIC remote shutdown transfer switches in

the emergency position at the RSP in Procedure LOA-FX-101, Unit 1 Safe Shutdown

with a Fire in the Control Room, and Procedure LOA-FX-201, Unit 2 Safe Shutdown

with a Fire in the Control Room. This transfer was intended to ensure that the alternate

shutdown capability was independent of the MCR fire area by isolating the MCR control

circuits for the RCIC MOVs and connecting a different set of control fuses that fed from a

separate power source at the RSP for each MOV.

However, in 2014, the NRC identified that the licensee failed to ensure that the alternate

shutdown capability was independent of the MCR during the NRC Triennial Fire

Protection inspection. Specifically, the inspectors noted that the control circuit design

did not ensure the MOV control power fuses trip before the associated feeder breakers

as a result of fire-induced failures, such as a short circuit in the control circuit. A tripped

MOV feed breaker would impair the operation of the associated MOV from the RSP.

In addition, the inspectors noted that Revision 26 of LOA-FX-101 and Revision 27 of

LOA-FX-201 did not include instructions to reset the affected breakers. This issue was

documented by the inspectors as NCV 05000373/2014008-01; 05000374/2014008-01,

Failure to Ensure Circuits Associated with Alternate Shutdown Capability Free of

Fire-Induced Damage, in Inspection Report 05000373/2014008; 05000374/2014008,

dated February 27, 2015. The licensee captured this issue in their CAP as

AR 02424674 and reviewed the control circuits of the affected MOVs. Specifically,

the licensee completed analysis L-004017, 250 Vdc Breaker Fuse Coordination for

RCIC, Revision 0, which evaluated breaker-fuse coordination for all 28 RCIC MOVs

(14 per reactor unit) during a postulated MCR fire event. This analysis identified

16 MOVs (8 per reactor unit) that could be adversely affected by a postulated MCR fire

and, thus, required further evaluation for potential lack of breaker fuse coordination. In

addition, the licensee revised Procedures LOA-FX-101 and LOA-FX-201 to verify closed

the breakers associated only with these 16 MOVs after control was transferred to the

RSP.

23

During this CDBI inspection, the team noted that analysis L-004017 calculated the fault

current using the maximum DC bus voltage divided by the resistance of each cable

(using a value of 0.273 ohms per 1000 feet). Thus, shorter cable lengths led to smaller

cable resistances resulting in higher fault current values. However, the analysis did not

consider all potential fire-induced short circuits that could potentially affect breaker-fuse

coordination and, as a result, failed to evaluate short circuits that resulted in shorter

short circuit cable lengths. Specifically, the analysis only considered a short circuit

(conductor to conductor dead short) for the control cable associated with each MOV

and that provided the shortest path for each MOV from the 250Vdc power source to

the MCR. For example, the analysis determined that the existing breaker settings for

MOVs 1E51-F019, 2E51-F019, and 1E51-F059 were acceptable because their

maximum calculated fault current was less than the minimum breaker trip setting using

a cable length of 2926 feet, 3512 feet, and 1821 feet, respectively. The analysis also

determined the margins between the minimum breaker setting and maximum fault

current were 14.49 percent, 19.92 percent, and 2.57 percent for these MOVs,

respectively. However, the analysis did not consider fire-induced circuit failures such

as shorts between cables associated with these MOVs and other MOVs from the same

250Vdc power source resulting in shorter short circuit cable lengths. The analysis also

failed to consider shorts between cables associated with these MOVs and the ground,

and cables associated with other MOVs with shorter cable lengths and the ground that

would end with short circuit via the ground.

The team was concerned because the unanalyzed fire-induced circuit failures

(i.e., short between cables and short to grounds) would have the potential to result in

higher available fault current values that could trip the feeder breaker for the affected

MOVs. In addition, the team was concerned because the AOPs revisions in effect at the

time of this inspection (i.e., Revision 27 of LOA-FX-101 and Revision 29 of LOA-FX-201)

did not include instructions to verify that the feeder breakers were closed for all of the

affected MOVs based on the conclusions of analysis L-004017. The team further noted

that the AOPs required operators to open valves 1E51-F019 and 2E52-F019 as part

of the expected response for a safe shutdown with a fire in the MCR and the AOPs

did not include alternative instructions in the event these valves could not be opened.

In addition, the AOPs required operators to open valve 1E15-F059 if RCIC flow was not

within the expected range. Thus, the team determined that the inability to operate these

values would not be within the bounds of the AOPs for a safe shutdown with a fire in the

MCR.

The licensee captured the team concerns in their CAP as AR 02668854. The immediate

corrective actions included revising Standing Order S14-09 to establish compensatory

actions to reset the affected breakers, if required. The licensee proposed plan to restore

compliance at the time of this inspection was to revise the AOPs to reset the affected

breakers, if required.

Analysis: The team determined that the licensees failure to ensure that procedures

were in effect to implement the alternate shutdown capability was contrary to LaSalle

County Station Operating License conditions for the Fire Protection Program and was a

performance deficiency. The performance deficiency was determined to be more than

minor because it was associated with the Mitigating Systems Cornerstone attribute of

protection against external events (fire), and affected the cornerstone objective of

24

ensuring the availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences (i.e., core damage). Specifically, the

failure to ensure that procedures were in effect to transfer RCIC control from the MCR to

the RSP in the event of an MCR fire does not ensure the alternate shutdown capability

of RCIC.

The team determined the finding could be evaluated using the SDP in accordance

with IMC 0609, Significance Determination Process, Attachment 0609.04, Initial

Characterization of Findings, issued on June 19, 2012. Because the finding affected

the ability to reach and maintain safe shutdown conditions in case of a fire, the team

screened the finding through IMC 0609, Appendix F, Fire Protection Significance

Determination Process, issued on September 20, 2013, using Attachment 1, Part 1:

Fire Protection SDP Phase 1 Worksheet, issued on September 20, 2013. The finding

screened as of very-low safety significance (Green) because it was assigned a low

degradation factor based on the criteria in IMC 0609, Appendix F, Attachment 2,

Degradation Rating Guidance, issued on February 28, 2005. Specifically, the team

assigned a low degradation factor because the procedural deficiencies could be

compensated by operator experience/familiarity and the fact that the procedure

included steps to verify other breakers at the same MCCs were closed.

The team determined that this finding had a cross cutting aspect in the area of problem

identification and resolution because the licensee failed to take effective corrective

actions. Specifically, AR 02424674 included actions to revise the affected AOPs to

include verifying all the RCIC MOVs supplied breakers were closed to correct an issue

identified on 2014. However, the licensee failed to include all of the MOVs in the revised

AOPs. [P.3]

Enforcement: License conditions 2.C.25 and 2.C.15 of the LaSalle County Station,

Unit 1 and Unit 2 Operating Licenses, respectively, require, in part, that the licensee

implement and maintain all provisions of the approved Fire Protection Program as

described in the UFSAR for LaSalle County Station, and as approved in NUREG-0519,

Safety Evaluation Report, dated March 1981 through Supplement No. 8 and all

associated amendments. The license conditions also indicate that the licensee may

make changes to the approved Fire Protection Program without prior approval of the

NRC only if those changes would not adversely affect the ability to achieve and maintain

safe shutdown in the event of a fire.

LaSalle Comparison to 10 CFR Part 50, Appendix R, in Revision 7 of the Fire Protection

Program, Section 3, stated in the 10 CFR 50 Appendix column that The shutdown

capability for specific fire areas may be unique for each such area, or it may be one

unique combination of systems for all such areas. It also stated In either case, the

alternative shutdown capability shall be independent of the specific fire area(s) and shall

accommodate post fire conditions where offsite power is not available for 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. In

addition, it stated Procedures shall be in effect to implement this capability. The

LaSalle Conformance column stated Comply, specific post fire safe shutdown

procedures have been developed for the Control Room and AEER. LOA-FX-101(201).

Contrary to the above, from December 12, 2015, to at least May 13, 2016, the licensee

failed to have procedures in effect to implement the alternative shutdown capability for

a fire area where alternative shutdown capability was established. Specifically, the

safe shutdown procedures developed for the MCR, a fire area, (i.e., Revision 27 of

25

LOA-FX-101 and Revision 29 of LOA-FX-201) did not include instructions for verifying

that the supply breakers for all RCIC MOVs susceptible to fire-induced failures were

closed to ensure the successful operation of the RCIC system, which is the credited

alternate shutdown system in the event of a fire in the MCR.

The licensee is still evaluating its planned corrective actions. However, the team

determined that the continued non-compliance does not present an immediate safety

concern because the licensee established compensatory actions to reset the affected

breakers, if required.

Because this violation was of very low safety significance (Green) and was entered into

the licensees CAP as AR02668854, this violation is being treated as an NCV, consistent

with Section 2.3.2 of the NRC Enforcement Policy. (NCV 05000373/2016007-04;

05000374/2016007-04, Alternate Shutdown Procedures Failed to Ensure RCIC MOVs

Supply Breakers Were Closed)

4OA6 Management Meetings

.1 Exit Meeting Summary

On May 13, 2016, the team presented the inspection results to Mr. Trafton, Site Vice

President, and other members of the licensee staff. The licensee acknowledged the

issues presented. The team asked the licensee whether any materials examined during

the inspection should be considered proprietary. Several documents reviewed by the

team were considered proprietary information and were either returned to the licensee or

handled in accordance with NRC policy on proprietary information.

ATTACHMENT: SUPPLEMENTAL INFORMATION

26

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

W. Trafton, Site Vice President

H. Vinyard, Plant Manager

J. Kowalski, Engineering Director

J. Keenan, Operations Director

V. Shah, Engineering Deputy Director

G. Ford, Regulatory Assurance Manager

M. Chouinard, Design Engineer

P. Patel, Electrical Engineer

A. Ahmad, Design Engineer

D. Murray, Regulatory Assurance Engineer

U.S. Nuclear Regulatory Commission

M. Jeffers, Chief, Engineering Branch 2

N. Féliz Adorno, Senior Reactor Inspector

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

05000373/2016007-01; NCV Failure to Monitor the Fouling Conditions of the CSCS

05000374/2016007-01 Equipment Area Coolers (Section 1R21.3.b(1))05000373/2016007-02; NCV Failure to Ensure that Both Feed Supply Breakers for

05000374/2016007-02 Swing DG Components Were Closed During Normal

Plant Operation (Section 1R21.3.b(2))05000373/2016007-03; NCV Inadequate Procedures for Containment Debris05000374/2016007-03 Management (Section 1R21.4.b(1))05000373/2016007-04; NCV Alternate Shutdown Procedures Failed to Ensure RCIC

05000374/2016007-04 MOVs Supply Breakers Were Closed (Section 4OA2.b(1))

Discussed

None

Attachment

LIST OF DOCUMENTS REVIEWED

The following is a list of documents reviewed during the inspection. Inclusion on this list does

not imply that the NRC inspectors reviewed the documents in their entirety, but rather, that

selected sections of portions of the documents were evaluated as part of the overall inspection

effort. Inclusion of a document on this list does not imply NRC acceptance of the document or

any part of it, unless this is stated in the body of the inspection report.

CALCULATIONS

Number Description or Title Revision

L-002051 ECCS Strainer Head Loss Performance Analysis 2A

L-003354 ECCS & RCIC Pumps NPSH Road Map Calculation 1

ATD-0070 Limiting Operating Conditions For Net Positive Suction Head 0

(NPSH) for HPCS, LPCS, RCIC & RHR pumps

L-001222 Estimation of Worst-Case Unit 1 RMI Debris Inventory Available 2

for Transport to the Suppression Pool

MAD-72-32 Pressure Drop Calculations, RCIC System 0

L-002540 NPSH Margin for HPCS, RHR, & RCIC Pumps, Backpressure for 2

RCIC Turbine

97-1998 VY Cooler Thermal Performance Model - 1(2)VY04A A

L-001024 LPCS Pump Cubicle Cooler Ventilation System 2

066455(EMD) Generic Evaluation of 5 Degree F Increase in Suppression Pool OA

Temperature

L-003317 RCIC Lube Oil Cooler Operation with SBO Event maximum 0

Suppression Pool Temperature

MAD 72-32 Pressure Drop Calc RCIC System 0

ATD-0351 RCIC Pump Room Temperature Transient Following Station 1

Blackout with Gland Seal Leakage

L-002440 Cross Index for Environmental Qualification Parameters and Their 1A

Respective Source Documents

L-000550 Zone H5A Equipment Qualification Dose 0

L-001384 Reactor Building Environmental Transient Conditions Following 10

RWCU and RCIC HELBs and LOCA/Loss of HVAC Event

L-003263 Volume Requirements for ADS Back-up Compressed Gas System 3A

(Bottle Banks)

EC 372452 Generic Letter 2008-01 Void Calculation and Acceptance Criteria 24

EC 343185 Maximum Expected Run Hours for Suppression Pool Cooling/Full 0

Flow Test Operating Modes of RHR

110A Ventilation Air Intake Extension for Diesel Generator 2

97-195 Thermal Model of ComEd/LaSalle Station Unit 0, 1 and 2 Diesel 0

Generator Jacket Water Cooler

DG-08 NPSH for HPCS DG Fuel Pumps 1B

DO-6 Elevation Diesel Fuel Oil Tanks 0

EC 366261 Revise Setpoint of DG Fuel Oil Storage Tank Low Level Switches 0

EC 372326 0DG Thermal Performance Margin with Tube Blocked 0

EC 381640 Minimum Required On-Site Usable Diesel Fuel Required to 0

Support Both Six Days and Seven Days of Continuous Emergency

Diesel Generator Operation Per Tech Spec Bases Table B.3.8.3-1

2

CALCULATIONS

Number Description or Title Date or Revision

EC 382235 Evaluation of The NPSH For Safety Related Pumps In 0

Support of Op Eval 10-005

EC 384217 2A DG Heat Exchanger Thermal Performance Test 0

Evaluation

EC 389270 UHS Temperature Increase 0

EC 395837 2A DG Heat Exchanger Thermal Performance Test 0

Evaluation

L-002901 Verification of the Division 1 and 2 Diesel Oil Storage and 1A

Day Tank Volumes

L-003364 0DG Electrical Loading Calculation 3

L-003416 Emergency Diesel Generators Onsite Usable Fuel 0B

Volume Requirements

VD-1A Standby Diesel Generator Room Ventilation System 0

VD-1C Diesel Generator Room Vent System Duct Pressure 0

Drops

VD-2A Standby Diesel Generator Room Ventilation System 0

VD-2C Diesel Generator System Duct Pressure Drops 0

VD-3C Engine-Generator for High Pressure Core Spray System 0

3C7-0788-001 Assessment of Bulk Pool Temperature Calculation 2

Methods [I&C interface review]

DCR 990833 Change NED-I-EIC-0260 to incorporate Results of 24 03/07/00

Month Drift Analysis

EC 380464 Evaluation of Preconditioning of TS and TRM Pressure 1

Switches

L-002590 Condensate Storage Tank Level Switch Setpoint Error 1

Analysis

L-002664 Review of Design Bases for 2° F Correction Factor Used 1

in LOP-CM-03, Rev. 11 [I&C interface review]

L-002968 DC System Ground Detector Action Levels, Sections 7.6, 0

8.0

L-003447 LaSalle Units 1 and 2,125 Vdc System Analysis 001B

L-003845 RCIC Steam Line High Flow Isolation Error Analysis 0

NED-I-EIC-0196 Suppression Chamber High Level Setpoint Error Analysis 0

NED-I-EIC-0213 RCIC Equipment Area/Pipe Tunnel High Ambient and 001G

Differential Temperature Outboard and Inboard Isolation

Error Analysis

NED-I-EIC-0259 Suppression Chamber Water Temperature Indication 1

Loop Analysis

NED-I-EIC-0260 Suppression Chamber Wide Range Water Level 0

Indication Error Analysis

PC-03 Design Analysis: Suppression Pool Volume Check [I&C 0

interface review]

LAS-2E51-F046 DC Motor Operated GL96-05 Globe1 Valve 8

LAS-2E51-F045 DC Motor Operated GL96-05 Globe1 Valve 8

L-003364 Attachment C - ETAP Output Report for EDG Load 3

Flow

3

CALCULATIONS

Number Description or Title Revision

L-003897 Setpoint Analysis for DG Feed Breaker Close Time Delay Relay 1

L-002589 Instrument Setpoint Analysis for 4.16KV Undervoltage (Loss of 0

Voltage) Relay-Time Delay Function

L-002588 Loss of Voltage Relay Setpoint for 4.16 KV Buses Undervoltage 0

Function

L-003823 1AP76E(135Y-2) MCC Voltage Drop, CB and TOL Setting 0

L-000300 Thermal Overload Relay Setting for Continuous Duty Motors 2

L-003448 LaSalle Units 1 and 2, 250 VDC System Analysis 0

L-003820 1AP72E (135X-2) MCC Voltage Drop, CB and TOL Setting 0

L-004017 250 VDC Breaker Fuse Coordination for RCIC 0

CORRECTIVE ACTION DOCUMENTS GENERATED DUE TO THE INSPECTION

Number Description or Title Date

AR02665463 NRC IDd, CDBI, Tube Plugging in 2VY04A 05/04/16

AR02654987 LOA-FC-101/201 Minor editorial procedure issue. 04/13/16

AR02655443 LOA-LOOP-101/201 Contains operating guidance for the RCIC 04/14/16

System that conflicts with operating guidance found in LGA-001.

AR02656039 DC Load Shedding procedure enhancements. 04/15/16

AR02661078 Configuration Control (Locking Status) of RCIC Pump Water Leg 04/26/16

Pump Discharge Valve (F062).

AR02659810 NRC CDBI 2016 - UFSAR Table 8.3-3 Shows Inaccurate Rev Bar 04/22/16

AR02661013 NRC-CDBI Identified SBLC Issue with UFSAR 04/26/16

AR02666354 NRC CDBI 2016 - UFSAR, App B PG B.0-11 Shows Inaccurate 05/06/16

Rating

AR02655170 NRC CDBI Identified Packing leak 04/13/16

AR02659688 NRC CDBI Identified Calculation NED-EIC-0196 Reference Has 04/22/16

Not Been Superseded

AR02665136 NRC CDBI Identified Error in Design Analysis NED-EIC-0260 05/04/16

AR02667806 NRC CDBI Identified Concern [Reporting and Trending of 05/10/16

Conditions Identified and Corrected During PM Activities]

AR02655692 0VD02C Fan Motor LRC Discrepancy 04/14/16

AR02668854 NRC - CDBI Identified Issue Related to Breaker Coordination 05/12/16

AR02668759 NRC Concern about 0VD01C Alarm in MCR 05/12/16

AR02663076 NRC CDBI Concerns on Strainers 04/29/16

AR02656299 NRC-CDBI - IDD LTS-600-41 PCRA Sludge Weight Correction 04/15/16

AR02668855 CDBI2016 NRC Observation on Use of Measured LRC for 1EBOP 05/12/16

AR02653895 NRC-CDBI Identified Issue - HPCS UFSAR description 04/11/16

AR02668085 NRC-CDBI Identified Issue - post-TIA 2001-14 procedures 05/11/16

AR02662445 NRC CDBI L-002051 Enhancements to Microtherm Assumptions 04/28/16

AR02655171 NRC-CDBI Identified Issue - RCIC storage ladders 04/13/16

AR02655372 NRC ID - CDBI LTS-600-41 PC Inspection PCRA Needed 04/14/16

AR02656385 NRC IDD: Discrepancy in PRA Documentation 04/15/16

AR02657236 NRC Identified - CDBI - Suction Strainer Calculation Review 04/18/16

AR02659561 NRC IDD: Incorrect Reference in LTS-600-41 04/22/16

AR02661223 NRC IDS CDBI Incorrect Input Values Listed in L-002540 04/26/16

4

CORRECTIVE ACTION DOCUMENTS REVIEWED DURING THE INSPECTION

Number Description or Title Date

AR02637587 NRC Question Coatings in Drywell on Floor Elevation 736 03/08/16

AR02571878 Unqualified Coatings Log Discrepancy 10/16/15

AR00673099 CDBI - RCIC Ops During SBO w/Elevated Suppression Pool 09/19/07

Temps

AR01575421 CDBI - IST Instrumentation Accuracy 10/22/13

AR01177556 2E51-C002 As-Found Condition of the #7 steam Jet Body 02/20/11

AR01177586 Potential FME Noted during Disassembly of RCIC Turbine 02/20/11

AR00157514 NRC Response to TIA 2001-14 05/06/03

AR01503409 Lightning Strike in 138KV Switchyard Results in Automatic 06/20/13

Reactor Shutdown of LaSalle Units 1 and 2 - Root Cause

Investigation Report

AR01088030 Procedure to align RCIC to draw suction from CST. 07/06/10

ACIT1356743-03 Braidwood and Byron EDG Full Load Reject Practice Review 06/13/12

AR00442006 Low Flow on Cooler 2VY02A During LOS-DG-Q3 01/13/06

AR00498484 OPEX Review - Fermi Impact of EDG Frequency on Loading 06/09/06

AR00534749 Potential Issues with the Use of Ultra Low Sulfur in EDGs 02/13/12

AR00547835 IN 2006-22 Ultra Low Sulfur Fuel633 10/23/07

AR00688908 Part 21 for 0 DG Air Start Solenoid Valve Never Installed 10/24/07

AR00820843 0DG HX Inspection Found 19 Tubes Blocked 09/22/08

AR01136071 CDBI: Potential Non-Conservative Tech Spec for EDG Fuel Oil 11/05/10

AR01141618 NRC Identified, CDBI, ECCS NPSH with Increased DG 11/17/10

Frequency

AR01164421 LOS-DG-Q1 Att A4 Failure 01/19/11

AR01166990 NOS ID: OPEX Actions From NRC IN 2009-02 were Not 01/26/11

Implemented

AR01175718 0XI-DG077 0 DG Conduit Came Loose for Pyrometer Leads 02/16/11

AR01232144 0 DG Fuel Oil Transfer Pump Excessive Start Freq Alarm 06/23/11

AR01232202 Header Downstream of Engine Air Box Drain Valve Blocked 06/23/11

AR01232221 0XI-DG077 Pyrometer Reading is Erratic 06/23/11

AR01243373 Feed Breaker to 0VD01C at 135X-2 Found Tripped 07/24/11

AR01244368 0VD01C Monitoring Plan 07/27/11

AR01257379 NRC Identified Issue with 0VD01YA manual Bypass Blade 08/30/11

AR01293864 0 DG Pyrometer Reading Low 11/23/11

AR01432987 0DG A Starting Air Comp Relief Lifting 10/29/12

AR01503431 0 DG Tied to Both Units During Transient 04/18/13

AR01557106 Inline Oiler Is Not Entraining Proper Amount of Oil 09/11/13

AR02381332 0 DG HX Inspection Found Evidence of Bypass Flow 09/15/14

AR02381627 0DG01A DG Heat Exchanger Does not Have Appropriate 09/16/14

Coating

AR02382031 STS Controller Outputs Found Degraded During PM Testing 09/17/14

AR02382989 0DG01A HX Coating Repairs Needed 09/18/14

AR02382997 Common DG Cooler Leak from North Blank Flange 09/18/14

5

CORRECTIVE ACTION DOCUMENTS REVIEWED DURING THE INSPECTION

Number Description or Title Date

AR02425069 0 DG Cooler Leaking from North End 12/14/14

AR02460815 0 Diesel Generator Issues 02/28/15

AR02571589 0DO01T Level Low 10/15/15

AR02599071 0 DG Cooler Flange Leak Increased When 0 DG Cooling Pump 12/11/15

Run

AT1166990-06 Station Diesel Owner to Review/Audit site-Specific Fuel Oil 05/31/11

Purchase, Delivery, and Processing Logistics for Each Station

Diesel Engine Application

AR00560991 Prints Not Correct: 2E51-K603 11/21/06

AR00872658 Red Power On Lamp for DC to AC Inverter Flickering On/Off 01/27/09

AR01030566 1DC13E Top Right Bolt Is Stripped and Will Not Tighten 02/15/10

AR01124515 MCR Recorder 2TR-CM038A Backup Battery Issue 10/10/10

AR01130619 MCR Recorder 2TR-CM028 Backup Battery Issue 10/26/10

AR01184065 2TR-CM037A Recorder Pen Stuck, Does not Respond to Change 03/07/11

AR01301597 2E31-N013BA Has Chemical Buildup at Ports on Switch 12/13/11

AR01353739 2E31-N013BA Trend Code B4 04/13/12

AR01377629 During LIS-RI-201 2E31-N013BA Stop Valve Leaking By 06/13/12

AR01406112 Instrument Out of Tolerance, 1E31-N013BA, Trend Code B4 08/28/12

AR01458428 Power Light not on for 2E51-K603 01/04/13

AR01470186 2TR-CM038A Recorder Pen Sticky 02/01/13

AR01519502 1E31-N013BA Failed/No Reset Obtainable LIS-RI-101 05/30/13

AR01524753 Instrument Out-of-Tolerance, 2E31-N013BA, Trend Code B1 06/13/13

AR01552116 Instrument Out of Tolerance, 1E31-N013BA, Trend Code 3 08/29/13

AR01605840 DC to AC Power On Light not Lit 01/09/14

AR01632613 U-2 Division 1 Ground - 75 Volts 03/12/14

AR01632888 U-2 Division 1 125 Vdc Ground - 60 Volts 03/13/14

AR01658819 U-2 Division 1 Ground Received 05/12/14

AR01659226 U-2 Division 1 Ground 05/13/14

AR01661043 U-2 Division 1 DC Ground 05/16/14

AR01663544 U-2 Division 1 Ground Alarm 05/23/14

AR01669065 Division 1 Ground U-2 06/08/14

AR01669913 Division 1 Battery Ground Alarm 06/11/14

AR01673406 Division 1 Ground Alarm Received 06/20/14

AR01676713 Division 1 125 VDC Ground Alarm 06/30/14

AR01693700 1LR-CM208 Suppression Chamber Water Level Recorder not 08/18/14

Reliable, Sticks at Zero

AR01695294 U-2 Division 1 Ground 08/22/14

AR01695615 2TE-CM-057C-A Reading Abnormally High 08/22/14

AR02381644 U-2 Division 1 DC Ground 09/16/14

AR02383228 Received Division 1 125 VDC Ground Alarm 09/19/14

AR02392651 Unexpected MCR Alarm - 211X/Y Ground Detector 10/08/14

6

CORRECTIVE ACTION DOCUMENTS REVIEWED DURING THE INSPECTION

Number Description or Title Date

AR02397905 Received Division 1 125 VDC Ground Detector Alarm 10/20/14

AR02418240 Unexpected MCR Alarm - 2PM01J-A409, Division 1 DC Ground 11/28/14

AR02418638 Intermittent Division 1 Ground Alarm Alarming in MCR 11/30/14

AR02419372 Received Momentary 2PM01J-B504 Division 2 Ground Detection 12/02/14

Alarm

AR02425660 Unit 2 Division 1 125 VDC Ground Alarms 12/15/14

AR02429456 Momentary Division 1 125 VDC Ground Detector Alarm 12/24/14

AR02447974 Unit 2 Division 1 DC Ground Spiking 02/05/15

AR02449037 Unit 2 Division 125 VDC Momentary Ground Alarm 02/07/15

AR02453155 Unexpected Momentary Unit 2 Division 2 125 VDC Ground Alarm 02/15/15

AR02455840 Condenser Tube Pull Area Fire Alarm Circuit Causes Division 1 02/19/15

Ground

AR02496015 Unexpected MCR Alarm 2PM013-A409 Division 1 Ground 05/05/15

AR02509179 Need Tolerance in mA DC for 2LY-CM030 Added to Passport 06/02/15

AR02509186 Need Setpoint Tolerance in mA DC for 1LY-CM030 Added to 06/02/15

Passport

AR02520165 Division 1 DC Bus Ground Detector Alarm 06/26/15

AR02520553 Annunciator 2PM01J-A409, Division 1 Ground Detector 06/27/15

AR02523164 Unexpected MCR Alarm, Division 1 Ground Detector Trouble 07/02/15

AR02577832 1DC11E Door Handle Mechanism is Broken 10/27/15

AR02599359 Division 1 Ground Detector Alarm 2PM01J-A409 Received Alarm 12/12/15

AR02636107 Instrument Out-of-Tolerance, 1LT-CM-062, Trend Code B4 03/04/16

AR02637638 Unit 2 Division 2 125 VDC Ground Due to MDRFP Seal Failure 03/28/16

AR01139601 CDBI Potential Deficiency in Calculation L-003364 11/12/10

AR01141298 CDBI Fast Bus Transfer of 4KV Buses 11/16/10

AR01244368 0VD01C Monitoring Plan 07/27/11

AR01243373 Feed Breaker to 0VD01C at 135X-2 Found Tripped 07/24/11

AR00699172 Division 3 DG Neutral Ground Resistor Location not per Design 11/12/07

DRAWINGS

Date or

Number Description or Title

Revision

M-149, Sh. 3 P&ID Reactor Building Floor Drains H

M-92, Sh. 1 P&ID Primary Containment Vent & Purge AU

M-147, Sh. 1 P&ID Reactor Core Isolation Coolant System (RCIC) BL

M-147, Sh. 2 P&ID Reactor Core Isolation Coolant System (RCIC) AO

761E205AA Process Diagram, Reactor Core Isolation Coolant System 8

M-127 P&ID Cycled Condensate Storage System AL

D-0805 26 Wafer Stop Valve Assembly L

28SW404563 Assembly Dwg, Safety Related Cooling Coils, CSCS Equipment 07/26/76

Area

66781E RCIC Pump Outline F

M-66 Drywell Pneumatic System P&ID; Sheets 1 AC

7

DRAWINGS

Number Description or Title Revision

M-66 Drywell Pneumatic System P&ID; Sheets 2 V

M-66 Drywell Pneumatic System P&ID; Sheets 3 AI

M-66 Drywell Pneumatic System P&ID; Sheets 4 AB

M-66 Drywell Pneumatic System P&ID; Sheets 5 O

M-66 Drywell Pneumatic System P&ID; Sheets 6 O

M-66 Drywell Pneumatic System P&ID; Sheets 7 U

M-66 Drywell Pneumatic System P&ID; Sheets 8 H

M-66 Drywell Pneumatic System P&ID; Sheets 9 B

M-66 Drywell Pneumatic System P&ID; Sheets 10 A

M-66 Drywell Pneumatic System P&ID; Sheets 11 A

M-96 Residual Heat Removal System P&ID; Sheets 1 BC

M-96 Residual Heat Removal System P&ID; Sheets 2 BB

M-96 Residual Heat Removal System P&ID; Sheets 3 AU

M-96 Residual Heat Removal System P&ID; Sheets 4 AG

M-96 Residual Heat Removal System P&ID; Sheets 5 M

19518 Performance Curve [ECCS Water Leg Pumps] 2

13251-1 DAAP-7402 Opposed Multiblade Damper Outline G

13251-2 Schedule for Drawings 13251 & 13251-1 G

1E-0-4418AA Schematic Diagram Diesel Fuel Oil System DO Part 1 U

1E-0-4433AB Schematic Diagram Diesel Generator Room Ventilation System L

VD Part 2

1E-1-4026AA Schematic Diagram Diesel Fuel Oil System DO Part 1 V

74-2131, Sh. 1 DG Storage Tank 4

74-2131, Sh. 1A DG Storage Tank 5

M-1444 P&ID Diesel Generator Room Ventilation System J

M-3444, Sh. 1 HVAC C&I Detail Diesel Generator Room Ventilation System D

Supply Fan Start-Stop & Damper Interlock

M-83, Sh. 2 P&ID Diesel Generator Auxiliary System AF

M-85, Sh. 1 P&ID Diesel Oil System AE

M-865, Sh. 1 Diesel Generator Room Misc. Piping U

M-865, Sh. 2 Diesel Generator Room Misc. Piping M

1E-1-4000LE Key Diagram, 120/208 VAC Distribution Panel at 480V MCC O

135x-2 (1AP72E)

1E-1-4018ZA Loop Schematic Diagram, Containment Monitoring System CM R

Part 1

1E-1-4018ZB Loop Schematic Diagram, Containment Monitoring System CM O

Part 2

1E-1-4018ZJ Loop Schematic Diagram, Containment Monitoring System CM AB

Part 9

1E-1-4214AA Schematic Diagram, Remote Shutdown System RS, Part 1 M

1E-2-4000FB Key Diagram 125 Vdc Distribution ESS Division 1 O

1E-2-4000FC Key Diagram 125 Vdc Distribution ESS Division 2 P

1E-2-4018ZE Loop Schematic Diagram Containment Monitoring System CM K

Part 5

8

DRAWINGS

Number Description or Title Revision

1E-2-4226AA Schematic Diagram, Reactor Core Isolation Cooling System RI R

(E51) Part 1

1E-2-4226AF Schematic Diagram, Reactor Core Isolation Cooling System RI AA

(E51)

1T-7000-E-EN-08 SOR Models 102 and 103 Equivalent Replacement, Sh. 1 F

1T-7000-E-EN-08 SOR Models 102 and 103 Equivalent Replacement, Sh. 2 D

M-1340 Instrument Installation Details, Sh. 15 J

1E-0-4412AA Schematic Diagram - 4160 SWGR 141Y, Diesel Generator 0 AD

Feed ACB 1413

1E-0-4412AB Schematic Diagram - 4160 SWGR 241Y, Diesel Generator 0 AD

Feed ACB 2413

1E-0-4412AJ Schematic Diagram - Diesel Generator 0 Generator / Engine W

Control System DG Part 9

1E-1-4026AB Schematic Diagram - Diesel Fuel Oil System DO Part 2 V

1E-1-4026AA Schematic Diagram - Diesel Fuel Oil System DO Part 1 V

1E-1-4000PG Relaying & Metering Diagram 4160 Switchgear Q

1E-1-4005AM Schematic Diagram - 4160 Switchgear N

1E-1-4226AU Schematic Diagram - Reactor Core Isolation Cooling System Z

1E51-F045

1E-0-4418AA Schematic Diagram - Diesel Fuel Oil System DO Part 1 U

1E-2-4000EB Key Diagram - 250V DC Bus No.2 and MCC 221X M

1E-2-4000EC Key Diagram - 250V DC MCC 221Y S

1E-0-4401S Relaying and Metering Diagram Standby Diesel Generator 0 V

1E-0-4433AA Schematic Diagram - Diesel Generator Room Ventilation M

System VD Part 1

10 CFR 50.59 DOCUMENTS (SCREENINGS/SAFETY EVALUATIONS)

Number Description or Title Date

ER 9501392 Filter Bag Installation in Reactor Building, Turbine Building and 08/30/95

Auxiliary Building Floor Drains

LST-95-085 Installation of Mesh Basket/Screens in the Floor Drains 12/07/95

L03-0273 UFSAR Change LU2003-024, Suppression Pool Cooling 07/24/03

Operating Time Limitation

L13-180 New Procedure LOA-LOOP-101(201) 09/27/13

L97-180 Diesel Generator VD Bypass Damper 05/05/98

L02-0242 50.59 Review - Revise TRM 3.7.g Area Temperature 07/24/02

Monitoring

L02-0359 EDG Ventilation Modified to Control Air In-Leakage 10/18/02

L-14-104 50.59 Screening for EC 396093 02/13/15

L15-58 Unit 1 4KV Bus Transfer Logic Modification for an Open Phase 08/24/15

Condition Concurrent with LOCA

9

MISCELLANEOUS

Date or

Number Description or Title

Revision

Containment Coatings Program UDC/UQF Log 03/16/16

Spec.No.T-3763 Mechanical and Structural Work Specification 20

Maintenance/Modification Work

Containment Coatings Program Plan 1

EC392593 Evaluation of Estimated Amount of L2R14 Suppression Pool 05/29/13

Sludge

EC401088 Assessment of De-Sludeging Deferral from L2R15 02/1715

SL-2038 Letter, H. Peffer to A. Meligi, LaSalle RCIC Turbine Seismic 05/11/81

Re-Evaluation

GEH-LCS-AEP-045 LaSalle TPO Station Blackout Evaluation - Task T0903 07/07/09

22A2869AF GE Design Specification Data Sheet, RCIC System 12

EMD-029197 Seismic Requalification of Reactor Core Isolation Cooling 03/27/81

Pump (E51-C001)

EC 376896 Establishment of IST Acceptance Criteria for RCIC Pump 0

DBD-LS-M11 Topical Design Basis Document - Flood Protection E

CQD-028928 Vent and Purge Valves Qualification - CECo Mod. 1-1-84- 03/26/86

026

VM J-0395 Clow-Tricentric Valves/GH Bettis Actuators 4

Atwood & Morrill Report No. 7-25-85, Purge & Vent Valve 0

Operability Qualification Analysis

22A3008 GE Design Specification, BWR Equipment Environmental 5

Interface Data

VM J-0010 RCIC Pump Performance 8

GL 89-13 Program Basis Document 10

0024-00991 (LST-81-057) DG-Start Test on Stored Air 10/27/81

0084-02812 (LST-82-104) DG-0, 1A,1B, 2A Starts on Stored Air (Pre-Op 04/05/82

Testing)

IST-LAS-PLAN IST Program Plan 10/12/07

J-2585 DG Fan Vendor Manual 06/09/78

PES-P-006 Diesel Fuel Oil (Standard) 11

RS-10-031 Application For Technical Specifications Change Regarding 02/15/10

Risk-Informed Justification For The Relocation of Specific

Surveillance Frequency Requirements To a Licensee

Controlled Program

RS-10-136 Additional Information Supporting Request For License 08/03/10

Amendment Regarding Application Of Alternate Source Term

TE 362860 Technical Evaluation Ultra Low Sulfur Diesel Fuel Evaluation 10/06/06

TE 375645 Technical Evaluation Biodiesel Blend Fuel Oil Evaluation 05/21/09

22A1483AJ General Electric Design Specification Data Sheet, High 9

Pressure Core Spray System, Sheet 8

ACE 2607807-02 Apparent Cause Investigation Report: Main Steam Line High 02/09/16

Flow Switch 2E31-N011D not Holding Pressure

IM-025046-1 NLI Instruction Manual for Inverter Assembly, P/N NLI- 0

INV250-125-115, LaSalle Station

10

MISCELLANEOUS

Date or

Number Description or Title

Revision

L-2459 - L2462; Drift Verification for SOR Models Suffix X6, X7, X8 Pressure 12/31/15

L-2497 - L2501 Switches: Calculation Spreadsheets L-2459 through L-2462; L-

2497 through L-2501

PES-S-002 Exelon Document: Shelf Life, pp. 1, 7 8

QR-025046-1 Qualification Report for NLI Inverter Assembly P/N NLI-INV250- 0

125-115

VETIP J-0800 GE-NUMAC Suppression Pool Temperature Monitor (SPTM), 1

GEK-97056B Appendix C, SPTM Functions

Plant Engineering failure trend data for SOR switches associated 1984 to

with leak detection system present

Vickery-Sims Orifice Performance Curve, E51-N001 11/29/72

AT01553707-07 OPEX Evaluation - NRC IN 2013-14, Potential Design Deficiency 10/29/13

MODIFICATIONS

Date or

Number Description or Title

Revision

02-008 Change Request to TRM 3.7.g 09/16/02

96-034 UFSAR Revision Associated with Tech Spec Amendment 109 05/16/96

and 94

LU 2002-023 UFSAR Change Section 9.4.5.1.2 10/18/02

LUCR-181 UFSAR Chang for EC 374810 05/07/09

LUCR-216 UFSAR Changes Associated with the Alternate Source Term 11/12/10

Implementation

EC 396093 Install 125 Vdc/120 Vac Inverter to Power Existing 120 Vac/24 02/26/15

Vdc Power Supply that Feeds Existing Containment

Instrumentation

EC 395217 Unit 2 Division 1 and 2 DG Feed Breaker Logic Mod due to C 1

RHR and LPCS Anti-Pump Logic

EC 331699 Abandonment of Diesel Fire Pump Fuel Oil Transfer Pump 07/27/01

Suction Valves 1(2)DO024

OPERABILITY EVALUATIONS

Number Description or Title Revision

EC 405589 VY Cooler Pressure Drop for Op Eval 16-003 0

EC 405581 VY Cooler Heat Transfer with Tubes Plugged for Op Eval 16- 0

003

OE 13-005 Non-compliance of Pump IST Instrumentation Accuracy with 1

ASME Code Requirements

OE 16-003 Impact of Increased Cooling Water dP Across Safety Related 0

Room Coolers on Heat Transfer Performance Capability

OE 10-005 Potential Non-Conservative Tech Spec for EDG Fuel Oil 6

11

PROCEDURES

Number Description or Title Revision

ER-AA-330-008 Exelon Service Level I, and Safety-Related (Service Level 10

III) Protective Coatings

CC-AA-205 Control of Undocumented/Unqualified Coatings Inside the 9

Containment

LTS-600-41 Primary Containment Inspections for ECCS Suction 9

Strainer Debris Sources

LMP-GM-80 Suppression Chamber Desludging 5

LOS-RI-Q5 RCIC System Pump Operability, Valve Inservice Tests in 39

Modes 1, 2, 3 and Cold Quick Start

LMP-RI-02 RCIC Turbine Maintenance 23

LTS-100-6 Primary Containment Vent and Purge Outlet Valves, 30

Local Leak Rate Test, 1(2)VQo31/32/34/35/36/40/68

OP-LA-102-106 LaSalle Station Operator Response Time Program 7

OP-LA-103-102-1002 Strategies for Successful Transient Mitigation 16

LGA-RH-103 Unit 1 A/B RHR Operations in the LGAS/LSAMGS 12

LGA-RH-203 Unit 2 A/B RHR Operations in the LGAS/LSAMGS 13

LOA-AP-101 Unit 1 AC Power System Abnormal 52

LOA-AP-201 Unit 2 AC Power System Abnormal 48

LOA-DG-101 DG Failure [Unit 1] 9

LOA-DG-201 DG Failure [Unit 2] 8

LOA-FC-101 Unit 1 Fuel Pool Cooling System/Reactor Cavity Level 25

Abnormal

LOA-FC-201 Unit 2 Fuel Pool Cooling System/Reactor Cavity Level 23

Abnormal

LOA-IN-101 Loss of Drywell Pneumatic Air Supply 9

LOA-LOOP-101 Loss of Offsite Power [Unit 1] 4

LOA-LOOP-201 Loss of Offsite Power [Unit 2] 4

ER-AA-340 GL 89-13 Program Implementing Procedure 7

ER-AA-340-1001 GL 89-13 Program Implementation Instructional Guide 9

LOP-CX-08 Uninterruptible Power Supply Startup, Operation, and 10

Shutdown

LOP-HY-04 Main Generator Hydrogen Removal 20

LOP-IN-05 Replacing Nitrogen Bottles on Instrument Nitrogen 25

System

LOP-RH-01 Filling and Venting the Residual Heat Removal System 57

LOP-RH-02 Venting the Residual Heat Removal System 9

LOP-VD-03 Startup and Operation of Ventilation Systems for Diesel 12

Generator 0DG01K Room and Associated Diesel Fuel

Storage Room

LOP-VD-05E Unit 0 Diesel Ventilation System Electrical Checklist 7

LOR-1H13-P601-C405 1A RHR PMP DSCH PRESS LO 5

LOR-1PM13J-A404 INSTRUMENT NITROGEN SYS TROUBLE 7

LOR-1PM13J-B404 INSTRUMENT NITROGEN SYS TROUBLE 6

ER-AA-200-1001 Equipment Classification 1

ER-AA-340-1002 Service Water Heat Exchanger Inspection Guide 6

LEP-EQ-127 Hydramotor Replacement 21

12

PROCEDURES

Date or

Number Description or Title

Revision

LMS-ZZ-04 Water Tight Door Inspection 6

LOP-DG-04 Diesel Generator Special Operations 66

LOP-DO-01 Receiving and sampling New Diesel Fuel Oil 39

LOP-PF-01 Closure of Water Tight Doors 6

LOR-0PL17J-1-1 Diesel Generator Room Ventilation Supply Air Filter 1

Differential Pressure High

LOS-DG-M2 1A Diesel Generator Fast Start 93

LOS-DG-Q1 0 Diesel Generator Auxiliaries Inservice Test 65

LOS-DG-Q3 1B DG Fuel Oil Transfer Pump Test 71

LOS-DO-SR2 Diesel Fuel Oil Analysis Verification (New Fuel Oil) 17

LOS-PF-M1 ECCS/CSCS Water Tight Door Surveillance 0

LTS-200-11 Diesel Generator Cooling Heat Exchanger Thermal 17

Performance Monitoring

LTS-800-101 0 Diesel Generator Start and Load Acceptance Surveillance 2

LES-GM-130 Inspection of Westinghouse Motor Control Center Equipment 23

and GE Molded Case Breakers

LIP-CM-605 Unit 2 Suppression Chamber High Level Calibration 2

LIS-CM-201 Unit 2 Suppression Chamber Wide and Narrow Range Water 17

Level Indication Calibration

LIS-RI-203A Unit 2 RCIC Equipment Room/Steam Line Tunnel High 15

Ambient and Differential Temperature Outboard Isolation

(Division 1) Calibration

LIS-RI-203B Unit 2 RCIC Equipment Room/Steam Line Tunnel High 15

Ambient and Differential Temperature Inboard Isolation

(Division 2) Calibration

LIS-RI-403A Unit 2 RCIC Equipment Room/Steam Line Tunnel High 10

Ambient and Differential Temperature Outboard Isolation

(Division 1) Functional Test

LIS-RI-403B Unit 2 RCIC Equipment Room/Steam Line Tunnel High 9

Ambient and Differential Temperature Outboard Isolation

(Division 2) Functional Test

LIS-RX-202 Unit 2 Remote Shutdown System Suppression Chamber 6

Water Temperature Indication Calibration

LOP-CM-03 Suppression Chamber Average Water Temperature 13

Determination

LOS-CM-M1 Monthly Accident Monitoring Instrumentation Channel Check, 44

Attachment 1A, Item 11, Suppression Pool Water Temperature

MA-AA-723-325 Molded Case Breaker Testing 15

OP-AA-102-106 Operator Response Time Validation Sheet [TCA 24: 30 minute 06/24/14

response time]

LOA-FX-101 Unit 1 Safe Shutdown with a Fire in the Control Room 27

LOA-FX-201 Unit 2 safe Shutdown with a Fire in the Control Room 29

LES-GM-109 Inspection of 480V Klockner-Moeller Motor Control Center 41

NES-E/I&C 10.01 Molded Case Circuit Breaker Selection and Setting Design 2

Standard

13

PROCEDURES

Number Description or Title Revision

MA-LA-773-401 Emergency Bus Loss of Voltage Relay Calibrations by OAD 6

LOP-CX-03 Attachment A - ESF Status Panel Operation and Response 14

to Panel Indication

SURVEILLANCES (COMPLETED)

Number Description or Title Date

WO 01534018 RCIC Control Sys Surveillance, LIS-RI-215 08/18/14

WO 01315081 RCIC Control Sys Surveillance, LIS-RI-215 04/09/12

WO 01602574 IM Verify APRM A, B, C, D Flow 02/19/15

WO 01885199 RCIC Cold Quick Start Quarterly Surveillance, LOS-RI-Q5 03/18/16

WO 01709225 RCIC Cold Quick Start Comprehensive Surveillance, LOS-RI- 09/08/15

Q5

WO 01885198 Unit 2 PCIS Valves Operability and Inservice Inspection Test 03/14/16

WO 01602514 Unit 2 VQ Valves Position Indication Test, Grease Inspection 12/13/14

and EQ Inspection for Primary containment Isolation Valves

WO 01182421-01 IM-CAL 0 DG Vent Damper Temp Control Loop 0VD003 07/09/14

WO 01620128-02 OP Perform LOS -DG-201 U-2 0 DG Start and Load 02/19/15

Acceptance

WO 01675903-01 IM LIP-DG-901 DG 0 Fuel Oil STG TK Level Switch & Ind Cal 07/21/14

WO 01681600-01 OP LOS-DG-Q1 0 DG FO Transfer Pump Test ATT A1 01/14/14

WO 01697599-14 OP Perform LOS-DG-101 For PMT of EC 395216 Div 1 03/04/16

WO 01755831-01 OP LOS-DG-M1 0 DG Idle Start ATT 0-Idle 08/20/14

WO 01799852-01 OP LOS-DG-Q1 0 DG FO Transfer Pump Test ATT A1 04/14/15

WO 01824458-01 OP LOS-DG-Q1 0 DG FO Transfer Pump Test ATT A1 07/10/15

WO 01846833-01 OP LOS-DG-M1 0 Diesel Generator Fast Start Att O-Fast 02/10/16

WO 01870155-01 OP LOS-DG-Q1 0 DG FO Transfer Pump Test ATT A1 01/12/16

WO 01906522-01 OP LOS-DG-M1 0 DG Idle Start Att 0-Idle 03/25/16

WO 01212770 IM LIS-RX-202 U2 Remote Shutdown System Suppression 08/19/10

Chamber Water Temperature

WO 01365359 IM LIS-RX-202 U2 Remote Shutdown System Suppression 08/15/12

Chamber Water Temperature

WO 01395536 2E51-K603 Inverter: Verify Proper Voltages 03/20/13

WO 01460932 IM LIS-CM-201 U2 Suppression Chamber Wide and Narrow 12/11/13

Range Water Level Indication

WO 01488819 IM LIP-CM-605 U2 Suppression Chamber High Level 10/01/14

Calibration

WO 01568087 IM LIS-RI-201 U2 Suppression Chamber Water Temperature 12/15/14

Indication Calibration

WO 01568153 IM LIS-RX-202 U2 Remote Shutdown System Suppression 10/12/14

Chamber Water Temperature

WO 01602534 RCIC Area/Pipe Tunnel High Ambient/Differential 12/12/14

Temperature Isolation Channel A & C [LIS-RI-403A]

WO 01625514 2E51-K603 Inverter: Verify Proper Voltages 03/11/15

WO 01635855 RCIC Area Pipe Tunnel High Ambient/Differential 04/07/15

Temperature Isolation Channels B&D

14

SURVEILLANCES (COMPLETED)

Number Description or Title Date

WO 01844790 IM LIS-RI-201 U2 Steam Line High Flow RCIC Isolation 10/13/15

Calibration

WO 01868212 RCIC Area Pipe Tunnel High Ambient/Differential 01/04/16

Temperature Isolation Channels B&D [LIS-RI-403B]

WO 01869497 IM LIS-RI-201 U2 Steam Line High Flow RCIC Isolation 01/16/16

Calibration

WO 01889791 RCIC Area/Pipe Tunnel High Ambient/Differential 04/18/16

Temperature Isolation Channel A & C [LIS-RI-403A]

WO 01890374 IM LIS-RI-201 U2 Steam Line High Flow RCIC Isolation 04/06/16

Calibration

WO 01907719 LOS-CM-M1 U2 Containment Monitoring Instrumentation 04/14/16

Att. 2A

WO 01601996 Perform LES-DG-100 Attachment 1 and 2 on 0DG01K 09/17/14

TRAINING DOCUMENTS

Number Description or Title Revision

011 EDG and Auxiliaries 14

Chapter 128 Safety Related Ventilation, VD, VY, VX 3

WORK DOCUMENTS

Number Description or Title Date

WO 01727033 Inspect U1 Primary Containment 02/27/16

WO 01522325 Inspect U1 Primary Containment 02/11/14

WO 01317612 Inspect U1 Primary Containment 03/01/12

WO 01317605 Desludge U1 Suppression Pool 02/26/12

WO 00932692 Desludge U1 Suppression Pool 02/21/08

WO 01629258 Inspect U2 Primary Containment 02/17/15

WO 01448698 Inspect U2 Primary Containment 02/28/13

WO 01330504 Desludge U2 Suppression Pool 03/07/13

WO 01214505 Inspect U2 Primary Containment 03/05/11

WO 01039324 Desludge U2 Suppression Chamber 01/28/09

WO 00637256 Desludge U2 Suppression Pool 02/22/05

WO 01235193 MM RCIC Turbine Inspection/Rebuild 03/06/11

WO 00544334-01 MM Disassemble, Inspect Heat Exchanger 10/03/07

WO 00551674-01 MM Perform 0 Diesel Generator Inspection Per LMS-DG- 03/05/04

01

WO 01445980-01 MM Disassemble, Inspect Heat Exchanger 07/09/14

WO 01501078-01 IM LIP-DG-903 DG Fuel Oil Day Tank Level Switch & Ind 07/13/15

Cal

WO 01673449-01 Inline Oiler Is Not Entraining Proper Amount of Oil 04/23/15

WO 01713585-01 0 DG Room HVAC Air Filter High D/P Alarm 04/10/15

WO 00328231 Perform LES-GM-130 for 2H13P601 at 212Y CB-3 01/23/03

(2DC13E)

WO 00584724 Perform LES-GM-130 for 2H13P612 at 211Y CB-8 02/17/05

(2DC11E)

15

WORK DOCUMENTS

Number Description or Title Date

WO 00584733 Perform LES-GM-130 for Cross-Tie 111Y at 211Y CB-23 02/16/05

WO 00584738 Perform LES-GM-130 for ESS-240 at 211Y CB-11 02/18/05

(2DC11E)

WO 00839517 Perform LES-GM-130 for X-Tie 112Y at 212Y CB23 10/27/08

(2DC13E)

WO 00839520 Perform LES-GM-130 for 2P08J at 212Y CB-15 (2DC15E) 04/03/08

WO 00839523 Perform LES-GM-130 for ESS #041 at 212Y CB-11 10/27/08

(2DC13E)

WO 01235373 Perform Breaker Inspection, Maintenance and Testing: 02/26/11

2DC08E-CB3B

WO 01235380 Perform LES-GM-130 for 2H13P601 at 212Y CB-3 02/18/11

(2DC13E)

WO 01239529 2E51-K603 Inverter: Verify Proper Voltages 12/15/10

WO 01427028 Perform LES-GM-130 for Swgr 251-1 at 211Y CB-15 02/15/13

(2DC11E)

WO 01428173 Perform LES-GM-130 for 2H13P612 at 211Y CB-8 02/18/13

(2DC11E)

WO 01428176 Perform LES-GM-130 for 2C61P001 at 211Y CB-24 02/18/13

(2DC11E)

WO 01621668 2TE-CM-057A/C Suppression Pool Thermocouple Reads 12/15/14

too High

WO 01695411-04 IM-PMT per EC 396093: LIS-CM-201 Sections E.3 and E.4 02/22/15

WO 01695411-12 IM-PMT per EC 396093: Perform Updated LIS-RX-202 02/09/15

WO 01629492 Perform Breaker Inspection, Maintenance, and Testing 02/08/15

[MA-AB-725-110] for 212Y Feed 2DC15E-CB3B

16

LIST OF ACRONYMS USED

AC Alternating Current

ADAMS Agencywide Document Access Management System

AOP Abnormal Operating Procedure

AR Action Request

CAP Corrective Action Program

CDBI Component Design Bases Inspection

CFR Code of Federal Regulations

CSCS Core Standby Cooling System

DC Direct Current

DG Diesel Generator

dP Differential Pressure

EC Engineering Change

ECCS Emergency Core Cooling System

ESF Engineered Safety Feature

GL Generic Letter

HELB High Energy Line Break

IMC Inspection Manual Chapter

IN Information Notice

kV Kilovolt

LERF Large Early Release Frequency

LOCA Loss-Of-Coolant Accident

LOOP Loss of Off-site Power

MCC Motor Control Center

MCR Main Control Room

MOV Motor-Operated Valve

NCV Non-Cited Violation

NPSH Net Positive Suction Head

NRC U.S. Nuclear Regulatory Commission

PARS Publicly Available Records System

PPC Plant Process Computer

PRA Probabilistic Risk Assessment

RCIC Reactor Core Isolation Cooling

RHR Residual Heat Removal

RSP Remote Shutdown Panel

SBO Station Blackout

SDP Significance Determination Process

TS Technical Specification

UFSAR Updated Final Safety Analysis Report

Vac Volts Alternating Current

Vdc Volts Direct Current

17

B. Hanson -2-

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public

Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy

of this letter, its enclosure, and your response (if any) will be available electronically for public

inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)

component of the NRC's Agencywide Documents Access and Management System (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html

(the Public Electronic Reading Room).

Sincerely,

/RA/

Mark T. Jeffers, Chief

Engineering Branch 2

Division of Reactor Safety

Docket Nos. 50-373; 50-374

License Nos. NPF-11; NPF-18

Enclosure:

IR 05000373/2016007; 05000374/2016007

cc: Distribution via LISTSERV

DISTRIBUTION:

Jeremy Bowen

RidsNrrDorlLpl3-2 Resource

RidsNrrPMLaSalle

RidsNrrDirsIrib Resource

Cynthia Pederson

Darrell Roberts

Richard Skokowski

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

ROPreports.Resource@nrc.gov

ADAMS Accession Number ML16174A094

Publicly Available Non-Publicly Available Sensitive Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII RIII RIII RIII

NAME NFeliz-Adorno:cl MJeffers

DATE 06/20/16 06/22/16

OFFICIAL RECORD COPY