IR 05000373/2023001

From kanterella
Jump to navigation Jump to search
County Station - Integrated Inspection Report 05000373/2023001 and 05000374/2023001
ML23130A218
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 05/10/2023
From: Robert Ruiz
NRC/RGN-III/DORS/RPB1
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2023001
Download: ML23130A218 (1)


Text

SUBJECT:

LASALLE COUNTY STATION - INTEGRATED INSPECTION REPORT 05000373/2023001 AND 05000374/2023001

Dear David P. Rhoades:

On March 31, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at LaSalle County Station. On April 12, 2023, the NRC inspectors discussed the results of this inspection with John VanFleet, acting Site Vice President, and other members of your staff.

The results of this inspection are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. Two of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at LaSalle County Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at LaSalle County Station.

May 10, 2023 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 05000373 and 05000374 License Nos. NPF-11 and NPF-18

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000373 and 05000374

License Numbers:

NPF-11 and NPF-18

Report Numbers:

05000373/2023001 and 05000374/2023001

Enterprise Identifier:

I-2023-001-0060

Licensee:

Constellation Nuclear

Facility:

LaSalle County Station

Location:

Marseilles, IL

Inspection Dates:

January 01, 2023 to March 31, 2023

Inspectors:

J. Benjamin, Senior Resident Inspector

J. Cassidy, Senior Health Physicist

G. Edwards, Senior Enforcement Specialist

E. Magnuson, Reactor Inspector

J. Park, Reactor Inspector

J. Reed, Health Physicist

E. Rosario, Reactor Inspector

A. Tran, Resident Inspector

R. Zuffa, Illinois Emergency Management Agency

Approved By:

Robert Ruiz, Chief

Reactor Projects Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at LaSalle County Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Assure Charpy V-Notch Impact Test Conformed to American Society of Mechanical EngineersSection III Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000374/2023001-01 Open/Closed

[H.12] - Avoid Complacency 71111.08G The inspectors identified a finding of very low safety significance (Green) and an associated non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) 50,

Appendix B, Criterion VII, Control of Purchased Material, Equipment, and Services, for the licensees failure to establish measures to assure that purchased material, equipment, and services through contractors conformed to the procurement documents. Specifically, the licensee failed to assure the Charpy V-Notch impact test conducted by its contractor for pipe material used for residual heat removal (RHR) system piping repair/replacement conformed to American Society of Mechanical Engineers (ASME)Section III, 1974 Edition, as specified in their procurement documents.

Failure to Secure Category 2 Quantity of Radioactive Material not Under Direct Control and Constant Surveillance Cornerstone Significance Cross-Cutting Aspect Report Section Public Radiation Safety Green NCV 05000374,05000373/2023001-02 Open/Closed

[H.12] - Avoid Complacency 71124.01 The inspectors reviewed a self-revealed Green finding and associated non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) 37.53 when the licensee failed to physically secure a mobile device containing category 2 levels of radioactive material.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000374/2022-003-01 LER 2022-003-01 for LaSalle County Station,

Unit 2, Manual Scram due to lsophase Bus Duct Fire followed by 2A RPS Normal Power Supply Trip 71153 Closed LER 05000374/2022-003-00 LER 2022-003-00 for LaSalle County Station,

Unit 2, Manual Scram Due to Isophase Bus Duct Fire and 2A RPS Normal Power Supply Trip 71153 Closed

PLANT STATUS

Unit 1 operated at or near rated thermal power for the entire inspection period.

Unit 2 began the inspection period at rated thermal power. On February 13, 2023, the unit was shut down to support refueling outage L2R19. The unit was returned to rated thermal power on March 11, 2023, and remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 2 2A emergency diesel generator (EDG) with 2B EDG inoperable on January 23, 2023
(2) Unit 2 high-pressure core spray (HPCS) return to service on February 22, 2023
(3) Unit 2 2A EDG following return to service on March 15, 2023

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone 212, reactor building, elevation 673'-4", Unit 1 HPCS cubicle
(2) Fire Zone 7B2, diesel building, elevation 710'-0", Unit 1 division 2 standby diesel generator room
(3) Fire Zone 2H4, reactor building, elevation 694'-6", Unit 1 reactor core isolation cooling/low-pressure core spray cubicle
(4) Fire Zone 8B1, diesel building, elevation 710'-0", Unit 2 HPCS system diesel generator room
(5) Fire Zone 7C1, diesel building, elevation 674-0", Unit 1 HPCS diesel fuel tank room

71111.08G - Inservice Inspection Activities (BWR)

The inspectors verified that the reactor coolant system boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from February 13, 2023 to March 16, 2023.

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01) (1 Sample)

The inspectors verified that the following nondestructive examination and welding activities were performed appropriately:

(1) The inspectors verified that the reactor coolant system boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from February 13, 2023, to March 16, 2023:

03.01.a - Nondestructive Examination and Welding Activities

1. Ultrasonic testing (UT) of component IDs IRH-2005-28 and -29, Cat. R-A,

Item R1.16, augmented

2. UT of component ID 2-NIR-N10A, Cat. B-D, Item B3.100

3. Magnetic particle exam of component ID FW02-2851S, Cat. B-K, Item B10.20

4. Weld repair/replacement of Unit 2 bottom head drain line, 1st installation,

Work Order (WO) 5237886-18, Weld #7

5. Weld repair/replacement of Unit 2 bottom head drain line, 2nd installation,

WO 5237886-19, Welds #1 and #17

6. Weld repair/replacement of 2RH03CB-12" downstream of Valve 2E12-F053B,

WO 5042338-67, Welds #1 and #2

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (2 Samples)

(1) The inspectors observed and evaluated licensed operator performance in the control room during reactor shutdown for L2R19 on February 13, 2023.
(2) The inspectors observed and evaluated licensed operator performance in the control room during reactor startup for L2R19 on March 6 and March 7, 2023.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated shutdown operations training on January 25, 2023.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Replacement of Eaton full voltage reversing contactors to address failure mode identified in Westinghouse in a Part 21 issued on April 11, 2022 (ML22140A208)

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 1 action Green risk 1B EDG out of service for maintenance on January 25, 2023
(2) Scheduled readiness certification meeting and risk management for work week 2243 (02/06/2023 - 02/12/2023) on January 30, 2023
(3) Unit 2 planned Yellow risk for refueling outage reactor coolant system drain down on February 13, 2023
(4) Unit 2 planned Yellow risk for refueling outage division 2 battery replacement on February 17, 2023
(5) Risk informed completion time evaluation of Unit 1 B1 reactor protection system relay 1C71A-K8B (turbine control valve #2 RETS pressure switch) degraded on February 18, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Action Request (AR) 4549216, "1RE024, Unit 1 Drywell Equipment Drain Inboard Isolation Valve, Primary Containment Isolation Valve Failed to Open"
(2) AR 4549032, "FLEX Diesel Fuel Sample did not Meet Spec"
(3) AR 4551562, "Unit 1 1A Emergency Diesel Generator Speed Control Governor not Responding"
(4) AR 4553493 "2A/2B RHR [residual heat removal] WS PMP Cubicle Cooler Fan 2VY05C Auto Trip"
(5) AR 455533455533 "2B RHR Partition Plate Condition"

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Engineering Change 638423, "Seismic Evaluation of the LaSalle Unit 2 Bottom Head Drain Plug"

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated Unit 2 refueling outage 2R19 activities from February 12, 2023 to March 6, 2023.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (4 Samples)

(1)1B diesel generator and HPCS operability run after breaker replacement on January 26, 2023

(2) Unit 2 HPCS system operability and inservice test after HPCS outage window on February 21, 2023 (3)2A diesel generator (DG) post cooling water and strainer replacement on February 23, 2023
(4) WO 5042338-67, "Unit 2 2E12-F053B Pipe Section Replacement Completed"

Surveillance Testing (IP Section 03.01) (6 Samples)

(1) Unit 2 2B diesel generator operability test on January 23, 2023
(2) WO 5134693, "Integrated Division II ECCS [emergency core cooling system]

Response Time 2A EDG"

(3) Unit 2 Group 4 inboard isolation logic system functional test on March 1, 2023
(4) Unit 2 valve 2E12-F053B motor-operated valve testing completed on March 3, 2023
(5) Unit 2 L2R19 American Society of Mechanical Engineers (ASME)Section XI hydrostatic and associated VT-2 visual examinations completed on March 3, 2023
(6) Unit 2 primary containment integrated leak rate test completed on March 7, 2023

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) Emergency preparedness drill in the technical support center and outage support center on January 17,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1) Workers utilizing the tool and equipment monitors and the whole-body contamination monitors while exiting the radiologically controlled area (RCA) during the Unit 2 refueling outage
(2) Radiation protection technicians performing doffing surveys and supplied air suit removal for work control rod drive work during the Unit 2 refueling outage

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following radiological work:

(1) Control rod drive exchange (2)2B33-F067A repairs/inspections
(3) Bottom head drain cut out/replace (4)2G33-F001 valve work activities High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (4 Samples)

The inspectors evaluated licensee controls of the following high radiation areas and very high radiation areas:

(1) Unit 2 drywell
(2) Unit 2 under vessel control rod drive exchange areas (3)layout of temporary hoses used for chemical decontamination on multiple elevations in the Unit 2 reactor building
(4) Refuel floor reactor cavity work cavity work platform Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Temporary Ventilation Systems (IP Section 03.02) (1 Sample)

The inspectors evaluated the configuration of the following temporary ventilation systems:

(1) Temporary breathing box setup for control rod drive exchange

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees use of respiratory protection devices.

71124.04 - Occupational Dose Assessment

Source Term Characterization (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated licensee performance as it pertains to radioactive source term characterization.

External Dosimetry (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee processes, stores, and uses external dosimetry.

Special Dosimetric Situations (IP Section 03.04) (1 Sample)

The inspectors evaluated the following special dosimetric situations:

(1) Use of effective dose equivalent from external exposure methodology utilizing multiple dosimetry for control rod drive exchange work

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) Unit 1 (January 1, 2022, through December 31, 2022)
(2) Unit 2 (January 1, 2022, through December 31, 2022)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (2 Samples)

(1) Unit 1 (January 1, 2022, through December 31, 2022)
(2) Unit 2 (January 1, 2022, through December 31, 2022)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (2 Samples)

(1) Unit 1 (January 1, 2022, through December 31, 2022)
(2) Unit 2 (January 1, 2022, through December 31, 2022)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

(1) The inspectors reviewed the licensees implementation of its corrective action program related to elevated collective radiation exposure during the L2R18 refueling outage.
(2) AR 4539324, "ACT Trip Reference Cards in Average Power Range Monitors and Rod Block Monitors are Failing"
(3) AR 4543774, "Unit 1 1B Diesel Generator Lockout on Differential Current"

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Follow-up (IP section 03.01)

(1) The inspectors evaluated Operations response to Unit 2 scram actuation during L2R19 shutdown conditions on March 4, 2023.

Event Report (IP section 03.02) (2 Samples)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000374/2022-003-00 for LaSalle County Station, Unit 2, "Manual Scram due to lsophase Bus Duct Fire followed by 2A RPS Normal Power Supply Trip,"

(ADAMS Accession No. ML22319A015). The inspectors determined that it was not reasonable to foresee or correct the cause discussed in the LER therefore no performance deficiency was identified. The inspectors did not identify a violation of NRC requirements.

(2) LER 05000374/2022-003-01 for LaSalle County Station, Unit 2, "Manual Scram due to lsophase Bus Duct Fire followed by 2A RPS Normal Power Supply Trip,"

(ADAMS Accession No. ML23040A104). The inspectors reviewed the updated LER submittal. The previous LER submittal was reviewed in NRC Integrated Inspection Report 05000373/2023001 AND 05000374/2023001.

INSPECTION RESULTS

Failure to Assure Charpy V-Notch Impact Test Conformed to American Society of Mechanical EngineersSection III Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000374/2023001-01 Open/Closed

[H.12] - Avoid Complacency 71111.08G The inspectors identified a finding of very low safety significance (Green) and an associated non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) 50, Appendix B, Criterion VII, Control of Purchased Material, Equipment, and Services, for the licensees failure to establish measures to assure that purchased material, equipment, and services through contractors conformed to the procurement documents. Specifically, the licensee failed to assure the Charpy V-Notch impact test conducted by its contractor for pipe material used for residual heat removal (RHR) system piping repair/replacement conformed to American Society of Mechanical Engineers (ASME)Section III, 1974 Edition, as specified in their procurement documents.

Description:

The licensees ASME Section XI repair/replacement plan for the RHR piping replacement activity under Work Order (WO) 5042338-67 delineated ASME Section III, 1974 Edition, as the construction code of record. The repair/replacement plan also delineated the subject pipe component as ASME Code Class 1. The replacement pipe was 12-inch nominal pipe size (NPS) Schedule 120, made of SA-333, Grade 6. This material was required to be impact tested in accordance with ASME Section III, 1974 Edition, Paragraph NB-2311, Materials for Which Impact Testing Is Required, to verify the material fracture toughness requirements were satisfied. The licensee elected Charpy V-Notch as the method to conduct the test in preparation for the repair/replacement activity. The licensees Purchase Order (PO) 1366400, Revision 3, specified ASME Section III, 1974 Edition, no addenda, as the code of record to which the impact test requirements were to be satisfied.

During review of the test report, the inspectors identified the Charpy V-Notch test was conducted using a set of three 5 x 10 millimeter

(mm) subsize test specimens. This was not in accordance with ASME Section III, 1974 Edition, Paragraph NB-2321.2, Charpy V-Notch Tests, which specifically required a set of standard full-size 10 x 10 mm test specimens. The paragraph also referenced Specification SA-370, Specification for Methods and Definitions for Mechanical Testing of Steel Products, for conducting the test. Specification SA-370, Section 19, Test Specimens, Subsection 19.2, Size and Type, stipulated the subsize test specimens such as those used by the licensee through their contractor were to be utilized when the material thickness was less than 7/16 inch (0.438 inch). The nominal thickness of pipe material subject to the repair/replacement activity was 1.000 inch, which required the full-size 10 x 10 mm specimens.

Corrective Actions: The licensee entered this issue into their corrective action program as Action Request (AR) 4560929. The licensee re-performed the Charpy V-Notch testing with a set of full-size specimens that conformed to the requirements. The results of this testing were satisfactory.

Corrective Action References: AR 4560929, "NRC ID Vendor Charpy Test on the Incorrect Specimen Size"

Performance Assessment:

Performance Deficiency: The licensee's failure to assure the Charpy V-Notch impact testing performed in support of pipe repair/replacement activity under WO 5042338-67 conformed to ASME Section III, 1974 Edition, Paragraph NB-2321.2, "Charpy V-Notch Tests," was contrary to 10 CFR Part 50, Appendix B, Criterion VII and was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Reactor Coolant System (RCS) Equipment and Barrier Performance attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, using the non-conforming impact test specimens did not provide reasonable assurance the pipe base material possessed the minimum required fracture toughness to prevent potential brittle fracture.

Significance: The inspectors assessed the significance of the finding using Inspection Manual Chapter 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Specifically, the inspectors answered "no" to the question in Exhibit 3.B. The licensee re-performed the Charpy V-Notch testing with specimens that conformed to the requirements. The results of this testing provided reasonable assurance the minimum material fracture toughness requirements were satisfied such that the replaced piping material would perform its required safety functions.

Cross-Cutting Aspect: H.12 - Avoid Complacency: Individuals recognize and plan for the possibility of mistakes, latent issues, and inherent risk, even while expecting successful outcomes. Individuals implement appropriate error reduction tools. Specifically, licensee individuals did not thoroughly review contractor's test plan and results, but instead, relied on contractor expertise and past successes perceived as satisfactory.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion VII, Control of Purchased Material, Equipment, and Services, requires, in part, that measures be established to assure purchased material, equipment, and services purchased through contractors conform to the procurement documents.

Contrary to the above, on November 23, 2022, the licensee failed to assure purchased material, equipment, and services conformed to the procurement documents. Specifically, the licensees PO 1366400, Revision 3, specified ASME Section III, 1974 Edition, no addenda, as the code of record to which the impact test requirements were to be satisfied. The licensee elected Charpy V-Notch as the method to perform the impact test. ASME Section III, 1974 Edition, Paragraph NB-2321.2, Charpy V-Notch Tests, requires, in part, that a test consists of a set of three full-size 10 x 10 mm specimens. However, the Charpy V-Notch test was conducted using a set of three 5 x 10 mm subsize specimens.

Enforcement Action: This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Secure Category 2 Quantity of Radioactive Material not Under Direct Control and Constant Surveillance Cornerstone Significance Cross-Cutting Aspect Report Section Public Radiation Safety Green NCV 05000374,05000373/2023001-02 Open/Closed

[H.12] - Avoid Complacency 71124.01 The inspectors reviewed a self-revealed Green finding and associated non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) 37.53 when the licensee failed to physically secure a mobile device containing category 2 levels of radioactive material.

Description:

To comply with 10 CFR 37.53, licensees that possess mobile devices containing category 1 or category 2 quantities of radioactive material must have two independent physical controls that form tangible barriers to secure the material from unauthorized removal when the device is not under direct control and constant surveillance by the licensee. For nuclear power plants, the established protected area boundary satisfies the requirement for one of the independent physical controls. The other physical control could take the form of a locked cage or room, a wheel lock, physical restraint of the device, or other means that are not easily defeated to disable the mobile device.

On October 17, 2022, the locking mechanism intended to render the device immobile was discovered to be deficient before starting the annual calibration of their Model 89 gamma calibrator. This condition would not have prevented the unauthorized movement or diversion.

Specifically, a chain was wrapped around the frame of the calibrator, so it appeared secure, but the padlock necessary for securing the chain was found unlocked by a technician supporting the annual calibration.

The device was secured upon discovery and Action request (AR) 4530043 was written to document the condition in the corrective action program. The cause of the issue of concern was reasonably within the licensees ability to foresee and correct and should have been prevented.

Corrective Actions: The licensee secured the mobile device via a chain and lock.

Corrective Action References: AR 4530043, "Shepherd Calibrator Unsecured"

Performance Assessment:

Performance Deficiency: The licensee failed to physically secure a mobile device containing category 2 levels of radioactive material as required by 10 CFR 37.53.

Screening: The inspectors determined the performance deficiency was more than minor because it could reasonably be viewed as a precursor to a significant event. Specifically, the failure to secure the padlock on the chain to immobilize the radioactive material diminished assurance that the security of category 2 quantities of radioactive material was protected from theft or diversion.

Significance: The inspectors assessed the significance of the finding using Inspection Manual Chapter 0609 Appendix D, Public Radiation Safety SDP. The inspectors determined that there was not an actual loss of material, access was not granted to an individual who was not trustworthy and reliable, and there was not an ineffective security zone. However, inspectors did determine there was a deficient security zone and therefore this finding is of very low safety significance (Green).

Cross-Cutting Aspect: H.12 - Avoid Complacency: Individuals recognize and plan for the possibility of mistakes, latent issues, and inherent risk, even while expecting successful outcomes. Individuals implement appropriate error reduction tools. Specifically, the licensee's existing processes and human performance tools were not effective to ensure the mobile device was physically secured.

Enforcement:

Violation: Title 10 CFR 37.53 requires in part that each licensee that possesses mobile devices containing category 1 or category 2 quantities of radioactive material must have two independent physical controls that form tangible barriers to secure the material from unauthorized removal when the device is not under direct control and constant surveillance by the licensee. The licensee utilized the protected area boundary and a locking mechanism on the mobile device to provide the two independent physical controls.

Contrary to the above, on October 17, 2022, a mobile device containing category 2 quantities of radioactive material was found not to have two independent physical controls to form tangible barriers to secure the material from unauthorized removal, and the device was not under direct control and constant surveillance by the licensee. Specifically, the required lock to ensure physical control of the device was attached in such a way that the device was not physically secured and was mobile.

Enforcement Action: This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.

Observation: Review of Source Term Reduction Actions 71152A In 2021, the licensee failed to survey to ensure occupational doses were as low as reasonably achievable (ALARA). This was documented in NRC Integrated Inspection Report 05000373/2021003; 05000374/2021003 and 07200070/2021001. The licensee evaluated this issue in Root Cause Evaluation (RCE) Report 4417704.

The inspectors reviewed RCE 4417704 to ensure that the licensee identified corrective actions commensurate with the significance of the identified issues. This evaluation determined the root cause was an increased source term due to cobalt intrusion into the reactor vessel and ancillary systems from foreign material originating from degraded reactor recirculation flow control valves. A contributing cause was determined to be the station did not evaluate or fully understand the consequences to material conditions, plant source term and Collective Radiation Exposure from identified foreign material. The licensee developed multiple corrective actions including Implementing a mitigation strategy for cobalt intrusion to reactor vessel (CAPR 4417704-15), performing high efficiency - ultrasonic fuel cleaning (HE-UFC), and bottom nozzle cleaning to recover foreign material from reactor vessel (CA 4417704-17).

The inspectors also observed the conduct of multiple jobs during the subsequent refueling outage (L2R19) that the licensee characterized as high radiological risk to evaluate how the actions were implemented. These jobs included:

  • Bottom head drain cut out/replace
  • Chemical decontamination
  • High efficiency ultrasonic fuel cleaning The licensee developed a comprehensive plan, including multiple examples of first use technologies, for removing cobalt from multiple locations at LaSalle Unit 2. The inspectors observed a high level of support (resources, time, and full-scale mock-ups) to complete the large number of activities to reduce source term needed to lower occupational doses. In general, the technicians performing the work and the radiation protection technicians covering the work activities appeared to understand the tasks to be completed, knowledgeable of the radiological hazards present in the work area and engaged in the work activities.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On April 12, 2023, the inspectors presented the integrated inspection results to John VanFleet, acting Site Vice President, and other members of the licensee staff.

On March 8, 2023, the inspectors presented the radiation protection inspection results to Deb McBreen, Organizational Performance and Regulatory Director, and other members of the licensee staff.

On March 16, 2023, the inspectors presented the inservice inspection results to Phil Hansett, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

AR 4556006

NRC-Identified Fire Door Issue

2/21/2023

71111.04

Procedures

OP-DG-01

Preparation for Standby Operations of Diesel Generators

AR 4404803

Foreign Material Found in JP 15 (GE INR L2R18 IVVI-21-01)

2/25/2021

Corrective Action

Documents

AR 4548159

L2R19 IVVI Scope Change

01/12/2023

AR 4554759

NRC Identified - NRC Questioned Weld Procedure

Specification

2/15/2023

AR 4554816

NRC Identified Open Task in WO from L2R18

2/15/2023

Corrective Action

Documents

Resulting from

Inspection

AR 4560929

NRC ID Vendor Charpy Test on the Incorrect Specimen Six

03/10/2023

1366400

Purchase Order

2974

ASME Section XI Repair/Replacement Plan for

WO 05237886-19

11/04/2022

2975

ASME Section XI Repair/Replacement Plan for

WO 05237886-18

08/30/2022

2991

ASME Section XI Repair/Replacement Plan for

WO 05042338-67

11/22/2022

LTI Order No.

CO22034975

Laboratory Report for Charpy V-Notch Impact Testing

11/02/2022

LTI Order No.

CO23008515

Laboratory Report for Charpy V-Notch Impact Testing

03/15/2023

PQR No. 1-50C

Procedure Qualification Record ASME Section IX

01/03/1984

PQR No. A-001

Procedure Qualification Record ASME Section IX

10/19/1998

PQR No. A-002

Procedure Qualification Record ASME Section IX

03/09/1999

PQR No. W-

2009-001

ASME Welding Procedure Qualification Record

08/25/2009

Miscellaneous

PQR No. W-

2009-002

ASME Welding Procedure Qualification Record

08/25/2009

23-090

TOPAZ Encoded Phased Array Examination for Component

ID 2RT01B-6 FW-17 R1

03/12/2023

23-092

TOPAZ Encoded Phased Array Examination for Component

ID 2RR28B-3 FW-1 R3

03/10/2023

71111.08G

NDE Reports23-093

TOPAZ Encoded Phased Array Examination for Component

03/11/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

ID 2RH03CB-12 FW-1 R1

23-094

TOPAZ Encoded Phased Array Examination for Component

ID 2RH03CB-12 FW-2 R1

03/14/2023

23-200

TOPAZ Encoded Phased Array Examination for Component

ID 2RR28A-2 FW-7

03/10/2023

L2R19-MT-009

MT Report for Component ID FW02-2851S

2/22/2023

L2R19-UT-005

UT Report for Component ID IRH-2005-29

2/19/2023

L2R19-UT-006

UT Report for Component ID IRH-2005-28

2/19/2023

L2R19-VEN-001

UT Report for Component ID 2-NIR-N10A

2/22/2023

No. 1

Radiographic Examination Interpretation Report for

WO 05237886-18, Weld No. 1, 2, 3, and 4

2/21/2023

ER-AA-335-003

Magnetic Particle (MT) Examination

GEH-PDI-UT-2

PDI Generic Procedure for the Ultrasonic Examination of

Austenitic Pipe Welds

GEH-UT-257

Procedure for Ultrasonic Examination in Lieu of Radiography

for Welds in Ferritic or Austenitic Pipe Section XI, Division 1

GEH-UT-311

Procedure for Manual Ultrasonic Examination of Nozzle

Inner Radius, Bore, and Selected Nozzle to Vessel Regions

WPS 1-1-GT-

PWHT-IQ2

ASME Welding Procedure Specification Record

Procedures

WPS 1-1-GTSM-

PWHT

ASME Welding Procedure Specification Record

Work Orders

WO 4691305-01

Disassemble/Inspect/Reassemble 2B33-F060B

04/16/2021

AR 4492563

Receipt of Part 21 for 480 V FRV Contactors

04/11/2022

AR 4554142

2E12-F009 Valve Took Multiple Attempts to Open

2/13/2023

Corrective Action

Documents

AR 4555427

L2R19 Add for Eaton Breaker Mechanical Interlock

Replacement

2/18/2023

Engineering

Changes

EC 636483

Upgrade Eaton Bucket Contactor Mechanical Interlock

from Rev. 1 to Rev 3.

LAS-0-2-2023-

0041

ODM - Eaton Contractor Binding

71111.12

Miscellaneous

LAS-0-2022-0030

Eaton FVR Contactor

Miscellaneous

L2R19 SDS

Unit 2 L2R19 Refueling Outage Shutdown Safety Plant

71111.13

Procedures

LEP-DC-113

Installation and Removal of Temporary Battery Chargers

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OU-LA-104

Shutdown Safety Management Program

AR 4515624515621A DG Speed Control Governor not Responding

01/31/2023

AR 4551243

U1 Div 2 Ground Caused by 1A DG Speed Control Switch

01/30/2023

71111.15

Corrective Action

Documents

AR 4551437

U1 Div 2 Ground During LOS-DG-M2, 1A DG Run

01/31/2023

71111.18

Engineering

Changes

EC 638423

Seismic Evaluation of the LaSalle Unit 2 Bottom

Head Drain Plug

Calculations

L-004408

Alternate Decay Heat Removal (ADHR) System Qual

for L2R19 Outage

EC 637927

Alternate Decay Heat Removal (ADHR) System Qual

for L2R19 Outage

Engineering

Changes

EC 638100

L2R19 Decay Heat and Related Computations

Miscellaneous

L2R19 SDS Plan

L2R19 Shutdown Safety Plan

71111.20

Procedures

LOP-WIC-01

Reactor Pressure Vessel Water Inventory Control

Corrective Action

Documents

AR 4555533

2B RHR Partition Plate Condition

2/19/2023

Engineering

Changes

EC 638181

Evaluation of Unit 2B RHR Heat Exchanger Thermal

Performance Data Using Alternate (ERPI) Methodology

LOS-HP-08

HPCS System Full Flow Test

01/26/2023

WO 1598755

2A DG Cooling Water System Flow Balance

2/22/2023

WO 1691124

Verify Performance of 2DG01P per LOS-DG-Q2

2/22/2023

WO 5134336

U-2 GROUP 4 I/B Isol Act Logic Sys Func Test

03/01/2023

WO 5304691

LOS-HP-Q4 ATT A, U1 HPCS SYSTEM

01/26/2023

WO 5314706

LOS-HP-Q1 U2 HPCS ATT 2A

2/21/2023

WO 5321850

LOS-DG-M3 2B DG IDLE START ATT 2B-IDLE

01/23/2023

71111.24

Work Orders

WO 5322465

LRA LOS-DG-M3 1B DG IDLE START ATT 1B-IDLE

01/26/2023

71114.06

Miscellaneous

LaSalle 1Q23

PI Drill Report

LaSalle 1Q23 PI Drill Report

2/03/2023

AR 4530043

Shepherd Calibrator Unsecured

10/17/2022

AR 4555415

Main Access Facility Portal Monitor Alarm Response

2/17/2023

Corrective Action

Documents

AR 4556914

Higher Than Anticipated Airborne Activity in U2 Drywell

2/24/2023

71124.01

Miscellaneous

23 Electronic

Dosimeter Alarm

Log

Listing of all Electronic Dosimeter Alarms for

2/13/23 - 02/20/23

2/21/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

L2R19 SAC #2

Station ALARA Committee Meeting Notes

2/19/2023

L2R19 SAC #3

Station ALARA Committee Meeting Notes

2/20/2023

Procedures

RP-AA-500-1003

CFR PART 37 Material Accountability Program

23-186741

740' Drywell Bottom Head Drain Shielding Survey

2/16/2023

23-186881

740' Drywell Bottom Head Drain Cut Out Survey

2/18/2023

23-186893

Drywell 740' Elevation

2/18/2023

Radiation

Surveys

23-186922

740' Drywell General Area

2/18/2023

LA-02-23-00513

L2R19 DW Control Rod Drive (CRD) Exchange

LA-02-23-00548

L2R19 DW 2B33-F067A Repairs/Inspections

LA-02-23-00551

L2R19 DW RWCU 2G33-F001 Valve Work Activities

LA-2-23-00544

L2R19 DW Bottom Head Drain Cut Out/Replace

Radiation Work

Permits (RWPs)

LA002-23-00414

L2R19 RB/DW Chem Decon Project

71124.03

Corrective Action

Documents

Resulting from

Inspection

AR 4556613

Collected Samples Not Taken to Chemistry for Analysis

2/23/2023

Engineering

Evaluations

RWP:

LA-02-23-00513

Multiple Dosimetry EDE Evaluation Sheet for

Control Rod Drive Exchange

2/07/2023

71124.04

Miscellaneous

Multiple

Dosimetry Issue

Log for Work on

2B33-F067A

Multiple Dosimetry Issue Log for Use of EDEX from

2/18/2023 - 02/21/2023 for RWP 548-02

2/18/2023

Unit 1 Initiating

Events Report

Unit 1 Initiating Events Report

01/23/2022

71151

Miscellaneous

Unit 2 Initiating

Events Report

Unit 2 Initiating Events Report

01/24/2023

Corrective Action

Documents

AR 4417704

Root Cause Investigation Report - Elevated Collective

Radiation Exposure on Unit 2 Resulting in a Total Outage

Dose of 664.718 Rem on an Original L2R18 Business Plan

Dose Goal of 235 Rem.

06/17/2021

71152A

Miscellaneous

LAS-1-2022-0250

Risk Assessment - 1B DG Lockout Trip

2/21/2022