ML24131A151

From kanterella
Jump to navigation Jump to search
County Station - Integrated Report 05000373/2024001 and 05000374/2024001
ML24131A151
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 05/13/2024
From: Robert Ruiz
NRC/RGN-III/DORS/RPB1
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2024001
Download: ML24131A151 (1)


See also: IR 05000373/2024001

Text

David P. Rhoades

Senior Vice President

Constellation Energy Generation, LLC

President and Chief Nuclear Officer (CNO)

Constellation Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT:

LASALLE COUNTY STATION - INTEGRATED INSPECTION REPORT

05000373/2024001 AND 05000374/2024001

Dear David P. Rhoades:

On March 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection

at LaSalle County Station. On April 17, 2024, the NRC inspectors discussed the results of this

inspection with Christopher Smith, Plant Manager, and other members of your staff. The results

of this inspection are documented in the enclosed report.

Four findings of very low safety significance (Green) are documented in this report. Four of

these findings involved violations of NRC requirements. We are treating these violations as

non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this

inspection report, you should provide a response within 30 days of the date of this inspection

report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission,

ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional

Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector

at LaSalle County Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a

response within 30 days of the date of this inspection report, with the basis for your

disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the

NRC Resident Inspector at LaSalle County Station.

May 13, 2024

D. Rhoades

2

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

Robert Ruiz, Chief

Reactor Projects Branch 1

Division of Operating Reactor Safety

Docket Nos. 05000373 and 05000374

License Nos. NPF-11 and NPF-18

Enclosure:

As stated

cc w/ encl: Distribution via LISTSERV

Signed by Ruiz, Robert

on 05/13/24

ML24131A151

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available

OFFICE

RIII

EICS

RIII

NAME

NShaw:sw

GEdwards via email

RRuiz

DATE

05/13/2024

05/07/2024

05/13/2024

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Numbers:

05000373 and 05000374

License Numbers:

NPF-11 and NPF-18

Report Numbers:

05000373/2024001 and 05000374/2024001

Enterprise Identifier:

I-2024-001-0074

Licensee:

Constellation Nuclear

Facility:

LaSalle County Station

Location:

Marseilles, IL

Inspection Dates:

January 01, 2024 to March 31, 2024

Inspectors:

J. Benjamin, Senior Resident Inspector

J. Cassidy, Senior Health Physicist

T. Hooker, Health Physicist

J. Meszaros, Resident Inspector

E. Rosario, Reactor Inspector

N. Shah, Senior Project Engineer

A. Shaikh, Senior Reactor Inspector

M. Siddiqui, Allegations/Enforcement Specialist

C. St. Peters, Resident Inspector

Approved By:

Robert Ruiz, Chief

Reactor Projects Branch 1

Division of Operating Reactor Safety

2

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at LaSalle County Station, in accordance

with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for

overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Follow Seismic Storage Requirements for a Temporary Battery Charger Stacked on

an Unrestrained Cart Configuration Adjacent to the Safety-Related Unit 1 125Vdc Division 2

Battery Rack and Exposed Terminals

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000373/2024001-01

Open/Closed

[H.8] -

Procedure

Adherence

71111.05

The inspectors identified a Green finding and an associated non-cited violation (NCV) of

10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, when the

licensee failed to follow the requirements of station procedure LAP-100-56, Equipment Parts

Storage in Plant Areas Containing Safety-Related Equipment, Revision 10. Specifically, the

licensee failed to ensure that a portable battery charger stacked on the top of a mobile cart

with a combined height to width ratio of greater than 2.0 was either stored in an approved

seismic storage area, seismically restrained, approved by engineering, or stored at least a

distance of 2 feet plus the height of the stacked configuration away from the safety-related

batteries with exposed terminals in accordance with the procedure requirements.

Failure to Test Motor-Operated Valve in Accordance with the Inservice Test Program

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Barrier Integrity

Green

NCV 05000374/2024001-02

Open/Closed

[H.11] -

Challenge the

Unknown

71111.24

The inspectors identified a finding of very low safety significance (Green) and a non-cited

violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) Part 50.55a(f)(4)(ii)

for the licensees failure to meet the in-service testing requirements set forth in the American

Society of Mechanical Engineers (ASME) Operations and Maintenance Code and Addenda

Code Case OMN-1 after performing maintenance that could affect motor-operated valve

(MOV) performance. Specifically, the licensee failed to perform testing on primary

containment isolation MOV, 2B21-F016, prior to returning the valve to service after electrically

backseating the valve, which was maintenance that could affect the valves performance.

3

Failure to Use Calibrated Measuring and Test Equipment to Electrically Backseat a Safety

Related Motor-Operated Valve

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Barrier Integrity

Green

NCV 05000374/2024001-03

Open/Closed

[H.11] -

Challenge the

Unknown

71111.24

The inspectors identified a finding of very low safety significance (Green) and a NCV of

Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XII,

Control of Measuring and Test Equipment, for the licensees failure to assure a tool used in

activities affecting quality was properly controlled, calibrated, and adjusted at specified

periods to maintain accuracy within necessary limits. Specifically, the licensee failed to apply

quality assurance requirements to the MOV BSRT when using the tool to electrically backseat

a Unit 2 safety-related valve.

Failure to Promptly Correct Degraded Pressure Switches in the Unit 1 and Unit 2 Main Steam

Line High Flow Isolation Logic System

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Initiating Events

Green

NCV 05000373,05000374/2024001-04

Open/Closed

None (NPP)

71152A

The inspectors identified a Green finding and associated non-cited violation of

10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, for the licensees failure to

promptly correct a condition adverse to quality associated with the Unit 1 and Unit 2 main

steam line (MSL) isolation logic system. Specifically, the licensee identified in a 2008

equipment apparent cause evaluation that pressure switches installed in the Unit 1 and Unit 2

MSL high-flow isolation logic trip systems were susceptible to multiple failure modes and had

been exposed to peak inductive currents during frequent calibration activities that may have

damaged switch contacts. A subsequent corrective action replaced half of the impacted

switches while the other half continued to be replaced on an as-needed basis.

Additional Tracking Items

Type

Issue Number

Title

Report Section

Status

URI

05000373,05000374/20

23002-01

Clarification of the Dew Point

Specification for the MSA

Firehawk M7 SCBA System

71124.03

Closed

4

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On February 19, 2024, the unit

coasted down to approximately 86 percent power and commenced refueling outage L1R20.

On March 8, 2024, the unit started up and reached rated thermal power on March 13, 2024.

On March 17, 2024, the unit was down powered to approximately 60 percent to perform power

suppression testing for a suspected fuel cladding failure. The suspected fuel failure was

suppressed and later that day, the unit returned to rated thermal power and remained at or near

rated thermal power for the duration of the inspection period.

Unit 2 began the inspection period at rated thermal power. On January 12, 2024, the unit was

down powered to approximately 80 percent for a control rod sequence exchange. The unit was

returned to rated thermal power on the same day and remained at rated thermal power for the

remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors performed activities described in IMC 2515,

Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of

IPs. The inspectors reviewed selected procedures and records, observed activities, and

interviewed personnel to assess licensee performance and compliance with Commission rules

and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated the licensees readiness for extreme cold weather condition

preparation for the following systems:

1.

unit common A train firewater pump

2.

cooling water intake systems

3.

FLEX buildings

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1)

1A residual heat removal system on January 4, 2024, after quarterly pump run

(2)

Unit 1 and Unit 2 station air following the trip of a station air compressor on

March 26, 2024

5

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (9 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a

walkdown and performing a review to verify program compliance, equipment functionality,

material condition, and operational readiness of the following fire areas:

(1)

Fire Zone 312, reactor building, elevation 673'-4", Unit 2 high-pressure core spray

cubicle on January 17, 2024

(2)

Fire Zone 3H2, reactor building, elevation 694'-6", Unit 2 high-pressure core spray

cubicle on January 19, 2024

(3)

Fire Zone 2K, reactor building, elevation 687'-0" to 768'-0", Unit 1 steam tunnel on

February 22, 2024

(4)

Unit 2 auxiliary electrical equipment room on March 13, 2024

(5)

Fire Zone 3B1, reactor building, elevation 820'-6", Unit 2 general area and standby

gas treatment area on March 13, 2024

(6)

Fire Zone 2B1, reactor building, elevation 820'-6", Unit 1 general area and standby

gas treatment area on March 13, 2024

(7)

Fire Zone 5D3, elevation 687'-0", Unit 1 high-pressure core spray switchgear area on

March 14, 2024

(8)

Fire Zone 5D2, elevation 687'-0", Unit 2 high-pressure core spray switchgear area on

March 14, 2024

(9)

Fire Zone 3I4, reactor building, Unit 2 low-pressure coolant system (LPCS)/reactor

core isolation cooling (RCIC) pump cubicle room on March 29, 2024

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated the temporary floor drain plugging configuration in the

turbine building to support the movement of 250Vdc batteries (RE: Engineering

Change 640690).

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01) (1 Sample)

The inspectors evaluated boiling-water reactor nondestructive testing by reviewing the

following examinations from February 26-March 1, 2024:

(1)

1.

visual examination of residual heat removal (RHR) constant support

RH40-1004C

2.

visual examination of MS restraint MS01-1352X

3.

ultrasonic examination of reactor pressure vessel (RPV) recirculation outlet

nozzle inner radius 1-NIR-10

4.

ultrasonic examination of RPV core spray nozzle inner radius 1-NIR-16

5.

ultrasonic examination of RPV bottom head meridional welds GEL-1006 DB,

DC, and DD

6.

weld repair on Unit 1 RHR HX weld 1RH-HX1B-9A

6

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1)

The inspectors observed and evaluated licensed operator performance in the control

room during reactor startup from outage L1R20 on March 8, 2024.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1)

The inspectors observed and evaluated license operator requalification simulator

out-of-box evaluation on March 19, 2024.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the

following planned and emergent work activities to ensure configuration changes and

appropriate work controls were addressed:

(1)

Unit 2 elevated action Green risk due to main steam line high-flow channel spurious

trips on January 17, 2024

(2)

Unit 2 L1R20 shutdown safety plan

(3)

Unit 2 planned elevated action Green risk for behind-the-meter related activities on

February 1, 2024

(4)

Unit 1 planned reduced inventory to support head removal on February 20, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (8 Samples)

The inspectors evaluated the licensees justifications and actions associated with the

following operability determinations and functionality assessments:

(1)

Unit 2 channel A1 main steam isolation valve high-flow isolation operability between

spurious signals on January 9, 2024, and January 12, 2024

(2)

operability assessment of the Unit 2B emergency diesel generator after

small amounts of metal debris were observed under the top deck cover on

January 23, 2024

(3)

Unit 2 RCIC issues with manual control

(4)

Unit 2 main stem line valve drain inboard isolation valve 2B21-F016 back seating

activity to reduce suspected packing leakage

(5)

Unit 1 1B reactor recirculation seal pressure temperature and pressure fluctuations

(6)

Unit 1 1A reactor recirculation seal pressure temperature and pressure fluctuations

(7)

Unit 1 L1R20 water rod inspection identification of three fuel spacers that shifted up

near the upper core plate

(8)

2CM023B operability as a primary containment isolation valve and associated

containment monitoring channel operability given continued indication and

manufacturing issues

7

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

(1 Sample)

(1)

Unit 2 main steam inboard drain primary containment isolation valve backseat to

reduce suspected packing leakage

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated Unit 1 refueling outage L1R20 related activities from

February 19, 2024, to March 8, 2024.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system

operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (4 Samples)

(1)

Unit 1 division 2 safety-related battery cell 56 equalizing charge on January 31, 2024

(2)

Unit 2 main stem line valve drain inboard isolation valve 2B21-F016 back seating

PMT

(3)

Unit 1 reactor vessel leakage test on March 5, 2024

(4)

Unit 1 1A emergency diesel generator fast start on March 29, 2024

Surveillance Testing (IP Section 03.01) (5 Samples)

(1)

Unit 2 main steam line high-flow main steam isolation valve (MSIV) isolation

calibration per LIS-MS-202 on January 9, 2024

(2)

Unit 1 MSIV stroke time testing on February 19, 2024

(3)

Unit 1 reactor recirculation flow control valve lockup testing on February 19, 2024

(4)

Unit 1 integrated division 1 response time surveillance per LOS-DG-109 on

February 21, 2024

(5)

Unit 2 2A emergency diesel generator idle start testing on March 15, 2024

Inservice Testing (IST) (IP Section 03.01) (2 Samples)

(1)

Unit 2 2A standby liquid control pump on March 15, 2024

(2)

Unit 2 2B emergency diesel generator cooling water pump comprehensive inservice

test on March 18, 2024

8

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated how the licensee identifies the magnitude and extent of

radiation levels, the concentrations and quantities of radioactive materials, and how

the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1)

The inspectors evaluated how the licensee instructs workers on plant-related

radiological hazards and the radiation protection requirements intended to protect

workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and

controlling contamination and radioactive material:

(1)

licensee surveys and decontamination of potentially contaminated material leaving

the main radiologically controlled area

(2)

licensee surveys and decontamination of potentially contaminated material leaving

the radiologically controlled area at the north service building

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

The inspectors evaluated the licensees control of radiological hazards for the following

radiological work:

(1)

Unit 1 undervessel installation

(2)

Unit 1 high-pressure turbine diaphragm inspection

(3)

refueling floor cavity platform activities

(4)

Unit 1 F004 valve room activities

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)

The inspectors evaluated licensee controls of the following high radiation areas and very

high radiation areas:

(1)

Unit 1 reactor building personnel access

(2)

Unit 1 turbine deck center court

(3)

Unit 1 drywell entry

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section

03.06) (1 Sample)

(1)

The inspectors evaluated radiation worker and radiation protection technician

performance as it pertains to radiation protection requirements.

9

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Temporary Ventilation Systems (IP Section 03.02) (1 Sample)

The inspectors evaluated the configuration of the following temporary ventilation systems:

(1)

LAS-416 HEPA unit

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1)

The inspectors evaluated the licensees use of respiratory protection devices.

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling,

Storage, & Transportation

Shipment Preparation (IP Section 03.04) (1 Sample)

(1)

The inspectors observed the preparation of radioactive shipment LM24-003 of control

rod drive boxes on February 29, 2024.

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01) (2 Samples)

(1)

Unit 1 (January 1, 2023, through December 31, 2023)

(2)

Unit 2 (January 1, 2023, through December 31, 2023)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02)

(2 Samples)

(1)

Unit 1 (January 1, 2023, through December 31, 2023)

(2)

Unit 2 (January 1, 2023, through December 31, 2023)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (2 Samples)

(1)

Unit 1 (January 1, 2023, through December 31, 2023)

(2)

Unit 2 (January 1, 2023, through December 31, 2023)

71152A - Annual Follow-up Problem Identification and Resolution

Annual Follow-up of Selected Issues (Section 03.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program

related to the following issues:

10

(1)

The inspectors evaluated spurious Unit 2 channel A1 main steam line isolation valve

isolation signals that occurred on several dates as documented in Action Requests

(ARs) 4730751 and 4727857. A finding of very low safety significance (Green) and

non-cited violation is associated with the inspectors review and are documented in

the Inspection Results section of this report.

71153 - Follow Up of Events and Notices of Enforcement Discretion

Event Report (IP Section 03.02) (1 Sample)

The inspectors evaluated the following licensee event reports (LERs):

(1)

LER 05000374/2023-003-00, LaSalle County Station, Unit 2, Automatic Actuation of

Reactor Protection System (RPS) During Restoration from Hydrostatic Test

Conditions (ADAMS Accession No. ML23122A016). The inspectors determined that

the cause of the condition described in the LER does not represent a finding because

the unit was already shut down at the time of actuation and the RPS signal was not

applicable. This LER is closed.

INSPECTION RESULTS

Failure to Follow Seismic Storage Requirements for a Temporary Battery Charge Stacked on

an Unrestrained Cart Configuration Adjacent to the Safety-Related Unit 1 125Vdc Division 2

Battery Rack and Exposed Terminals

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000373/2024001-01

Open/Closed

[H.8] -

Procedure

Adherence

71111.05

The inspectors identified a Green finding and an associated non-cited violation (NCV) of

10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, when the

licensee failed to follow the requirements of station procedure LAP-100-56, Equipment Parts

Storage in Plant Areas Containing Safety-Related Equipment, Revision 10. Specifically, the

licensee failed to ensure that a portable battery charger stacked on the top of a mobile cart

with a combined height to width ratio of greater than 2.0 was either stored in an approved

seismic storage area, seismically restrained, approved by engineering, or stored at least a

distance of 2 feet plus the height of the stacked configuration away from the safety-related

batteries with exposed terminals in accordance with the procedure requirements.

Description:

During the walkdown portion of this inspection, the inspectors identified that a portable battery

charger stacked on a mobile cart was within in very close proximity to the Unit 1 division 2

125Vdc safety-related batteries. The licensee was using the temporary battery charger for an

extended single charge of cell #56 per licensee procedure LEP-DC-01. The inspectors

identified a concern that if a seismic event occurred, or if bumped, that the stacked metal

frame battery charger unit could fall off the plastic cart and onto the exposed battery terminals

resulting in an arc event and loss of 125Vdc battery charger or batteries themselves. The

inspectors immediately notified the Unit 1 senior reactor operator of their concerns. The

licensee promptly secured the single cell charge, removed the cart and battery charger from

the 125Vdc division 2 battery room. The licensee discussed the station storage requirements

11

and expectations with the appropriate site personnel and entered this issue into their

corrective action program (AR 4739747). The licensee concluded that this configuration did

not meet station requirements and expectations, however, the battery and associated

permanent battery charger remained operable in this configuration based upon their

judgement.

The inspectors reviewed the licensee corrective action document and procedure that

maintains structure, system, and component quality with respect to equipment storage,

LAP-100-56, revision 10, Equipment/Parts Storage in Plant Areas Containing Safety-Related

Equipment. A specific purpose listed in the procedure was to define the LaSalle station

requirements for equipment/parts storage in plant areas containing safety-related

equipment. The inspectors approximated the height (H) to weight (W) ratio to be 6 based

upon the smallest width of the battery charger combined with the total height of the stacked

configuration to be approximately 48 inches. The inspectors approximated the distance from

the stacked metal frame battery charge to be approximately 1 foot higher and 10 inches from

the open battery terminals. The inspectors identified the specific procedural requirements not

met included:

Specifically (Ref: LAP-100-56, revision 10):

B.4.2.1 Stored items with a height (H) to width (W) ration (H/W) greater than 2.0 may

require a seismic restraint.

B.4.2.2 If H/W is greater than 2.0, proceed to B.4.4 . . .

B.4.3 Stored items with H/W < 2.0. . . .

B.4.4 Stored items with H/W > 2.0.

B.4.4.1 Items stored inside or outside one of the approved storage areas.

B.4.4.1.1 If the edge of the stored item is located at least 24-inches plus the height (H) of

the stored item away from the nearest piece of safety-related equipment/component. . .

otherwise proceed to B.4.6 (seismic restraint required).

B.4.6 Seismic Restraint

B.4.6.1 All stored items not meeting the requirements of B.4.3 and B.4.4 shall require

seismic restraints unless otherwise approved by Engineering. . .

Procedure LAP-100-56, revision 10, attachment, provides an activity flow chart which restates

the procedural requirements in a different format.

Corrective Actions: The licensee entered this condition into the stations corrective action

program AR 4739747. Corrective actions include promptly securing the single cell charger

and relocating the cart and stacked battery charger out of the Unit 1 125Vdc division 2 battery

room, individual coaching, and an assignment to determine if the procedure could be

enhanced.

Corrective Action References: AR 4739747

12

Performance Assessment:

Performance Deficiency: The licensees failure to follow station procedure LAP-100-56,

Equipment Parts Storage in Plant Areas Containing Safety-Related Equipment, Revision 10,

was a performance deficiency. Specifically, the procedure accurately captured the licensee

requirements in both the procedure body and associated attachment A and therefore was

reasonable for the licensee to foresee and prevent.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Configuration Control attribute of the Mitigating Systems

cornerstone and adversely affected the cornerstone objective to ensure the availability,

reliability, and capability of systems that respond to initiating events to prevent undesirable

consequences. Specifically, one of the purposes of licensee procedure LAP-100-56 is to

ensure safety-related components such as the Unit 1 division 2 125Vdc battery remain

available, reliable, and capable, during design-basis events. The cart and stacked battery

charger were in an unrestrained configuration such that if a seismic event occurred, the

battery charger could have tipped forward onto and shorted out 125Vdc battery terminal(s)

resulting in the loss of Unit 1 division 2 125Vdc safety-related batteries and/or charger.

Absent a seismic event, the charger could have also been knocked over onto the

safety-related battery terminals during normal day-to-day plant operations. In addition,

the inspectors reviewed the more-than-minor examples in NRC Inspection Manual

Chapter 0612, Appendix E, Examples of Minor Issues. The inspectors informed their use of

the more-than-minor questions by comparing this finding to the more-than-minor example 3a.

This example illustrates a calculational error with the potential to adversely affect the

mitigating system cornerstone objective. Similar to example 3a, the inspectors determined

that the finding was more than minor, regardless of the licensees operability assessment,

based upon the inspectors reasonable doubt that this stacked configuration could have

adversely effected Unit 1 division 2 125Vdc battery availability, reliability, and capability had

the battery charger fallen off the mobile cart during a seismic event.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The

finding is a deficiency affecting the qualification of a mitigating SSC that maintained its

operability.

Cross-Cutting Aspect: H.8 - Procedure Adherence: Individuals follow processes, procedures,

and work instructions. Specifically, the inspectors determined that a primary cause for the

performance deficiency was because the licensee did not follow procedure LAP-100-56,

Equipment Parts Storage in Plant Areas Containing Safety-Related Equipment, Revision 10,

as part of this work activity.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and

Drawings requires, in part, that activities affecting quality be prescribed by documented

procedures of a type appropriate to the circumstances and be accomplished in accordance

with these procedures. The licensee established LAP-100-56, Equipment Parts Storage in

Plant Areas Containing Safety-Related Equipment, Revision 10, as the implementing

procedure for storing equipment near safety-related equipment, as an activity affecting

quality.

13

Procedure LAP-100-56, Revision 10, states:

B.4.2.1 Stored items with a height (H) to width (W) ration (H/W) greater than 2.0 may

require a seismic restraint.

B.4.2.2 If H/W is greater than 2.0, proceed to B.4.4 . . .

B.4.3 Stored items with H/W < 2.0. . ..

B.4.4 Stored items with H/W > 2.0.

B.4.4.1 Items stored inside or outside one of the approved storage areas.

B.4.4.1.1 If the edge of the stored item is located at least 24-inches plus the height (H) of

the stored item away from the nearest piece of safety-related equipment/component. . .

otherwise proceed to B.4.6 (seismic restraint required).

B.4.6 Seismic Restraint

B.4.6.1 All stored items not meeting the requirements of B.4.3 and B.4.4 shall require

seismic restraints unless otherwise approved by Engineering. . .

Contrary to the above, from January 29, 2024, to January 31, 2024, the licensee failed to

follow step B.4.6.1 of procedure LAP-100-56, Revision 10. Specifically, the licensee failed to

use required seismic restraints or have the storage configuration approved by Engineering

when a temporary battery charger was stored in a stacked configuration on top of a mobile

cart with an overall height to width ratio of approximately 6 within approximately 10 inches of

the safety-related Unit 1 division 2 125Vdc batteries.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Failure to Test Motor-Operated Valve in Accordance with the Inservice Test Program

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Barrier Integrity

Green

NCV 05000374/2024001-02

Open/Closed

[H.11] -

Challenge the

Unknown

71111.24

The inspectors identified a finding of very low safety significance (Green) and a non-cited

violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) Part 50.55a(f)(4)(ii)

for the licensees failure to meet the in-service testing requirements set forth in the American

Society of Mechanical Engineers (ASME) Operations and Maintenance Code and Addenda

Code Case OMN-1 after performing maintenance that could affect motor-operated valve

(MOV) performance. Specifically, the licensee failed to perform testing on primary

containment isolation MOV, 2B21-F016, prior to returning the valve to service after electrically

backseating the valve, which was maintenance that could affect the valves performance.

Description:

In December 2023, the licensee noticed an increasing trend in Unit 2 reactor coolant system

(RCS) unidentified leakage inside the drywell. The licensee performed troubleshooting to

14

identify the possible leak sources and identified a potential packing leak of the main steam

isolation valve (MSIV) drain header inboard isolation valve, 2B21-F016. This was based, in

part, on the as-left condition of this valve during the last RCS hydrostatic test. Due to the

exponentially increasing leak rate, the licensee chose to electrically backseat the MOV. On

January 25, 2024, the licensee was successful in limiting the RCS unidentified leak rate back

to baseline by electrically backseating the MOV using a new tool to operate the actuator

remotely from motor control center (MCC).

Backseating a valve is a maintenance activity allowing the stem to contact the backseat,

which can either reduce or stop packing leakage. Additionally, backseating a valve can affect

the valves performance (e.g., cause damage to the valve or bind it into its backseat). Since

this activity can affect the valve, NUREG-1482, revision 3, Guidelines for Inservice Testing at

Nuclear Power Plants, Section 4.4.2, Post-Maintenance Testing After Stem Packing

Adjustments and Backseating of Valves to Prevent Packing Leakage, provides guidance for

stroking the valve stem away from the backseat after the initial backseating operation to

demonstrate the valve did not become bound in the backseat. Although the licensee reviewed

this guidance describing an NRC approved testing method for validating a valves

performance, the licensee chose not to implement this guidance. Consequently, the licensee

did not stroke the valve away from the backseat after the initial backseating operation of the

valve.

The licensee performed an engineering evaluation in support of backseating the valve under

engineering change request (ECR) 461530. The inspectors reviewed the evaluation and

noted there were two reasons for performing this evaluation. One aspect of the evaluation

was to evaluate the backseating evolution, which was to be performed for the first time with a

new MOV backseat relay tool (BSRT), under Work Order (WO) 5443427-01. This tool is

installed at the MCC and bypasses the open limit switch to allow the stem to contact the

backseat. The second purpose of the evaluation was to perform a formal technical evaluation

to assess the limitation of the backseating, the potential effects on the MOV structural

capability, and the valve requirements. The licensee evaluated the following three criteria:

increased stroke time, thrust and torque loads applied during backseating of the valve

compared to valve/actuator structural capability, and post-maintenance

requirements/testing/evaluations. From the review, the inspectors noted the structural

capabilities of the valve and actuator were calculated to be acceptable within design limits.

Regarding the licensees evaluation on PMT requirements, MA-AA-716-012, Post

Maintenance Testing, (PMT) revision 28, contains an MOV PMT test matrix which lists

common maintenance activities, such as valve replacement, and assigns pre-established

PMT verification(s) to be performed. Although neither manual nor electrical backseating

were included in the test matrix, the licensee considered the listed maintenance activity of

control circuit disconnect and reconnect to be applicable since this would occur during the

MOV BSRT installation. Therefore, the listed test verifications included rotation and logic

check, control room functional stroke, and an IST operability stroke time test. However,

attachment 2 of the PMT procedure, Waiver Requirement Guidance, allowed engineering to

waive a PMT provided a written justification was completed. The licensee also provided

guidance for engineering to waive the PMT under procedure ER-AA-302-1006, revision 21,

Motor-Operated Valve Maintenance Testing Guidelines, under step 4.2, Guidelines for

Exempting Certain Motor-Operated Valve (MOV) Post-Maintenance Diagnostic (PMDT)

Recommendations from MA-AA-716-012. The written justification for waiving the referenced

test verification was documented in the engineering evaluation. Therefore, no testing was

performed prior to returning the valve to service after the valve was electrically backseated.

15

LaSalle County Station (LSCS) Inservice Testing (IST) Program Plan - 4th Interval,

Revision 0, states the Code of Record for the Fourth 10-Year IST Program interval is the

ASME Code for Operation and Maintenance of Nuclear Power Plants (OM) Code, 2004

Edition through 2006 Addenda. The IST requirements apply, in part, to valves required to

perform a specific function in shutting down the reactor to the safe shutdown condition, in

maintaining the safe shutdown condition, or in mitigating the consequences of an accident.

The IST Program Plan - 4th Interval incorporates ASME Code Case OMN-1, 2006 Addenda,

through the alternative granted by the Nuclear Regulatory Commission (NRC) in valve relief

request - RV-01, Utilization of ASME Code Case OMN-1. With this alternative granted by

the NRC for this IST Program interval, the inspectors noted primary containment isolation

MOV 2B21-F016 was subject to ASME Code Case OMN-1, Alternative Rules for Preservice

and Inservice Testing of Active Electric Motor-Operated Valve Assemblies in Light-Water

Reactor Power Plants.

The IST Program Plan - 4th Interval states 2B21-F016 is an ASME Class 1, Category A,

normally open, motor-operated, active valve with a safety function in the closed position. The

ASME OM-2006 Code Case OMN-1, paragraph 3.4, states, in part, When an MOV or its

control system is replaced, repaired, or undergoes maintenance that could affect the valves

performance, new inservice test values shall be determined, or the previously established

inservice test values shall be confirmed before the MOV is returned to service... This testing

is intended to demonstrate that performance parameters, which could have been affected by

the replacement, repair, or maintenance, are within acceptable limits. The Owners program

shall define the level of testing required after replacement, repair, or maintenance...

Since both the valve and its control system underwent maintenance that could affect the

MOVs performance, the inspectors determined the valve was required to be tested in

accordance with Paragraph 3.4 of Code Case OMN-1. The Code Case does not provide the

allowance to perform an evaluation in lieu of the required inservice testing. Although this does

not conform to the requirements, the licensees evaluation and work results provided

reasonable assurance the structural integrity of the MOV was not exceeded. However, not

performing any testing after maintenance prior to returning the valve to service did not

maintain the requisite level of assurance for the valve. Considering operating experiences

with backseating, the number of assumptions embedded in the evaluation, and the use of the

new MOV BSRT, the inspectors noted there were several uncertainties associated with the

engineering evaluation and its use to restore operability. Based on the inspectors review of

the IST plan and procedures for the valve, the inspectors determined the licensee failed to

ensure the testing required after maintenance under WO 5443427-01 was performed in

accordance with Code Case OMN-1. In addition, the licensee did not request relief from the

code via an ASME Code relief request to the NRC which, if approved, would have allowed

the valve to be returned to service without performing the required testing.

Corrective Actions: The licensee entered this issue into their corrective action program. The

licensee is evaluating the technical and regulatory requirements for resolution and alignment.

Corrective Action References: AR 4754319, NRC ID ASME OM Code Potential

Finding/Violation; and AR 4753350, NRC IS Questions on Valve Backseating Activity

Performance Assessment:

Performance Deficiency: The licensees failure to perform required testing after

maintenance for the primary containment isolation MOV 2B21-F016 in accordance with

ASME OM Code-2004, 2006 Addenda, Code Case OMN-1, Paragraph 3.4, was a violation of

16

10 CFR 50.55a(f)(4)(ii) and a performance deficiency. Specifically, the licensee failed to

perform required testing on the MOV prior to returning the valve to service after electrically

backseating the valve, which was maintenance that could affect the valves performance.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the SSC and Barrier Performance attribute of the Barrier

Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable

assurance that physical design barriers protect the public from radionuclide releases caused

by accidents or events. The inspectors determined the finding was associated with the SSC

and Barrier Performance objective of the Barrier Integrity cornerstone and adversely affected

the cornerstone objective to provide reasonable assurance physical design barriers (fuel

cladding, reactor coolant system, and containment) protect the public from radionuclide

releases caused by accidents or events. Specifically, by not performing the required testing,

the licensee did not maintain the requisite level of assurance of the valves reliability of

performing its intended function after performing maintenance that could affect the valves

performance.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The

inspectors determined the finding was of very low safety significance (Green) because they

answered No to all exhibit 3, Barrier Integrity Screening Questions, section C, Reactor

Containment, screening questions.

Cross-Cutting Aspect: H.11 - Challenge the Unknown: Individuals stop when faced with

uncertain conditions. Risks are evaluated and managed before proceeding. Specifically,

when presented with an emergent and exponentially increasing RCS unidentified leakage,

the licensee determined testing after maintenance was not required prior to returning the

valve to service through an engineering evaluation. This was the licensees first time

performing this evolution and using the new MOV BSRT, and the licensee did not adequately

challenge, understand, and manage the activity affecting quality to ensure regulatory

requirements were met.

Enforcement:

Violation: Title 10 CFR 50.55a(f)(4)(ii), requires, in part, Inservice tests to verify operational

readiness of pumps and valves, whose function is required for safety, conducted during

successive 120-month intervals must comply with the requirements of the latest edition and

addenda of the ASME OM Code incorporated by reference in paragraph (a)(1)(iv) of this

section 18 months before the start of the 120-month interval (or the optional ASME Code

Cases listed in NRC Regulatory Guide 1.192 as incorporated by reference in paragraph

(a)(3)(iii) of this section).

LaSalle County Station IST Program Plan - 4th Interval, Revision 0, establishes the Code of

Record for the Fourth 10-Year IST Program Interval (October 12, 2017 - October 11, 2027)

as the ASME OM Code, 2004 Edition through 2006 Addenda, as incorporated by reference in

10 CFR 50.55a. LSCS submitted a Valve Relief Request RV-01 to implement the optional

ASME Code Case OMN-1 in their Fourth 10-Year IST Program Plan.

ASME OM Code-2006, Code Case OMN-1, Paragraph 3.4, Effect of MOV Replacement,

Repair, or Maintenance, states, in part, When an MOV or its control system is replaced,

repaired, or undergoes maintenance that could affect the valves performance, new inservice

test values shall be determined, or the previously established inservice test values shall be

17

confirmed before the MOV is returned to service.

Contrary to the above, on January 25, 2024, the licensees inservice tests to verify

operational readiness of pumps and valves, whose function is required for safety,

did not comply with the requirements of the 2004 Edition through the 2006 Addenda of the

ASME OM Code as incorporated by reference in 10 CFR 50.55a for the current 10-Year IST

program interval at LaSalle County Station effective October 17, 2017. Specifically, the

licensee failed to perform any testing on primary containment isolation MOV 2B21-F016, a

valve within the scope of the ASME OM Code and Addenda, before returning the valve to

service after electrically backseating the valve, which was maintenance that could affect the

valves performance.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Failure to Use Calibrated Measuring and Test Equipment to Electrically Backseat a Safety

Related Motor-Operated Valve

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Barrier Integrity

Green

NCV 05000374/2024001-03

Open/Closed

[H.11] -

Challenge the

Unknown

71111.24

The inspectors identified a finding of very low safety significance (Green) and a NCV of

Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XII,

Control of Measuring and Test Equipment, for the licensees failure to assure a tool used in

activities affecting quality was properly controlled, calibrated, and adjusted at specified

periods to maintain accuracy within necessary limits. Specifically, the licensee failed to apply

quality assurance requirements to the MOV BSRT when using the tool to electrically backseat

a Unit 2 safety-related valve.

Description:

On January 25, 2024, the licensee used a tool, the MOV BSRT, to electrically backseat the

B MSIV drain header inboard isolation valve 2B21-F016, a safety-related containment

isolation MOV. The valve was backseated to address a suspected packing leak, which was

contributing to an increase of Unit 2 RCS unidentified leakage. Although backseating is a

known method available to mitigate valve packing leaks, backseating is not commonly

performed. Furthermore, electrically backseating is an even more uncommon evolution. In

both manual and electrical backseating of valves, operating experience has shown

backseated valves can be either damaged or become bound into their backseats. The NRC

has provided guidance on backseating under section 4.4.2, Post-Maintenance Testing After

Stem Packing Adjustments and Backseating of Valves to Prevent Packing Leakage, of

NUREG-1482, revision 3, Guidelines for Inservice Testing at Nuclear Power Plants.

The inspectors performed a review of the MOV BSRT used to accomplish this

activity. Engineering evaluation documented under ECR 461530 was reviewed and

found to incorporate guidance of draft procedure MA-AA-723-304, Electrical Backseating

Motor-Operated Valves Remotely from a Motor-Control Center - Current Cut-Off Method, for

using this tool. From the evaluations conclusion, the inspectors noted this was the first use of

the MOV BSRT on a currently installed valve at the site. The guidance from the referenced

draft procedure was also incorporated in WO 5443427-01, which was implemented to

18

perform the electrical backseating of the valve with the MOV BSRT. The MOV BSRT was

installed remotely at the MOVs MCC on the open control circuit in parallel with the Limitorque

actuator open limit and torque switch. This allowed the tool to bypass the MOV open limit

settings to stroke the valve in the open direction. Normally, during an open stroke of the

valve, the valves actuator would stop the valve travel near the fully open position when the

open limit switch trips before the stem contacts the backseat. The MOV BSRT uses a

specified threshold percentage of minimum recorded running current to stop the valve travel

after the valve stem contacts the backseat.

The inspectors questioned the quality of the MOV BSRT used for this maintenance evolution

as this was an activity affecting quality. The licensee stated the MOV BSRT was not

considered measurement and testing equipment (M&TE) per procedure MA-AA-716-040,

revision 16, Control of Portable Measurement and Test Equipment Program. The licensee

also stated, The backseat relay tool monitors current and then performs its function in terms

of percent. Since it gives functions in terms of percentages and not absolute terms, no

calibration for current reading is necessary.

The inspectors reviewed the MOV BSRT users manual, TM201602, revisions 9 and 13. In

both revisions, section 9, Maintenance, states, in part, Calibration of the device may be

performed but is not required. Trip setpoints are specified as a percentage of current. As

such, the actual current does not matter to meet the intent. Current readings are provided for

information. Refer to the calibration procedure available at the link below. The licensee

determined the Quality Assurance (QA) required calibration and verification of the tool

measured current would not be performed based on the users manual. Through discussions

with the licensee, the inspectors noted that the users manual step 4.9 of revision 13 the

licensee later referenced was not found in the evaluation, which referenced revision 9.

Revision 13, step 4.9, states, Since all setpoints are expressed as percentages, accurate

calibration of the relay or probes is not relevant to trip functioning. The inspectors also

reviewed the MOV BSRT functional test and calibration procedure, TP201602-03, revision 1,

and found the stated purpose was to provide a means of bench verifying the relay responds

correctly to current inputs. The test also verifies that each phase current input is operational

as well as the displayed value of current. Additionally, the procedure states, Since the relay

operates on relative current readings to detect increased motor load as the valve reaches the

backseat, calibration of current reading is not required for proper functioning of the device.

Therefore, although the current reading displayed is not required for proper functioning of the

tool, it is still necessary to test and calibrate the MOV BSRT to ensure both the relays operate

correctly and the phase current inputs are operational.

When Constellation procured the MOV BSRT in 2019, the tool was classified as the following:

For General Use Only, Not for Qualitative or Quantitative Measurements, and Indication

Only. After purchasing from a commercial vendor, the MOV BSRT was entered into the

companys M&TE log for tool traceability. However, the licensee did not establish QA related

controls for the tool.

The inspectors reviewed the following quality assurance requirement. Title 10 CFR Part 50,

Appendix B, Criterion XII, states: Measures shall be established to assure that tools, gages,

instruments, and other measuring and testing devices used in activities affecting quality are

properly controlled, calibrated, and adjusted at specified periods to maintain accuracy within

necessary limits. Since the tool was used in activities affecting quality, the inspectors

determined the licensee failed to classify the MOV BSRT as a tool to be controlled and

calibrated in accordance with 10 CFR 50, Appendix B, Criterion XII, and their Quality

19

Assurance Topical Report (QATR) section 12, Control of Measuring and Test Equipment.

Therefore, the licensee failed to established measures to assure that the MOV BSRT, which

was used in an activity affecting quality, was properly controlled, calibrated, and adjusted at

specified periods to maintain accuracy within necessary limits.

Corrective Actions: The licensee has entered the inspectors concern into their corrective

action program. The licensee developed and performed just-in-time training for operating the

MOV BSRT prior to performing WO 5443427-01. Also, QA controlled MOV diagnostic testing

equipment was installed at the MCC to monitor current in parallel with the MOV BSRT current

monitoring probes. The licensee compared the data from the QA equipment to previous

diagnostic testing data and determined the tool operated as expected.

Corrective Action References: AR 4754320, NRC ID Use of Backseating Tool Potential

Finding/Violation

Performance Assessment:

Performance Deficiency: The licensees failure to establish quality assurance measures for

the MOV backseat relay tool used to electrically backseat a safety-related valve was contrary

to 10 CFR 50, Appendix B, Criterion XII, and was a performance deficiency. Specifically, the

licensee failed to assure the MOV BSRT was properly controlled, calibrated, and adjusted at

specified periods to maintain accuracy within necessary limits.

Screening: The inspectors determined the performance deficiency was more than minor

because if left uncorrected, it would have the potential to lead to a more significant safety

concern. Specifically, continued use of an uncontrolled and uncalibrated MOV BSRT has the

potential to cause structural damage to a valve.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The

inspectors determined the finding was of very low safety significance (Green) because they

answered No to all exhibit 3, Barrier Integrity Screening Questions, section C, Reactor

Containment, screening questions.

Cross-Cutting Aspect: H.11 - Challenge the Unknown: Individuals stop when faced with

uncertain conditions. Risks are evaluated and managed before proceeding. Specifically,

when electrically backseating a safety-related valve, the licensee did not evaluate and

manage the risk of using an unqualified tool to perform a maintenance activity affecting

quality.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion XII, Control of Measuring and Test

Equipment, requires, that measures shall be established to assure that tools, gauges,

instruments, and other measuring and testing devices used in activities affecting quality are

properly controlled, calibrated, and adjusted at specified periods to maintain accuracy within

necessary limits.

Contrary to the above, on January 25, 2024, the licensee failed to assure that a tool used in

activities affecting quality was properly controlled, calibrated, and adjusted to maintain

accuracy within necessary limits. Specifically, the licensee failed to establish quality

assurance measures for the MOV backseat relay tool used to electrically backseat a

safety-related valve.

20

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Unresolved Item

(Closed)

Clarification of the Dew Point Specification for the MSA

Firehawk M7 SCBA System

URI 05000373,05000374/2023002-01

71124.03

Description:

The inspectors reviewed a previously identified unresolved item for a condition where the

quality of breathing air used to fill self-contained breathing apparatus (SCBA) bottles did not

meet all of the parameters specified by the manufacturer as specified in the user instructions

manual. National Institute for Occupational Safety and Health (NIOSH) regulations and

guidance state that user instructions are included as part of the NIOSH approval. Nuclear

Regulatory Commission regulations require that NRC licensees use NIOSH approved

equipment in their respiratory protection programs, or that they obtain approval from the

USNRC to use equipment that has not been approved by NIOSH. However, it was not clear if

the NIOSH approval was contingent upon the dew point guidance that applied to Grade D air,

or a dew point of -65°F, two parameters of breathing air quality that conflicted with each

within the user instructions.

Review of this issue was discontinued in accordance with the Very Low Safety Significance

Issue Resolution (VLSSIR) process as documented in this report. No further evaluation is

required.

This item is closed.

Corrective Action Reference(s): AR 4686286

Very Low Safety Significance Issue Resolution Process: Very Low Safety

Significance Issue Resolution Process: Dew Point Specification for the MSA

M7XT SCBA System

71124.03

This issue is a current licensing basis question and inspection effort is being discontinued in

accordance with the Very Low Safety Significance Issue Resolution (VLSSIR) process. No

further evaluation is required.

Description:

The NRC promulgated requirements for the use of respiratory protection and controls to

restrict internal exposure in Subpart H to 10 CFR 20 Standards for Protection Against

Radiation. Within this regulation are requirements when a licensee assigns or permits the

use of respiratory protection equipment to limit the intake of radioactive material. Some

anticipated uses of respiratory protective equipment to reduce the intake of radioactive

material include repair of highly contaminated equipment, decontamination of large surface

areas, and responding to an accident or a fire involving radioactive contamination. The

respiratory protection equipment with highest protection factor is the SCBA. These are used

for responding to an accident or a fire involving radioactive contamination. The SCBA unit is a

device that includes a face mask connected to a bottle of compressed air carried on the back

of the user. This is also known as an atmosphere-supplying respirator, as the only air

available to the user is from the bottle of compressed air.

21

Atmosphere-supplying respirators, such as SCBAs, must be supplied with respirable air of

Grade D quality or better as defined by the Compressed Gas Association in publication

G-7.1, Commodity Specification for Air, 1997 and included in the regulations of the

Occupational Safety and Health Administration (29 CFR 1910.134(i)(1)(ii)(A) through (E)).

Grade D quality air criteria include

(1) oxygen content (v/v) of 19.5-23.5%

(2) hydrocarbon (condensed) content of 5 milligrams per cubic meter of air or less

(3) carbon monoxide (CO) content of 10 ppm or less

(4) carbon dioxide content of 1,000 ppm or less

(5) lack of noticeable odor

Compressed Gas Association in publication G-7.1, Commodity Specification for Air, 1997

Table 1 - Directory of Limiting Characteristics, also includes maximum dew point or

moisture content for compressed air used as breathing air. The value listed in the table for

Grade D air is blank but covered by a footnote from the dew point parameter. Specifically, this

states The water content of compressed air required for any particular quality verification

level may vary with the intended use from saturated to very dry. For breathing air used in

conjunction with a self-contained breathing apparatus in extreme cold where moisture can

condense and freeze causing the breathing apparatus to malfunction, a dew point not to

exceed -65°F (24 ppm v/v) or 10 degrees Fahrenheit lower than the coldest temperature

expected in the area is required. If a specific water limit is required, it should be specified as a

limiting concentration in ppm (v/v) or dew point...

The inspectors have observed test results for breathing air quality consistently achieved

results with moisture content between 63 ppm (v/v) and 24 ppm (or dew point between -50°F

and -65°F).

The inspectors reviewed the operation and instructions manual published by the SCBA

manufacturer to identify limitations or evaluations that might assist with the evaluating the

apparent failure to ensure the SCBA will remain functional if used in extreme cold where

moisture can condense and freeze causing the breathing apparatus to malfunction. The

inspectors identified inconsistencies as it pertains to dew point specifications for SCBA.

Specifically, within the same user instruction documentation, in one section of the instructions

include a more conservative dew point might be prescribed when compared to the dew point

specified in another section. The least stringent dew point inspectors observed corresponds

to Grade D air (i.e., -50°F or 10°F) less than coldest expected ambient temp), whereas the

more conservative dew point corresponds to that of Grade L air (i.e., -65°F). Additionally, the

manual includes a special or critical user instruction that states the equipment is approved for

use at temperatures above -25°F.

The licensee has revised air quality testing procedure parameters. Since these changes were

implemented, the licensee has demonstrated the breathing air used to fill bottles used for

SCBA consistently satisfies the more stringent standard (-65°F).

Licensing Basis: The requirements for use of respiratory protection equipment to limit the

intake of radioactive material are established in 10 CFR 20.1703. Specifically, § 20.1703

states -

(a) The licensee shall use only respiratory protection equipment that is tested and certified

by the National Institute for Occupational Safety and Health (NIOSH) except as otherwise

noted in this part.

22

User instructions are part of the NIOSH certification; therefore, the inconsistency in the user

instructions introduces a situation where the equipment cannot be used per its instructions;

presumably leading to a violation of the NIOSH certification and our requirements.

Significance: The inspectors determined the issue was of very low safety significance

because the less stringent dew point specification of Grade D air (-50°F) was sufficient for the

environment (ambient temperatures above -25°F) in which the equipment was used or would

be used. Additionally, some of this equipment has been in service for many years without

issue.

For the purpose of the VLSSIR process, the inspectors screened the issue of concern

through IMC 0609, Appendix C and determined the issue of concern would likely be

Green had a performance deficiency been identified. Specifically, it would not have been an

as-low-as-reasonably-achievable planning issue, there would not have been overexposures,

nor substantial potential for overexposures, and the licensees ability to assess dose would

not be compromised. Therefore, the condition represents an issue of very low safety

significance that does not warrant additional review.

Technical Assistance Request: The inspectors did not enter either the TIA or technical

assistance request process. However, the inspectors contacted the cognizant branch in the

Office of Nuclear Reactor Regulation (NRR). Attempts to resolve whether the inconsistency in

the user instructions introduced a situation where the equipment cannot be used per its

instructions or invalidated the NIOSH certification were inconclusive. Consequently, the

inspectors could not determine whether the respiratory protection equipment was used as

certified by the NIOSH and required by 10 CFR 20.1703(a).

Corrective Action Reference: AR 4686286

Failure to Promptly Correct Degraded Pressure Switches in the Unit 1 and Unit 2 Main Steam

Line High Flow Isolation Logic System

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Initiating Events

Green

NCV 05000373,05000374/2024001-04

Open/Closed

None (NPP)

71152A

The inspectors identified a Green finding and associated non-cited violation of

10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, for the licensees failure to

promptly correct a condition adverse to quality associated with the Unit 1 and Unit 2 main

steam line (MSL) isolation logic system. Specifically, the licensee identified in a 2008

equipment apparent cause evaluation that pressure switches installed in the Unit 1 and Unit 2

MSL high-flow isolation logic trip systems were susceptible to multiple failure modes and had

been exposed to peak inductive currents during frequent calibration activities that may have

damaged switch contacts. A subsequent corrective action replaced half of the impacted

switches while the other half continued to be replaced on an as-needed basis.

Description:

On January 9, 2024, LaSalle County Station (LSCS) Unit 2 received a main steam line

isolation valve (MSIV) half-isolation signal from the A trip system during a scheduled MSL

high-flow isolation calibration activity. Troubleshooting performed by the licensee

subsequently identified a failed pressure switch in the MSL high-flow isolation logic that they

23

believe caused the spurious half-isolation signal.

There are four differential pressure switches connected to each of the four MSLs in the MSL

high-flow isolation logic system, for a total of 16 differential pressure switches per unit. Each

of the four pressure switches connected to a steam line input to a trip channel and there are

two trip channels in each trip system. A half-isolation signal with no associated MSIV closure

occurs when the relays in a single trip system drop out. Currently, the licensee uses pressure

switches manufactured by Static-O-Ring (SOR). Two SOR models are installed in the trip

channels including the 102 series that was installed starting in the 1980s. The licensee began

to replace the 102 series with the 131 series on an as-needed basis in 2005 due to internal

diaphragm failures, contact quality issues, and setpoint drift experienced with the 102 series.

The resident inspectors evaluated the maintenance history of the failed pressure switch and

concluded that it was a 102-series SOR switch and was 22 years old at the time of the

spurious Unit 2 half isolation. Further, the resident inspectors reviewed an equipment

apparent cause evaluation (EACE) from 2008 for a similar spurious MSIV half-isolation signal

that occurred on Unit 1 in the B trip system. The EACE notes that the half-isolation signal

was caused by a failed pressure switch. The EACE also notes that the faulty pressure switch

removed after the event presented with contacts that were severely arc damaged. It suggests

that observed damage was caused by peak inductive currents generated during the

calibration activity. In 2008, LaSalle technical specifications only required this calibration

activity every 2 years, though the licensee was performing it every 92 days to address

setpoint drift exhibited by 102 series switches as noted above. Thus, the EACE suggests that

the observed damage to switch contacts was caused by the accelerated frequency of the

pressure switch calibration activity.

The cited apparent cause listed in the 2008 EACE was the design of the MSL High Flow

Switchis susceptible to multiple failure modes. The basis associated with a subsequent

causal factor further notes that shortly after the 2008 half-isolation, only 8 of the 32 (16 per

unit) MSL pressure switches had been upgraded to 131 series and reflects that if the

replace as they fail philosophy were not employed, this event could have been avoided.

Corrective actions listed in the EACE included replacement of the failed defective flow switch

and implementation of a replacement schedule so that at least one string in each trip system

will be replaced in approximately 6 months. An action item to develop a test box was

further listed in the EACE that could be installed during the calibration activity and suppress

the inductive current experienced by the switch contacts.

The residents reviewed maintenance records associated with the MSL isolation high-flow

pressure switches and determined that all Unit 1 and Unit 2 pressure switches in the B1 and

B2 trip channels were replaced by May 2009 in response to the corrective actions noted

above. They reviewed calibration procedures and noted that the test box identified by

another corrective action was developed and implemented in May 2011 via test procedure

LIS-MS-102/202, Unit 1/Unit 2 Main Steam Line High Flow MSIV Isolation Calibration.

The resident inspectors note however, that at the time of the January 2024 Unit 2 MSIV

half-isolation, only 8 of the 16 Unit 1 and Unit 2 pressure switches on the A1 and A2 trip

channels had been upgraded to the 131-series model. In fact, switches in these trip channels

have a mean in-service age of 28 years. The resident inspectors have not identified

a corrective action assigned to the pressure switches in these trip channels, even those the

licensee concluded in the 2008 EACE that the half-isolation was caused by the multiple

failure modes of the SOR model 102 pressure switches and frequent calibration activities

24

without surge protection most likely induced degradation across the pressure switch contacts.

Instead, these switches have been replaced as needed based on quarterly calibration testing.

The inspectors also reviewed several other maintenance issues associated with the MSL

high-flow pressure switches that occurred between 2008 and 2024. In 2014, the licensee

identified that both the 102 and 131-series SOR switches were exhibiting an increasing trend

in diaphragm failures. Another EACE documented in 2016 logged a series of calibration

issues seen in both 102 and 131-series SOR switches. An action item resulting from that

EACE produced a project to replace SOR-manufactured switches with Rosemount

Transmitters and trip units. Although this project was originally planned to be implemented in

approximately 2018, the upgrade has been delayed until 2028. Currently, the licensee

maintains a quarterly calibration frequency and is replacing pressure switches with the

SOR 131-series model on an as-needed basis.

Corrective Actions: In response to the January 2024 half-isolation signal, the licensee

replaced the bad SOR 102-series switch with a SOR 131-series switch. They also performed

a failure analysis on the bad switch and determined that the half-isolation signal occurring in

2024 was most likely caused by a poor solder connection at the micro-switch.

In response to the inspectors observations, the licensee wrote corrective action AR 4761815

to evaluate Unit 1 and Unit 2 MSIV isolation pressure switches that have not been replaced

since May 2011 and generate work requests as needed.

Corrective Action References: ARs 4727857, 4730751, 844283, 2607807, and 4761815

Performance Assessment:

Performance Deficiency: The inspectors determined that the licensees failure to promptly

replace SOR pressure switches in the A1 and A2 MSL high-flow trip channels that were

exposed to potential degradation across contacts is a performance deficiency. Specifically, a

2008 EACE evaluated a spurious MSIV half-isolation similar to the isolation that occurred in

January 2024 and cited the known multiple failure modes associated with the switches as an

apparent cause of the 2008 half-isolation. It also identified that the switch contacts had been

exposed on multiple occasions to peak inductive currents, potentially causing degradation

to those contacts. A corrective action to replace half the impacted switches was identified

and implemented at the time. The remainder of the switches have been replaced on an

as-needed schedule. To date, seven pressure switches on the Unit 1 and Unit 2 MSLs have

not been replaced.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Equipment Performance attribute of the Initiating Events

cornerstone and adversely affected the cornerstone objective to limit the likelihood of events

that upset plant stability and challenge critical safety functions during shutdown as well as

power operations. Specifically, the licensees failure to replace SOR pressure switches in the

A1 and A2 MSL high-flow trip channels after identifying that the switches were susceptible

to multiple failure modes and had been exposed to peak inductive currents increased the

potential for a spurious MSL isolation and reactor scram. Unit 1 is currently operating with five

pressure switches which were subjected to the noted degradation mechanism and Unit 2 is

currently operating with two such switches.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The

25

finding screened as Green, or very low safety significance, because the inspectors answered

No to Exhibit 1, Section B questions. To date, no full MSIV isolation/reactor trip has been

attributed to faulty pressure switches at LaSalle.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to

this finding because the inspectors determined the finding did not reflect present licensee

performance.

Enforcement:

Violation: 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, states that

measures shall be established to assure that conditions adverse to quality, such as failures,

malfunctions, deficiencies, deviations, defective material and equipment, and

nonconformances are promptly identified and corrected.

Contrary to the above, as of April 17, 2024, the licensee failed to establish measures to

assure that conditions adverse to quality are promptly corrected. Specifically, the licensee

failed to correct pressure switches installed in the Unit 1 and Unit 2 MSL high-flow isolation

logic trip systems that are susceptible to multiple failure modes and have been exposed to

peak inductive currents during frequent calibration activities that may have damaged the

switch contacts. The licensee replaced all switches in the B1 and B2 trip channels while

switches in the A1 and A2 trip systems have been replaced on an as-needed basis.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On April 17, 2024, the inspectors presented the integrated inspection results to

Christopher Smith, Plant Manager, and other members of the licensee staff.

On March 1, 2024, the inspectors presented the radiation protection inspection results to

John VanFleet, Site Vice President, and other members of the licensee staff.

On March 1, 2024, the inspectors presented the inservice inspection results to

John VanFleet, Site Vice President, and other members of the licensee staff.

26

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

M-96, Sheet 1

P&ID Residual Heat Removal System (RHRS)

BC

Drawings

M-96, Sheet 4

P&ID Residual Heat Removal System (RHRS)

AH

71111.04

Procedures

LOS-RH-Q1

RHR (LPCI) and RHR Service Water Pump and

Valve Inservice Test for Modes 1, 2, 3, 4, and 5

101

FZ 2K

Rx Bldg. 687'-0" to 768'-0" Elev. U1 Steam Tunnel

71111.05

Fire Plans

FZ 3I4

Rx Bldg. 673'-4" Elev. U2 LPCS/RCIC Pump Cubicle

2

71111.06

Engineering

Changes

EC-640690

Evaluate Plugging Floor Drains to Support Maintenance in the

Replacing of the U1 L1R20 250V Batteries (1DC01E)

02/08/2024

L1R20-VEN-002

Ultrasonic Examination of RPV Recirculation Outlet Nozzle

IR 1-NIR-10

02/24/2024

L1R20-VEN-004

Ultrasonic Examination of RPV Core Spray Nozzle

IR 1-NIR-16

02/25/2024

L1R20-VEN-020

Ultrasonic Examination of RPV Bottom Head Meridional Weld

GEL-1006-DB

02/27/2024

L1R20-VEN-021

Ultrasonic Examination of RPV Bottom Head Meridional Weld

GEL-1006-DC

02/27/2024

L1R20-VEN-022

Ultrasonic Examination of RPV Bottom Head Meridional Weld

GEL-1006-DD

02/27/2024

L1R20-VT-004

Visual Examination of MS Restraint MS01-1352X

02/21/2024

NDE Reports

L1R20-VT-015

Visual Examination of RHR Constant Support RH40-1004C

02/23/2024

GEH-PDI-UT-1

PDI Generic Procedure for the Ultrasonic Examination of

Ferritic Welds

12.1

GEH-PDI-UT-2

PDI Generic Procedure for the Ultrasonic Examination of

Austenitic Pipe Welds

13

GEH-UT-300

Procedure for the Manual Ultrasonic Examination of Reactor

Vessel Assembly Welds IAW PDI

14

Procedures

GEH-UT-311

Procedure for Manual Ultrasonic Examination of Nozzle Inner

Radius, Bore, and Selected Nozzle to Vessel Regions

20

71111.08G

Work Orders

WO 5235786

Unit 1 RHR HX Weld 1RH-HX1B-9A Repair

03/04/2022

LGP-1-1

Normal Unit Startup

134

NF-AB-720-F-1

L1C21 Startup Sequence

02

71111.11Q

Procedures

OP-AB-300-1003

L1C21 BOC Startup ReMA

20

27

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 4691511

1B RR Seal Pressure and Temperature Fluctuations

0

AR 4713949

1A RR Seal Pressure and Temperature Fluctuations

0

AR 4725603

LAS Named in 10CFR Part 21 Notification from

Valcor Eng Co.

12/27/2023

AR 4734732

Metal Shavings Discovered during 2B DG Top Deck

Inspection

01/23/2024

Corrective Action

Documents

AR 4752108

GGJ319 GNF Water Rod Inspection Not Complete

02/21/2004

71111.15

Work Orders

WO 8003976-fa

Failure Analysis of Woodward EGR Actuator

0

71111.20

Work Orders

WO 5440449

L1R20 Water Rod Inspections

02/22/2024

L-003089

Seismic Qualification of Velan 3" Class 900 MO Gate Valves

for Use in Applications 1(2)B21-F016, 19

1

Calculations

LAS-2B21-F016

MIDACALC MOV Datasheet

13

AR 4752062

1AP04E-13 Will Not Close - 1A RR LFMG BKR 1A

02/21/2024

Corrective Action

Documents

AR 4755468

HYDRO Test Issues

03/04/2024

AR 4753350

NRC ID Questions on Valve Backseating Activity

02/26/2024

AR 4754319

NRC ID ASME OM Code Potential Finding/Violation

02/29/2024

AR 4754320

NRC ID Use of Backseating Tool Potential Finding/Violation

02/29/2024

AR 4760314

NRC-Identified IR for WO 5403063

03/22/2024

Corrective Action

Documents

Resulting from

Inspection

AR 4761643

Work Order 05443427-01 Amendment

03/27/2024

Engineering

Changes

EC-461530

Evaluate Electrically Backseating 2B21-F016 Remotely from

Motor Control Center Using MOV Backseat Relay Tool

2

IST-LAS-BDOC-

V-14

IST Basis Document for 2B21-F016

03/01/2019

IST-LAS-PLAN

Inservice Testing Program Plan Fourth Ten-Year Interval

0

NO-AA-10

Quality Assurance Topical Report

98

TM201602-AC

MOV Backseat Relay for AC Motors Users Manual

13

TM201602-AC

MOV Backseat Relay for AC Motors Users Manual

9

Miscellaneous

TP201602-03

MOV Backseat Relay Model 201602-AC Functional Test and

Calibration

1

LIS-MS-202

Unit 2 Main Steam Line High Flow MSIV Isolation Calibration

27

LOS-DG-109

Unit 1 Integrated Division 1 Response Time Surveillance

30

LOS-NB-R1

U1 Reactor Vessel Leakage Test

34

71111.24

Procedures

MA-AA-716-012

Post Maintenance Testing

28

28

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

MA-AA-716-040

Control of Portable Measurement and Test Equipment

Program

16

MA-AA-723-304

Electrical Backseating Motor-Operated Valves Remotely from

a Motor Control Center - Current Cut-Off Method

0

WO 5199997

IST Comprehensive Pump Test for 2E22-C002

03/18/2024

WO 5241707

Div 1 Integrated Divisional Response Time Test

02/22/2024

WO 5241753

ASME XI ISI of Class I Components and Associated Piping

VT-2

03/05/2024

WO 5403063

IM LIS-MS-202 U2 MSL High Flow MSIV Isolation Cal

01/11/2024

WO 5426168

WO Needed to Perform LEP-DC-01 for 1DC 14E Cell 56

01/29/2024

WO 5428846

LOS-SC-Q1 U2 B SBLC Pump Quarterly

03/15/2024

WO 5443427

U2 Drywell Leakage Has Increased

01/25/2024

Work Orders

WO 5486878

2A Diesel Generator Idle Start

03/15/2024

71114.06

Work Orders

WO 5397549

1A DG Fast Start

03/29/2024

LA-01-24-00502

Refueling Outage: Drywell Radiation Protection Dept.

Activities

30

LA-01-24-00513

L1R20 Control Rod Drive (CRD)/Undervessel Activities

30

ALARA Plans

LA-01-24-00601

L2R20 RB RWCU System Maintenance Activities

30

Corrective Action

Documents

AR 4751872

APS: Unexpected Dose (WO 5236584-04)

02/20/2024

AR 4754030

NRC Observations of Radiological Activities

02/28/2024

Corrective Action

Documents

Resulting from

Inspection

AR 4754485

NRC Observations

02/29/2024

Miscellaneous

LA-01-24-00601

TEDE ALARA Evaluation Screening Worksheet for

L1R20 RB RWCU System Maintenance Activities 500k G/A,

40 dpm alpha

01/31/2024

RP-AA-302

Determination of Alpha Levels and Monitoring

12

RP-AA-410

Refueling Outage DW Under Vessel CRD Preps/Exchange

Protective Clothing Matrix

Procedures

RP-AA-460-001

Controls for Very High Radiation Areas

8

LA-01-24-00903

L1R20 RFF Cavity Platform IVVI and Associated Activities

04/19/2023

71124.01

Radiation Work

Permits (RWPs)

LA-010-24-00601

L1R20 RB Reactor Water Clean Up System Maintenance

00

71124.08

Shipping Records

Shipment LM24-

Control Rod Drive Boxes

02/29/2024

29

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

003

AR 4545235

RM - U1 Chemistry Sampling Indicates Potential Fuel Defect

12/28/2022

71151

Corrective Action

Documents

AR 4564119

U1 Tertiary Oil Addition Troubleshooting

03/22/2023

AR 2607807

EACE for Critical Component Failure of 2E31-N011D

01/05/2016

AR 4727857

Spurious U2 A1 MSIV Isol Trip

01/09/2024

AR 4730751

UMCRA: 2H13-P601-F504 CHAN A1/A2 MSIV ISOL Trip

01/12/2024

Corrective Action

Documents

AR 844283844283Unexpected Group 1 MSIV Half-Isolation Signal

11/12/2008

Corrective Action

Documents

Resulting from

Inspection

AR 4761815

NRC ID - MSL Flow Switch Degradation Not Addressed

03/28/2024

Drawings

1E-2-4232AB

Schematic Diagram Primary Containment & Reactor Vessel

Isolation System PC (B21H) Part 2

AB

71152A

Engineering

Changes

EC 348598

SOR Model Replacement/Alternative Solution

03/16/2010

71153

Miscellaneous

Licensee Event

Report

05000374/2023-

003-00

Automatic Actuation of Reactor Protection System (RPS)

05/02/2023