IR 05000373/2023004

From kanterella
Jump to navigation Jump to search
County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004
ML24024A126
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 01/24/2024
From: Robert Ruiz
NRC/RGN-III/DORS/RPB1
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2023004
Download: ML24024A126 (1)


Text

SUBJECT:

LASALLE COUNTY STATION - INTEGRATED INSPECTION REPORT 05000373/2023004 AND 05000374/2023004

Dear David Rhoades:

On December 31, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at LaSalle County Station. On January 17, 2024, the NRC inspectors discussed the results of this inspection with John VanFleet, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 05000373 and 05000374 License Nos. NPF-11 and NPF-18

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000373 and 05000374

License Numbers:

NPF-11 and NPF-18

Report Numbers:

05000373/2023004 and 05000374/2023004

Enterprise Identifier:

I-2023-004-0052

Licensee:

Constellation Nuclear

Facility:

LaSalle County Station

Location:

Marseilles, IL

Inspection Dates:

October 01, 2023, to December 31, 2023

Inspectors:

J. Benjamin, Senior Resident Inspector

N. Cuevas, Resident Inspector

J. Kutlesa, Emergency Preparedness Inspector

J. Meszaros, Resident Inspector

J. Nance, Operations Engineer

G. Roach, Senior Operations Engineer

N. Shah, Senior Project Engineer

R. Zuffa, Illinois Emergency Management Agency

Approved By:

Robert Ruiz, Chief

Reactor Projects Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at LaSalle County Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000374/2021-002-02 LER 2021-002-02 for LaSalle County Station,

Unit 2, Supplement to Reactor Protection System Half Scram Due to Motor Generator Set Output Breaker Trip 71153 Closed LER 05000373,05000374/2022-004-00 LER 2022-004-00 for LaSalle County Station,

Units 1 and 2, Both Trains of Main Control Room and Auxiliary Electric Room HVAC Declared Inoperable Due to Compressor Trips 71153 Closed LER 05000374/2023-001-00 LER 2023-001-00 for LaSalle County Station,

Unit 2 - Standby Liquid Control Valve Inoperable Due to Failed Motor Starter Contactor 71153 Closed

PLANT STATUS

Unit 1 Unit 1 began the inspection period and operated at rated thermal power with the following exceptions:

  • On October 14, 2023, the unit was down powered to approximately 87 percent for planned plant main turbine valve testing. The unit returned to full power later that day.
  • On November 18, 2023, the unit was down powered to approximately 73 percent for a planned control rod pattern adjustment. The unit returned to full power on November 19, 2023.
  • On December 9, 2023, the unit was down powered to approximately 74 percent for planned main turbine valve testing. The unit returned to full power on December 10, 2023.
  • On December 28, 2023, the unit was down powered to approximately 76 percent for a planned control rod pattern adjustment. The unit returned to full power on December 16, 2023.

Unit 2 Unit 2 began the inspection period and operated at rated thermal power with the following exceptions:

  • On October 31, 2023, the unit was down powered to approximately 90 percent for an unplanned advance nuclear dispatch request. The unit returned to full power later that day.
  • On November 20, 2023, the unit was down powered to approximately 82 percent for an unplanned advance nuclear dispatch request. The unit returned to full power later that day.
  • On December 15, 2023, the unit was down powered to approximately 60 percent for planned main turbine valve testing and control rod sequence exchange. The unit was returned to full power on December 16,

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

(1)common Unit 0B diesel following testing restoration on October 3, 2023

(2) Unit 2 control rod drive hydraulic control units on October 3, 2023

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the Unit 2 reactor core isolation cooling system configuration during a complete system walkdown inspection from October 20 through November 10, 2023.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone 8C5, diesel generator building, elevation 674' 0", Unit 2 division 1 residual heat removal pump room on October 5, 2023
(2) Fire Zone 4D2, Unit 2 auxiliary building cable spreading room on December 18, 2023
(3) Fire Zone 4D1, Unit 1 auxiliary building cable spreading room on December 18, 2023
(4) Fire Zone 7C2, diesel generator building, elevation 674'-0", Unit 1 division 2 diesel fuel tank room on December 29, 2023

Fire Brigade Drill Performance Sample (IP Section 03.02) (2 Samples)

(1) The inspectors evaluated the onsite fire brigade training and performance during an unannounced fire drill on October 26, 2023.
(2) The inspectors evaluated the onsite fire brigade training and performance during an unannounced fire drill on December 18, 2023.

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Unit 1 high pressure core spray 1B emergency diesel generator cooler

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered between October 11, 2023, and November 17, 2023.

71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)

(1) Biennial Requalification Written Examinations The inspectors evaluated the quality of the licensed operator biennial requalification written examination administered on October 21, 2023.

Annual Requalification Operating Tests The inspectors evaluated the adequacy of the facility licensees annual requalification operating test.

Administration of an Annual Requalification Operating Test The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.

Requalification Examination Security The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised.

Remedial Training and Re-examinations The inspectors evaluated the effectiveness of remedial training conducted by the licensee, and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.

Operator License Conditions The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.

Control Room Simulator The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (2 Samples)

(1) The inspectors observed and evaluated licensed operator performance in the control room during Unit 1 down power and rod sequence exchange on October 14, 2023.
(2) The inspectors observed and evaluated licensed operator performance in the control room during dispatch request for 100 MWe load shed on October 31, 2023. Unit 2 down power to approximately 92 percent from full power.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator requalification classroom training Fukushima/Chernobyl lessons learned on October 25, 2023.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) B diesel driven fire pump prolonged out of service period
(2) Unit 2 reactor core isolation cooling (RCIC) manual controller not functional

Quality Control (IP Section 03.02) (1 Sample)

Quality control verifications are properly specified in accordance with the Quality Assurance Program and are implemented as specified for the following work activities.

(1) Work Order (WO) 5237886, Unit 2 Reactor Bottom Head Drain Replacement Activities WO 5127978, 2B33-F067A Pre-weld Activities WO 5042338, 2RH03CB-12 Weld Pipe to Valve Activities

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)planned Green online risk during Unit 1 RCIC work window from October 10, 2023, through October 12, 2023

(2) Unit 1 Green risk, RCIC available with main control room controller out of service for maintenance on December 11, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (7 Samples 2 Partials)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1)

(Partial)2CM023B operability as a primary containment isolation valve and associated containment monitoring channel operability given continued indication and manufacturing issues (2)standby gas treatment vent stack operability determination due to inability to verify loop seal is filled on October 3, 2023, as described in Action Request (AR) 4694775

(3) AR 4707251, Unit 1 Turbine Stop Valve Limit Switches Incorrect Model Installed (4)reactor protection system average power range monitor channel operability with multiple local power range monitor in bypass on October 17, 2023 (5)bulk suppression pool water temperature post-accident monitoring indication operability as described in AR 4711127 (6)

(Partial)

Unit 2 RCIC issues with manual control

(7) AR 4720521, Unit 1 Turbine Bypass Valve Failed to Fast Open During Test
(8) AR 4710153, Unit 1 1B Emergency Diesel Generator Governor Oil Leak
(9) A supply air filter unit failed damper in the auxiliary electrical equipment rooms ventilation system as described in AR 4719870, 0VE07YA Found Failed Open

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Engineering Change 396748, Upgrade U1/U2 Main Control Room Leak Detection Recorders

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (5 Samples)

(1) Unit 1 reactor core isolation cooling trip throttle valve 1E51-F360 PMT and actuator diagnostic testing on October 12, 2023 (2)upgrade Unit 2 main control room leak detection recorders, 2E31-R002B
(3) Unit 1B reactor recirculation hydraulic power loop, subloop 2 PMT following solenoid replacement on October 17, 2023
(4) Unit 1 division 3 125 Vdc circuit after battery replacement on October 26, 2023 (5)common B diesel fire pump after engine block replacement on October 25, 2023

Surveillance Testing (IP Section 03.01) (3 Samples)

(1) Unit 2B emergency diesel generator fast start 24-hour run on October 23, 2023
(2) Unit 2B emergency diesel generator response time testing per LOS-DG-2111 on December 20, 2023
(3) Unit 2B emergency diesel generator start and load acceptance surveillance per LOS-DG-203 on December 19, 2023

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) Unit 2 high pressure core spray system operability and inservice test on November 21, 2023

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated the following maintenance and testing of the alert and notification system:
  • annual siren inspection and maintenance records for the period of September 2021 to September 2023
  • weekly alert notification system (siren) tests for the period of September 2021 to September 2023

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of the emergency preparedness organization.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.

§50.54(q) PROGRAM EVALUATION/ASSESSMENT REVIEW: Emergency Action Levels for LaSalle Station: EP-AA-1005 Addendum 3, Revision 9; Evaluation No.: 22-06

  • EP-AA-1005 Addendum 1, Lasalle Station On-Shift Staffing Technical Basis, Revision 2
  • EP-AA-1005, Addendum 2, Evacuation Time Estimates for Lasalle County Generating Station Plume Exposure Pathway Emergency Planning Zone, Revision 1
  • EP-AA-1005 Addendum 3, Emergency Action Levels for Lasalle Station, Revision 8
  • EP-AA-1005 Addendum 3, Emergency Action Levels for Lasalle Station, Revision 9
  • EP-AA-1005, Radiological Emergency Plan Annex for Lasalle Station, Revision 41 This evaluation does not constitute NRC approval.

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program.

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)

(1) Unit 1 (October 1, 2022, through September 30, 2023)
(2) Unit 2 (October 1, 2022, through September 30, 2023)

MS08: Heat Removal Systems (IP Section 02.07) (2 Samples)

(1) Unit 1 (October 1, 2022, through September 30, 2023)
(2) Unit 2 (October 1, 2022, through September 30, 2023)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 (October 1, 2022, through September 30, 2023)
(2) Unit 2 (October 1, 2022, through September 30, 2023)

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) July 1, 2022, through June 30, 2023 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) July 1, 2022, through June 30, 2023 EP03: Alert And Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
(1) July 1, 2022, through June 30, 2023

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)follow up of licensee actions to address issues identified during NRC review of mitigating system performance indicator (MSPI) data submittals

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action backlog for potential adverse trends that might be indicative of a more significant safety issue.

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000373, 05000374/2022-004-00, Both Trains of Main Control Room and Auxiliary Electric Room HVAC Declared Inoperable Due to Compressor Trips (ADAMS Accession No. ML22362A015). The inspectors determined that the cause of the condition described in the LER was not reasonably within the licensees ability to foresee and correct, and therefore was not reasonably preventable. No performance deficiency nor violation of NRC requirements was identified. This LER is closed.
(2) LER 05000374/2023-001-00, Standby Liquid Control Valve Inoperable Due to Failed Motor Starter Contactor (ADAMS Accession No. ML23107A190). The inspectors determined that the cause of the condition described in the LER was not reasonably within the licensees ability to foresee and correct, and therefore was not reasonably preventable. No performance deficiency nor violation of NRC requirements was identified. This LER is closed.
(3) LER 05000374/2021-002-02, Supplement to Reactor Protection System Half Scram Due to Motor Generator Set Output Breaker Trip (ADAMS Accession No. ML23145A012). The inspectors determined that the cause of the condition described in the LER was not reasonably within the licensees ability to foresee and correct, and therefore was not reasonably preventable. No performance deficiency nor violation of NRC requirements was identified. This LER is closed.

Personnel Performance (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees performance on December 29, 2023, following a trip of the Unit 1 1A circulating water pump which resulted in an unplanned down power.

INSPECTION RESULTS

Minor Violation 71152A Evaluation of Licensee Actions to Address Issues Identified During NRC Review of Mitigating System Performance Indicator (MSPI) Submittals Minor Violation: The inspectors reviewed licensee MSPI submittals for the period from September 2022 until August 2023, for the following systems:

Specifically, the inspectors reviewed the hours charged against the MSPI for the above systems in the licensee submittal documents against the inoperability and unavailability periods documented in the operator logs for the same period.

The inspectors identified several periods of unavailability for the above systems documented in the operator logs that were not included in the MSPI data submittal sheets. While most of these periods were relatively small, typically <5 hours each occurrence, there were two periods where about 61 and 62 hours7.175926e-4 days <br />0.0172 hours <br />1.025132e-4 weeks <br />2.3591e-5 months <br /> of unavailability respectively, for the Unit 1 EAC, were documented in the operator logs but were not recorded in the data sheets. Although the cause was still being investigated, it appeared that inexperience among the licensee engineering staff involved in the review and the need for additional guidance regarding when a component is considered unavailable per the licensees risk management process should also be counted as unavailable for the MSPI, were contributing causes. These issues were being tracked in the CAP as ARs 4705411 and 4718222.

As documented in the ARs, the licensee was planning to amend the affected data sheets and had verified that the additional hours did not change the status of the MSPI. The licensee was also performing an evaluation to understand the cause of the discrepancies and an extent-of-condition review for the above MSPI systems to identify any other missed unavailability time. The licensee planned to resubmit the revised MSPI data sheets to the NRC.

Screening: The inspectors determined the performance deficiency was minor. Although the MSPI data was submitted to the NRC under 10 CFR 50.9 as part of the regulatory oversight process, the failure to submit an accurate accounting was considered a minor violation, as the MSPI would not have changed color. The inspectors concluded that the licensee was taking appropriate action to address the issue.

Enforcement:

This failure to submit accurate information to the NRC as required by 10 CFR 50.9 constitutes a minor violation that is not subject to enforcement action in accordance with the NRCs Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 17, 2024, the inspectors presented the integrated inspection results to John VanFleet, Site Vice President, and other members of the licensee staff.
  • On October 20, 2023, the inspectors presented the licensed operator biennial requalification program inspection results to Christopher Smith, Plant Manager, and other members of the licensee staff.
  • On October 20, 2023, the inspectors presented the emergency preparedness inspection results to Christopher Smith, Plant Manager, and other members of the licensee staff.
  • On December 20, 2023, the inspectors presented the emergency action level and emergency plan changes inspection results to Melissa Frantzen, Emergency Preparedness Coordinator, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 4458963

U2 RCIC Pump Oil Leak

11/05/2021

AR 4556910

Unable to Isolate 2E51-B010

2/24/2023

AR 4559266

U2 Rod 10-35 Scram Time Trace Took 3

Attempts to Receive

03/04/2023

AR 4561879

RCIC Suction Valve IST Testing Issue

03/14/2023

Corrective Action

Documents

AR 4704224

LOS-RI-Q5 Complete with Portions UNSAT

09/22/2023

Drawings

M-146

P&ID Control Rod Drive Hydraulic Piping System

AF

71111.04

Work Orders

WO 5345658

Scram Times / 10% of Rods/Every 120 Days of

Oper (>800 psi) / PMT

09/17/2023

Corrective Action

Documents

AR 4553249

Smoke from MAF Ceiling Tiles

2/07/2024

Fire Plans

FZ 7C2

DG Bldg. 674'-0" Elev. U1 Division 2 Diesel Fuel

Tank Room

71111.05

Miscellaneous

FPR

LaSalle Fire Protection Report

71111.11A

Procedures

TQ-AA-150-F25

23 LaSalle LORT Annual Exam Status Report

11/27/2023

AR 4559305

Unit 2 Received an Automatic Scram Signal on

Low Charging Water Pressure

03/04/2023

AR 4690126

4.0 Critique From 1/2 Scram On B RPS

07/20/2023

Corrective Action

Documents

AR 4698083

NOS ID: Inconsistent Labeling for Reg Guide 1.97

Instruments

08/23/2023

373690

23 LORT NRC Exam Week 2 (RO) Crew D

10/20/2023

373697

23 LORT NRC Exam Week 2 (SRO) Crew D

10/20/2023

A-SRO-100

Administrative Job Performance Measure

ESG 111

Simulator Dynamic Scenario

ESG 127

Simulator Dynamic Scenario

ESG 59

Simulator Dynamic Scenario

ESG 6

Simulator Dynamic Scenario

LORT Long Range Training

Plan

22

71111.11B

Miscellaneous

LORT Long Range Training

Plan

23

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

P-AN-01

In-Plant Job Performance Measure

P-FX-03

In-Plant Job Performance Measure

P-NB-03

In-Plant Job Performance Measure

P-RH-02

In-Plant Job Performance Measure

P-SC-01

In-Plant Job Performance Measure

S-RH-25

Simulator Job Performance Measure

S-RI-15

Simulator Job Performance Measure

S-RP-04

Simulator Job Performance Measure

S-VR-03

Simulator Job Performance Measure

Simulator Core Testing

(Various)

LaSalle 1 Cycle 20

11/03/2022

Simulator Scenario Based

Testing

21-1 ILT NRC Exam Scenario 2

01/26/2023

Simulator Scenario Based

Training

ESG 128 (LORT)

07/14/2022

Simulator Steady State Test

100% Power

10/18/2022

Simulator Steady State Test

75% Power

10/18/2022

Simulator Steady State Test

46% Power

10/18/2022

Simulator Transient Test -

Transient 10

Simultaneous Closure of All MSIVs, One Open

Safety Relief Valve, No High-Pressure Core

Spray (HPCS)

10/18/2022

Simulator Transient Test -

Transient 2

Simultaneous Trip of All Feedwater Pumps

10/18/2022

Simulator Transient Test -

Transient 3

Simultaneous Closure of All Main Steam Isolation

Valves (MSIVs)

10/18/2022

Simulator Transient Test -

Transient 5

Single Recirculation Pump Trip (A)

10/18/2022

Simulator Transient Test -

Transient 6

Main Turbine Trip (Max Power without Scram)

10/18/2022

Simulator Transient Test -

Transient 8

Maximum Size Reactor Coolant System (RCS)

Rupture with Loss of Offsite Power (LOOP)

10/18/2022

TQ-AA-150-F03A

JPM Evaluation Results Form A - Overall

Walkthrough Grade Pass with Remediation

(S-RH-25)

10/13/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

TQ-AA-224-F100

Remedial Training Notification and Action on

Failure - 2022 LORT Annual Off Year Exam A:

RO

09/28/2022

TQ-AA-224-F100

Remedial Training Notification and Action on

Failure - LORT Cycle 23-4 OBE 3

07/27/2023

TQ-AA-306-F-02

Simulator Review Board Minutes

06/17/2022

TQ-AA-306-F-02

Simulator Review Board Minutes

11/29/2022

TQ-AA-306-F-02

Simulator Review Board Minutes

05/24/2023

Procedures

TQ-AA-150

Operator Training Programs

AR 4669516

Pre-NRC 71111.11 Licensed Operator

Requalification Program and Licensed Operator

Performance

06/09/2023

Self-

Assessments

AR 4689875

NOSA-LAS-23-05; Training and Staffing Audit

Report

08/30/2023

SWR 136748

Modification - EC 632377 Unit 1 Reactor

Recirculation High Oil Level Setpoint Change

2/09/2021

SWR 137615

Modification - EC 632741 LaSalle Unit 1 Cycle 20

(L1C20) GNF3 Fuel

03/07/2022

SWR 137751

Reactor Water Cleanup Isolation at Low Pressure

06/01/2022

SWR 137786

B1 Manual Scram Button Causes Half Scram

Without Being Armed

06/22/2022

SWR 137810

Rod Block Monitoring Channel A Not Reading

Correctly on 1C51-R603C

06/29/2022

SWR 137948

Turbine Failure to Trip

09/12/2022

SWR 138240

Control Rod Drive / Reactor Vessel Temperatures

Recorder

03/07/2023

SWR 138280

SRM D Does Not Work, Multiple SRM / IRM

Pushbutton Indications Out

03/24/2023

SWR 138481

1H13-P632 and 1H13-P642 Recorders Powered

from the Incorrect Source

06/29/2023

SWR 138557

Modification - EC 638128 1A Circulating Water

Motor Replacement

08/17/2023

Work Orders

SWR 138597

Modification - EC 638267 Unit 1 Behind the Meter

08/30/2023

71111.11Q

Corrective Action AR 4709787

4.0 Critique for U1 October Load Drop

10/14/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

HU-AA-1211-F-02

L1C20-15 October Load Drop HLA Briefing

Package

Miscellaneous

OP-AB-300-1003

L1C20 October 2023 Rod Pattern Adjustment

Reactivity Maneuver

10/12/2023

LGP-3-1

Power Changes

Procedures

OP-LA-102-1001

LaSalle Response to Request for Load Following

Corrective Action

Documents

AR 4553284

Cracks in Tops of Unit 1 Div 3 Battery Cells

2/08/2023

71111.13

Engineering

Evaluations

357017

Evaluation of Crack in the Cell 56 Cover of Div. 3

25 VDC Battery (2DC18E) On Its Ability to

Perform Its Design Function

09/02/2005

AR 4500310

RM - Unit 1 LPRM 16-57C Erratic

05/17/2022

AR 4682422

2CM023B Fuse Blown

06/03/2023

AR 4690573

CID 46425-1 Stem Travel & Limit Switch Issues

07/14/2023

AR 4699490

RM U1 LPRM Downscale Alarm 16-49C

08/30/2023

AR 4699774

RM U1 LPRM Downscale Alarm 16-57A

08/31/2023

AR 4701392

RM U1 LPRM 48-09A Bypassed Due to

Downscale

09/09/2023

AR 4701393

RM U1 LPRM 56-17A Bypassed Due to

Downscale

09/09/2023

AR 4707529

Valcor Corp Reports 2CM023B SR Valve Cv Not

Per Design

10/06/2023

AR 4709251

RM U1 LPRM Downscale Alarm 08-49A

10/13/2023

AR 4711127

1TE-CM057R Element B Reading High

10/20/2023

Corrective Action

Documents

AR 4719870

0VE07YA Found Failed Open

11/27/2023

2E118A, Sheet 2

IED - Neutron Monitoring System

M-105

P & ID Auxiliary Building Floor Drains

X

M-106

P & ID Diesel, Auxiliary, Turbine & Service

Building Floor Drains

AB

M-1443

P & ID Auxiliary Electrical Equipment Rooms

Airconditioning System

Q

71111.15

Drawings

M-153

P & ID Process Radiation Monitoring System

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

M-156, Sheet 3

P& ID Containment Monitoring System

AG

M-89

P & ID Standby Gas Treatment

AG

M-92

P & ID Primary Containment Vent & Purge

AU

Miscellaneous

WC-AA-111-F-01

Partial LOS-CM-M1 U1 Cont. Monitoring

Inst Att 1A

10/20/2023

LOP-CS-02

Tracking and Authorization of Controlled

Openings in the Secondary Containment

LOP-VG-01

Preparation for Standby Operation if the Standby

Gas Treatment System

LOS-CM-M1

Monthly Accident Monitoring Instrumentation

Channel Check

LOS-VG-M1

Standby Gas Treatment System Operability and

Inservice Test

Procedures

MA-AA-716-010-1103

Leak Classification Table

WO 5342532

EWP Troubleshoot 2CM023B No Open Indication

11/03/2023

Work Orders

WO 5396392

LIS-PC-207B U2 Div 2 Post Acc O2/H2 Cal & Botl

Rpl

2/14/2023

L-0030904

Seismic Evaluation for Yokogawa DX Advanced

Series Recorders and Seismic Mounting Evolution

in Control Room Panels

Calculations

L-003997

Seismic Mounting Adequacy of Non-Safety

Related Yokogawa DX Advanced Series

Recorders

07/08/2021

71111.18

Engineering

Changes

EC 396748

Upgrade U1/U2 MCR Leak Detection Recorders

(Obsolescence)

2/20/2017

AR 4712627

LOS-DC-Q2 Att. B, Complete with Portions

UNSAT

10/26/2023

AR 4712783

B DFP Pressure Switch Not in Expected State

10/26/2023

AR 4713327

B Diesel Fire Pump Over Pressurized

10/28/2023

Corrective Action

Documents

AR 4725010

4.0 Critique for LOS-DG-203 and LOS-DG-211

Procedures

LES-FP-31

Fire Pump Controller Logic Test

WO 1931878-02

Upgrade U2 Main Control Room Leak Detection

Recorders - 2E31-R002B

08/17/2023

71111.24

Work Orders

WO 5005796

EM Replace Unit 1 Division 3 125V Battery

10/26/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

(1DC18E)

WO 5005796-21

PMT Replace Unit 1 Division 3 125V Battery

(1DC18E)

10/26/2023

WO 5043631

Diesel Generator 2B Start and Load Acceptance

Surveillance

2/19/2023

WO 5044788-03

OPS PMT: 1E51-F360 Functions Properly

10/12/2023

WO 5044788-05

EQ Inspection and As Found / Left Test

1E51-F360 Turbine Trip / Throttle Valve

10/12/2023

WO 5150884

2B Diesel Generator 24-hour Run Surv Per

LOS-DG-R2B

10/24/2023

WO 5384238

HPCS Pump Flow and Discharge Pressure

Timing

11/22/2023

WO 5408383

LOA-RR-101 Entry Due to Stuck 2B RR FCV

10/17/2023

AR 4475308

EP - Multiple Siren Activations During Monthly

Siren Test

2/01/2022

EN 55723

Inadvertent Siren Actuation

2/01/2022

Miscellaneous

N/A

LaSalle Semi Annual Siren Preventive

Maintenance Report

09/01/2021

to

09/20/2023

EP-AA-1005, Addendum 2

Evacuation Time Estimates for LaSalle County

Generating Station Plume Exposure Pathway

Emergency Planning Zone

71114.02

Procedures

N/A

Siren Operations Manual

08/01/2022

Calculations

OP-LA-101-111-1001

On-Shift Staffing Requirements

ERO Augmentation Memo

Call in Drill Reports: 1st, 2nd, 3rd, 4th Quarters

22; 1st, 2nd, 3rd Quarters 2023

Various

Miscellaneous

LMS

EP Staff Training and Qualification Records:

Samples

Various

EP-AA-1000

Standardized Radiological Emergency Plan

EP-AA-112

Emergency Response Organization

(ERO)/Emergency Response Facility (ERF)

Activations and Operation

71114.03

Procedures

TQ-AA-113

ERO Training and Qualification

71114.04

Calculations

§50.54(q) PROGRAM

Emergency Action Levels for LaSalle Station:

03/23/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EVALUATION/ASSESSMENT

REVIEW: 22-06

EP-AA-1005 Addendum 3, Revision 9; Evaluation

No.: 22-06

EP-AA-1005

Radiological Emergency Plan Annex for Lasalle

Station

EP-AA-1005, Addendum 1

Lasalle Station On-Shift Staffing Technical Basis

EP-AA-1005, Addendum 2

Evacuation Time Estimates for Lasalle County

Generating Station Plume Exposure Pathway

Emergency Planning Zone

EP-AA-1005, Addendum 3

Emergency Action Levels for Lasalle Station

Procedures

EP-AA-1005, Addendum 3

Emergency Action Levels for Lasalle Station

AR 4493176

Clarify ALT Facility Inventory for Cell Phone Test

04/14/2022

AR 4504190

EP Van Would Not Start

06/06/2022

Corrective Action

Documents

AR 4561602

Monthly EONS Communications Testing - Grundy

County

03/13/2023

Corrective Action

Documents

Resulting from

Inspection

AR 4711000

NRC Identified: EP-AA-124-F-04 Missing Main

Control Room / Simulator Binder List

10/19/2023

ANS Design Report LaSalle

Off-Site Emergency Plan Alert and Notification

System Addendum (ANS) for the LaSalle Nuclear

Power Station

Miscellaneous

Letters of Agreement with:

Seneca FD; LaSalle Sheriff;

Seneca FD; LaSalle Sheriff; Marseilles Area

Ambulance; Marseilles FD; Morris Hospital;

Seneca Ambulance

Various

Current

Procedures

EP-AA-1005

Radiological Emergency Plan Annex for LaSalle

Station

71114.05

Self-

Assessments

NOSA-LAS-22-02

(AR 4478170)

Emergency Preparedness Audit Report

03/11/2022

Corrective Action

Documents

AR 4673749

DEP Failure During LORT Cycle

04/13/2023

LS-AA-2110

Monthly Data Elements for NRC ROP

Indicator - Emergency Response Organization

Drill Participation

3rd Qtr 2022

- 2nd Qtr

23

71151

Miscellaneous

LS-AA-2120

Monthly Data Elements for NRC ROP

3rd Qtr 2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Indicator - Drill/Exercise Performance

- 2nd Qtr

23

LS-AA-2130

Monthly Data Elements for NRC ROP

Indicator - Alert and Notification System (ANS)

Reliability

3rd Qtr 2022

- 2nd Qtr

23

N/A

LaSalle EP Performance Indicator Drill Reports

3rd Qtr 2022

- 2nd Qtr

23

AR 4705411

MSPI Reporting Review by NRC

71152A

Corrective Action

Documents

AR 4718222

MSPI Reporting Review by NRC