Information Notice 2012-16, Preconditioning of Pressure Switches Before Surveillance Testing

From kanterella
(Redirected from Information Notice 2012-16)
Jump to navigation Jump to search
Preconditioning of Pressure Switches Before Surveillance Testing
ML120170120
Person / Time
Issue date: 08/29/2012
From: Laura Dudes, Mcginty T
Division of Construction Inspection and Operational Programs, Division of Policy and Rulemaking
To:
Beaulieu, D P, NRR/DPR, 415-3243
References
IN-12-016
Download: ML120170120 (5)


UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

OFFICE OF NEW REACTORS

WASHINGTON, DC 20555-0001 August 29, 2012 NRC INFORMATION NOTICE 2012-16: PRECONDITIONING OF PRESSURE SWITCHES

BEFORE SURVEILLANCE TESTING

ADDRESSEES

All holders of an operating license or construction permit for a nuclear power reactor under

Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Domestic Licensing of

Production and Utilization Facilities, except those who have permanently ceased operations

and have certified that fuel has been permanently removed from the reactor vessel.

All holders of and applicants for a power reactor early site permit, combined license, standard

design certification, standard design approval, or manufacturing license under 10 CFR Part 52, Licenses, Certifications, and Approvals for Nuclear Power Plants.

PURPOSE

The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice (IN) to inform

addressees of recent examples of technical specification-required surveillance testing using

procedures that unacceptably preconditioned pressure switches associated with various safety- related functions. The NRC expects that recipients will review the information for applicability to

their facilities and consider actions, as appropriate, to avoid similar problems. Suggestions

contained in this IN are not NRC requirements; therefore, no specific action or written response

is required.

DESCRIPTION OF CIRCUMSTANCES

Monticello Nuclear Generating Plant

On July 7, 2008, at the Monticello Nuclear Generating Plant, NRC inspectors observed the

performance of a surveillance procedure for main steam line isolation instrumentation channel

functional tests and calibration, which includes pressure switches that trip on low main steam

line pressure. The NRC inspectors found that the surveillance procedure unacceptably

preconditioned the pressure switches by fully cycling them during test equipment installation, before obtaining the as-found trip setpoint. Given that the pressure switch instrumentation line

configuration at Monticello is designed with a test equipment connection point that consists of a

cap only, with no adjacent isolation valve, the surveillance procedure tested the pressure

switches as follows:

1. Isolate the pressure switch to be tested;

2. Uncap the test connection;

3. Connect the test equipment to the test connection;

4. Increase the pressure until the pressure switch resets and record the reset test data;

5. Bleed off the pressure until the pressure switch trips and record the as-found trip

setpoint;

6. Remove the test equipment and restore the pressure switch to operation.

This testing methodology caused the pressure switch and associated contacts to change their

state when the system pressure was relieved in step 2; again when pressure was applied to

reset the pressure switch in step 4; then a third time when the pressure was bled off to obtain

the as-found trip setpoint in step 5. Relieving system pressure to install test equipment results

in the maximum net actuating force on the pressure switch diaphragm which exercises the

pressure switch and potentially frees sticking contacts or mechanical binding. This calls into

question the subsequent measurement of the as-found trip setpoint and the ability of the

surveillance to verify the as-found operability. The licensee similarly tested approximately

30 pressure switches at Monticello that are relied upon to initiate technical specification-related

protective functions.

The NRC inspectors discussed this surveillance with the NRC Office of Nuclear Reactor

Regulation staff who issued Task Interface Agreement (TIA) 2009-006, Unacceptable

Preconditioning of Safety-Related Pressure Switches during Required Surveillance Testing at

Monticello. This TIA concluded that the licensees surveillance testing methodology constitutes

unacceptable preconditioning of the pressure switch and, absent an engineering evaluation, the

current surveillance testing methodology is unacceptable and must be changed so that the

applicable pressure switches are not cycled before obtaining as-found trip setpoint data.

Licensee corrective actions included developing an engineering evaluation of current

surveillance testing methodology to justify the preconditioning as acceptable.

Additional information is available in Monticello-NRC Integrated and Power Uprate Review

Inspection Report 05000263/2009004, dated October 26, 2009, and can be found on the NRCs

public Web site under Agencywide Documents Access and Management System (ADAMS)

Accession No. ML092990580, and in TIA 2009-006, dated September 30, 2009 (ADAMS

Accession No. ML092730349).

Waterford Steam Electric Station, Unit 3

During a 19-month period ending October 27, 2008, Waterford Steam Electric Station, Unit 3 experienced five differential pressure switch failures in the containment vacuum relief system, a

safety-related system that provides the means to prevent potential containment failures resulting

from a vacuum condition. The first failure occurred during functional testing when a differential

pressure switch failed to actuate on two attempts, and on the third attempt, it became unstuck

and responded normally to the applied pressure. After the first failure, the licensee identified

that under normal conditions, the differential pressure switches experienced differential

pressures that exceeded the calibration pressure of 150 percent of the design range.

The licensee determined that the root cause of the five differential pressure switch failures was

that design engineers did not perform a thorough evaluation of the operating conditions in 1987 as part of a technical specification change evaluation. The licensee suspected that

preconditioning before 2008 had masked potential sticking during prior functional tests. The

licensee assigned the human performance error related to preconditioning as a contributing

cause.

Additional information is available in Waterford Steam Electric Station, Unit 3 - NRC Problem

Identification and Resolution Inspection Report 05000382/2008007, dated December 11, 2008 (ADAMS Accession No. ML083500479).

BACKGROUND

Related NRC generic communications include the following:

  • NRC IN 96-24, Preconditioning of Molded-Case Circuit Breakers before Surveillance

Testing, dated April 25, 1996 (ADAMS Accession No. ML031060110). This IN discusses

the detrimental effect that preconditioning of molded-case circuit breakers could have on the

diagnostic validity of surveillance tests.

  • NRC IN 97-16, Preconditioning of Plant Structures, Systems, and Components before

American Society of Mechanical Engineers (ASME) Code Inservice Testing or Technical

Specification Surveillance Testing, dated April 4, 1997 (ADAMS Accession No.

ML031050353). This IN discusses the potential for maintenance activities performed before

surveillance testing (preconditioning or grooming) to adversely affect the validity of the

surveillance test results for structures, systems, and components (SSCs) or equipment.

DISCUSSION

Criterion XI, Test Control, of Appendix B, Quality Assurance Criteria for Nuclear Power

Plants, to 10 CFR Part 50 requires nuclear power plants to establish a test program to ensure

that all testing required to demonstrate that SSCs will perform satisfactorily in service is

performed. This IN discusses test procedures that did not ensure pressure switches would

operate satisfactorily in service because the test procedures unacceptably preconditioned the

pressure switches by fully cycling them before obtaining an as-found trip setpoint.

NRC Inspection Manual, Part 9900 Technical Guidance, Maintenance - Preconditioning of

Structures, Systems, and Components before Determining Operability, defines unacceptable

preconditioning as the alteration, variation, manipulation or adjustment of the physical condition

of SSCs before or during technical specification surveillance testing or ASME code testing that

will alter one or more of the SSCs operational parameters, which results in acceptable test

results. Such changes could mask the actual as-found condition of the SSC and possibly result

in an inability to verify the operability of the SSC. In addition, unacceptable preconditioning

could make it difficult to determine whether the SSC would perform its intended function during

an event in which the SSC might be needed. Preconditioning of pressure switches, as

described above, could potentially mask existing conditions, such as sticking contacts, mechanical binding, or setpoint drift. The pressure switch instrumentation line configuration at Monticello is designed with a test

equipment connection point that consists of a cap only, with no adjacent isolation valve.

Therefore, to install test equipment, upstream isolation valves must be closed, which also

isolates the pressure switch, causing it to depressurize when the cap is removed to connect the

test equipment. However, the Monticello engineering evaluation listed three plants that are able

to avoid pressure switch preconditioning because the plant is designed with a test equipment

connection point that consists of a cap, as well as an adjacent isolation valve, which allows

them to connect the test equipment and pressurize it to system pressure before opening the

isolation valve, thus maintaining system pressure at the pressure switch. These three plants

avoid pressure switch preconditioning by using an isolation valve (original or installed through

modification) at the test equipment connection point or by using an alternate connection point, such as a drain line that already had an installed isolation valve.

Criterion 21, Protection System Reliability and Testability, of Appendix A, General Design

Criteria for Nuclear Power Plants, to 10 CFR Part 50 states, The protection system shall be

designed for high functional reliability and inservice testability commensurate with the safety

functions to be performed. Preconditioning is a factor in inservice testability and, as such, requires consideration commensurate with the safety functions to be performed. However, there is no explicit regulatory requirement to modify the plant to add an isolation valve to avoid

preconditioning of pressure switches.

CONTACT

This IN requires no specific action or written response. Please direct any questions about this

matter to the technical contacts listed below or the appropriate Office of Nuclear Reactor

Regulation (NRR) or Office of New Reactors project manager.

/RA by JLuehman for/ /RA/

Laura A. Dudes, Director Timothy J. McGinty, Director

Division of Construction Inspection Division of Policy and Rulemaking

and Operational Programs Office of Nuclear Reactor Regulation

Office of New Reactors

Technical Contacts: Stephen Wyman, NRR Kenneth Riemer, Region III

301-415-3041 630-829-9628 E-mail: stephen.wyman@nrc.gov E-mail: kenneth.riemer@nrc.gov

Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under NRC Library.

ML120170120 TAC ME7680

OFFICE DRP/RIII Tech Editor EICB/NRR BC:DRP/RIII

NAME CScott CHsu SWyman KRiemer

DATE 1/18/12 06/26/12 e-mail 7/27/12 e-mail 1/18/12 OFFICE BC:EICB/NRR D:DE/NRR LA:PGCB:NRR

NAME JThorp PHiland MCheok for CHawes

DATE 7/27/12 e-mail 8/6/12 8/7/12 OFFICE PM:PGCB:NRR BC:PGCB:NRR D:DCIP/NRO D:DPR:NRR

NAME DBeaulieu DPelton TAlexion for LDudes (JLuehman for) TMcGinty

OFFICE 8/6/12 08/14/12 8/23/12 8/29/12