Summary of Annual Assessment Meeting with Entergy Operations Inc Regarding Waterford-3 2015 Performance
ML16125A083
Person / Time
Site: Waterford Entergy icon.png
Issue date: 05/04/2016
From: Jeffrey Josey
NRC/RGN-IV/DRP/RPB-D
To: Chisum M
Entergy Operations
Josey J
References
Download: ML16125A083 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD.

ARLINGTON, TX 76011-4511 May 4, 2016 Mr. Michael R. Chisum Site Vice President Entergy Operations, Inc.

17265 River Road Killona, LA 70057-0751

SUBJECT:

SUMMARY

OF ANNUAL ASSESSMENT MEETING WITH ENTERGY OPERATIONS INC REGARDING WATERFORD-3 2015 PERFORMANCE Dear Mr. Chisum This refers to the Category 3 Open House and Annual Assessment Meeting conducted at the St. Charles Parish Emergency Operations Center in Hahnville, Louisiana on April 21, 2016, between the Nuclear Regulatory Commission and your staff. The purpose of this meeting was to provide members of the community an opportunity to meet with Nuclear Regulatory Commission (NRC) staff members to discuss issues related to the Waterford Steam Electric Station. Approximately 12 people attended the meeting, including Entergy employees, St. John the Baptist and St. Charles Parish Emergency Operations Center staff, Louisiana Department of Environmental Quality staff, and the Governors Office of Homeland Security staff.

During the meeting, NRC staff was available to provide an overview of inspection activities, findings and an overall performance assessment for Waterford-3. The NRC determined that Waterford 3 operated safely in 2015, and all Reactor Oversight Process cornerstone objectives were met. The NRC determined that the performance at Waterford-3 was within the Licensee Response Column of the NRCs Action matrix, because all inspection findings had very low (i.e.,

Green) safety significance, and all performance indicators showed that performance was within the nominal, expected range (i.e., Green).

During the meeting, the NRC staff had informal interactions with the people present. Two NRC staff members were present: Frances Ramirez, Senior Resident Inspector and Chris Speer, Resident Inspector. The NRC staff were asked questions related to emergency preparedness sirens and the Reactor Oversight Process.

Copies of the NRC's 2015 assessment letter (ML16061A394) and feedback forms were made available to attendees.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRCs

M. Chisum Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room)

Please contact Jeffrey Josey at 817-200-1173 with any questions you have regarding this letter.

Sincerely,

/RA/

Jeffrey Josey, Acting Chief Project Branch D Division of Reactor Projects Docket No. 50-382 License No. NPF-38

Enclosure:

Annual Public Assessment Meeting Attendance Sheet

ML16125A083 SUNSI Review ADAMS Non-Sensitive Publicly Available Keyword:

By: JFM1 Yes No Sensitive Non-Publicly Available NRC-002 OFFICE SRI:DRP/D RI:DRP/D PE:DRP/D BC:DRP/D NAME FRamirez CSpeer JMelfi JJosey SIGNATURE /RA/ /RA/ /RA/ /RA/

DATE 5/3/16 05/4/16 05/3/16 5/4/16 Letter to Michael R. Chisum from Jeffrey Josey dated May 4, 2016

SUBJECT:

SUMMARY

OF ANNUAL ASSESSMENT MEETING WITH ENTERGY OPERATIONS INC REGARDING WATERFORD-3 2015 PERFORMANCE DISTRIBUTION Regional Administrator (Marc.Dapas@nrc.gov)

Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)

DRP Director (Troy.Pruett@nrc.gov)

DRP Deputy Director (Ryan.Lantz@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Senior Resident Inspector (Frances.Ramirez@nrc.gov)

Resident Inspector (Chris.Speer@nrc.gov)

WAT Administrative Assistant (Dawn.Yancey@nrc.gov)

Branch Chief, DRP/D (Jeffrey.Sowa@nrc.gov)

Senior Project Engineer, DRP (Vacant)

Project Engineer, DRP/D (Jan.Tice@nrc.gov)

Project Engineer, DRP/D (Jim.Melfi@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Project Manager (April.Pulvirenti@nrc.gov)

Team Leader, DRS/TSS (Thomas.Hipschman@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)

RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)

RIV RSLO (Bill.Maier@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Enclosure UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD.

ARLINGTON, TX 76011-4511 May 4, 2016 Mr. Michael R. Chisum Site Vice President Entergy Operations, Inc.

17265 River Road Killona, LA 70057-0751

SUBJECT:

SUMMARY

OF ANNUAL ASSESSMENT MEETING WITH ENTERGY OPERATIONS INC REGARDING WATERFORD-3 2015 PERFORMANCE Dear Mr. Chisum This refers to the Category 3 Open House and Annual Assessment Meeting conducted at the St. Charles Parish Emergency Operations Center in Hahnville, Louisiana on April 21, 2016, between the Nuclear Regulatory Commission and your staff. The purpose of this meeting was to provide members of the community an opportunity to meet with Nuclear Regulatory Commission (NRC) staff members to discuss issues related to the Waterford Steam Electric Station. Approximately 12 people attended the meeting, including Entergy employees, St. John the Baptist and St. Charles Parish Emergency Operations Center staff, Louisiana Department of Environmental Quality staff, and the Governors Office of Homeland Security staff.

During the meeting, NRC staff was available to provide an overview of inspection activities, findings and an overall performance assessment for Waterford-3. The NRC determined that Waterford 3 operated safely in 2015, and all Reactor Oversight Process cornerstone objectives were met. The NRC determined that the performance at Waterford-3 was within the Licensee Response Column of the NRCs Action matrix, because all inspection findings had very low (i.e.,

Green) safety significance, and all performance indicators showed that performance was within the nominal, expected range (i.e., Green).

During the meeting, the NRC staff had informal interactions with the people present. Two NRC staff members were present: Frances Ramirez, Senior Resident Inspector and Chris Speer, Resident Inspector. The NRC staff were asked questions related to emergency preparedness sirens and the Reactor Oversight Process.

Copies of the NRC's 2015 assessment letter (ML16061A394) and feedback forms were made available to attendees.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRCs

M. Chisum Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room)

Please contact Jeffrey Josey at 817-200-1173 with any questions you have regarding this letter.

Sincerely,

/RA/

Jeffrey Josey, Acting Chief Project Branch D Division of Reactor Projects Docket No. 50-382 License No. NPF-38

Enclosure:

Annual Public Assessment Meeting Attendance Sheet

ML16125A083 SUNSI Review ADAMS Non-Sensitive Publicly Available Keyword:

By: JFM1 Yes No Sensitive Non-Publicly Available NRC-002 OFFICE SRI:DRP/D RI:DRP/D PE:DRP/D BC:DRP/D NAME FRamirez CSpeer JMelfi JJosey SIGNATURE /RA/ /RA/ /RA/ /RA/

DATE 5/3/16 05/4/16 05/3/16 5/4/16 Letter to Michael R. Chisum from Jeffrey Josey dated May 4, 2016

SUBJECT:

SUMMARY

OF ANNUAL ASSESSMENT MEETING WITH ENTERGY OPERATIONS INC REGARDING WATERFORD-3 2015 PERFORMANCE DISTRIBUTION Regional Administrator (Marc.Dapas@nrc.gov)

Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)

DRP Director (Troy.Pruett@nrc.gov)

DRP Deputy Director (Ryan.Lantz@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Senior Resident Inspector (Frances.Ramirez@nrc.gov)

Resident Inspector (Chris.Speer@nrc.gov)

WAT Administrative Assistant (Dawn.Yancey@nrc.gov)

Branch Chief, DRP/D (Jeffrey.Sowa@nrc.gov)

Senior Project Engineer, DRP (Vacant)

Project Engineer, DRP/D (Jan.Tice@nrc.gov)

Project Engineer, DRP/D (Jim.Melfi@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Project Manager (April.Pulvirenti@nrc.gov)

Team Leader, DRS/TSS (Thomas.Hipschman@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)

RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)

RIV RSLO (Bill.Maier@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Enclosure