MONTHYEARML23047A3822023-03-21021 March 2023 Summary of December 15, 2022 Periodic Advanced Reactor Stakeholder Public Meeting ML22217A0072022-07-29029 July 2022 NRC Regulatory Conference Summary - Licensee Entergy Operations Inc Date of Conference - July 29 2022 ML22167A0882022-06-24024 June 2022 Summary of June 14, 2022, Public Meeting with Entergy Operations, Inc. to Discuss Upcoming Relief Request to Use Code Case N-752 for Grand Gulf Nuclear Station, Unit 1, River Bend Station, Unit 1, and Waterford Steam Electric Station, Unit ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML21323A0472021-12-0606 December 2021 Summary of Public Meeting on November 5, 2021, with the National Organization of Test, Research, and Training Reactors on Operator Licensing for Research and Test Reactors ML21181A3352021-07-0101 July 2021 June 23, 2021, Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21158A2232021-06-0808 June 2021 Meeting Summary for Ticap Workshop 3 ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21132A2952021-05-14014 May 2021 Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21112A2492021-05-0707 May 2021 Summary of April 14, 2021, Redacted - Partially Closed Observation Meeting with Entergy Operations Inc., LAR to Install Digital Upgrade in Accordance with Digital I&C Interim Staff Guidance No. 06, Revision 2 (EPID L-2020-LLA-0164) (Non-Pro ML21085A8652021-04-0808 April 2021 Summary of March 17, 2021, Category 1 Public Meeting with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C Interim Staff Guidance No. 06, Rev. 2, Licensing Processes (EPID L-2020-LLA-0164) Non ML21075A0322021-04-0202 April 2021 Summary of Redacted - Category 1 Public Meeting with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C ISG No. 06, Revision 2, Licensing Processes ML21071A2862021-04-0101 April 2021 Summary of Cat. 1 Public Meeting with Entergy Operations,Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital Instrumentation and Control Interim Staff Guidance No.06,Rev.2,Licensing Processes NON-PROPRIETARY ML21039A2682021-02-22022 February 2021 Summary of Category 1 Meetings with Entergy Operations, Inc. LAR to Install Digital Upgrade in Accordance with Digital I&C ISG No. 06, Rev. 2 for Waterford Steam Electric Station, Unit 3 ML21032A0132021-02-19019 February 2021 01/06 and 01/21/2021 Summary of - Category 1 Meetings with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C ISG No. 06, Rev. 2 for Waterford Steam Electric Station ML21013A3362021-01-26026 January 2021 December 17, 2020, Summary of Category 1 Public Pre-Application Meeting with Entergy Operations,Inc. Regarding Proposed LAR to Adopt Risk-Informed TS Allowed Outage Times for Waterford Steam Electric Station, Unit 3 ML21012A2022021-01-15015 January 2021 Summary of December 15, 2020, Category 1 Public Pre-Application Meeting with Entergy Operations, Inc. Regarding Proposed LAR to Relocate Specific Technical Specifications for Waterford Steam Electric Station, Unit 3 ML20325A2412020-12-17017 December 2020 Summary of November 18, 2020, REDACTED- Category 1 Meeting with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C Interim Staff Guidance No. 06, Rev. 2, Licensing Processes ML20325A3212020-12-17017 December 2020 Summary of November 4, 2020, Nonproprietary - Category 1 Meeting with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C Interim Staff Guidance No. 06, Rev. 2, Licensing Processes (Redacted) ML20315A2672020-12-17017 December 2020 Summary of October 21,2020, Redacted Category 1 Public Meeting with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C Interim Staff Guidance No. 06,Rev.2, Licensing Processes(NON-PROPRIETARY) ML20288A7422020-10-22022 October 2020 Summary of September 22, 2020, Meeting License Amendment Request to Install Digital Upgrade (EPID L-2020-LLA-0164) (Non-proprietary Version) ML20182A4472020-07-0808 July 2020 Summary of June 11, 2020, Teleconference Meeting with Entergy Operations, Inc. to Discuss Proposed License Amendment Request for Waterford Steam Electric Station, Unit 3 Regarding Adoption of 10 CFR 50.69 ML20189A2832020-07-0707 July 2020 Summary of Region IV Annual Assessment Public Meeting ML20113E8362020-04-23023 April 2020 Summary of March 19, 2020, Category 1 Public Meeting with Entergy Operations Inc. a Planned LAR to Install Digital Systems in Accordance with Di&C ISG-06 Revision 2, Licensing Processes at Waterford Steam Electric Station ML20106E8882020-04-20020 April 2020 Summary of Public Meeting with Entergy Operations, Inc. Planned LAR to Install Digital Systems in Accordance with Di&C ISG-06 Revision 2, Licensing Processes ML20059K1562020-03-19019 March 2020 Discussion Topics for March 19, 2020 Fourth Partially Closed Public Meeting Regarding a Planned License Amendment Request to Install a Digital Modification to CPC and Ceac Systems Entergy Operations, Inc ML20013G2592020-02-0707 February 2020 Summary of December 11, 2019 Partially Closed Presubmittal Meeting with Entergy Operations, Inc., to Discuss the Effect of a Planned LAR for Digital Instrumentation and Control Modification on Accident Analyses at Waterford (L-2019-LRM-0079 ML19298B9182019-11-0505 November 2019 Summary of 9/19/19 Presubmittal Meeting with Entergy Operations, Inc. Re Request to Replace Core Protection Calculator and CEA Calculator Systems with Digital Systems in Accordance with DI&C-ISG-06, Revision 2 for Waterford Unit 3 ML19247C3882019-09-10010 September 2019 Summary of August 29, 2019, Category 1 Public Meeting with Entergy a Request for a Fee Waiver for the Review of a Planned Digital Instrumentation and Control License Amendment Request ML18323A4212018-11-26026 November 2018 Summary of Teleconference with Entergy Operations, Inc. License Amendment Request for Use of Tranflow Code for Determining Pressure Drops Across the Steam Generator Secondary Side Internal Components ML18120A3112018-05-10010 May 2018 Summary of April 17, 2018, Category 1 Public Meeting with Entergy Operations, Inc., Regarding Relief Request for Visual Inspection of Charging Pipes for the Waterford Steam Electric Station, Unit 3 ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML18099A0712018-04-16016 April 2018 March 20, 2018, Summary of Meeting with the Nuclear Energy Institute and Other Industry Representatives Regarding the Surveillance Frequency Control Program ML18059A0152018-03-0505 March 2018 Summary of February 8, 2018, Category 1 Public Meeting with Entergy Operations, Inc., Regarding Planned License Amendment Request to Revise the Waterford Unit 3 Updated Final Safety Analysis Report Section 15.4.3.1 ML18005A0992018-01-25025 January 2018 Summary of November 16, 2017, Public Meeting with Entergy Operations, Inc., Regarding Planned License Amendment Request to Revise the Waterford Steam Electric, Station Unit 3 Technical Specification 3/4.3.2 Table 4.3-2 ML17353A1542017-12-22022 December 2017 Summary of Public Meeting with Entergy Operations, Inc., on Proposed Changes to Emergency Plans to Revise Emergency Action Levels for Arkansas; Grand Gulf; River Bend; and Waterford (EPID-L-2017-LRM-0060) ML17331A0882017-12-0606 December 2017 Summary of Public Meeting with Entergy Operations, Inc. Neutron Fluence Calculation Method for the Waterford Steam Electric Station, Unit 3 ML17174B1922017-06-29029 June 2017 Summary of June 8, 2017, Category 1 Teleconference with Entergy Regarding Planned Request for Alternative Regarding High Pressure Safety Injection Pump for Waterford Steam Electric Station, Unit 3 ML17174B2262017-06-28028 June 2017 Summary of June 1, 2017, Public Meeting with Entergy Regarding Planned License Amendment Request to Revise Technical Specification (TS) Table 3.7-3 and TS 3/4.7.4, Ultimate Heat Sink for Waterford Steam Electric Station ML17090A0472017-03-31031 March 2017 Summary of Telecon Held on March 28, 2017, Between the NRC and Entergy Concerning RAI Pertaining to the Waterford Steam Electric Station License Renewal Application (Cac. No. MF7493) - Updated with ADAMS Accession Nos ML17088A1852017-03-30030 March 2017 Summary of Telecon Held on March 28, 2017, Between NRC and Entergy Concerning RAI Pertaining to the Waterford Steam Electric Station License Renewal Application (Cac. No. MF7493) ML16364A2902017-01-24024 January 2017 12/8/16, Summary of Public Meeting with Entergy Operations, Inc., Regarding the License Amendment Request to Revise Technical Specification Table 4.3-2 to Relocate ESFAS Subgroup Relays to the SFCP for Waterford Steam Electric Station, Unit ML16323A2292017-01-24024 January 2017 08/23-25/2016 Summary of Teleconference Meetings with Entergy Operations Inc., Concerning RAI Set 1 Pertaining to the Waterford Steam Electric Station, Unit 3 License Renewal Application ML16356A5822016-12-30030 December 2016 12/07/2016 Summary of Teleconference with Entergy Operations, Inc. Concerning Requests for Additional Information Set 10 Pertaining to the Waterford Steam Electric Station Unit 3 License Renewal Application ML16341B0632016-12-21021 December 2016 November 30, 2016 Summary of Teleconference Held Between NRC and Entergy Operations, Inc. Concerning RAI Set 9 Pertaining to the Waterford Steam Electric Station, Unit 3, License Renewal Application ML16125A0832016-05-0404 May 2016 Summary of Annual Assessment Meeting with Entergy Operations Inc Regarding Waterford-3 2015 Performance ML15239A7392015-08-31031 August 2015 Summary of Public Meeting with Entergy Operations, Inc. to Discuss Main Control Room Abandonment Regarding NFPA-805 License Amendment Request ML15196A4152015-07-15015 July 2015 Summary of Meeting with Entergy Corporation to Discuss Annual Performance Assessment ML15117A5032015-05-0606 May 2015 April 22, 2015, Summary of Pre- Application Public Meeting with Entergy Operations, Inc., Waterford, Unit 3, to Discuss the License Amendment Request to Modify Technical Specification 3.1.3.4 and the Final Safety Analysis Report ML15099A5632015-04-0909 April 2015 Public Meeting Summary - Regulatory Conference with Entergy Operations, Inc., for Waterford Steam Electric Station, Unit 3 2023-03-21
[Table view] |
Text
April 20, 2020 LICENSEE: Entergy Operations, Inc.
FACILITY: Waterford Steam Electric Station, Unit 3
SUBJECT:
SUMMARY
OF JANUARY 16, 2020, CATEGORY 1 PUBLIC MEETING WITH ENTERGY OPERATIONS, INC. REGARDING A PLANNED LICENSE AMENDMENT REQUEST TO INSTALL DIGITAL SYSTEMS IN ACCORDANCE WITH DIGITAL INSTRUMENTATION AND CONTROL INTERIM STAFF GUIDANCE (DI&C ISG)-06 REVISION 2, LICENSING PROCESSES (EPID L-2019-LRM-0093)
On January 16, 2020, a Category 1 partially closed public meeting was held between the U.S.
Nuclear Regulatory Commission (NRC), representatives of Entergy Operations, Inc. (the licensee), and Westinghouse Electric Company, LLC. (Westinghouse) regarding a planned license amendment request (LAR) for Waterford Steam Electric Station, Unit 3 (Waterford 3).
The meeting notice and agenda, dated December 31, 2019, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML19365A097. A public version of the licensees presentation is available at ADAMS Accession No. ML20008F008. A list of attendees is enclosed with this summary.
By letter dated May 16, 2019 (ADAMS Accession No. ML19137A082), the licensee expressed intent to submit an LAR for an upgrade to the digital instrumentation and control (DI&C) system at Waterford 3 in spring 2020. The same letter also requested a fee waiver for the review of the application. A partial fee waiver was granted by letter dated October 30, 2019 (ADAMS Accession No. ML19280C270).
The purpose of this partially closed meeting was to further discuss a planned LAR to replace the core protection calculator (CPC) and control element assembly calculator (CEAC) systems with digital systems in accordance with DI&C Interim Staff Guidance (ISG) DI&C-ISG-06, Revision 2, Licensing Processes (ADAMS Accession No. ML18269A259). This letter summarizes the third presubmittal meeting pertaining to this planned LAR.
During the open portion of the meeting, the licensee presented an overview of the CPC and CEAC systems, including high-level descriptions of the functional architecture and the main control room. The licensee presented a description of the functional architecture of the proposed Westinghouse Common Q digital upgrade. The licensee stated that the LAR would include a licensing technical report prepared by Westinghouse. In addition, the licensees presentation included a draft table of contents of the technical report.
The NRC staff and the licensee discussed the timeline for the submittal of the LAR. The licensee proposed to submit a draft version of the LAR in early June 2020 for cursory review by the NRC staff, which will be followed by a final partially closed presubmittal meeting. The licensee stated that the purpose of a draft submittal is for the NRC staff to provide initial feedback and potentially identify major deficiencies in the draft. The NRC staff discussed the
difference between the review of a draft LAR and a typical acceptance review. The NRC staff also discussed the value of a draft LAR in evaluating the licensees vendor oversight plan (VOP) and assessing whether the level of development of the digital instrumentation architecture in the LAR has met the intent of DI&C-ISG-06 Revision 2. The NRC staff agreed to consider the proposal for reviewing a draft LAR.
During the closed portion of the meeting, the licensee presented proprietary details of the impact of the proposed digital modification on the current Waterford 3 technical specifications (TSs). The NRC staff expressed concern with the licensees proposal to eliminate the channel function test surveillance requirement in the TSs and instead credit the self-diagnostic feature of the Common Q digital platform. The NRC staff and the licensee also discussed the failure mode effects analysis for the proposed changes and how this feature affected the proposed changes to the TS surveillance requirements. Further, the NRC staff and the licensee discussed whether a digital modification installed at Vogtle Electric Generating Plant, Units 3 and 4 was an appropriate precedent for the proposed modification at Waterford 3.
At the partially closed meeting held on September 19, 2019 (summary is available at ADAMS Accession No. ML19298B918), the NRC staff identified further topics as needing additional detail and discussion. At the current meeting, the licensee provided further proprietary details on those topics as follows:
Disposition of Common Q platform generic open items and plant-specific action items Revision of the equipment qualification summary report, Timing analysis of the Common Q platform, and Activities to undertake during the NRC review of the LAR, including periodic meetings and use of an open items list.
The NRC staff discussed with the licensee the proposed VOP for the planned digital modification. The licensee stated it plans to audit Westinghouse regarding regression analyses for the CPC reference design, Waterford 3-specific changes to the CPC reference design, and traceability of system requirements and software and hardware testing. The NRC staff expressed interest in observing the licensees audits because similar vendor audits had been normally conducted by NRC for prior applications.
The licensee also provided a list of regulatory commitments expected to be included with the LAR. Finally, the licensee described its approach to addressing human factors, such as staffing levels, automated actions, procedural changes, and multidisciplinary project teams. The NRC staff suggested that the licensee follow NUREG-0711, Revision 3, Human Factors Engineering Program Review Model, and NUREG-0700, Revision 3, Human-System Interface Design Review Guidelines (ADAMS Accession Nos. ML12324A013 and ML19339H052, respectively),
when addressing human factors issues in the LAR.
At the close of the meeting, The NRC staff and the licensee identified the following topics for a followup presubmittal meeting: additional details pertaining to the VOP, additional discussion of the failure mode effect analysis, and a detailed discussion of the impact of the proposed amendment on TSs. The followup presubmittal meeting was tentatively proposed for March of 2020. The followup meeting is also expected to be partially closed.
No regulatory decisions were reached at this meeting. No members of the public attended the meeting. No Public Meeting Feedback forms were received.
Please direct any inquiries to me at 301-415-1390 or April.Pulvirenti@nrc.gov.
/RA/
April Pulvirenti, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-382
Enclosures:
List of Attendees cc: Listserv
LIST OF ATTENDEES JANUARY 16, 2019, PARTIALLY CLOSED PRESUBMITTAL MEETING WITH ENTERGY OPERATIONS, INC WATERFORD STEAM ELECTRIC STATION, UNIT 3 U.S. Nuclear Regulatory Commission Excel Service Corporation April Pulvirenti Pareez Golub Steven Arndt Jennifer Dixon-Herrity DaBin Ki Jensen Hughes, Inc.
Louise Lund Alan Harris Jeanne Johnston Gregory Suber Juan Fernandez Westinghouse Electric Company, LLC Eric Benner Warren Odess-Gillett Jack Zhao Steven Merkiel Rich Stattel Eric Fredrickson Samir Darbali Allen Denyer Rossnyev Alvarado Paul Clifford Kristy Bucholtz Public Calvin Cheung None Entergy Operations, Inc.
David Constance Janice Cruz Loren Miller Christopher Talazac Roger Rucker Jacob Champagne William Steelman Ron Gaston William Truss John Schrage Enclosure
ML20106E888 *via e-mail OFFICE NRR/DORL/LPL4/PM* NRR/DORL/LPL4/LA* NRR/DORL/LPL4/BC* NRR/DORL/LPL4/PM*
NAME APuvirenti PBlechman JDixon-Herrity APulvirenti DATE 04/20/2020 04/17/2020 04/20/2020 04/20/2020