EPID:L-2019-LRM-0079, SECY-18-0100: Annual Update Regarding the Integrated Strategy to Modernize the Nuclear Regulatory Commission'S Digital Instrumentation and Control Regulatory Infrastructure (Open) |
|
MONTHYEARML18275A3272018-10-0909 October 2018 SECY-18-0100: Annual Update Regarding the Integrated Strategy to Modernize the Nuclear Regulatory Commission'S Digital Instrumentation and Control Regulatory Infrastructure Project stage: Request W3F1-2019-0034, Letter-of-Intent to Submit License Amendment Requesting Using Digital Instrumentation and Control Interim Staff Guidance-(ISG)-06, Revision 2 and Request for NRC Fee Waiver2019-05-16016 May 2019 Letter-of-Intent to Submit License Amendment Requesting Using Digital Instrumentation and Control Interim Staff Guidance-(ISG)-06, Revision 2 and Request for NRC Fee Waiver Project stage: Request W3F1-2019-0082, Transmittal of Slides for Second Partially Closed Presubmittal Meeting with Entergy Operations, Inc. to Discuss a Planned License Amendment Request for Digital Instrumentation and Control Modification2019-12-0505 December 2019 Transmittal of Slides for Second Partially Closed Presubmittal Meeting with Entergy Operations, Inc. to Discuss a Planned License Amendment Request for Digital Instrumentation and Control Modification Project stage: Meeting ML19344D0362019-12-19019 December 2019 Request for Withholding Information from Public Disclosure Affidavit Dated December 4, 2019, Executed by Zachary S. Harper of Westinghouse Electric Company LLC Meeting Slides Project stage: Withholding Request Acceptance ML20013G2592020-02-0707 February 2020 Summary of December 11, 2019 Partially Closed Presubmittal Meeting with Entergy Operations, Inc., to Discuss the Effect of a Planned LAR for Digital Instrumentation and Control Modification on Accident Analyses at Waterford (L-2019-LRM-0079 Project stage: Meeting 2019-12-05
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML23047A3822023-03-21021 March 2023 Summary of December 15, 2022 Periodic Advanced Reactor Stakeholder Public Meeting ML22217A0072022-07-29029 July 2022 NRC Regulatory Conference Summary - Licensee Entergy Operations Inc Date of Conference - July 29 2022 ML22167A0882022-06-24024 June 2022 Summary of June 14, 2022, Public Meeting with Entergy Operations, Inc. to Discuss Upcoming Relief Request to Use Code Case N-752 for Grand Gulf Nuclear Station, Unit 1, River Bend Station, Unit 1, and Waterford Steam Electric Station, Unit ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML21323A0472021-12-0606 December 2021 Summary of Public Meeting on November 5, 2021, with the National Organization of Test, Research, and Training Reactors on Operator Licensing for Research and Test Reactors ML21181A3352021-07-0101 July 2021 June 23, 2021, Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21158A2232021-06-0808 June 2021 Meeting Summary for Ticap Workshop 3 ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21132A2952021-05-14014 May 2021 Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21112A2492021-05-0707 May 2021 Summary of April 14, 2021, Redacted - Partially Closed Observation Meeting with Entergy Operations Inc., LAR to Install Digital Upgrade in Accordance with Digital I&C Interim Staff Guidance No. 06, Revision 2 (EPID L-2020-LLA-0164) (Non-Pro ML21085A8652021-04-0808 April 2021 Summary of March 17, 2021, Category 1 Public Meeting with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C Interim Staff Guidance No. 06, Rev. 2, Licensing Processes (EPID L-2020-LLA-0164) Non ML21075A0322021-04-0202 April 2021 Summary of Redacted - Category 1 Public Meeting with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C ISG No. 06, Revision 2, Licensing Processes ML21071A2862021-04-0101 April 2021 Summary of Cat. 1 Public Meeting with Entergy Operations,Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital Instrumentation and Control Interim Staff Guidance No.06,Rev.2,Licensing Processes NON-PROPRIETARY ML21039A2682021-02-22022 February 2021 Summary of Category 1 Meetings with Entergy Operations, Inc. LAR to Install Digital Upgrade in Accordance with Digital I&C ISG No. 06, Rev. 2 for Waterford Steam Electric Station, Unit 3 ML21032A0132021-02-19019 February 2021 01/06 and 01/21/2021 Summary of - Category 1 Meetings with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C ISG No. 06, Rev. 2 for Waterford Steam Electric Station ML21013A3362021-01-26026 January 2021 December 17, 2020, Summary of Category 1 Public Pre-Application Meeting with Entergy Operations,Inc. Regarding Proposed LAR to Adopt Risk-Informed TS Allowed Outage Times for Waterford Steam Electric Station, Unit 3 ML21012A2022021-01-15015 January 2021 Summary of December 15, 2020, Category 1 Public Pre-Application Meeting with Entergy Operations, Inc. Regarding Proposed LAR to Relocate Specific Technical Specifications for Waterford Steam Electric Station, Unit 3 ML20325A2412020-12-17017 December 2020 Summary of November 18, 2020, REDACTED- Category 1 Meeting with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C Interim Staff Guidance No. 06, Rev. 2, Licensing Processes ML20325A3212020-12-17017 December 2020 Summary of November 4, 2020, Nonproprietary - Category 1 Meeting with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C Interim Staff Guidance No. 06, Rev. 2, Licensing Processes (Redacted) ML20315A2672020-12-17017 December 2020 Summary of October 21,2020, Redacted Category 1 Public Meeting with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C Interim Staff Guidance No. 06,Rev.2, Licensing Processes(NON-PROPRIETARY) ML20288A7422020-10-22022 October 2020 Summary of September 22, 2020, Meeting License Amendment Request to Install Digital Upgrade (EPID L-2020-LLA-0164) (Non-proprietary Version) ML20182A4472020-07-0808 July 2020 Summary of June 11, 2020, Teleconference Meeting with Entergy Operations, Inc. to Discuss Proposed License Amendment Request for Waterford Steam Electric Station, Unit 3 Regarding Adoption of 10 CFR 50.69 ML20189A2832020-07-0707 July 2020 Summary of Region IV Annual Assessment Public Meeting ML20113E8362020-04-23023 April 2020 Summary of March 19, 2020, Category 1 Public Meeting with Entergy Operations Inc. a Planned LAR to Install Digital Systems in Accordance with Di&C ISG-06 Revision 2, Licensing Processes at Waterford Steam Electric Station ML20106E8882020-04-20020 April 2020 Summary of Public Meeting with Entergy Operations, Inc. Planned LAR to Install Digital Systems in Accordance with Di&C ISG-06 Revision 2, Licensing Processes ML20059K1562020-03-19019 March 2020 Discussion Topics for March 19, 2020 Fourth Partially Closed Public Meeting Regarding a Planned License Amendment Request to Install a Digital Modification to CPC and Ceac Systems Entergy Operations, Inc ML20013G2592020-02-0707 February 2020 Summary of December 11, 2019 Partially Closed Presubmittal Meeting with Entergy Operations, Inc., to Discuss the Effect of a Planned LAR for Digital Instrumentation and Control Modification on Accident Analyses at Waterford (L-2019-LRM-0079 ML19298B9182019-11-0505 November 2019 Summary of 9/19/19 Presubmittal Meeting with Entergy Operations, Inc. Re Request to Replace Core Protection Calculator and CEA Calculator Systems with Digital Systems in Accordance with DI&C-ISG-06, Revision 2 for Waterford Unit 3 ML19247C3882019-09-10010 September 2019 Summary of August 29, 2019, Category 1 Public Meeting with Entergy a Request for a Fee Waiver for the Review of a Planned Digital Instrumentation and Control License Amendment Request ML18323A4212018-11-26026 November 2018 Summary of Teleconference with Entergy Operations, Inc. License Amendment Request for Use of Tranflow Code for Determining Pressure Drops Across the Steam Generator Secondary Side Internal Components ML18120A3112018-05-10010 May 2018 Summary of April 17, 2018, Category 1 Public Meeting with Entergy Operations, Inc., Regarding Relief Request for Visual Inspection of Charging Pipes for the Waterford Steam Electric Station, Unit 3 ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML18099A0712018-04-16016 April 2018 March 20, 2018, Summary of Meeting with the Nuclear Energy Institute and Other Industry Representatives Regarding the Surveillance Frequency Control Program ML18059A0152018-03-0505 March 2018 Summary of February 8, 2018, Category 1 Public Meeting with Entergy Operations, Inc., Regarding Planned License Amendment Request to Revise the Waterford Unit 3 Updated Final Safety Analysis Report Section 15.4.3.1 ML18005A0992018-01-25025 January 2018 Summary of November 16, 2017, Public Meeting with Entergy Operations, Inc., Regarding Planned License Amendment Request to Revise the Waterford Steam Electric, Station Unit 3 Technical Specification 3/4.3.2 Table 4.3-2 ML17353A1542017-12-22022 December 2017 Summary of Public Meeting with Entergy Operations, Inc., on Proposed Changes to Emergency Plans to Revise Emergency Action Levels for Arkansas; Grand Gulf; River Bend; and Waterford (EPID-L-2017-LRM-0060) ML17331A0882017-12-0606 December 2017 Summary of Public Meeting with Entergy Operations, Inc. Neutron Fluence Calculation Method for the Waterford Steam Electric Station, Unit 3 ML17174B1922017-06-29029 June 2017 Summary of June 8, 2017, Category 1 Teleconference with Entergy Regarding Planned Request for Alternative Regarding High Pressure Safety Injection Pump for Waterford Steam Electric Station, Unit 3 ML17174B2262017-06-28028 June 2017 Summary of June 1, 2017, Public Meeting with Entergy Regarding Planned License Amendment Request to Revise Technical Specification (TS) Table 3.7-3 and TS 3/4.7.4, Ultimate Heat Sink for Waterford Steam Electric Station ML17090A0472017-03-31031 March 2017 Summary of Telecon Held on March 28, 2017, Between the NRC and Entergy Concerning RAI Pertaining to the Waterford Steam Electric Station License Renewal Application (Cac. No. MF7493) - Updated with ADAMS Accession Nos ML17088A1852017-03-30030 March 2017 Summary of Telecon Held on March 28, 2017, Between NRC and Entergy Concerning RAI Pertaining to the Waterford Steam Electric Station License Renewal Application (Cac. No. MF7493) ML16364A2902017-01-24024 January 2017 12/8/16, Summary of Public Meeting with Entergy Operations, Inc., Regarding the License Amendment Request to Revise Technical Specification Table 4.3-2 to Relocate ESFAS Subgroup Relays to the SFCP for Waterford Steam Electric Station, Unit ML16323A2292017-01-24024 January 2017 08/23-25/2016 Summary of Teleconference Meetings with Entergy Operations Inc., Concerning RAI Set 1 Pertaining to the Waterford Steam Electric Station, Unit 3 License Renewal Application ML16356A5822016-12-30030 December 2016 12/07/2016 Summary of Teleconference with Entergy Operations, Inc. Concerning Requests for Additional Information Set 10 Pertaining to the Waterford Steam Electric Station Unit 3 License Renewal Application ML16341B0632016-12-21021 December 2016 November 30, 2016 Summary of Teleconference Held Between NRC and Entergy Operations, Inc. Concerning RAI Set 9 Pertaining to the Waterford Steam Electric Station, Unit 3, License Renewal Application ML16125A0832016-05-0404 May 2016 Summary of Annual Assessment Meeting with Entergy Operations Inc Regarding Waterford-3 2015 Performance ML15239A7392015-08-31031 August 2015 Summary of Public Meeting with Entergy Operations, Inc. to Discuss Main Control Room Abandonment Regarding NFPA-805 License Amendment Request ML15196A4152015-07-15015 July 2015 Summary of Meeting with Entergy Corporation to Discuss Annual Performance Assessment ML15117A5032015-05-0606 May 2015 April 22, 2015, Summary of Pre- Application Public Meeting with Entergy Operations, Inc., Waterford, Unit 3, to Discuss the License Amendment Request to Modify Technical Specification 3.1.3.4 and the Final Safety Analysis Report ML15099A5632015-04-0909 April 2015 Public Meeting Summary - Regulatory Conference with Entergy Operations, Inc., for Waterford Steam Electric Station, Unit 3 2023-03-21
[Table view] |
Text
February 7, 2020 LICENSEE: Entergy Operations, Inc.
FACILITY: Waterford Steam Electric Station, Unit 3
SUBJECT:
SUMMARY
OF DECEMBER 11, 2019, PARTIALLY CLOSED PRESUBMITTAL MEETING WITH ENTERGY OPERATIONS, INC., TO DISCUSS THE EFFECT OF A PLANNED LICENSE AMENDMENT REQUEST FOR DIGITAL INSTRUMENTATION AND CONTROL MODIFICATION ON ACCIDENT ANALYSES AT WATERFORD STEAM ELECTRIC STATION, UNIT 3 (EPID L-2019-LRM-0079)
On December 11, 2019, a Category 1 partially closed public meeting was held between the U.S. Nuclear Regulatory Commission (NRC), representatives of Entergy Operations, Inc.
(Entergy, the licensee), and Westinghouse Electric Company, LLC (Westinghouse) regarding a planned license amendment request (LAR) for Waterford Steam Electric Station, Unit 3 (Waterford 3). The meeting notice and agenda, dated November 26, 2019, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML19337B567. The licensee provided a public version of its presentation, which is available at ADAMS Accession No. ML19339J407. A list of attendees is enclosed with this summary.
By letter dated May 16, 2019 (ADAMS Accession No. ML19137A082), the licensee expressed intent to submit an LAR for an upgrade to the digital instrumentation and control (DI&C) system at Waterford 3 in spring 2020. A partial fee waiver was granted for the review of the LAR by letter dated October 30, 2019 (ADAMS Accession No. ML19280C270). A previous presubmittal meeting was held on September 19, 2019. A summary of that meeting is available at ADAMS Accession No. ML19298B918.
The purpose of the December 11, 2019, partially closed meeting was to discuss a particular feature of the planned LAR to replace the core protection calculator (CPC) and control element assembly calculator (CEAC) systems with digital systems in accordance with DI&C Interim Staff Guidance (DI&C ISG)-06, Revision 2, Licensing Processes, December 2018 (ADAMS Accession No. ML18269A259), using the alternate review process. Specifically, installation of the CPC and CEAC digital systems is anticipated to change the response times related to the calculation of margin for events analyzed in Chapter 15, Accident Analyses, of the Waterford Updated Final Safety Analysis Report (UFSAR), and impact the safety analysis of record.
During the meeting, Entergy and Westinghouse explained how the CPC system response times were currently calculated. Then, they explained how the replacement of the CPC system with the Common Q digital system would change the response times for the CPC system. Entergy and Westinghouse discussed with the NRC staff their proposed approach to calculate the new CPC and CEAC system response times and provide response time feedback to the core
load analysis to assure that adequate safety margins are maintained in accordance with the safety analysis.
Item D.2.4.1 of DI&C-ISG-06 states, in part, that, The LAR should demonstrate how the range of response times in the new design falls within the range of response times credited in the accident analysis for the applicable modes of replacement system operation. The licensee stated that Waterford 3s updated core reload safety analyses will not be completed by June 2020, which is the scheduled date for the submittal of the LAR. Therefore, in order to demonstrate that Item D.2.4.1 of DI&C-ISG-06 is met, Entergy and Westinghouse proposed an approach to estimate the impact of modified response times on the safety analysis of record and include those estimated results in the LAR. The licensee will use the process outlined in Title 10 of the Code of Federal Regulations, Section 50.59, Changes, tests, and experiments, to evaluate the new response times and accident analysis impact using the reload methodology prior to new fuel load.
During the proprietary portion of the meeting, Westinghouse demonstrated the proposed approach of estimating response times. Westinghouse used representative examples from a similar Common Q digital system configuration installed at Palo Verde Nuclear Generating Station (Palo Verde), to estimate response times for events such as hot leg temperature variable overpower trip and pressurizer pressure. Westinghouse extrapolated the response time results from Palo Verde to estimate the response times for similar events for the proposed Common Q digital configuration at Waterford 3. Westinghouse determined the impact that these estimated response times would have on the corresponding UFSAR Chapter 15 analyzed events such as steam generator tube rupture or letdown line break. The licensee stated that the LAR would contain the Waterford 3 response times, and not the Palo Verde numbers used for the representative examples.
The licensee provided proprietary results of the demonstration, which showed the safety margin to the acceptance criteria for the UFSAR Chapter 15 analyzed events. The licensee stated that that the response times for the proposed Common Q system would continue to satisfy the UFSAR Chapter 15 acceptance criteria.
The licensee stated that the same approach was employed to update the average and slowest drop times for control element assemblies at Waterford 3. These drop times were approved at Waterford 3 in License Amendment No. 246, dated November 13, 2015 (ADAMS Accession No. ML15289A143).
During the meeting, the NRC staff acknowledged that alternate approaches have been included in previous LARs for review. The NRC staff stated that such an approach for Waterford 3, when included in the proposed LAR, would likely provide sufficient technical information to begin the review of the LAR.
In addition, the NRC staff clarified that although the licensee references a Palo Verde modification as a precedent, the licensee cannot take credit for the NRC staffs evaluation of the Palo Verde modification without demonstrating why the basis is the same for the Waterford modification. The NRC staff stated that the LAR should include information that demonstrates how the Waterford 3 modification complies with the regulatory criteria and conforms with the regulatory guidance.
No regulatory decisions were reached at this meeting. No members of the public attended the meeting. No Public Meeting Feedback forms were received.
Please direct any inquiries to me at 301-415-1390 or April.Pulvirenti@nrc.gov.
April L. Pulvirenti, Project Manager /RA/
Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-382
Enclosure:
List of Attendees cc: Listserv
ML20013G259 OFFICE DORL/LPL4/PM DORL/LPL4/LA NRR/DEX/EICA/BC NRR/DEX/EICB/BC NAME APuvirenti PBlechman JJohnston MWaters DATE 01/23/2020 01/15/2020 02/03/2020 02/03/2020 OFFICE NRR/DSS/SNSB/BC(A) DORL/LPL4/BC DORL/LPL4/PM NAME JBorromeo JDixon-Herrity APulvirenti DATE 01/15/2020 02/07/2020 02/07/2020 LIST OF ATTENDEES DECEMBER 11, 2019, PARTIALLY CLOSED PRESUBMITTAL MEETING WITH ENTERGY OPERATIONS, INC WATERFORD STEAM ELECTRIC STATION, UNIT 3 U.S. Nuclear Regulatory Commission Jensen Hughes, Inc Rossnyev Alvarado Alan Harris Steven Arndt Robert Beaton Sargent & Lundy Joshua Borromeo Pareez Golub Paul Clifford Samir Darbali Westinghouse Electric Company, LLC Jeanne Johnston Amanda Charleroy Angel Moreno Kim Jones William Orders Warren Odess-Gillett April Pulvirenti Richard Stattel EXCEL Services Michael Waters Jim Andersen Jack Zhao Charles DeDeaux Entergy Operations, Inc. Public Jacob Champaign None Janice Cruz Jerry Holman Joe Reese Roger Rucker John Schrage William Schuss Billy Steelman Christopher Talazac Paul Wood Enclosure