|
---|
Category:Inspection Plan
MONTHYEARIR 05000336/20240052024-08-29029 August 2024 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Reports 05000336/2024005 and 05000423/2024005 IR 05000336/20244032024-07-22022 July 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000336/2024403 and 05000423/2024403 ML24004A1052024-01-0404 January 2024 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000336/2024010 & 05000423/2024010 IR 05000336/20230052023-08-31031 August 2023 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Report 05000336/2023005 and 05000423/2023005) IR 05000336/20220062023-03-0101 March 2023 Annual Assessment Letter for Millstone Power Station, Units 2 and 3 (Reports 05000336/2022006 and 05000423/2022006) IR 05000336/20220052022-08-31031 August 2022 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Report 05000336/2022005 and 05000423/2022005) IR 05000336/20224022022-05-23023 May 2022 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000336/2022402 and 05000423/2022402 ML22081A1992022-03-28028 March 2022 Notification of Conduct of a Fire Protection Team Inspection IR 05000336/20210062022-03-0202 March 2022 Annual Assessment Letter for Millstone Power Station, Units 2 and 3 (Reports 05000336/2021006 and 05000423/2021006) IR 05000336/20210052021-09-0101 September 2021 Updated Inspection Plan for the Millstone Power Station, Units 2 and 3 (Report 05000336/2021005 and 05000423/2021005) IR 05000336/20200062021-03-0303 March 2021 Annual Assessment Letter for Millstone Power Station, Units 2 and 3 (Reports 05000336/2020006 and 05000423/2020006) ML20323A1092020-11-18018 November 2020 Information Request to Support Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000336/2021011 and 05000423/2021011 IR 05000336/20200052020-08-31031 August 2020 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Inspection Report 05000336/2020005 and 05000423/2020005) ML20160A1362020-06-0808 June 2020 Request for Information to Support Triennial Baseline Design-Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000336/2020013 and 05000423/2020013 ML20084J9452020-03-24024 March 2020 Ti 2515/194 Inspection Documentation Request IR 05000336/20190062020-03-0303 March 2020 Annual Assessment Letter for Millstone Power Station, Units 2 and 3 (Report 05000336/2019006 and 05000423/2019006) IR 05000336/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 05000336/2019005 and 05000423/2019005) IR 05000336/20180062019-03-0404 March 2019 Annual Assessment Letter for Millstone Power Station, Units 2 and 3 (Reports 05000336/2018006 and 05000423/2018006) IR 05000336/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000336/2018005 and 05000423/2018005) IR 05000336/20170062018-02-28028 February 2018 Annual Assessment Letter for Millstone Power Station, Units 2 and 3 (Report 05000336/2017006 and 05000423/2017006, Report 05000336/2017402 and 05000423/2017402, Report 05000336/2017501 and 05000423/2017501) IR 05000336/20170052017-08-28028 August 2017 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Report 05000336/2017005 and 05000423/2017005) IR 05000336/20160062017-03-0101 March 2017 Annual Assessment Letter for Millstone Power Station, Units 2 and 3 (Report 05000336/2016006 and 05000423/2016006) IR 05000336/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Millstone Power Station, Units 2 and 3 (Report 05000336/2016005 and 05000423/2016005) ML16074A2562016-03-14014 March 2016 Notification of Conduct of a Triennial Fire Protection Baseline Inspection 2016007 IR 05000336/20150062016-03-0202 March 2016 2015 Annual Assessment Letter for Millstone Power Station, Units 2 and 3 (Report 05000336/2015006 and 05000423/2015006) IR 05000336/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Millstone Power Station Units 2 and 3 (Report 05000336/2015005 and 05000423/2015005) IR 05000336/20140012015-03-0404 March 2015 2014 Annual Assessment Letter for Millstone Power Station, Units 2 and 3, (Report 05000336/2014001 and 05000423/2014001)(w/Inspection Plan) IR 05000336/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter and Inspection Plan 2014 (ROP-15) - Millstone Power Station Units 2 and 3 (Report 05000336/2014006 and 05000423/2014006) IR 05000336/20130012014-03-0404 March 2014 2013 Annual Assessment Letter for Millstone Power Station Units 2 and 3 (Report 05000336/2013001 and 05000423/2013001)(w/Inspection Plan) IR 05000336/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan 2013 (ROP-14) - Millstone Power Station Units 2 and 3 (Report 05000336-13-006 and 05000423-13-006) ML13198A4452013-07-12012 July 2013 Notification of Inspection of Implementation of Interim Cyber Security Milestones 1-7 ML13109A2232013-04-18018 April 2013 Notification of Conduct of a Triennial Fire Protection Baseline Inspection IR 05000336/20120012013-03-0404 March 2013 Annual Assessment Letter for Millstone Power Station Unit 2 and Unit 3 (Report 05000336/2012001 and 05000423/2012001) ML12244A4022012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - 2013 Millstone Power Station Units 2 and 3 IR 05000336/20110012012-03-0505 March 2012 Unit 3 Annual Assessment Letter (Report 05000336/2011001) ML1124400122011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Millstone Power Station Unit 2 and Unit 3 IR 05000336/20100012011-03-0404 March 2011 Annual Assessment Letter for Millstone Power Station Unit 2 and Unit 3 (Report 05000336/2010001 and 05000423/2010001) ML1024405802010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Millstone Power Station ML1006214202010-03-0303 March 2010 Annual Assessment Letter - Millstone 2010 (Reports 05000336-10-001 and 05000423-10-001) ML0924401912009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Millstone Power Station IR 05000336/20090012009-03-0404 March 2009 Annual Assessment Letter - Millstone Power Station (Reports 05000336/2009001 and 05000423/2009001) ML0824702232008-09-0202 September 2008 Mid-Cycle Performance Review and Inspection Plan, Millstone IR 05000336/20080012008-03-0303 March 2008 IR 05000336-08-001, and IR 05000423-08-001, Millstone Power Station - Annual Assessment Letter ML0734709562007-12-13013 December 2007 ROP8 - Millstone - Change to Inspection Plan, 12/13/07 ML0724309462007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan - Millstone Station Units 2 and 3 ML0706104642007-03-0202 March 2007 Annual Assessment Letter - EOC 2006 - Millstone (05-336/2007001 and 05-423/2007001) ML0624305322006-08-31031 August 2006 Mid-cycle Performance Review and Inspection Plan - Millstone Station Units 2 and 3 IR 05000336/20060012006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Millstone Power Station Units 2 and 3 (Reports 05000336-06-001 and 05000423-06-001) ML0524207162005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Millstone Station, Units 2 and 3 IR 05000336/20050012005-03-0202 March 2005 Annual Assessment Letter - Millstone Units 2 & 3 (Report (05000336/2005001 and 05000423/2005001) 2024-08-29
[Table view] Category:Letter
MONTHYEARIR 05000336/20240032024-11-0707 November 2024 Integrated Inspection Report 05000336/2024003 and 05000423/2024003 and Apparent Violation and Independent Spent Fuel Storage Installation Inspection Report 07200008/2024001 ML24289A0152024-10-21021 October 2024 Review of the Fall 2023 Steam Generator Tube Inspection Report 05000423/LER-2024-001, Loss of Safety Function and Condition Prohibited by Technical Specifications for Loss of Secondary Containment Boundary2024-10-14014 October 2024 Loss of Safety Function and Condition Prohibited by Technical Specifications for Loss of Secondary Containment Boundary IR 05000336/20244022024-10-0808 October 2024 Security Baseline Inspection Report 05000336/2024402 and 05000423/2024402 (Cover Letter Only) ML24281A1102024-10-0707 October 2024 Requalification Program Inspection 05000423/LER-2023-006-02, Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications2024-09-26026 September 2024 Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24260A2192024-09-16016 September 2024 Decommissioning Trust Fund Disbursement - Revision to Previous Thirty-Day Written Notification ML24260A1952024-09-16016 September 2024 Response to Request for Additional Information Regarding Proposed Amendment to Support Implementation of Framatome Gaia Fuel ML24248A2272024-09-0404 September 2024 Operator Licensing Examination Approval ML24240A1532024-09-0303 September 2024 Summary of Regulatory Audit Supporting the Review of License Amendment Request for Implementation of Framatome Gaia Fuel IR 05000336/20240052024-08-29029 August 2024 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Reports 05000336/2024005 and 05000423/2024005 IR 05000336/20240022024-08-13013 August 2024 Integrated Inspection Report 05000336/2024002 and 05000423/2024002 ML24221A2872024-08-0808 August 2024 Independent Spent Fuel Storage Installation (ISFSI) - Submittal of Cask Registration for Spent Fuel Storage IR 05000336/20244412024-08-0606 August 2024 Supplemental Inspection Report 05000336/2024441 and 05000423/2024441 and Follow-Up Assessment Letter (Cover Letter Only) ML24212A0742024-08-0505 August 2024 Request for Withholding Information from Public Disclosure - Millstone Power Station, Unit No. 3, Proposed Alternative Request IR-4-13 to Support Steam Generator Channel Head Drain Modification ML24211A1712024-07-25025 July 2024 Associated Independent Spent Fuels Storage Installation, Revision to Emergency Plan - Report of Change IR 05000336/20244032024-07-22022 July 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000336/2024403 and 05000423/2024403 IR 05000336/20245012024-07-0101 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000336/2024501 and 05000423/2024501 ML24180A0932024-06-28028 June 2024 Readiness for Additional Inspection: EA-23-144 IR 05000336/20240102024-06-26026 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000336/2024010 and 05000423/2024010 ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 IR 05000336/20244402024-06-24024 June 2024 Final Significance Determination for Security-Related Greater than Green Finding(S) with Assessment Follow-up; IR 05000336/2024440 and 05000423/2024440 and Notice of Violation(S), NRC Investigation Rpt 1-2024-001 (Cvr Ltr Only) ML24176A1782024-06-20020 June 2024 Update to the Final Safety Analysis Report ML24176A2622024-06-20020 June 2024 Update to the Final Safety Analysis Report, Revision 37 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24280A0012024-06-20020 June 2024 Update to the Final Safety Analysis Report (Redacted Version) ML24281A2072024-06-20020 June 2024 Update to the Final Safety Analysis Report, Revision 37 (Redacted Version) 05000336/LER-2024-001, Control Room Air Conditioning Unit Inoperable Due to Refrigerant Overcharge Resulting in a Condition Prohibited by Technical Specifications2024-06-10010 June 2024 Control Room Air Conditioning Unit Inoperable Due to Refrigerant Overcharge Resulting in a Condition Prohibited by Technical Specifications ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code ML24165A1292024-06-0505 June 2024 ISFSI, 10 CFR 50.59 Annual Change Report for 2023 Annual Regulatory Commitment Change Report for 2023 ML24128A2772024-06-0404 June 2024 Issuance of Amendment No. 290 to Revise TSs for Reactor Core Safety Limits, Fuel Assemblies, and Core Operating Limits Report for Use of Framatome Gaia Fuel (EPID L-2023-LLA-0074) (Non-Proprietary) ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24110A0562024-05-21021 May 2024 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, and Appendix K Regarding Use of M5 Cladding Material (EPID L-2023-LLE-0013) (Letter) ML24109A0032024-05-21021 May 2024 Issuance of Amendment No. 289 to Revise Technical Specifications to Use Framatome Loss of Coolant Accident Evaluation Methodologies for Establishing Core Operating Limit (EPID L-2023-LLA-0065) (Non-Proprietary) ML24142A0952024-05-20020 May 2024 End of Cycle 22 Steam Generator Tube Inspection Report 05000423/LER-2023-006-01, Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications2024-05-20020 May 2024 Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications ML24141A2432024-05-20020 May 2024 Response to Request for Additional Information Regarding Alloy 600 Aging Management Program Submittal Related to License Renewal Commitment No. 15 IR 05000336/20240012024-05-14014 May 2024 Integrated Inspection Report 05000336/2024001 and 05000423/2024001 and Apparent Violation ML24123A2042024-05-0202 May 2024 Pre-Decisional Replay to EA-23-144 05000423/LER-2023-006, Pressurizer Power Operated Relief Valve Failed to Stroke Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications2024-05-0202 May 2024 Pressurizer Power Operated Relief Valve Failed to Stroke Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications IR 05000336/20244012024-04-30030 April 2024 Security Baseline Inspection Report 05000336/2024401 and 05000423/2024401 (Cover Letter Only) ML24123A1222024-04-30030 April 2024 Inservice Inspection Program - Owners Activity Report, Refueling Outage 22 ML24116A0452024-04-25025 April 2024 Special Inspection Follow-Up Report 05000336/2024440 and 05000423/2024440 and Preliminary Finding(S) of Greater than Very Low Significance and NRC Investigation Report No. 1-2024-001 (Cover Letter Only) ML24116A1742024-04-24024 April 2024 Annual Radiological Environmental Operating Report ML24114A2662024-04-24024 April 2024 Submittal of 2023 Annual Radioactive Effluent Release Report ML24103A0202024-04-22022 April 2024 Summary of Regulatory Audit in Support of License Amendment Request to Use Framatome Small Break and Realistic Large Break Loss of Coolant Accident Evaluation Methodologies for Establishing Core Operating Limits ML24106A2032024-04-15015 April 2024 2023 Annual Environmental Operating Report ML24088A3302024-04-0404 April 2024 Regulatory Audit Plan in Support of License Amendment Request to Implement Framatome Gaia Fuel ML24093A2162024-04-0101 April 2024 Response to Request for Additional Information Regarding License Amendment Request to Use Framatome Small Break and Realistic Large Break Loss of Coolant Accident Evaluation Methodologies for Establishing Core Operating Limits 2024-09-04
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406*1415 September 1, 2010 Mr. David A. Heacock Sr. Vice President and Chief Nuclear Officer Dominion Resources 500 Dominion Boulevard Glenn Allen, VA 23060-6711
~
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN MILLSTONE POWER STATION
Dear Mr. Heacock:
On August 12,2010, the Nuclear Regulatory Commission (NRC) staff completed its performance review of the Millstone Power Station. Our technical staff reviewed performance indicators (Pis) for the most recent quarter and inspection results for the period from July 1, 2009, through June 30, 2010. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only - Security Related Information" will include the security cornerstone review and resultant inspection plan.
Plant performance for the most recent quarter at Millstone Units 2 and 3 was within the licensee Response column of the NRC's Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all Pis indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (RaP) baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2011. In addition to baseline inspections, we plan to conduct a follow-up inspection for three severity level IV non-cited violations issued within the same traditional enforcement area during the assessment period. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-ot-cycle review.
D. Heacock 2 In accordance with 10 CFR Part 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading rm/adams.html (the Public Electronic Reading Room).
If circumstances arise Which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5306 with any questions you may have regarding this letter or the inspection plan.
n~ Donald E. Ja on, Chief Projects Branch 5 Division of Reactor Projects Docket Nos. 50-336, 50-423 License Nos. DPR-65, NPF-49
Enclosure:
Millstone Inspection! Activity Plan ccw/encl: Distribution via ListServ
D. Heacock 2 In accordance with 10 CFR Part 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5306 with any questions you may have regarding this letter or the inspection plan.
Sincerely.
IRA!
Donald E. Jackson, Chief Projects Branch 5 Division of Reactor Projects Docket Nos. 50~336, 50-423 License Nos. DPR-65, NPF-49
Enclosure:
Millstone Inspectionl Activity Plan ccw/encl: Distribution via ListServ M. Oapas, Acting RA S. Shaffer, DRP, SRI N. Sheehan, PAO D. Lew, Acting ORA B. Haagensen, RI R. Barkley, ORA J. Clifford, DRP J. Krafty. DRP, RI A. Klett, NRR O. Collins, DRP C. Kowalyshyn. OA RidsNRRPM Millstone Resource D. Roberts, DRS L. Trocine, RI OEDO RidsNRRDor1Lp11-2 Resource P. Wilson, DRS DRS Branch Chiefs (6) ROPreportsResource@nrc.gov D. Jackson, DRP N. McNamara, SLO RidsNrrDirsJpabResource T. Setzer, DRP D. Tifft. SLO D. Dodson, DRP D. Screnci, PAO SUNSI Review Complete: TCS (Reviewer's Initials) ML102440580 DOCUMENT NAME: S:\ROP-11 Mid-Cycle Review\Branch 5\MilIstone\201 0 Mid-Cycle Assessment Letter MIL.doc After dedaring this document "An Official Agency Record" it will be released to the Public.
To receive acopy oftbis document, indicate in the box: 'C' = Copy witllout attachmentlenclosure "E" = Copy with attachment/enclosure "1\1." =No copy OFFICE RIIDRP I RI/DRP I I NAME T Setzerl TCS D Jacksonl DEJ DATE 08/25/10 08/31/10 OFFICIAL RECORD COPY
Page 1 of2 Millstone 08125/2010 08:57:39 Inspection I Activity Plan Report 22 07/01/2010 - 12131/2011 Planned Dates Start End ~nspectlon Activity Ie TiUe TRI FIRE
- TRIENNIAL FIRE PROTECTION INSPECTION 6 2.3 07/1912010 07/2312010 IF' 7111105T Fire Protection rrrienniaQ 2,3 0810212010 0810612010 IF' 7111105T Fire Protection rrrienniaij TI~181
- FIRE PROTECTION CIRCUIT ANALYSIS & OMA 2 2 07119/2010 01123/2010 IP 25151181 Validate the Effectiveness of the Regulatory Infrastructure Related to Fire-Induced Circuit Failures 92723
- MILLSTONE TRAD ENF NCVS - FOLLOW UP INSP 2 2,3 1010412010 1010812010 IP 92723 Follow Up Inspection for Three or More Severity Level IV Traditional Enforcement Violations In the S 71124 - PUB RAD SAFETY - RADWASTE 2,3 08/30/2010 09/03/2010 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage. and Transportation 7111111B
- REQUAL INSP (MS2) WITH P/F RESULTS 3 2,3 11/0112010 11/05/2010 IP 71111118 Licensed Operator Requalification F'rogram EPEX
- EP EXERCISE EVALUATION 4 2,3 10/18/2010 10/22/2010 IF' 7111401 Exercise Evaluation 2,3 10/1812010 10/22/2010 IP 7111404 Emergency Action Level and Emergency Plan Changes 2,3 10/1812010 10/22/2010 IP 71151-EP01 DrililExercise Performance 2,3 1011812010 10/22/2010 IP 71151-EP02 ERO Drill Participation 2,3 10/1812010 10/22/2010 IP 71151*EP03 Alert & Notification System ISFSI
- ANNUAL SAMPLE - ISFSIINSPECTION 2 10/01/2010 1213112010 IP 60855 Operation Of An ISFSI 3/14EXM - OPERATOR UCENSING INITIAL EXAMS 5 2 02114/2011 02118/2011 U01834 FY11- MILLSTONE 2, INITIAL OL EXAM 2 0311412011 03125/2011 U01834 FY11* MILLSTONE 2, INITIAL OL EXAM MODS
- PERMANENT PLANT MODIFICATIONS 3 2,3 11/01/2010 11/05/2010 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 2,3 11/15/2010 11/19/2010 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 71124
- OCC RAD SAFETY* INSTRUMENTS & ISFSI 2.3 11/1512010 11/1912010 IP 60855 Operation Of An ISFSI 2,3 11/1512010 11/19/2010 IF' 71124.05 Radiation Monitoring Instrumentation 2,3 11/15/2010 11/1912010 IP 71151 Performance indicator Verification 07/11EXM "OPERATOR LICENSING INITIAL EXAMS 5 3 06113/2011 06/1712011 U01832 FY11- MILLSTONE 3, INITIAL OL EXAM
- 3 07/11/2011 07/20/2011 U01832 FY11- MILLSTONE 3, INITIAL Ol EXAM 71124
- OCC RAD SAFETY 1 2,3 02/28/2011 03/04/2011 IP 71124.01 Radiological Hazard Assessment and ExPosure Controls 2,3 02/28/2011 03/04/2011 IP 71124.02 Occupational ALARA Planning and Controls
~hiS report does notTnclude INPO and OUTAGE activities .
.!hiS report shows only on-site and announced inspection procedures.
Page2of2 Millstone 0812512010 08:57:39 Inspection I Activity Plan Report 22 07/01/2010 - 12131/2011 Planned Dates Start End Title TI-177 * 'MANAGING GAS ACCUMULATION IN ECCS 3 2,3 03/07/2011 03/11/2011 IP 25151177 Managing Gas Accumulation In Emergency Core Cooling. Decay Heat Removal & Containment Spray System 7111108P - U21NSERVICE INSPECTION 2 04/11/2011 04/22/2011 IP 7111108P Inservice Inspection Activities* PWR 71124 - OCC RAD SAFETY 2,3 04/18/2011 04/22/2011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 2.3 04118/2011 04122/2011 IP 71124,02 Occupational ALARA Planning and Controls 2,3 0411812011 0412212011 IP 71124.04 Occupational Dose Assessment 71124
- EFFLUENTS 1 2,3 05/23/2011 05/2712011 lP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 711111B
- MS3 REQUAL INSP WI P/F RESULTS 3 2,3 0812912011 09/0212011 IP 7111111 B Licensed Operator Requalification Program EP PROGR - EP PROGRAM INSPECTION 2.3 08101/2011 08/05/2011 IP 7111402 Alert and Notification System Testing 2,3 08/01/2011 08105/2011 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 2.3 08/0112011 08/05/2011 IP 7111404 Emergency Action Level and Emergency Plan Changes 2,3 06/01/2011 08/05/2011 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 2.3 08/01/2011 OB/0512011 IP 71151*EP02 ERO Drill Participation 2,3 OB/01/2011 OB/05/Z011 IP 71151*EP03 Alert & Notification System 2.3 OB/01/2011 0810712011 IP 71151*EP01 Drill/Exercise Performance 71124 - PUB RAD SAFETY - REMP 2,3 0812212011 08126/2011 IP 71124.07 Radiological Environmental Monitoring Program 71124 - OCC RAD SAFETY 1 2.3 1011712011 10121/2011 IP 71124.01 Radiological Hazard Assessment and ExPosure Controls 2,3 10/17/2011 10121/2011 IP 71124.02 Occupational ALARA Planning and Controls 2,3 10/1712011 1012112011 lP 71124.04 Occupational Dose Assessment 711110SP
- U3 INSERVICE INSPECTION 1 3 10/17/2011 10/2812011 IP 7111108P Inservice Inspection Activities - PWR his report does not indude INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.