Mid-Cycle Performance Review and Inspection Plan - Millstone Station Units 2 and 3
ML072430946
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 08/31/2007
From: Racquel Powell
NRC/RGN-I/DRP/PB5
To: Christian D
Dominion Resources
References
Download: ML072430946 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 August 31, 2007 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Dominion Resources 5000 Dominion Boulevard Glenn Allen, VA 23060-6711

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - MILLSTONE STATION UNITS 2 AND 3

Dear Mr. Christian:

On August 8, 2007, the NRC staff completed its performance review of Millstone Station Units 2 and 3 for the first half of the calendar year 2007 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only--Security Information" will include the security cornerstone review and resultant inspection plan.

Plant performance for the most recent quarter of 2007 at Millstone Units 2 and 3 was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.

The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2008. In addition to baseline inspections, we plan on conducting an independent spent fuel storage installation (ISFSI) inspection. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

D. Christian 2 As you may know, the NRC is currently evaluating the scope and frequency of all of the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-6967 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Raymond J. Powell, Chief Projects Branch 5 Division of Reactor Projects Docket Nos.: 50-336, 50-423 License Nos.: DPR-65, NPF-49

Enclosure:

Millstone Units 2 and 3 Inspection/Activity Plan cc w/encl:

J. A. Price, Site Vice President, Millstone Station C. L. Funderburk, Director, Nuclear Licensing and Operations Support D. W. Dodson, Supervisor, Station Licensing J. Spence, Manager Nuclear Training L. M. Cuoco, Senior Counsel C. Brinkman, Manager, Washington Nuclear Operations J. Roy, Director of Operations, Massachusetts Municipal Wholesale Electric Company First Selectmen, Town of Waterford B. Sheehan, Co-Chair, NEAC E. Woollacott, Co-Chair, NEAC E. Wilds, Director, State of Connecticut SLO Designee J. Buckingham, Department of Public Utility Control G. Proios, Suffolk County Planning Dept.

R. Shadis, New England Coalition Staff G. Winslow, Citizens Regulatory Commission (CRC)

S. Comley, We The People D. Katz, Citizens Awareness Network (CAN)

R. Bassilakis, CAN J. M. Block, Attorney, CAN P. Eddy, Electric Division, Department of Public Service, State of New York M. Balboni, Deputy Secretary for Public Safety, New York State J. Spath, SLO Designee, New York State Energy Research and Development Authority N. Burton, Esq.

Institute of Nuclear Power Operations (INPO)

As you may know the NRC is currently evaluating the scope and frequency of all of the baseline

D. Christian 3 inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible.

Please contact me at 610-337-6967 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Raymond J. Powell, Chief Projects Branch 5 Division of Reactor Projects Docket Nos.: 50-336, 50-423 License Nos.: DPR-65, NPF-49

Enclosure:

Millstone Units 2 and 3 Inspection/Activity Plan J. A. Price, Site Vice President, Millstone Station C. L. Funderburk, Director, Nuclear Licensing and Operations Support D. W. Dodson, Supervisor, Station Licensing J. Spence, Manager Nuclear Training L. M. Cuoco, Senior Counsel C. Brinkman, Manager, Washington Nuclear Operations J. Roy, Director of Operations, Massachusetts Municipal Wholesale Electric Company First Selectmen, Town of Waterford B. Sheehan, Co-Chair, NEAC E. Woollacott, Co-Chair, NEAC E. Wilds, Director, State of Connecticut SLO Designee J. Buckingham, Department of Public Utility Control G. Proios, Suffolk County Planning Dept.

R. Shadis, New England Coalition Staff G. Winslow, Citizens Regulatory Commission (CRC)

S. Comley, We The People D. Katz, Citizens Awareness Network (CAN)

R. Bassilakis, CAN J. M. Block, Attorney, CAN P. Eddy, Electric Division, Department of Public Service, State of New York M. Balboni, Deputy Secretary for Public Safety, New York State J. Spath, SLO Designee, New York State Energy Research and Development Authority N. Burton, Esq.

Institute of Nuclear Power Operations (INPO)

DOCUMENT NAME: S:\ROP 8 Mid Cycle Review\Letters for Mid Cycle\Branch 5 Mid-cycle letters\ROP-8 2007 Mid-cycle Millstone Letter.Rev6.wpd SUNSI Review Complete: BSN (Reviewers Initials)

After declaring this document An Official Agency Record it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP RI/DRP NAME NSieller/BSN FOR BNorris/BSN RPowell/RJP DATE 08/30/07 08/30/07 08/31/07 OFFICIAL RECORD COPY

Letter for David A. Christian from Raymond J. Powell 4 dated August 31, 2007 Distribution w/encl: (via E-mail) D. Screnci, PAO S. Collins, RA N. Sheehan, PAO M. Dapas, DRA R. Barkley, ORA D. Lew, DRP D. Holody, ORA J. Clifford, DRP S. Collins, RA M. Cox, RI OEDO M. Dapas, DRA J. Thompson, NRR R. Laufer, RI OEDO R. Powell, DRP H. Chernoff, NRR B. Norris, DRP J. Lubinski, NRR N. Sieller, DRP J. Hughey NRR, PM M. Gamberoni, DRS E. Miller, NRR D. Roberts, DRS N. Sieller, Acting RI J. Trapp, DRS R. Powell, DRP J. Rogge, DRS B. Norris, DRP M. Sykes, DRS Region I Docket Room (with concurrences)

J. White, DRS RidsNrrDirslpab@nrc.gov L. Doerflein, DRS ROPreports@nrc.gov R. Conte, DRS L. Scholl, DRS P. Frechette, DRS D. Silk, DRS

Page 1 of 2 Millstone 08/27/2007 13:52:56 Inspection / Activity Plan Report 22 07/01/2007 - 12/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 7111111B - L.O. REQUAL.PROG.(FOCUS U3)+P/F RVW 3 2, 3 IP 7111111B Licensed Operator Requalification Program 10/15/2007 10/19/2007 Baseline Inspections 71114 - EP PRGM INSP 1 2, 3 IP 7111402 Alert and Notification System Testing 09/10/2007 09/14/2007 Baseline Inspections 2, 3 IP 7111403 Emergency Response Organization Augmentation Testing 09/10/2007 09/14/2007 Baseline Inspections 2, 3 IP 7111404 Emergency Action Level and Emergency Plan Changes 09/10/2007 09/14/2007 Baseline Inspections 2, 3 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 09/10/2007 09/14/2007 Baseline Inspections 2, 3 IP 71151-EP01 Drill/Exercise Performance 09/10/2007 09/14/2007 Baseline Inspections 2, 3 IP 71151-EP02 ERO Drill Participation 09/10/2007 09/14/2007 Baseline Inspections 2, 3 IP 71151-EP03 Alert & Notification System 09/10/2007 09/14/2007 Baseline Inspections TRI FIRE - TRIENNIAL FIRE PROTECTION INSPECTION 3 3 IP 7111105T Fire Protection [Triennial] 09/17/2007 09/21/2007 Baseline Inspections 3 IP 7111105T Fire Protection [Triennial] 10/01/2007 10/05/2007 Baseline Inspections 7112103 - OCC RAD SAFETY - INSTRUMENTS 1 2, 3 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 09/24/2007 09/28/2007 Baseline Inspections ISFSI - ISFSI INSPECTIONS 1 2, 3 IP 60854.1 Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants 10/01/2007 12/31/2007 Other Routine 7112203 - PUB RAD SAFETY - REMP 1 2, 3 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 10/29/2007 11/02/2007 Baseline Inspections 7111117B - MODS AND 50.59 2 2, 3 IP 7111102 Evaluation of Changes, Tests, or Experiments 11/05/2007 11/09/2007 Baseline Inspections 2, 3 IP 7111117B Permanent Plant Modifications 11/05/2007 11/09/2007 Baseline Inspections 7112101 - OCC RAD SAFETY - ACCESS 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 02/11/2008 02/15/2008 Baseline Inspections 71152B - PI&R 4 2, 3 IP 71152B Identification and Resolution of Problems 02/11/2008 02/15/2008 Baseline Inspections 2, 3 IP 71152B Identification and Resolution of Problems 02/25/2008 02/29/2008 Baseline Inspections EP - EP EXERCISE EVALUATION 4 2, 3 IP 7111401 Exercise Evaluation 03/17/2008 03/21/2008 Baseline Inspections 2, 3 IP 7111404 Emergency Action Level and Emergency Plan Changes 03/17/2008 03/21/2008 Baseline Inspections 2, 3 IP 71151-EP01 Drill/Exercise Performance 03/17/2008 03/21/2008 Baseline Inspections 2, 3 IP 71151-EP02 ERO Drill Participation 03/17/2008 03/21/2008 Baseline Inspections 2, 3 IP 71151-EP03 Alert & Notification System 03/17/2008 03/21/2008 Baseline Inspections 7111108P - U2 INSERVICE INSPECTION 1 2 IP 7111108P Inservice Inspection Activities - PWR 04/07/2008 04/11/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 2 Millstone 08/27/2007 13:52:56 Inspection / Activity Plan Report 22 07/01/2007 - 12/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 7111108P - U2 INSERVICE INSPECTION 1 2 IP 7111108P Inservice Inspection Activities - PWR 04/21/2008 04/25/2008 Baseline Inspections 7112102 - OCC RAD SAFETY - ALARA 1 2, 3 IP 7112102 ALARA Planning and Controls 05/12/2008 05/16/2008 Baseline Inspections 7111111B - L.O. REQUAL.PROG.(FOCUS U2)+P/F RVW 5 2, 3 IP 7111111B Licensed Operator Requalification Program 09/08/2008 09/12/2008 Baseline Inspections 7111121 - CDBI 7 2, 3 IP 7111121 Component Design Bases Inspection 07/14/2008 07/18/2008 Baseline Inspections 2, 3 IP 7111121 Component Design Bases Inspection 07/28/2008 08/01/2008 Baseline Inspections 2, 3 IP 7111121 Component Design Bases Inspection 08/04/2008 08/08/2008 Baseline Inspections 7112202 - PUB RAD SAFETY - RADWASTE 1 2, 3 IP 7112202 Radioactive Material Processing and Transportation 07/14/2008 07/18/2008 Baseline Inspections 7111107B - HEAT SINK (BOTH UNITS) 1 2 IP 7111107B Heat Sink Performance 08/18/2008 08/22/2008 Baseline Inspections 7112102 - OCC RAD SAFETY - ALARA 1 2, 3 IP 7112102 ALARA Planning and Controls 09/08/2008 09/12/2008 Baseline Inspections 1/12EXAM - U2 INITIAL OPERATOR LICENSING EXAMS 4 2 U01634 MILLSTONE 2 INITIAL EXAM (FY08) 12/16/2008 12/19/2008 Not Applicable 7111108P - U3 INSERVICE INSPECTION 1 3 IP 7111108P Inservice Inspection Activities - PWR 10/13/2008 10/17/2008 Baseline Inspections 3 IP 7111108P Inservice Inspection Activities - PWR 10/20/2008 10/24/2008 Baseline Inspections TRI FIRE - TRIENNIAL FIRE PROTECTION INSPECTION 3 2 IP 7111105T Fire Protection [Triennial] 11/17/2008 11/21/2008 Baseline Inspections 2 IP 7111105T Fire Protection [Triennial] 12/01/2008 12/05/2008 Baseline Inspections 7112103 - OCC RAD SAFETY - INSTRUMENTS 1 2, 3 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 12/01/2008 12/05/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.