UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406 December 13, 2007 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Dominion Resources 5000 Dominion Boulevard Glenn Allen, VA 23060-6711

SUBJECT:

CHANGE TO THE INSPECTION PLAN - MILLSTONE STATION UNITS 2 AND 3

Dear Mr. Christian:

As part of a periodic self-assessment, the Nuclear Regulatory Commission (NRC) thoroughly reviewed the inspection procedures to ensure the continued effective application of inspection resources. The main objective of the review was to determine the appropriate inspection scope for the majority of the inspection procedures in the reactor oversight process (ROP). The result of this effort (designated ROP realignment) created changes to both inspection scope and/or inspection frequency for selected inspection procedures in the ROP. The purpose of this letter is to update the schedule of future inspection activities at your facility that was provided with the mid-cycle assessment letter in August 2007. Please note that there were no changes made to inspection procedures in the security, emergency preparedness, and health physics areas.

The enclosed inspection plan details the inspections (less those related to physical protection) scheduled for calendar year 2008. The inspection plan is provided to resolve any scheduling and/or personnel availability issues well in advance of the inspector(s) arrival onsite. Routine resident inspections are not listed due to their continuous nature.

In accordance with 10 CFR 2.390 of the NRCs Rules and Practices a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room).

D. Christian 2 Please contact me at 610-337-6967 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Raymond J. Powell, Chief Projects Branch 5 Division of Reactor Projects Docket Nos. 50-336 and 50-423 License No. DPR-65 and NPF-49

Enclosures:

Millstone Station Units 2 and 3 Inspection/Activity Plans cc w/encl:

J. A. Price, Site Vice President, Millstone Station C. L. Funderburk, Director, Nuclear Licensing and Operations Support D. W. Dodson, Supervisor, Station Licensing J. Spence, Manager Nuclear Training L. M. Cuoco, Senior Counsel C. Brinkman, Manager, Washington Nuclear Operations J. Roy, Director of Operations, Massachusetts Municipal Wholesale Electric Company First Selectmen, Town of Waterford B. Sheehan, Co-Chair, NEAC E. Woollacott, Co-Chair, NEAC E. Wilds, Jr., Ph.D, Director, State of Connecticut SLO Designee J. Buckingham, Department of Public Utility Control C. Meek-Gallagher, Commissioner, Suffolk County, Department of Environment and Energy V. Minei, P.E., Director, Suffolk County Health Department, Division of Environmental Quality R. Shadis, New England Coalition Staff S. Comley, We The People D. Katz, Citizens Awareness Network (CAN)

R. Bassilakis, CAN cc w/encl:

J. M. Block, Attorney, CAN P. Eddy, Electric Division, Department of Public Service, State of New York P. Tonko, President and CEO, New York State Energy Research and Development Authority J. Spath, SLO Designee, New York State Energy Research and Development Authority N. Burton, Esq.

D. Christian 3 Please contact me at 610-337-6967 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Raymond J. Powell, Chief Projects Branch 5 Division of Reactor Projects Docket Nos. 50-336 and 50-423 License No. DPR-65 and NPF-69

Enclosures:

Millstone Station Units 2 and 3 Inspection/Activity Plans Distribution w/encl: ROPreports@nrc.gov S. Collins, RA J. Trapp, DRS M. Dapas, DRA J. Rogge, DRS G. West, RI OEDO (Acting) M. Sykes, DRS H. Chernoff, NRR J. White, DRS J. Lubinski, NRR L. Doerflein, DRS J. Hughey NRR, PM R. Conte, DRS E. Miller, NRR L. Scholl, DRS S. Shaffer, SRI P. Frechette, DRS J. Benjamin, RI D. Silk, DRS R. Powell, DRP D. Screnci, PAO B. Norris, DRP N. Sheehan, PAO Region I Docket Room (w/concurrences) R. Barkley, ORA RidsNrrDirslpab@nrc.gov D. Holody, ORA J. Thompson, NRR (JWT1@nrc.gov)

SUNSI Review Complete: RJP (Reviewer=s Initials)

DOCUMENT NAME: G:\DRP\BRANCH2\ROP 8\ROP Realignment Letters\IP2 and IP3 ROP Realignment Letter.wpd After declaring this document AAn Official Agency Record@ it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP NAME NSieller/NSS RPowell/RJP DATE 12/12/07 12/12/07 OFFICIAL RECORD COPY

Page 1 of 1 Millstone 12/11/2007 14:30:25 Inspection / Activity Plan Report 22 01/01/2008 - 12/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 7112101 - OCC RAD SAFETY - ACCESS 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 02/11/2008 02/15/2008 Baseline Inspections 71152B - PI&R 7 2, 3 IP 71152B Identification and Resolution of Problems 02/11/2008 02/15/2008 Baseline Inspections 2, 3 IP 71152B Identification and Resolution of Problems 02/25/2008 02/29/2008 Baseline Inspections EP - EP EXERCISE EVALUATION 4 2, 3 IP 7111401 Exercise Evaluation 03/17/2008 03/21/2008 EP Baseline Inspectio 2, 3 IP 7111404 Emergency Action Level and Emergency Plan Changes 03/17/2008 03/21/2008 EP Baseline Inspectio 2, 3 IP 71151-EP01 Drill/Exercise Performance 03/17/2008 03/21/2008 Baseline Inspections 2, 3 IP 71151-EP02 ERO Drill Participation 03/17/2008 03/21/2008 Baseline Inspections 2, 3 IP 71151-EP03 Alert & Notification System 03/17/2008 03/21/2008 Baseline Inspections 7111108P - U2 INSERVICE INSPECTION 1 2 IP 7111108P Inservice Inspection Activities - PWR 04/07/2008 04/11/2008 Baseline Inspections 2 IP 7111108P Inservice Inspection Activities - PWR 04/21/2008 04/25/2008 Baseline Inspections 7112102 - OCC RAD SAFETY - ALARA 1 2, 3 IP 7112102 ALARA Planning and Controls 05/05/2008 05/09/2008 Baseline Inspections 7111111B - L.O. REQUAL.PROG.(FOCUS U2)+P/F RVW 3 2, 3 IP 7111111B Licensed Operator Requalification Program 09/08/2008 09/12/2008 Baseline Inspections 7112202 - PUB RAD SAFETY - RADWASTE 1 2, 3 IP 7112202 Radioactive Material Processing and Transportation 07/14/2008 07/18/2008 Baseline Inspections 7112102 - OCC RAD SAFETY - ALARA 1 2, 3 IP 7112102 ALARA Planning and Controls 09/08/2008 09/12/2008 Baseline Inspections 1/19EXAM - U2 INITIAL OPERATOR LICENSING EXAMS 4 2 U01634 FY U2 MILLSTONE INITIAL OL EXAM 12/15/2008 12/19/2008 Not Applicable 7111108P - U3 INSERVICE INSPECTION 1 3 IP 7111108P Inservice Inspection Activities - PWR 10/13/2008 10/17/2008 Baseline Inspections 3 IP 7111108P Inservice Inspection Activities - PWR 10/20/2008 10/24/2008 Baseline Inspections 71121.02 - OCC RAD SAFETY 1 2 IP 7112102 ALARA Planning and Controls 10/20/2008 10/24/2008 Baseline Inspections TRI FIRE - TRIENNIAL FIRE PROTECTION INSPECTION 3 2 IP 7111105T Fire Protection [Triennial] 11/17/2008 11/21/2008 Baseline Inspections 2 IP 7111105T Fire Protection [Triennial] 12/01/2008 12/05/2008 Baseline Inspections 7112103 - OCC RAD SAFETY - INSTRUMENTS 1 2, 3 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 12/01/2008 12/05/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.