Mid-Cycle Performance Review and Inspection Plan - 2013 Millstone Power Station Units 2 and 3
ML12244A402
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 09/04/2012
From: Darrell Roberts
Division Reactor Projects I
To: Heacock D
Dominion Resources
References
IR-12-006
Download: ML12244A402 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 September 4, 2012 Mr. David Heacock Sr. Vice President and Chief Nuclear Officer Dominion Resources 500 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

MILLSTONE POWER STATION UNIT 2 AND UNIT 3 (REPORT 05000336/2012006 and 05000423/2012006)

Dear Mr. Heacock:

On August 14, 2012, the U. S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Millstone Power Station Unit 2 and Unit 3. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2011, through June 30, 2012. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

This assessment reflects the integration of the Security Cornerstone into the Reactor Oversight Process (ROP) performance assessment program governed by Inspection Manual Chapter (IMC) 0305, Operating Reactor Assessment Program.

The NRC determined the performance at Millstone Power Station Unit 2 during the most recent quarter was within the Regulatory Response Column of the NRCs ROP Action Matrix based on one finding assigned to the second quarter of 2011 having low to moderate safety significance (White) in the Initiating Events Cornerstone. This finding involved the failure of Unit 2 Millstone personnel to carry out their assigned roles and responsibilities and inadequate reactivity management during main turbine valve testing, which contributed to an unintended eight percent reactor power transient (88 percent to 96 percent) on February 12, 2011.

As a result of our review of Millstone Power Station Unit 2 performance, we plan to conduct a supplemental inspection using NRC Inspection Procedure 95001, Inspection for One or Two White Inputs in a Strategic Performance Area, in September 2012. This inspection procedure is conducted to provide assurance that the root cause and contributing causes of risk significant performance issues are understood, the extent of condition is identified, and the corrective actions are sufficient to prevent recurrence.

The NRC determined the performance at Millstone Power Station Unit 3 during the most recent quarter was within the Licensee Response Column of the NRC=s Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at Unit 3.

The enclosed inspection plan lists the inspections scheduled through December 31, 2013.

Routine inspections performed by resident inspectors are not included in the inspection plan.

D. Heacock 2 In addition to the baseline inspections, consistent with the Agencys actions related to Fukushima, the NRC will perform TI-187, Inspection of Near-Term Task Force Recommendation 2.3 Flooding Walkdowns, and TI-188, Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review.

The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.

In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Dr. Ronald R. Bellamy at (610) 337-5200 with any questions you have regarding this letter.

Sincerely,

/RA/

Darrell J. Roberts, Director Division of Reactor Projects Docket Nos.: 50-336, 50-423 License Nos.: DPR-65, NPF-49

Enclosure:

Millstone Inspection/Activity Plan cc w/encl: Distribution via ListServ

ML12244A402 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME TSetzer RBellamy DRoberts DATE 08/28/12 08/29/12 08/30/12 Page 1 of 3 Millstone 08/30/2012 12:33:38 Inspection / Activity Plan Report 22 07/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EP - EP ANNUAL REPORT 4 2, 3 06/30/2012 12/31/2012 IP 7111406 Drill Evaluation EP EX - EP EXERCISE EVALUATION 9 2, 3 06/21/2012 08/28/2012 IP 7111401 Exercise Evaluation 2, 3 08/19/2012 08/24/2012 IP 71151 Performance Indicator Verification 71152B - PI&R 4 2, 3 07/16/2012 07/20/2012 IP 71152B Problem Identification and Resolution 2 07/30/2012 08/03/2012 IP 71152B Problem Identification and Resolution TI 182 - DEGRADATION OF UNDERGROUND PIPING 1 2, 3 07/09/2012 07/13/2012 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 71124 - RADWASTE 1 2, 3 07/23/2012 07/27/2012 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 7111111B - MS2 ON-SITE REQUAL INSP W/ P/F RESULTS 2 2 09/17/2012 09/21/2012 IP 7111111B Licensed Operator Requalification Program 71152 - PIR SAMPLE MILLSTONE COMMITMENT FOLLOWUP 1 2, 3 07/30/2012 08/03/2012 IP 71152 Problem Identification and Resolution 2515/188 - SEISMIC WALKDOWNS 3 2, 3 08/06/2012 08/10/2012 IP 2515/188 Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns 2515/187 - FLOODING WALKDOWNS 3 2, 3 08/20/2012 08/24/2012 IP 2515/187 Inspection of Near-Term Task Force Recommendation 2.3 Flooding Walkdowns 95001 - 95001 SUPPLEMENTAL INSPECTION 2 2 09/17/2012 09/21/2012 IP 95001 Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area 71124 - OCC RADIATION SAFETY 1 2, 3 10/15/2012 10/19/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 2, 3 10/15/2012 10/19/2012 IP 71124.02 Occupational ALARA Planning and Controls 2, 3 10/15/2012 10/19/2012 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 2, 3 10/15/2012 10/19/2012 IP 71124.04 Occupational Dose Assessment 7111108P - UNIT 2 INSERVICE INSPECTION 1 2 10/15/2012 10/26/2012 IP 7111108P Inservice Inspection Activities - PWR 71124 - OCC RAD SAFETY 1 2, 3 12/10/2012 12/14/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 2, 3 12/10/2012 12/14/2012 IP 71124.02 Occupational ALARA Planning and Controls 2, 3 12/10/2012 12/14/2012 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 3 Millstone 08/30/2012 12:33:38 Inspection / Activity Plan Report 22 07/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 71124 - OCC RAD SAFETY 1 2, 3 12/10/2012 12/14/2012 IP 71124.04 Occupational Dose Assessment 71124 - HP INSTRUMENTATION 1 2, 3 12/17/2012 12/21/2012 IP 71124.05 Radiation Monitoring Instrumentation EP - EP ANNUAL REPORT 4 2, 3 07/01/2013 12/31/2013 IP 7111406 Drill Evaluation MODS - PERMANENT PLANT MODIFICATIONS 7 2, 3 01/28/2013 02/01/2013 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 2, 3 02/11/2013 02/15/2013 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications EP PROGR - EP PROGRAM INSPECTION 1 2, 3 02/11/2013 02/15/2013 IP 7111402 Alert and Notification System Testing 2, 3 02/11/2013 02/15/2013 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 2, 3 02/11/2013 02/15/2013 IP 7111404 Emergency Action Level and Emergency Plan Changes 2 02/11/2013 02/15/2013 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 8/12 EXM - MILLSTONE 2 INITIAL EXAM 4 2 07/15/2013 07/19/2013 U01871 FY13-MILLSTONE 2 INITIAL OPERATOR LICENSING EXAM 2 08/12/2013 08/16/2013 U01871 FY13-MILLSTONE 2 INITIAL OPERATOR LICENSING EXAM 7111108P - U3 INSERVICE INSPECTION 1 3 04/15/2013 04/26/2013 IP 7111108P Inservice Inspection Activities - PWR 71124 - OCC RADIATION SAFETY 1 2, 3 04/29/2013 05/03/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 2, 3 04/29/2013 05/03/2013 IP 71124.02 Occupational ALARA Planning and Controls 71124 - REMP 1 2, 3 05/20/2013 05/24/2013 IP 71124.07 Radiological Environmental Monitoring Program 7111111B - MILLSTONE 3 REQUAL INSP WITH P/F RESULTS 2 3 08/26/2013 08/30/2013 IP 7111111B Licensed Operator Requalification Program TRI FI - TRIENNIAL FIRE PROTECTION INSPECTION 7 2, 3 07/22/2013 07/26/2013 IP 7111105T Fire Protection [Triennial]

2, 3 08/05/2013 08/09/2013 IP 7111105T Fire Protection [Triennial]

10/21EXM - MILLSTONE 3 INITIAL EXAM 4 3 11/04/2013 11/08/2013 U01874 FY14-MILLSTONE 3 INITIAL OPERATOR LICENSING EXAM 3 12/02/2013 12/11/2013 U01874 FY14-MILLSTONE 3 INITIAL OPERATOR LICENSING EXAM This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 3 of 3 Millstone 08/30/2012 12:33:38 Inspection / Activity Plan Report 22 07/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 7111107T - TRIENNIAL HEAT SINK 1 2, 3 07/29/2013 08/09/2013 IP 7111107T Heat Sink Performance 71124 - RADIO EFFLUENTS 1 2, 3 08/26/2013 08/30/2013 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 2, 3 08/26/2013 08/30/2013 IP 71151 Performance Indicator Verification 71124 - ALARA, IN-PLANT AIRBORNE AND DOSE ASSESS 1 2, 3 09/23/2013 09/27/2013 IP 71124.02 Occupational ALARA Planning and Controls 2, 3 09/23/2013 09/27/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 2, 3 09/23/2013 09/27/2013 IP 71124.04 Occupational Dose Assessment 71124 - RAD HAZARD, IN-PLANT AIRBORNE, DOSE ASSE 1 2, 3 12/16/2013 12/20/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 2, 3 12/16/2013 12/20/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 2, 3 12/16/2013 12/20/2013 IP 71124.04 Occupational Dose Assessment 2, 3 12/16/2013 12/20/2013 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.