MONTHYEARML25022A2962025-01-23023 January 2025 Technical Specification Bases Pages ML25023A0392025-01-23023 January 2025 Senior Reactor and Reactor Operator Initial License Examinations L-25-001, Endorsement of Framatomes Requested Review Schedule for Topical Report ANP-10358P, Revision O Increased Burnup for PWRs2025-01-23023 January 2025 Endorsement of Framatomes Requested Review Schedule for Topical Report ANP-10358P, Revision O Increased Burnup for PWRs ML25014A2862025-01-21021 January 2025 Alternative Request to Defer ASME Code Section XI Inservice Inspection Examinations for Pressurizer and Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles IR 05000336/20244032025-01-13013 January 2025 Cyber Security Inspection Report 05000336/2024403 and 05000423/2024403 (Cover Letter Only) ML24365A2032024-12-30030 December 2024 ISFSI - 10 CFR 72.30 Decommissioning Funding Plan ML24351A2422024-12-19019 December 2024 Reactor Coolant System Alloy 600 Inspection Program for License Renewal Commitment No. 15 ML24351A2412024-12-19019 December 2024 Reactor Vessel Internals Inspections Aging Management Program Submittal Related to License Renewal Commitment No. 13 ML24346A2532024-12-12012 December 2024 Correction to Implementation Date for License Amendment No. 291 Regarding Framatome Gaia Fuel IR 05000336/20243012024-12-0606 December 2024 Initial Operator Licensing Examination Report 05000336/2024301 ML24324A0442024-12-0303 December 2024 Issuance of Amendment No. 292 Regarding Adoption of Technical Specification Task Force Traveler TSTF-421 05000336/LER-2024-002, Two Main Steam Safety Valves Failed to Lift within the Acceptance Criteria Resulting in a Condition Prohibited by Technical Specifications2024-11-26026 November 2024 Two Main Steam Safety Valves Failed to Lift within the Acceptance Criteria Resulting in a Condition Prohibited by Technical Specifications 05000423/LER-2024-002, Door Latch Failure Resulted in Loss of Safety Function for Secondary Containment Boundary2024-11-26026 November 2024 Door Latch Failure Resulted in Loss of Safety Function for Secondary Containment Boundary ML24296B2352024-11-19019 November 2024 Issuance of Amendment No. 291 License Amendment to Support the Implementation of Framatome Gaia Fuel (EPID L-2023-LLA-0150) (Non-Proprietary) IR 05000245/20240012024-11-12012 November 2024 Safstor Inspection Report 05000245/2024001 ML24317A2562024-11-12012 November 2024 Core Operating Limits Report, Gycle 30 IR 05000336/20240032024-11-0707 November 2024 Integrated Inspection Report 05000336/2024003 and 05000423/2024003 and Apparent Violation and Independent Spent Fuel Storage Installation Inspection Report 07200008/2024001 ML24289A0152024-10-21021 October 2024 Review of the Fall 2023 Steam Generator Tube Inspection Report 05000423/LER-2024-001, Loss of Safety Function and Condition Prohibited by Technical Specifications for Loss of Secondary Containment Boundary2024-10-14014 October 2024 Loss of Safety Function and Condition Prohibited by Technical Specifications for Loss of Secondary Containment Boundary IR 05000336/20244022024-10-0808 October 2024 Security Baseline Inspection Report 05000336/2024402 and 05000423/2024402 (Cover Letter Only) ML24281A1102024-10-0707 October 2024 Requalification Program Inspection 05000423/LER-2023-006-02, Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications2024-09-26026 September 2024 Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24260A1952024-09-16016 September 2024 Response to Request for Additional Information Regarding Proposed Amendment to Support Implementation of Framatome Gaia Fuel ML24260A2192024-09-16016 September 2024 Decommissioning Trust Fund Disbursement - Revision to Previous Thirty-Day Written Notification ML24248A2272024-09-0404 September 2024 Operator Licensing Examination Approval ML24240A1532024-09-0303 September 2024 Summary of Regulatory Audit Supporting the Review of License Amendment Request for Implementation of Framatome Gaia Fuel IR 05000336/20240052024-08-29029 August 2024 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Reports 05000336/2024005 and 05000423/2024005 IR 05000336/20240022024-08-13013 August 2024 Integrated Inspection Report 05000336/2024002 and 05000423/2024002 ML24221A2872024-08-0808 August 2024 Independent Spent Fuel Storage Installation (ISFSI) - Submittal of Cask Registration for Spent Fuel Storage IR 05000336/20244412024-08-0606 August 2024 Supplemental Inspection Report 05000336/2024441 and 05000423/2024441 and Follow-Up Assessment Letter (Cover Letter Only) ML24212A0742024-08-0505 August 2024 Request for Withholding Information from Public Disclosure - Millstone Power Station, Unit No. 3, Proposed Alternative Request IR-4-13 to Support Steam Generator Channel Head Drain Modification ML24211A1712024-07-25025 July 2024 Associated Independent Spent Fuels Storage Installation, Revision to Emergency Plan - Report of Change ML24200A1062024-07-22022 July 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000336/2024403 and 05000423/2024403 IR 05000336/20245012024-07-0101 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000336/2024501 and 05000423/2024501 ML24180A0932024-06-28028 June 2024 Readiness for Additional Inspection: EA-23-144 IR 05000336/20240102024-06-26026 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000336/2024010 and 05000423/2024010 ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 IR 05000336/20244402024-06-24024 June 2024 Final Significance Determination for Security-Related Greater than Green Finding(S) with Assessment Follow-up; IR 05000336/2024440 and 05000423/2024440 and Notice of Violation(S), NRC Investigation Rpt 1-2024-001 (Cvr Ltr Only) ML24281A2072024-06-20020 June 2024 Update to the Final Safety Analysis Report, Revision 37 (Redacted Version) ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24280A0012024-06-20020 June 2024 Update to the Final Safety Analysis Report (Redacted Version) ML24176A1782024-06-20020 June 2024 Update to the Final Safety Analysis Report ML24176A2622024-06-20020 June 2024 Update to the Final Safety Analysis Report, Revision 37 ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code 05000336/LER-2024-001, Control Room Air Conditioning Unit Inoperable Due to Refrigerant Overcharge Resulting in a Condition Prohibited by Technical Specifications2024-06-10010 June 2024 Control Room Air Conditioning Unit Inoperable Due to Refrigerant Overcharge Resulting in a Condition Prohibited by Technical Specifications ML24170A7832024-06-0606 June 2024 ISFSI, Virgil C. Summer, Unit 1, and ISFSI, North Anna, Units 1 & 2, and ISFSI, Surry, Units 1 & 2, and ISFSI - Submittal of Revision 36 of the Quality Assurance Topical Report ML24165A1292024-06-0505 June 2024 ISFSI, 10 CFR 50.59 Annual Change Report for 2023 Annual Regulatory Commitment Change Report for 2023 ML24128A2772024-06-0404 June 2024 Issuance of Amendment No. 290 to Revise TSs for Reactor Core Safety Limits, Fuel Assemblies, and Core Operating Limits Report for Use of Framatome Gaia Fuel (EPID L-2023-LLA-0074) (Non-Proprietary) ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities 2025-01-23
[Table view] |
Text
September 4, 2024 Eric S. Carr President - Nuclear Operations and Chief Nuclear Officer Dominion Energy, Inc.
Innsbrook Technical Center 5000 Dominion Blvd.
Glen Allen, VA 23060-6711
SUBJECT:
MILLSTONE POWER STATION, UNIT 2 - OPERATOR LICENSING EXAMINATION APPROVAL
Dear Eric Carr:
The purpose of this letter is to provide U.S. Nuclear Regulatory Commission (NRC) approval of the proposed written examination and operating test under Title 10 of the Code of Federal Regulations (10 CFR) 55.40(b)(4) and to confirm the final arrangements for the upcoming operator licensing examination at Millstone Power Station, Unit 2.
The NRC has approved the subject examinations, and you may administer the written examination on September 18, 2024, in accordance with Revision 12 to NUREG-1021, Operator Licensing Examination Standards for Power Reactors, issued September 2021. The NRC staff will administer the operating test during the week of September 9, 2024. The NRC has provided the list of the applicants approved to take the examinations to Mr. Paul Scott, Training Supervisor. The examinations have undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examinations meet the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering the written examination, you also agree that the examinations meet NUREG-1021 guidelines and are appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that these examinations are not appropriate for licensing operators at your facility, do not administer the written examination and contact me at (610) 337-5306.
E. Carr 2
Please contact your NRC Chief Examiner, Chris Lally, at (610) 337-5124, if you have questions or identify any errors or changes in the license level (reactor operator or senior reactor operator) or type of examination (partial or complete written examination or operating test, or both) specified for each applicant approved to take the examinations.
Sincerely, Donald E. Jackson, Chief Operations Branch Division of Operating Reactor Safety Docket No. 05000336 License No. DPR-65 cc: Distribution via ListServ DONALD JACKSON Digitally signed by DONALD JACKSON Date: 2024.09.04 14:48:29 -04'00'
E. Carr 3
SUBJECT:
MILLSTONE POWER STATION, UNIT 2 - OPERATOR LICENSING EXAMINATION APPROVAL DATED SEPTEMBER 4, 2024 DISTRIBUTION:
CLally, DORS DJackson, DORS LPinkham, DORS RClagg, DORS MYoung, DORS SElkhiamy, DORS AChristiano, DORS JFuller, DORS, SRI EBousquet, DORS, RI DAntonangeli, DORS DHochmuth, DORS, AA MEvans, DORS, AA MSimmons, RI OEDO RidsNrrPMMillstone Resource RidsNrrDorlLpl1 Resource DOCUMENT NAME: G:\\DRS\\Operations Branch\\Lally\\Exam FY24-Millstone 2 Sept 2024\\Admin\\Millstone 2 2024 Rev 12 Letter 2.3-1 Examination Approval.docx ADAMS Package Accession Number: ML23349A071 ADAMS Accession Number: ML24248A227 SUNSI Review Non-Sensitive Publicly Available OFFICE RI/DORS/OB:CE RI/DORS/OB:BC NAME CLally/CML DEJackson/DEJ DATE 9/4/24 9/4/24 OFFICIAL RECORD COPY