IR 05000483/2020011

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Teams) Inspection Report 05000483/2020011
ML20106F187
Person / Time
Site: Callaway 
(NPF-030)
Issue date: 04/15/2020
From: Vincent Gaddy
Region 4 Engineering Branch 1
To: Diya F
Ameren Missouri
References
IR 2020011
Preceding documents:
Download: ML20106F187 (22)


Text

April 15, 2020

SUBJECT:

CALLAWAY PLANT - DESIGN BASIS ASSURANCE INSPECTION (TEAMS)

INSPECTION REPORT 05000483/2020011

Dear Mr. Diya:

On March 31, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Callaway Plant. On March 31, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. Two of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Callaway Plant.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Callaway Plant. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Vincent G. Gaddy, Chief Engineering Branch 1 Division of Reactor Safety

Docket No. 05000483 License No. NPF-30

Enclosure:

As stated

Inspection Report

Docket Number:

05000483

License Number:

NPF-30

Report Number:

05000483/2020011

Enterprise Identifier: I-2020-011-0012

Licensee:

Ameren Missouri

Facility:

Callaway Plant

Location:

Steedman, MO

Inspection Dates:

March 2, 2020 to March 20, 2020

Inspectors:

J. Braisted, Reactor Inspector

G. Callaway, Senior Reactor Technology Instructor

S. Gardner, Contractor

G. George, Senior Reactor Inspector, Team Lead

S. Makor, Reactor Inspector

M. Yeminy, Contractor

Approved By:

Vincent G. Gaddy, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Callaway Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to evaluate Class 1E 4160 VAC (NB) System Train A for (a)(1) Status in Maintenance Rule Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000483/2020011-01 Open/Closed

[H.8] -

Procedure Adherence 71111.21M The inspectors identified a Green non-cited violation of 10 CFR 50.65 (a)(1), for failure to evaluate a maintenance preventable functional failure of Class 1E 4160 Vac system for 10 CFR 50.65 (a)(1) status following the failure of breaker NB0101.

Failure to Use Appropriate Design Pressure Inputs for Diesel Generator Room and Essential Service Water Pumphouse HVAC System Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000483/2020011-02 Open/Closed None (NPP)71111.21M The inspectors identified a Green non-cited violation of 10 CFR 50, Appendix B, Criterion III,

"Design Control," for the failure of the licensee to specify design inputs for design pressures of the emergency diesel generator and essential service water pumphouse ventilation ducts that are required to withstand the negative pressure caused by the fan when its suction path is blocked by a tornado damper.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), regional inspectors were directed to begin teleworking. The inspection documented below was determined that the objectives and requirements stated in the IP could be completed remotely.

REACTOR SAFETY

===71111.21M - Design Bases Assurance Inspection (Teams)

The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (6 Samples 1 Partial)

From March 2, 2020, to March 20, 2020, the team inspected the following components and listed applicable attributes.

(1)480 V Bus NG02

Component walkdown and visual inspection was performed to assess the material condition and configuration

Maintenance and testing procedures and performance history was reviewed to assure consistency with vendor and industry recommendations

Design bases documents, updated safety analysis report, technical specifications and bases to assure licensing bases match component capabilities

Component maintenance history and corrective action program reports to verify the monitoring of potential degradation

Calculations for electrical distribution, system load flow, voltage drop, short-circuit, and electrical protection to verify that bus capacity and voltages remained within minimum acceptable limits

(2)4.16 KV Bus NB02

Component maintenance history and corrective action program reports to verify the monitoring for potential degradation

Short circuit calculation to determine adequacy of design

Procedures for circuit breaker inspection and testing to compare maintenance practices against industry and vendor guidance Calculations for DC control voltage to meet acceptance criteria for new Square D breakers

Breaker tracking for maintenance history by serial number

(3)480 V Motor Control Center, NG03C

Component walkdown and vendor document review to verify installed configuration, specifications and acceptance criteria and design bases functions

Procedures for circuit breaker inspection and testing to compare maintenance practices against industry standards and vendor guidance

Maintenance and testing procedures and performance history was reviewed to assure consistency with vendor and industry recommendations

Design bases documents, updated safety analysis report, technical specifications and bases to assure licensing bases match component capabilities

(4) Motor Driven Auxiliary Feedwater Pump A, PAL01A

Pump inservice testing plan which established the test intervals and parameters to be measured to meet ASME Code requirements

Results of comprehensive and quarterly motor driven auxiliary feedwater pump testing

Calculations for auxiliary feedwater pump available net positive suction head and suction pressure setpoints for suction source swapover

Flow models of the auxiliary feedwater system during normal operating conditions or postulated scenarios

Design bases document and piping and instrumentation diagram for the auxiliary feedwater system.

Vendor manuals for the motor driven auxiliary feedwater pump

Corrective action documents to verify the monitoring of potential degradation

(5) Diesel Generator Supply Fan, CGM01A

Component walkdown and vendor document review to verify installed configuration, specifications and acceptance criteria, and design bases functions

Fan and duct design drawing, vendor specifications, pressure curves, flow calculations and structural integrity calculations

Emergency room heating and ventilation calculations

Protection against external events (seismic and tornado)

Setpoints and instrument uncertainty of recirculation damper system operating instrumentation and controls

Normal and emergency operating procedures

Maintenance effectiveness

(6) Load Shed and Sequencing Train B, NF039B

Validate qualification and seismic requirements

Control logic for capacitor bank permissives

Procedures for response time testing to determine consistency between design bases, calculations, and testing acceptance criteria

Effect of charging times of new Square D breakers on sequencing interval

(7) Evaluation of Operator Procedures and Actions Related to Components

1. Control room operator actions resulting from a simulated steam generator

tube rupture (SGTR) with a stuck open atmospheric steam dump (ASD). Verify the following actions are performed within the required completion times in accordance with the FSAR:

a. Close block valve to failed open ASD 20 minutes after the ASD opens b. Isolate the failed train to the control room HVAC filtration system in 30 minutes from event initiation c. Initiate a reactor coolant system (RCS) cooldown in 40 minutes from event initiation d. Complete the RCS cooldown in 56 minutes from event initiation e. Complete the RCS depressurization in 60 minutes from event initiation f.

Terminate safety injection (SI) in 5 minutes after the depressurization is completed g. Equalize RCS and ruptured steam generator pressures in 15 minutes after SI termination

2. Control room operator actions resulting from a simulated feedwater line break

to the steam generators between the feedwater isolation valve and the check valve. Verify the resulting internal flooding is isolated in 30 minutes from event initiation.

3. Control room operator actions resulting from a simulated loss of secondary

heat sink. Verify that the crew re-establishes main feedwater flow prior to the need to initiate bleed and feed cooling of the reactor coolant system.

4. Auxiliary operator actions to locally line up the hardened condensate storage

tank (HCST) to the non-safety auxiliary feedwater pump within 20 minutes of task assignment.

Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===

From March 2, 2020, to March 20, 2020, the team inspected the following large-early-release-frequency component.

(1) Residual Heat Removal Pumps to Reactor Coolant System Cold Leg Loops Check Valves, EP8818 A, B, C, D

Valve inservice testing plan which established the test intervals and parameters to be measured to meet ASME Code requirements

Results of inservice testing of full stroke open capability and seat leakage rate (valve closure)

Results of instrument calibrations for seat leakage rate testing.

Design bases document and piping and instrumentation diagram for the emergency core cooling system

Vendor manuals for the residual heat removal pumps to reactor coolant system cold leg loops check valves

Corrective action documents to verify the monitoring of potential degradation

Modification Review - Permanent Mods (IP Section 02.03) (4 Samples)

From March 2, 2020, to March 20, 2020, the team inspected the following permanent modifications.

(1) MP 13-0002, "Replace EDG Supply Fans CGM01 A and B"
(2) MP 16-0027, "Approval of Remanufactured ESFAS and LSELS Circuit Boards"
(3) MP 17-0006, "ESW Water Hammer Mitigation Modification"
(4) MP 18-0019, "NG02BER2-Replace SR 480 VAC MCC Buckets"

Review of Operating Experience Issues (IP Section 02.06) (3 Samples)

From March 2, 2020, to March 20, 2020, the team inspected the following operating experience issues.

(1) Callaway OpE 201801880, "OE Received from Comanche Peak Station Electric Station Related to Component Cooling Water System Cross Tie Valves"
(2) Callaway OpE 20190019, "Ametek Solid State Controls Part 21"
(3) NRC Operating Experience Smart Sample (OpESS) 2019/01, "Commercial Grade Dedication, Procurement, and Design Control"

INSPECTION RESULTS

Failure to evaluate Class 1E 4160 VAC (NB) System Train A for (a)(1) Status in Maintenance Rule Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green NCV 05000483/2020011-01 Open/Closed

[H.8] -

Procedure Adherence 71111.21M The inspectors identified a Green non-cited violation of 10 CFR 50.65 (a)(1), for failure to evaluate a maintenance preventable functional failure of Class 1E 4160 Vac system for 10 CFR 50.65 (a)(1) status following the failure of breaker NB0101.

Description:

The functions of the breakers of the Class 1E 4160 Vac system, in addition to providing circuit protection, are to shed load by demand from the control room or engineered safety features actuation system and load shedder and emergency load sequencer (LSELS).

The Ameren maintenance rule program procedures outline the requirements and responsibilities for compliance with Paragraphs (a)(1), (a)(2), and (a)(3) of 10 CFR 50.65, Requirements for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants. These maintenance rule procedures consist of EDP-ZZ-001128, Revision 28, Maintenance Rule Program; EDP-ZZ-001128 Appendix 2, Revision 36, Summary of SSC Performance Criteria; EDP-ZZ-001128 Appendix 4, Revision 22, Maintenance Rule System Functions; and APA-ZZ-0500, Appendix 5, Revision 30, Maintenance Rule. These procedures identify the applicable structures, systems, and components to which 10 CFR 50.65 applies, their performance criteria, the thresholds for meeting their performance criteria, and requirements in the event the criteria are not met.

On March 21, 2019, a control room hand switch malfunction created an electrical short around the trip coil circuit of Class 1E 4160 Vac breaker NB0101, which resulted in the unavailability of the load shed function for the residual heat removal pump motor. On August 26, 2019, the maintenance rule expert panel determined that the failure of breaker NB0101 was a maintenance preventable functional failure. It was considered to be a maintenance preventable functional failure of the residual heat removal system, load shedder, and emergency load shed sequencer system, the 13.8 kV system, and the Class 1E 4160 Vac system. In accordance with EDP-ZZ-01128 Appendix 4, Revision 22, Maintenance Rule System Functions, the maintenance rule expert panel determined that maintenance rule criteria, NB-03, Provides protective features for Class 1E busses, which includes the isolation of certain Non-Safety Related loads from the Safety Related bus in the event of an SIS, was not met. According to EDP-ZZ-001128, Appendix 2, Revision 36, the 4160 Vac system A train performance criteria NB-03 has a threshold of 0 maintenance preventable functional failures per rolling 18 months.

Procedure EDP-ZZ-001128, Revision 28, Maintenance Rule Program, step 4.5.3(b)requires, when a structure, system, or components performance criterion has not been met or repetitive maintenance preventable function failures are identified, initiate a condition report in accordance with APA-ZZ-00500, Corrective Action Program.

Procedure APA-ZZ-00500, Appendix 5, Revision 30, step 4.1.2, requires that a 10 CFR 50.65 (a)(1) evaluation be completed within 60 days of the initiation of this condition report. Contrary to this, on August 26, 2019, no condition report was initiated following the expert panel determination of the maintenance preventable functional failure on the Class 1E 4160 Vac system A train. Consequently, no 10 CFR 50.65 (a)(1) evaluation was initiated or completed within 60 days.

Corrective Actions: On March 19, 2020, a 10 CFR 50.65 (a)(1) evaluation was completed under CR 202001216. It was determined that the Class 1E 4160 Vac system was to be moved to 10 CFR 50.65 (a)(1) status and performance goals and monitoring criteria were identified.

Corrective Action References: Condition Report 202001216-001

Performance Assessment:

Performance Deficiency: The failure to initiate a condition report and complete a 10 CFR 50.65(a)(1) evaluation in accordance with EDP-ZZ-001128, Maintenance Rule Program, was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the equipment performance attribute of the Mitigating Systems Cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, similar to Example 8.g of Manual Chapter 0612 Appendix E, "Examples of Minor Issues," the inspectors determined that the significance was more than minor because the Mitigating Systems Cornerstone objectives were adversely affected because, when the Maintenance Rule functional failure was considered, performance indicates that the SSC was not being effectively controlled through appropriate preventive maintenance and that the SSC was not moved to 10 CFR 50.65(a)(1).

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 2, Mitigating Systems Screening Questions, the inspectors determined the finding to be of very low safety significance (Green) because the finding affected the qualification of a mitigating SSC and did not affect its operability or PRA functionality.

Cross-Cutting Aspect: H.8 - Procedure Adherence: Individuals follow processes, procedures, and work instructions. This finding had a human performance cross-cutting aspect, associated with procedure adherence, because individuals failed to follow maintenance rule processes and procedures.

Enforcement:

Violation: Title 10 CFR Part 50.65 (a)(1) requires each holder of an operating license for a nuclear power plant shall monitor the performance or condition of structures, systems, or components, against licensee-established goals, in a manner sufficient to provide reasonable assurance that these structures, systems, and components are capable of fulfilling their intended functions. These goals shall be established commensurate with safety and, where practical, take into account industry wide operating experience. When the performance or condition of a structure, system, or component does not meet established goals, appropriate corrective action shall be taken.

Contrary to the above, from August 26, 2019, to March 19, 2020, the licensee failed to monitor the performance or condition of structures, systems, or components, against licensee-established goals, in a manner sufficient to provide reasonable assurance that these structures, systems, and components are capable of fulfilling their intended functions. When the performance did not meet established goals, appropriate action was not taken.

Specifically, the licensee failed to evaluate the Class 1E 4160 Vac system for 10 CFR 50.65 (a)(1) status, when the performance criteria of "0" maintenance preventable functional failures per rolling 18-month period was not met. Additionally, the licensee did not take any corrective action to ensure the Class 1E 4160 Vac bus would be capable of meeting their intended functions.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Use Appropriate Design Pressure Inputs for Diesel Generator Room and Essential Service Water Pumphouse HVAC System Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green NCV 05000483/2020011-02 Open/Closed

None (NPP)71111.21M The inspectors identified a Green non-cited violation of 10 CFR 50, Appendix B, Criterion III, "Design Control," for the failure of the licensee to specify design inputs for design pressures of the emergency diesel generator and essential service water pumphouse ventilation ducts that are designed to withstand the negative pressure caused by the fan when its suction path is blocked by a tornado damper.

Description:

Each emergency diesel generator room is equipped with an inlet duct, connecting the outside air source for room ventilation and combustion air. The system design incorporates a recirculation damper designed to protect the room temperature from overcooling in case the outside air temperature is very low. The recirculation damper modulates its opening and closing based on emergency diesel generator room temperature; thus, providing part of the 120,000 CFM flow rate from inside the room, such that the volumetric flow rate from the cold environment is greatly reduced. When the room temperature reaches 101 °F, the inlet duct supply fan operates to provide additional air flow for cooling the emergency diesel generator room. However, when the emergency diesel generator room temperature reaches 103 °F, the recirculation damper closes to maximize the air flow rate from outdoors in order to maximize cooling.

The system is also equipped with a tornado damper designed to shut at the onset of a reverse flow, because of low ambient air pressure caused by a tornado. The tornado damper reopens when the tornado event passes. The tornado damper is designed to seal the air inlet opening, thereby shutting air flow to the supply fan. The closing of the tornado damper is not accompanied with logic to stop operation of the fan. When the tornado damper closes, the fan will continue to operate at full angular speed attempting to provide 120,000 CFM to the room. Therefore, in a design basis tornado event that causes a corresponding loss of offsite power with emergency diesel generators running, there is a potential condition where little to no air will flow to the fan, while operating, when the tornado damper is fully closed coincident with a mostly closed recirculation damper because of elevated room temperature while the diesel generators are running.

The fans design curve shows that the fan can create a negative pressure of -6.8 inches of water in the duct while operating with no air flow. The inlet duct design documents show that the duct was built to withstand a negative pressure of only -3.75 inches of water. Therefore, during the postulated design basis conditions, the negative pressure created by the fan can exceed the documented duct design pressure, causing the duct to potentially implode. When the tornado damper then opens, the reduced area duct would potentially limit the suction flowrate below the design flowrate necessary to maintain the emergency diesel generator room at operable temperatures. This condition affected both emergency diesel generator rooms.

Following the discovery of emergency diesel generator room issue, the licensee determined that the essential service water pumphouse ventilation system is subjected to the same condition, where the inlet fan suction can draw pressure of -6.4 inches of water, while the ventilation duct is designed to withstand a documented maximum pressure of -3.75 inches of water. Therefore, under postulated design conditions, the duct would potentially implode and limit the flowrate below the required flowrate which provides cooling air to maintain the essential service water pumphouse at operable temperatures.

After discovery of the issues, the licensee performed a prompt operability determination because there was no information or analysis available to ensure that the ventilation ducts would maintain structural integrity to support emergency diesel generator operability. The licensee contracted an engineering firm to analyze the strength of the ventilation ducts and their ability to resist collapse at internal pressures greater than its design value of -3.75 inches of water. The analysis evaluated an internal pressure on the inlet duct of -7 inches of water using the ANSYS Version 19.2 Finite Element Analysis software. The analysis illustrated that minor yielding would occur in localized regions near the bottom of the duct at a ninety-degree bend near the inlet to the fan; however, the yielding was very small at 0.00025 in/in. This is below the 0.19 in/in strain necessary to cause a failure. Therefore, the emergency diesel generators and essential service water system remain operable.

The Callaway Operating Quality Assurance Manual states that Ameren Missouri complies with the recommendations of NRC Regulatory Guide 1.64, Revision 2. NRC Regulatory Guide 1.64 endorses ANSI 45.2.11-1974, Quality Assurance Requirements for the Design of Nuclear Power Plants, as acceptable method to comply with the quality assurance requirements of Title 10 CFR Part 50. ANSI 45.2.11-1974, Section 3.1, Design Requirements, states, The design input shall be specified on a timely basis and to the level of detail necessary to permit the design activity to be carried out in a correct manner and to provide a consistent basis for making design decisions, accomplishing design verification measures, and evaluating design changes. The inspectors determined that Callaway failed to specify design inputs for design pressures of the emergency diesel generator and essential service water pumphouse ventilation ducts to provide a consistent basis for making design decisions, accomplishing design verification measures, and evaluating design changes.

Corrective Actions: After discovery of the issues, the licensee performed a prompt operability determination because there was no information or analysis available to ensure that the ventilation ducts would maintain structural integrity to support emergency diesel generator operability.

Corrective Action References: Condition Reports 202001566 and 202001602

Performance Assessment:

Performance Deficiency: The inspectors determined that the failure to specify design inputs for design pressures of the emergency diesel generator and essential service water pumphouse ventilation ducts, in accordance with ANSI N45.2.11-1974, was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the design control attribute of the Mitigating Systems Cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, similar to example 3.e in Manual Chapter 0612, Appendix E, "Example of Minor Issues," in order to justify the as-found condition, the licensee had to revise calculations in order to establish operability and functionality of the ventilation ducts as-found conditions.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 2, Mitigating Systems Screening Questions, the inspectors determined the finding to be of very low safety significance (Green) because the finding affected the qualification of a mitigating SSC and did not affect its operability or PRA functionality.

Cross-Cutting Aspect: Not Present Performance. No cross cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion III, "Design Control," states, "Measures shall be established to assure that applicable regulatory requirements and the design basis, as defined in § 50.2 and as specified in the license application, for those structures, systems, and components to which this appendix applies are correctly translated into specifications, drawings, procedures, and instructions."

Contrary to the above, since December 19, 1984, to March 20, 2020, the licensee failed to assure that applicable regulatory requirements and the design basis for emergency diesel generator and essential service water pumphouse ventilation systems were correctly translated into specifications. Specifically, the licensee failed to specify design inputs for design pressures of the emergency diesel generator and essential service water pumphouse ventilation ducts in accordance with ANSI N45.2.11-1974, Quality Assurance Requirements for the Design of Nuclear Power Plants.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On March 20, 2020, the inspectors presented the design bases assurance inspection (teams) inspection results to Mr. F. Diya, Senior Vice President and Chief Nuclear Officer, and other members of the licensee staff.

On March 31, 2020, the inspectors presented the design bases assurance inspection (teams) inspection results to Mr. B. Cox, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Calculations

13000678.940

Diesel Generator Ventilation Supply Fan Flow Determined by

Velocty Pressure

71111.21M Calculations

7001280

Pipe Stress Analysis of ESW Supply Piping

71111.21M Calculations

81402-J-001

HCST Supply Valve ALHV0220 Opening Setpoint

71111.21M Calculations

AL-22

Aux Feedwater Pumps Suction Pressure Setpoints

71111.21M Calculations

AL-24

Determine the Effect of Dissolved Nitrogen on the NPSHa for

AL Pumps. Determine the Effect on Available NPSH for the

Aux Feedwater Pumps.

71111.21M Calculations

AL-29

Auxiliary Feedwater System Performance During Feedline

Break

71111.21M Calculations

AL-30

Auxiliary Feedwater System Performance During a Loss of

Normal Feedwater Flow and Loss of Non-Emergency A/C

Power

71111.21M Calculations

AL-56

Loop Tolerance Calculation for ALP-0037, 38, & 39

71111.21M Calculations

ARC-1590

EDG Suction Plenum Analysis

71111.21M Calculations

ARC-595

Aux. Feedwater Flow Model

71111.21M Calculations

B-10

Voltage Drop in MCC Control Circuits

71111.21M Calculations

Callaway Human

Reliability

Analysis

F

HRA Calculator output for Post-Initiator HFES

71111.21M Calculations

E-B-09

DC Control Circuits Voltage Drops

71111.21M Calculations

E-B-10

MCC Control Circuit Voltage Drop Calculation for MP 18-0003

71111.21M Calculations

FAI/18-0349,

Callaway ESW Water Hammer Mitigation Modification Support

Analysis

71111.21M Calculations

GM-03

EDG Room Temperature Without HVAC

71111.21M Calculations

H-9

Systems NG/PG Protective Relay Settings

71111.21M Calculations

M-EG-24

CCW Nuclear Aux. Component Train Switchover Single

Failure Analysis

71111.21M Calculations

M-FL-13

Auxiliary Building Flooding: Calculate the Maximum Flood

Level in Auxiliary Building Rooms 1304, 1305, 1324, 1325,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

26, 1327, 1328, 1329, 1330, and 1331 due to a Pipe Break

or Crack

71111.21M Calculations

M-GM-320

Emergency Diesel Generator Building HVAC

71111.21M Calculations

NAI-1560-001

HELB in the Callaway Auxiliary Building with Additional

Openings

71111.21M Calculations

NG-22

NG Load Center Overcurrent Setpoint Calculation1

71111.21M Calculations

NG-23

MCC Set Point Calculation for MP 18-0003

71111.21M Calculations

NK-10

NK System DC Voltage Drop

71111.21M Calculations

ZZ-145

Short Circuit Calculation

71111.21M Calculations

ZZ-561

Open Phase Fault Study for Callaway Energy Center

71111.21M Calculations

ZZ-62

Plant Load Flow Calculation

71111.21M Corrective Action

Documents

Condition Report

201606143, 201703700, 201703962, 201703981, 201703992,

201705506, 201705509, 201705513, 201705514, 201801880,

201805948, 201800047, 201605682, 201703961, 201707011,

201707076. 201806177, 201900377, 201903601, 201701331,

201801897, 201803497, 201803907, 201906494, 200700040,

201901697, 201706449, 200711067, 201702850, 201703342,

201703699, 201802482

71111.21M Corrective Action

Documents

Resulting from

Inspection

Condition Reports

2001172, 202001211, 202001216, 202001220, 202001256,

2001563, 202001566, 202001602

71111.21M Drawings

E-017-00004

AKD-6 Powermaster Indoor Unit Substation

71111.21M Drawings

E-018-00010

Motor Control Center Layout

71111.21M Drawings

E-018-00011

Motor Control Center Layout

71111.21M Drawings

E-1041A-00714

Replacement MCC Cubicles

71111.21M Drawings

E-1041A-00753

Replacement MCC Cubicles

71111.21M Drawings

E-1044-0014

XNB02 LTC Wiring Schematic

71111.21M Drawings

E-1044-0019

XNB02 DC Wiring Schematic

71111.21M Drawings

E-1044-0029

XNB01 DC Wiring Schematic

71111.21M Drawings

E-1052-0001

Control Diagram for 5GSB3, 15GSB3 and 15GSB4 Medium

Voltage 1200A, 2000A, 3000A Circuit Breakers

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Drawings

E-21001

Main Single Line Diagram

71111.21M Drawings

E-21NB02

Lower Medium Voltage System Class 1E 4.16KV Single Line

Meter and Relay Diagram

71111.21M Drawings

E-21NG01

Low Voltage System Class 1E 480V. Single Line Meter &

Relay Diagram

71111.21M Drawings

E-21NG02

Low Voltage System Class 1E 480V Single Line Meter &

Relay Diagram

71111.21M Drawings

E-22NF01

Load Shedding And emergency Load Sequencing Logic

71111.21M Drawings

E-23EG01C

Schematic Component Cooling Water Pump B

71111.21M Drawings

E-23EG01C

Schematic Component Cooling Water Pump B

71111.21M Drawings

E-23EG07

Schematic Diagram Component Cooling Water Supply to RHR

Heat Exchanger

71111.21M Drawings

E-23EG07

Schematic Diagram Component Cooling Water Supply to RHR

Heat Exchanger

71111.21M Drawings

E-23EG07

Schematic Diagram Component Cooling Water Supply to RHR

Heat Exchanger

71111.21M Drawings

E-23EJ01

Schematic Residual Heat Removal Pumps

71111.21M Drawings

E-23EJ04A

Schematic Diagram RHR Pump 1 to Charging Pump Valve

71111.21M Drawings

E-23NB16

ESF Transformers Auxiliary Power and Control Schematic

71111.21M Drawings

E-23NB18A

NB04 Capacitor Step 1 Control Schematic

71111.21M Drawings

E-23NE13(Q)

Schematic Diesel Generator KKJ01B Exciter/Voltage Control

014

71111.21M Drawings

E-23NG01

Low Voltage System Class 1E 480 V Three Line Meter and

Relay Diagram

71111.21M Drawings

J-22GM01B(Q)

Diesel Generator Building HVAC Exhaust Dampers

71111.21M Drawings

M-2014-00003

Size 6 Class 1690 CF8M Swing Check Clear Waterway

71111.21M Drawings

M-22AL01(Q)

Auxiliary Feedwater System

71111.21M Drawings

M-22AP01

Condensate Storage and Transfer System

71111.21M Drawings

M-22EF02(Q)

Essential Service Water System

71111.21M Drawings

M-22EG01(Q), M-

2EG02(Q), M-

2EG03(Q)

Component Cooling Water System

71111.21M Drawings

M-22EJ01(Q)

Residual Heat Removal System

71111.21M Drawings

M-22EM01(Q)

High Pressure Coolant Injection System

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Drawings

M-22EP01(Q)

Accumulator Safety Injection

71111.21M Drawings

M-22GM01(Q)

P&ID Diesel Generator Building

71111.21M Drawings

M-2H5211(Q)

HVAC Diesel Generator Building Plan and Sections

71111.21M Drawings

M-924-00001

Drawing for Vaneaxial Fan

71111.21M Engineering

Changes

MP 07-0070

Replace Safety-Related and Non-Safety Metal-Clad Breakers

000.7

71111.21M Engineering

Changes

MP 13-0002

Replace EDG Supply Fans CGM01A & B

71111.21M Engineering

Changes

MP 16-0027

Approval of Remanufactured ESFAS and LSELS Circuit

Boards

71111.21M Engineering

Changes

MP 17-0006

ESW Water Hammer Mitigation Modification

71111.21M Engineering

Changes

MP 18-0003

Replace Safety Related 480VAC MCC BUckets

71111.21M Engineering

Changes

MP 18-0019

NG02BER2 - Replace Safety Related 480 VAC MCC Buckets

71111.21M Engineering

Changes

MP 19-0113

ESW Water Hammer Mitigation Phase 2

71111.21M Engineering

Evaluations

C-04A05S

Floor Response Spectra for Standardized Nuclear Unit Power

Plant System

71111.21M Engineering

Evaluations

E170.0102

Approval of ABC Fire Extinguishers on Carts

07/02/1997

71111.21M Engineering

Evaluations

RFR 21816

Determine Impact on M-AL-16 for N2 and Low AL Flow

A

71111.21M Engineering

Evaluations

STRIDE 18-03

Integrated Engineered Safety Features Actuation System

(ESFAS) Testing

71111.21M Miscellaneous

Inservice Testing Program

71111.21M Miscellaneous

10466-M-627A-

0149-02

Test Report For Tornado Dampers

71111.21M Miscellaneous

3857-RPT-003

Required Response Spectra for Seismic Qualification of

Replacement I&C Electronics for Callaway Plant

71111.21M Miscellaneous

BLUE 2066

Category C Justification of Class IE Equipment

03/05/1986

71111.21M Miscellaneous

C-04A05B

Floor Response Spectra for Standardized Nuclear Unit Power

Plant System (SNUPPS)

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Miscellaneous

E-017-00397

IM Load Center Unit Substations

71111.21M Miscellaneous

E-1052-00031

Instruction Manual for 5GSB3-350-1200/2000 Medium Voltage

Circuit Breakers

000

71111.21M Miscellaneous

E-mail

E-mail DRS to Callaway regarding seismic failures

03/05/2020

71111.21M Miscellaneous

J-104-00594

Seismic Test Report for Callaway and Wolf Creek Modules

B

71111.21M Miscellaneous

J-104-00602

Acceptance Test Procedure for Isolation Module 6N234-1

71111.21M Miscellaneous

J-104-0151-03

Quality Conformance Test Procedure #6N234

A

71111.21M Miscellaneous

J-104-271-07

Environmental Qualification Report for ESFAS and LSELS

F

71111.21M Miscellaneous

J-104-271-07

Environmental Qualification Report for ESFAS and LSELS

C

71111.21M Miscellaneous

Letter

Letter from Archon Engineering PC to AmerenUE, EDG

Suction Plenum Preliminary Results

03/20/2020

71111.21M Miscellaneous

M-105A

Design Specification for the Shop Fabricated Tanks (ASME III)

for the SNUPPS

71111.21M Miscellaneous

M-1205

Design Specification for ASME Section III Class 3 Stainless

Steel Air Accumulators

71111.21M Miscellaneous

M-627A

Specification for Dampers

71111.21M Miscellaneous

M-924

Specification for Safety Related Fans

71111.21M Miscellaneous

M-924-00025

Instruction Manual for 150 HP Fan Motor Data Package

71111.21M Miscellaneous

M-924-00026

Instruction Manual for VOLU Probe and Dwyer Gauge

71111.21M Miscellaneous

Performance

Monitoring

Circuit Breakers

03/03/2020

71111.21M Miscellaneous

SSA-201900029-

054

Design Basis Assurance Self Assessment

71111.21M Miscellaneous

System Health

Report - NB

Low Med Vlt Sys 1E

2/24/2020

71111.21M Miscellaneous

System Health

Report - NF

LSELS

2/24/2020

71111.21M Miscellaneous

TRRQ 201700343 Lesson Learned for Incorporation into ESP Training Program

05/03/2018

71111.21M Miscellaneous

ULDBD-AL-001

Auxiliary Feedwater System

71111.21M Miscellaneous

ULDBD-Class 1E-

001

Class 1E Design

71111.21M Miscellaneous

ULDBD-CLASS

1E-001

Class 1E Design

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Miscellaneous

ULDBD-ECCS-

001

Emergency Core Cooling System

71111.21M Miscellaneous

ULDBD-EG-001

Component Cooling Water

71111.21M Miscellaneous

ULDBD-GM-001

Diesel Generator Building HVAC System

71111.21M Miscellaneous

ULDBD-NB-001

Lower Medium Voltage (Class 1E 4.16 KV)

71111.21M Miscellaneous

ULDBD-NF-001

Load Shedding and Emergency Load Sequencing

71111.21M Miscellaneous

ULDBD-NG-001

Low Voltage (480V) - Class 1E

71111.21M Procedures

1046-M-627A-

0081-01

American Warming and Ventilating Test Procedure for

Tornado Dampers

03/16/1978

71111.21M Procedures

14005614.500

Determine Leak By of EAV0185 Per Post Change Test Plan

71111.21M Procedures

APA-ZZ-00322

Appendix B

Work Week Schedule and Execution

71111.21M Procedures

APA-ZZ-00323

Configuration Management Process

71111.21M Procedures

APA-ZZ-00356

Pump and Valve Inservice Test Program

71111.21M Procedures

APA-ZZ-00390

Environmental and Seismic Qualification of Safety-Related

Equipment

71111.21M Procedures

APA-ZZ-00395

Significant Operator Response Timing

71111.21M Procedures

APA-ZZ-00500

Appendix 5

Maintenance Rule

71111.21M Procedures

E-0

Reactor Trip or Safety Injection

71111.21M Procedures

E-3

Steam Generator Tube Rupture

71111.21M Procedures

EC Supp Guide

Emergency Coordinator Supplemental Guideline

71111.21M Procedures

EDP-ZZ-01122

Check Valve Predictive Performance Manual

71111.21M Procedures

EDP-ZZ-01128

Appendix

SSCS in the Scope of the Maintenance Rule at Callaway

71111.21M Procedures

EDP-ZZ-01128

Maintenance Rule Program

71111.21M Procedures

EDP-ZZ-01128

Appendix 2

Summary of SSC Performance Criteria

71111.21M Procedures

EDP-ZZ-01128

Appendix 4

Maintenance Rule System Functions

71111.21M Procedures

EDP-ZZ-04015

Evaluating and Processing Requests for Resolution

71111.21M Procedures

EDP-ZZ-04600

Engineering Change Control

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Procedures

Emergency

Operating

Procedure

Addendum 30

Establishing Main Feedwater Flow

71111.21M Procedures

ETP-ZZ-01331

Crane Nuclear Diagnostic System for Testing Check Valves

71111.21M Procedures

FR-H.1

Response to Loss of Secondary Heat Sink

71111.21M Procedures

IP-ENG-001

Standard Design Process

71111.21M Procedures

J-104-00593

Alternate Parts Equivalency Evaluation for 9N39 and 9N40

Assemblies

71111.21M Procedures

J-104-00602

Acceptance Test Procedure for Isolation Module

71111.21M Procedures

J-104-0151-C03

Quality Conformance Test Procedure for Isolation Module

A

71111.21M Procedures

M-021-00061

Installation, Operation, Maintenance, Site Storage and

Handling Instructions for 4 HMTA-9 Stage Auxiliary Feed

Water Pumps

71111.21M Procedures

M-619.2-00136

Instructions Manual for Safety Related Fans

71111.21M Procedures

MDP-ZZ-0STOR

Staging and Storage of Materials, Equipment & Tools

71111.21M Procedures

MPE-ZZ-QS014

General Electric 4.16 KV Switchgear PM

71111.21M Procedures

MPE-ZZ-QS015

Square D Magnum Breaker Preventive Maintenance

71111.21M Procedures

MPM-ZZ-QH001

Inspection and Maintenance of Tornado Damper

71111.21M Procedures

OSP-AL-P001A

Motor Driven Aux. Feedwater Pump a Inservice Test - Group

A

71111.21M Procedures

OSP-AL-PV04A

Train A Motor Driven Auxiliary Feedwater Comprehensive

Pump and Check Valve Test

71111.21M Procedures

OSP-BB-VL006

RCS Pressure Isolation Valves Inservice Tests-IPTE

71111.21M Procedures

OSP-EJ-PV04A

Train A RHR and RCS Check Valve Inservice Test

71111.21M Procedures

OSP-NE-0001B

Standby Diesel Generator B Periodic Tests

71111.21M Procedures

OSP-SA-0017B

Train B SIS-CSAS Slave Relay Test

71111.21M Procedures

OSP-SA-2413B

Train B Diesel Generator and Sequencer Testing

71111.21M Procedures

OSP-ZZ-00001

Control Room Shift and Daily Log Readings and Channel

Checks

71111.21M Procedures

OTA-RK-00016

Addendum 22B

Voltage Control Freeze

71111.21M Procedures

OTN-EF-00001

ESW Air Accumulator Operation

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Procedures

OTO-EG-00001

CCW System Malfunction

71111.21M Procedures

OTO-ZZ-00012

Severe Weather

71111.21M Procedures

ZZ-006

Engineering Design Guide

71111.21M Work Orders

Job

17502728, 19001424, 20500603, 18504744, 17513089,

19511872, 17508987, 14005288, 16506328, 19502282,

19502288, 05516338, 11504156, 12504716, 12509849,

2511442