IR 05000461/2011010

From kanterella
Jump to navigation Jump to search
IR 05000461-11-010, on 4/11/11 - 4/15/11, Clinton Power Station (Cps), Unit 1
ML111260048
Person / Time
Site: Clinton Constellation icon.png
Issue date: 05/05/2011
From: Ring M
NRC/RGN-III/DRP/B1
To: Pacilio M
Exelon Generation Co, Exelon Nuclear
References
IR-11-010
Download: ML111260048 (17)


Text

UNITED STATES May 5, 2011

SUBJECT:

CLINTON POWER STATION - NRC FOLLOW UP INSPECTION REPORT 05000461/2011-010

Dear Mr. Pacilio:

On April 15, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed a follow up inspection for four Severity Level (SL)-IV violations identified between November 20, 2009, and June 30, 2010, at your Clinton Power Station. The enclosed report documents the results of this inspection, which were discussed on April 15, 2011, with Mr. F. Kearney, and other members of your staff.

The objectives of this follow up inspection were to provide assurance that: (1) the cause(s) of multiple SL-IV traditional enforcement violations were understood by the licensee; (2) the extent of condition and extent of cause of multiple SL-IV traditional enforcement violations were identified; and (3) licensee corrective actions to traditional enforcement violations were sufficient to address the cause(s). The inspection consisted of examination of activities conducted under your license as they relate to safety, compliance with the Commissions rules and regulations, and the conditions of your operating license, and the objectives stated above. Based on the results of this inspection, the inspector determined that, in general, the causes of the violations were understood by the licensee, the extent of condition and extent of cause of the violations were identified to the extent required by station procedures, and corrective actions were adequate.

Based on the results of this inspection, no findings of significance were identified. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS)

component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Mark A. Ring, Chief Branch 1 Division of Reactor Projects Docket No. 50-461 License No. NPF-62

Enclosure:

Inspection Report 05000461/2011-010; w/Attachment: Supplemental Information

REGION III==

Docket No: 50-461 License No: NPF-62 Report No: 05000461/2011-010 Licensee: Exelon Generation Company, LLC Facility: Clinton Power Station Location: Clinton, IL Dates: April 11 through April 15, 2011 Inspector: Robert Orlikowski, Project Engineer Approved by: Mark A. Ring, Chief Branch 1 Division of Reactor Projects Enclosure

SUMMARY OF FINDINGS

IR 05000461/2011-010, 4/11/11 - 4/15/11; Clinton Power Station (CPS), Unit 1.

This report covers a one-week period of inspection by a Region III inspector. No findings of significance were identified. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,

Revision 4, dated December 2006.

The inspectors concluded that, in general, for these violations, the causes were understood by the licensee, the extent of condition and extent of cause were identified to the extent required by Clinton Power Station procedures, and the licensees corrective actions were sufficient to address the indentified causes. However, the inspector identified that because the cause evaluations completed for each of the Severity Level (SL)-IV violations were typically Work Group Evaluations, which is the lowest level of evaluation performed, many of the causes identified were superficial in nature and were only concerned with the obvious cause. Had a more in-depth and rigorous cause evaluation been performed, the licensee may have been better able to identify the underlying issues that led to the violations.

NRC-Identified

and Self-Revealed Findings No violations of significance were identified.

Licensee-Identified Violations

No violations of significance were identified.

REPORT DETAILS

OTHER ACTIVITIES

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and Emergency Preparedness

4OA5 Other Activities

.1 Follow Up Inspection for Three or More Severity Level IV Traditional Enforcement

Violations in the Same Area in a 12-Month Period (IP 92723)

a. Inspection Scope

This inspection was conducted in accordance with Inspection Procedure (IP) 92723, Follow Up Inspection for Three or More Severity Level (SL) IV Traditional Enforcement Violations in the Same Area in a 12-Month Period, to assess the licensees evaluation of four SL-IV violations that occurred within the area of impeding the regulatory process from November 20, 2009, to June 30, 2010. These violations were documented in NRC Inspection Reports as:

(1) non-cited violation (NCV)05000461/2009502-01;
(2) NCV 05000461/2009004-03;
(3) NCV 05000461/2010003-01; and
(4)05000461/2010003-02. The inspection objectives were to:
  • Provide assurance that the causes of multiple SL-IV traditional enforcement violations are understood by the licensee;
  • Provide assurance that the extent of condition and extent of cause of multiple SL-IV traditional enforcement violations are identified; and
  • Provide assurance that licensee corrective actions to traditional enforcement violations are sufficient to address the causes.

The inspector reviewed the licensees cause evaluations associated with each of the NCVs. Additionally, the inspector reviewed Check in Self Assessment Report 1094472-02, Pre-NRC Inspection Check In: NRC Inspection Procedure 92723, Follow Up Inspection for Three or More SL-IV Traditional Enforcement Violations in the Same Area in a 12-Month Period (AR 1094472). The inspector reviewed corrective actions that were identified to address the causes. The inspector also held discussions with licensee personnel to ensure that the causes were understood and corrective actions were appropriate to address the causes.

.2 Evaluation of the Inspection Requirements

2.01 Review of Problem Identification a. Determine that the licensees evaluation identifies how each of the issues were identified, how long each issue existed, and prior opportunities for identification The inspector determined that the licensees evaluation identified how the issues were identified, how long the issues existed, and the prior opportunities for identification.

The licensee did not perform a collective evaluation for the four NRC identified SL-IV violations. Instead, each violation was evaluated on its own by the licensees Corrective Action Program (CAP). However, the licensee did perform a pre-NRC inspection self assessment. This self assessment identified an instance where an engineer failed to write an Issue Report (IR) for a known discrepancy between the Updated Final Safety Analysis Report (UFSAR) and the Technical Specifications (TSs). Had an IR been entered into Clintons CAP, the discrepancy may have been identified by the licensee and not the NRC. Action Request (AR) 1166085 was initiated to document the failure to enter the known deficiency into the Clinton Power Station (CPS) CAP.

b. Findings

No findings were identified.

2.02 Evaluate Cause, Extent of Condition and Extent of Cause Evaluations a. Determine that the group of SL-IV violations received an evaluation at an appropriate level of detail using a systematic method(s) to identify cause(s)

Each of the SL-IV violations received their own evaluation using the CAP. The group of SL-IV violations were not reviewed collectively using a systematic method to identify causes. While no collective evaluation was performed, the inspector did verify that each SL-IV violation received an evaluation in accordance with Clintons CAP requirements.

CPSs self assessment did identify that IRs 992920 and 1015038, both of which were Level 3 IRs and related to violations05000461/2009004-01 and 05000461/2009501-01 respectively, did not include a cause statement. This was contrary to Licensing Procedure LS-AA-120, Issue Identification and Screening Process, which requires that all Level 1, 2, or 3 IRs shall include a known cause statement. IRs 1166053 and IR 1166036 were written to document these deficiencies, and IRs 992920 and 1015038 were revised to include a cause statement.

The inspector noted that the cause investigations performed for each of the SL-IV violations was a Work Group Evaluation (Class D). This Evaluation is required to be performed by an individual knowledgeable in the Subject and, in the case of a Level 3 IR, is approved by Management Review Committee (MRC). Per procedure LS-AA-120, the Work Group Evaluation is not considered a formal investigation. CPS lists formal investigations as a Common Cause Analysis (CCA) (Class C), Apparent Cause Evaluation (ACE) (Class B), or a Root Cause Evaluation (RCE) (Class A).

Clinton Procedure LS-AA-120 states that if the actions to limit future failures are not known, strong consideration should be given to performing at least an Apparent Cause Evaluation for all externally identified Significance Level 3 or above issues.

The inspector noted that none of the SL-IV NCVs received a formal investigation (such as an Apparent Cause Evaluation). Due to the process of the Work Group Evaluation, the causes identified for each of the SL-IV NCVs may not be at a level of depth to prevent similar violations from recurring. As an example, the Cause Evaluation for NCV 2010003-01, Failure to Satisfy 10 CFR 50.72 and 10 CFR 50.73 Reporting Requirements, stated:

The cause for not reporting the design deficiency under the provisions of 10 CFR 50.72 and 10 CFR 50.73 was that the station and Corporate Licensing reviewed the reporting requirements provided in 10 CFR 50.72 and 10 CFR 50.73 and the reporting guidance in NUREG-1022 considering the engineering evaluation of this issue and concluded that none of the reporting requirements was applicable to this issue. The reportability assessment was documented in IR 976295 and discussed in LER [Licensee Event Report]

2010-001.

While the Work Group Evaluation identified the actual cause of the violation, the evaluation did not identify the underlying cause of why multiple organizations within CPS incorrectly concluded the issue was not reportable under 10 CFR 50.72 and 10 CFR 50.73. The licensees corrective actions for this violation included providing training to applicable personnel for awareness of the issue.

The inspector noted that because the cause evaluations completed for each of the SL-IV violations were typically Work Group Evaluations, many of the causes identified were superficial in nature and were only concerned with the obvious cause. Had a more in depth and rigorous cause evaluation been performed, the licensee may have been better able to identify the underlying issues that led to the violations. This observation was shared with the station management at the inspection exit. The licensee wrote IR 1207487, Depth of Investigation for NRC Findings and Violations, to evaluate classifying IRs associated with NRC findings and violations as Level 3 IRs requiring at least an ACE be performed.

b. Determine that the evaluation included a consideration of how prior occurrences in the same traditional enforcement area (willfulness, regulatory process, or consequences)were addressed by the licensee The inspector determined that the licensees evaluation included a consideration of how prior occurrences in the area of impeding the regulatory process were addressed.

The four SL-IV violations were reviewed to determine if they were due to a more fundamental concern involving weaknesses in the stations CAP. The inspector did not identify any commonality among the four SL-IV violations that would point to a fundamental weakness with the stations CAP.

c. Determine that the evaluation addresses the extent of the condition and the extent of cause of the problem The inspectors reviewed the individual CAP items for each of the four SL-IV violations as well as the self assessment. The inspector determined that only one of the four SL-IV violations had an extent of condition performed. This was also identified by the licensees self assessment. A review of the stations CAP procedures identified that LS-AA-125, Corrective Action Program (CAP) Procedure, does not require an extent of condition review for a Class D evaluation unless it is specifically requested of the Ownership Committee or MRC. Procedure LS-AA-125 only requires an extent of condition evaluation for Class A (Root Cause) and Class B (Apparent Cause)evaluations.

The inspector determined that none of the four SL-IV violations had an extent of cause performed. This was also identified by the licensees self assessment.

Procedure LS-AA-125 only requires extent of cause reviews for Class A and B evaluations. The inspector reviewed CPSs procedures and verified that extent of cause evaluations were not required to be performed for these four SL-IV violations.

The licensees self assessment identified a programmatic weakness in that the station procedures did not require extent of cause evaluations for Class D IRs. CPS wrote IR 1151591, Guidance Needed for NRC Inspection of Level IV Violations, to document that Exelon standard procedures do not clearly require analysis of Level IV violations to the extent described in NRC Inspection Procedure 92723. Specifically, Exelon procedure LS-AA-120 only requires that NRC SL-IV violations and non-cited violations (NCVs) be classified as a Level 3 IR. In addition, extent of cause and extent of condition reviews are only required for Class A and Class B IRs, and none of the IRs written for the four SL-IV violations was classified as Class A or B. IR 1151591 was initiated to recommend that Exelon standard processes be evaluated and revised if needed to address these issues.

d. Findings

No findings were identified.

2.03 Evaluate Corrective Actions a. Determine that appropriate corrective action(s) are specified for each cause identified for the group of violations or that there is an evaluation indicating that no actions are necessary The inspector determined that appropriate corrective actions were specified for the causes identified for each of the SL-IV violations. Because no cause evaluation was completed for the group of violations, no corrective action was taken to address the group of violations as a whole.

As noted in Section 2.02.a, the inspector noted that the level of cause evaluations performed for the SL-IV violations appeared superficial. Because of this, the corrective actions tended to only address the violation and focused on correcting the immediate problem. Had more rigorous evaluations been performed, additional underlying causes may have been identified that would have lead to further corrective actions to help prevent recurrence.

b. Determine that the corrective actions have been prioritized with consideration of the regulatory compliance The inspector determined that corrective actions were adequately prioritized with the consideration of the regulatory compliance.

Procedure LS-AA-125 provides guidance for prioritizing corrective actions. A sample review conducted by the inspector indicated that corrective actions were appropriately prioritized.

c. Determine that a schedule has been established for implementing and completing the corrective actions The inspector determined that a schedule was established for implementing and completing the corrective actions.

Procedure LS-AA-125 provides guidance for establishing due dates for corrective actions. The inspector conducted a sample review of completed and planned corrective actions and did not identify any discrepancies.

d. Determine that measures of success have been developed for determining the effectiveness of the corrective actions to prevent recurrence The inspector determined that there were no measures of success developed for determining the effectiveness of the corrective actions to prevent recurrence.

Procedures LS-AA-125 and LS-AA-125-1004, Effectiveness Review Manual, provide guidance for assigning and conducting effectiveness reviews.

Effectiveness reviews are only required to be performed for corrective actions to prevent recurrence (CAPR) or for an individual corrective action that the Corrective Action Program Coordinators (CAPCOs) or MRC deem necessary. None of these SL-IV violations reviewed had CAPRs, and none of the corrective actions were required to have an effectiveness review completed.

The Licensee's self assessment identified that there were no effectiveness reviews established for the corrective actions associated with the four SL-IV violations.

The lack of procedural requirements to perform effectiveness reviews for those corrective actions associated with NRC violations is to be evaluated as part of IR 1151591, Guidance Needed for NRC Inspection of Level IV Violations.

e. Findings and observations

No findings were identified.

4OA6 Management Meetings

.1 Exit Meeting Summary

On April 15, 2011, the inspector presented the inspection results to Mr. F. Kearney, and other members of the licensee staff. The licensee acknowledged the issues presented.

The inspectors confirmed that none of the potential report input discussed was considered proprietary.

ATTACHMENT:

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

K. Baker, Design Engineering Senior Manager
T. Chalmers, Operations Director
J. Cunningham, Security Manager
B. Davis, Regulatory Assurance Manager
J. Domitrovich, Work Management Director
C. Dunn, Shift Operations Superintendent
S. Fatora, Maintenance Director
R. Frantz, Regulatory Assurance
S. Gackstetter, Training Director
M. Heger, Mechanical/Structural Design Engineering Manager
N. Hightower, Radiological Engineering Manager
M. Kanavos, Plant Manager
F. Kearney, Site Vice President

D. Kemper; Plant Engineering Senior Manager

A. Khanifar, Engineering Director
S. Lakebrink, Mechanical Design Engineering
K. Leffel, Operations Support Manager
J. Peterson, Regulatory Assurance
J. Stovall, Radiation Protection Manager
R. E. Zacholski, Nuclear Oversight Manager (Acting)

Nuclear Regulatory Commission

M. Ring, Chief, Reactor Projects Branch 1
R. Orlikowski, Project Engineer
B. Kemker, Senior Resident Inspector
D. Lords, Resident Inspector

Attachment

LIST OF ITEMS

OPENED, CLOSED AND DISCUSSED

Opened

None

Closed

None

Discussed

05000461/2009004-01 NCV Interconnecting Floor Drains Between the Residual Heat Removal A Pump Room and Radwaste Pipe Tunnel (Section 4OA5)
05000461/2009502-01 NCV Implementation of a Change which Decreased the Effectiveness of the Emergency Plan (Section 4OA5)
05000461/2010003-01 NCV Failure to Satisfy 10 CFR 50.72 and 50.73 Reporting Requirements (Section 4OA5)
05000461/2010003-02 NCV Failure to Perform an Adequate 10 CFR 50.59 Evaluation for CPS Procedure 3711.01 (Section 4OA5)

Attachment

LIST OF DOCUMENTS REVIEWED