IR 05000461/2020003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000461/2020003
ML20315A244
Person / Time
Site: Clinton Constellation icon.png
Issue date: 11/09/2020
From: Kenneth Riemer
NRC/RGN-III/DRP/B1
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2020003
Download: ML20315A244 (14)


Text

November 9, 2020

SUBJECT:

CLINTON POWER STATION - INTEGRATED INSPECTION REPORT 05000461/2020003

Dear Mr. Hanson:

On September 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Clinton Power Station and discussed the results of this inspection with Mr. J. Kowalski, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Kenneth R. Riemer, Chief Branch 1 Division of Reactor Projects

Docket No. 05000461 License No. NPF-62

Enclosure:

As stated

Inspection Report

Docket Number:

05000461

License Number:

NPF-62

Report Number:

05000461/2020003

Enterprise Identifier: I-2020-003-0023

Licensee:

Exelon Generation Company, LLC

Facility:

Clinton Power Station

Location:

Clinton, IL

Inspection Dates:

July 01, 2020 to September 30, 2020

Inspectors:

J. Beavers, Senior Resident Inspector

S. Bell, Health Physicist

C. Mathews, Illinois Emergency Management Agency

D. Sargis, Resident Inspector

Approved By:

Kenneth R. Riemer, Chief

Branch 1

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Clinton Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On September 5, 2020, the unit was down powered to 70 percent for a control rod sequence exchange. The unit remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week and during that time conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities, and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

External Flooding Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated that flood protection barriers, mitigation plans, procedures, and equipment are consistent with the licensees design requirements and risk analysis assumptions for coping with external flooding

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)

'A' residual heat removal train on August 31, 2020

Complete Walkdown Sample (IP Section 03.02) (2 Samples)

(1) The inspectors evaluated system configurations during a complete walkdown of the carbon dioxide system on September 2, 2020
(2) The inspectors evaluated system configurations during a complete walkdown of the 4-kilovolt safety bus and supply system on September 10, 2020

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone F-1i, fuel pool cooling pump room, elevation 712', on July 15, 2020
(2) Fire Zone F-1b, high pressure core spray pump room, elevation 712', on August 18, 2020
(3) Fire Zone M-4, screen house 'A' fire pump room, elevation 699', on September 2, 2020
(4) Fire Zone A-3f, Division 2 essential switchgear room on September 17, 2020

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (2 Samples)

The inspectors evaluated internal flooding mitigation protections in the:

(1) High pressure core spray pump room
(2) Division 1 shutdown service water pump room

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during the power restoration Data Reconciliation & Validation Implementation Plan on July 22, 2020

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator requalification training in the simulator on July 21, 2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Work Order 5064232-05, "Division 1 Shutdown Service Water Strainer Piping Elbow Emergent Maintenance"
(2) Power reduction and condensate polisher swap for troubleshooting on August 20, 2020
(3) Yellow risk condition due to planned maintenance on Division 1 emergency diesel generator on September 17, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Action Request 4357056, "Packing Leak on 1B21-F019"
(2) Action Request 4361015, "Unplanned Power Change"
(3) Action Request 4362498, "Digital Feed Water Level Control Fault"
(4) Action Request 4368613, "LPRM [local power range monitor] Upscale 1/2 SCRAM"

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Division 1 shutdown service water strainer piping elbow emergent maintenance

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) Work Order 4915968, "3D Monicore Update Due to GEH [General Electric Hitachi]

Part 1 Notification"

(2) Work Order 5047632, "1TD25AA Temporary Leak Seal Installation"
(3) Work Order 5064232-01, "Division 1 SX [shutdown service water] Piping Elbow Fabrication"
(4) Work Order 5068733-05, "Digital Feedwater Level Control Drop 5 Repair"
(5) Work Order 497422-04, "Division 1 Diesel Generator Output Breaker"
(6) Work Order 4624505, "Division 1 Diesel Generator"

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Work Order 4994541, "'B' FLEX Pump Semiannual Run"
(2) Work Order 5045136, "Reactor Water Level 1B21-N681B Channel Functional"

Inservice Testing (IP Section 03.01) (3 Samples)

(1) Work Order 5039567, "'B' Fuel Pool Cooling Pump in Service Test"
(2) Work Order 4899284, "'C' Residual Heat Removal (RHR) Pump Comprehensive Pump Test"
(3) Work Order 5056584, "'A' RHR Pump in Service Test"

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) Full participation emergency preparedness drill on August 25, 2020

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) Licensed operator requalification out-of-the-box evaluation on September 29,

RADIATION SAFETY

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (5 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1) Area radiation monitors in the auxiliary building and fuel handling building
(2) Continuous air monitors in the auxiliary building
(3) Portable Geiger Mueller survey instruments in the auxiliary building
(4) Portable ionization chamber survey instruments in the instrumentation laboratory facility in the control building
(5) Radiologically controlled area exit personnel contamination monitors and small article monitors

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &

Transportation

Radioactive Material Storage (IP Section 03.01)

(1) Inspectors evaluated the licensees performance in controlling, labelling, and securing radioactive materials

Radioactive Waste System Walkdown (IP Section 03.02 (1 Sample)

(1) Inspectors walked down accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality

Waste Characterization and Classification (IP Section 03.03) (2 Samples)

(1) The inspectors evaluated the licensees characterization and classification of spent resin radioactive waste
(2) The inspectors evaluated the licensees characterization and classification of irradiated hardware radioactive waste

Shipment Preparation (IP Section 03.04) (1 Sample)

(1) The inspectors observed that a shipment containing radioactive material is prepared according to requirements

Shipping Records (IP Section 03.05) (3 Samples)

The inspectors evaluated the following non-excepted radioactive material shipments through a record review:

(1) Radioactive waste shipment W18-012 of spent resin radioactive waste shipped for disposal on August 1, 2018
(2) Radioactive waste shipment W19-007 of irradiated hardware radioactive waste shipped for disposal on April 23, 2019
(3) Radioactive waste shipment W20-009 of mixed radioactive waste shipped for disposal on July 15,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 1 (07/01/2019 - 06/30/2020)

MS09: Residual Heat Removal Systems (IP Section 02.08) (1 Sample)

(1) Unit 1 (07/01/2019 - 06/30/2020)

MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)

(1) Unit 1 (07/01/2019 - 06/30/2020)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (1 Sample)

(1) Unit 1 (10/01/2019 - 06/30/2020)

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

(1) Unit 1 (07/01/2019 - 06/30/2020)

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1) Unit 1 (01/01/2019 - 06/30/2020)

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in shutdown service water leaks that might be indicative of a more significant safety issue

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Incorrect air regulator installed on high pressure core spray room cooler flow control valve

71153 - Followup of Events and Notices of Enforcement Discretion Event Followup (IP Section 03.01)

(1) The inspectors evaluated an unplanned power change and licensees response on August 4,

INSPECTION RESULTS

Minor Violation 71152 Minor Violation: The inspectors reviewed the operation of valves 1SX041A and 1SX041B because the licensee documented in multiple action requests that the valves would not fail open when operators bled air from the air operator. This was contrary to the design of the valves, which should have failed open upon losing air pressure. The inspectors identified a minor violation of 10 CFR Part 50, Appendix B, Criterion III, "Design Control," when the licensee failed to ensure that the high-pressure core spray room cooler flow isolation valves 1SX041A and 1SX041B would fail open on a loss of instrument air. The flow isolation valves are air operated valves that have an air regulator to control air pressure to the valves. The station installed an air regulator that would not cause the flow isolation valves to fail open if instrument air lost pressure. The flow isolation valves also have a solenoid valve that vents the air operator whenever the high-pressure core spray room cooler was operating. The components were arranged so that the flow isolation valves would still be able to open whenever there was a demand signal for the room cooler to start. In the case of a loss of instrument air pressure, the valves would initiate flow only if the high-pressure core spray pump was started. The inspectors determined that the high-pressure core spray room cooler would be able to perform its function to support high pressure core spray pump operability.

Screening: The inspectors determined the performance deficiency was minor. The inspectors determined that the performance deficiency was minor because it did not adversely affect the mitigating systems cornerstone. Specifically, the room cooler flow isolation valve was still able to open when room cooling was required.

Enforcement:

This failure to comply with 10 CFR Part 50, Appendix B, Criterion III, "Design Control," constitutes a minor violation that is not subject to enforcement action in accordance with the NRCs Enforcement Policy.

Observation: Adverse Trend in Shutdown Service Water Components 71152 The inspectors identified a negative trend in the integrity of components in the shutdown service water system Specifically, over the previous year, the licensee experienced through-wall leaks in the shutdown service water strainer drain piping, the 'A' RHR room cooler, and the 'C' RHR room cooler. Each leak resulted in the licensee declaring the associated systems inoperable and entering the Technical Specification Limiting Conditions for Operations action statements. As corrective action, the licensee replaced each component that was leaking and created actions to address components identified in their extent of condition evaluation. The licensee determined that the failures of the room coolers were due to erosion of the piping and that the failure of the strainer drain piping was due to microbiological induced corrosion. The inspectors noted that drain piping was not required to be included in the licensee's Generic Letter 89-13 program and that the licensee did not add the section of piping to the program for continued monitoring. The inspectors noted that although it was not required to add the section of piping to the GL 89-13 program, it would have been a conservative action since the piping experienced a failure. The inspectors did not identify any violations of NRC requirements while evaluating this trend.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On September 30, 2020, the inspectors presented the integrated inspection results to Mr. J. Kowalski, Plant Manager, and other members of the licensee staff.
  • On September 23, 2020, the inspectors presented the radiation protection baseline inspection results to Mr. T. Chalmers, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Corrective Action

Documents

AR 4359313

1CO609 (1CO01T Tank Outlet) Found Shut during Tagout

Hang

07/28/2020

Drawings

M05-9014

C02 Fire Protection Diesel Gen's & Turbine-Gen Exciter

N

Procedures

CPS

3312.01V001

Residual Heat Removal Valve Lineup

17c

71111.05

Fire Plans

CPS

1893.04M130

781 - 790 Auxiliary: Div 2 Switchgear Prefire Plan

5b

CPS

1893.04M400

2 Fuel: Basement Prefire Plan

5a

CPS

1893.04M803

699 Screen House: 'A' (North) Fire Pump Room Prefire Plan 6a

71111.11Q Engineering

Changes

EC 622157

Power Recovery Via BELSIM Data Reconciliation &

Validation (DVR) Methodology

71111.15

Corrective Action

Documents

AR 4362498

MCR Alarm 5002-3P for P612 Hardware Fault on Drop 5

AR 4368613

LPRM Upscale 1/2 SCRAM

71111.19

Corrective Action

Documents

AR 4348178

HK: Steam Leak at 737 Heater Bay F-116 on 2in Pipe

Flange

06/04/2020

Shipping Records WO 4624505

Division 1 Diesel Generator

Work Orders

WO 497422-04

Division 1 Diesel Generator Output Breaker

WO 5047632

MM 1TD25AA Temp Leak Seal Installation

07/01/2020

WO 5064232-01

Replace Div 1 SX Pipe and Elbow

WO 5068733-05

Digital Feed Water Level Control Drop 5 Repair

71111.22

Procedures

CPS 9061.10

Fuel Pool Cooling Valve Operability

48c

Work Orders

WO 04899284

9053.07, 1E12C002C Comprehensive Pump Test

09/02/2020

WO 4994541

FLEX - 1FX01PB Hale Pump Functional

08/05/2020

WO 5039567

Fuel Pool Cooling Pump 1B and 1A Valve IST Testing

07/15/2020

WO 5045136

9030.01C05 CF ATM - (NS4 Reactor Water Level B21-

N681A-D) C005

09/15/2020

WO 5056584

9052.01A21 OP RHR 'A' Pump Operability

09/16/2020

71114.06

Miscellaneous

LOR Simulator

Scenario

September 29, 2020 Licensed Operator Requalification Out

of the Box Simulator Scenario

09/29/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Self-Assessments None

Clinton Off-Year Exercise Evaluation Report

71124.08

Corrective Action

Documents

AR 4217530

Truck Breakdown During Shipment

2/05/2019

AR 4243118

Delays in Shipping TN - RAM Cask

04/24/2019

AR 4310907

Defective Drums

01/17/2020

Corrective Action

Documents

Resulting from

Inspection

AR 4370961

NRC Observation - Shipping Enhancement

09/21/2020

Miscellaneous

White Paper: RP-AA-1003 Compliance Program

03/06/2017

Training Qualification Records for Radioactive Material

Transportation Individuals

Various

L76417

CFR 61 Analysis for Spent Resin

01/17/2018

L80526

CFR 61 Analysis for Dry Active Waste (DAW)

2/01/2018

L81020

CFR 61 Analysis for Fuel Building Skimmer Smear

01/16/2019

L82415

CFR 61 Analysis for Fuel Pool Filter Demineralizer

04/10/2019

L86412

CFR 61 Analysis for Spent Resin

2/14/2020

Procedures

RP-AA-500-1003

CFR Part 37 Material Accountability Program

RP-AA-600

Radioactive Material/Waste Shipments

RP-AA-600-1005

Radioactive Material and Non-Disposal Site Waste

Shipments

RP-AA-600-1006

Shipment of Category 1 Quantities of Radioactive Material or

Waste (Category 1 RAMQC)

Self-Assessments 4297181

NRC Inspection 71124.08 Radioactive Solid Waste

Processing and Radioactive Material Handling, Storage and

Transportation

07/02/2020

Shipping Records W18-012

Radioactive Waste Shipment of Spent Resin

08/01/2018

W19-007

Radioactive Waste Shipment of Irradiated Hardware

04/23/2019

W20-009

Radioactive Waste Shipment of Mixed Radioactive Waste.

07/15/2020

71151

Miscellaneous

Chemistry Reactor Coolant Summary Data 10/01/2019

through 06/30/2020

Radioactive Effluent Release Summary Data 01/01/2019

through 06/30/2020

Dose Equivalent Iodine Determination

07/29/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71152

Corrective Action

Documents

AR 1637200

AOV 1SX041A Failed to Open When Air Bled Off

03/22/2014

AR 4086972

Could Not Bleed Air Off 1SX041A Per 3211.01C003

2/23/2017

AR 4296225

EOID: RHR 'C' Room Cooler South Cooling Coil Leakage

11/11/2019

AR 4322571

CCP: 1SX041A/B Will Not Fail Open Per 3211.01C003

2/29/2020

AR 4352219

EOID: 1VY03S RHR 1A Room Cooler Thru Leak

06/24/2020

AR 4352621

Emerging Trend For ECCS Room Cooler Tubing Leaks

06/25/2020

AR 4359065

Large Leak Div 1 SX Strainer Piping Elbow

07/26/2020