IR 05000373/1988024

From kanterella
Jump to navigation Jump to search
Insp Repts 50-373/88-24 & 50-374/88-23 on 880831-0908.No Violations Noted.Major Areas Inspected:Licensee Liquid & Gaseous Radwaste Mgt Program & Prevous Open Items
ML20154S632
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 09/23/1988
From: Greger L, Paul R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20154S600 List:
References
50-373-88-24, 50-374-88-23, IEC-80-14, IEIN-88-022, IEIN-88-22, NUDOCS 8810050114
Download: ML20154S632 (7)


Text

-

'

. .

.

.

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Reports No. 50-373/880024(DRSS); 50-374/88023(DRSS)

Docket Nos. 50-373; 50-374 Licensec No. NPF-11; NPF-18 Licensee: Commonwealth Edison Company Post Office Box 767 Chicago, IL 60690 Facility Name: LaSalle County Station, Units 1 and 2 Inspection At: LaSalle County Station, Marseilles, Illinois Inspection Conducted- August 31 through September 8, 1988 Inspector: ,

. Paul

~f (/- 2 % f d; Date

'

we p Approved By: Lf eger, Chief f-23-EE#'

Facilities Radiation Protection Date Section Inspection Summary Inspection on August 31 through September 8, 1988 (Reports No. 50-373/88024(ORSS);

No. 50-374/88023(DRSS))

Areas Inspected: Routine, unannounced inspection of the licensee's liquid and gaseous radwaste management program, including: gaseous radwaste (IP 84724 and IP 84750) and liquid radwaste (IP 84723 and IP 84750). Also reviewed were previous open items (IP 92701) and two incidents concerning control of radioactive materia Results: The licensee's programs for controlling liquid and gaseous radwaste appear effective. No violations were identified. The inspector reviewed two incidents identified by the licensee involving weaknesses in the radiological and contamination control program. The licensee is taking actions to correct the identified problem kh00gh;$, f O

_ _ _ _ _ _ _ _ _ _ _ _ _ .

'

. .

.

.

DETAILS 1. Persons Contacted

  • Diederich, Station Manager M. Friedmann, Health Physicist T. Greene, Health Physicist
  • D. Hieggelke, Lead Health Physicist W. Huntington, Services Superintendent J. Lewis, ALARA Coordinator W. Luett, Rad / Chem Supervisor Staff
  • P. Manning, Assistant Superintendent, Technical Services G. McCallum, Health Physicist
  • J. Renwick, Production Superintendent
  • J. Schrage, Technical Services Health Physicist
  • R. Kopriva, NRC Resident Inspector The inspector also contacted other licensee and contractor personne * Denotes those present at the exit meeting on September 8,1938.

) 2. General This inspection which began on August 31, 1988, was conducted to review the licensee's liquid and gaseous radwaste management programs. Previous open items and two radiation occurrence reports were also reviewe . Licensee Action on Previous Inspection Findings (IP 92701 and 9270Q (Closed) Open Item 50-373/67032-02; 50-374/87031-02: Clarify procedure LRP-1340-10, calculation of MPC-hours from WBC Dat The licensee's corporate staff has revised the CECO generic procedure for computing HPC-hours from WBC data. The licensee has incorporated the changes into the above noted procedure. Based on the inspector's review, it appears the revised procedure can be adequately used to estimate MPC-hours from whole body count results for acute uptake . Gaseous Radioactive Waste (IP 84524,84750j The licensee's gaseous radwaste management program was reviewed, including determination whether changes to equipment and procedures were in accordance with 10 CFR 50.59; determination whether gaseous radioactive waste effluents were in accordance with regulatory requirements; adequacy of required records, reports, and notifications; determination whether process and effluent monitors are maintained, l

calibrated, md operated as required; and experience concerning

'

identification and correction of programmatic weaknesse '

The inspector reviewed selected records of radioactive gaseous effluent -

records and semiannual effluent reports for 1987 and 1988 to date. The pathways sampled and analyses performed appear to comply with technical

, specification requirement _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _______ _ ___ ____________ _ _ _ _____ _____ _____ ____ _____ ______ ________

. .

,

.

Gaseous effluents are exhausted from the plant via a single vent stac The standby gas treatment system (SGTS) has a separate flue inside the vent stack with a separate monitoring / sampling system. Containment vent and purges normally are exhausted via the regular vent stack but may be diverted through the SGTS if filtration is needed. Gaseous releases are quantified weekly from stack grab samples for noble gas and weekly particulate filter and charcoal samples. Similar samples are taken to quantify SGTS releases. Stack tritium samples are collected on cilica gel weekly and under special conditions to meet technical specification requirement Prior to containment purges noble gas and tritium samples are that collected releases will andnot analyzed exceed from the Offsite the vent Dose stack and containment Calculational Manual to verify )

(ODCM criteri The CECO computer program for dose updates and projections is run weekly and before containment purges. Gama and beta air doses, total body dose, skin dose and most restrictive organ doses are provided by the program using annual average meteorolog Radioactive effluent release rates and offsite dose calculations were reviewed. In 1987, about 6200 curies of noble gas and about 3E-1 curies of iodine-131 were released in gaseous effluents. An increase in 1987 gaseous effluents was caused by greater reactor availability. Through June 1988, 3000 curies of noble gas have been released. Using the OOCH methodology the licensee calculated maximum whole body and thyroid doses in 1987 to an individual beyond the site boundary were 5.5E-02 mrem and

3.5E-02 mRm respectivel An apparent minor fuel cladding problem was identified in Unit 2

,

in July 1987, as evidenced by an increase in pre-treatment noble i gas activity (about a tenfold increase before stabilizing) and was

! detectable at the stack. No significant increase in the dose equivalent I-131 of primary coolant resulted from the small lea . Licuids and Liquid Radioactive Wastes (IP 84723,84750)

The licensee's reactor liquids and liquid radwaste management programs l were reviewed, including: determination whether changes to equipment and procedures were in accordance with 10 CFR 50.59; determination whether liquid radioactive waste effluents were in accordance with regulatory

! requirements; adequacy of required records, reports, and notifications; determination whether process and effluent monitors are maintained, calibrated, and operated as required; and experience concerning

,

I l

identification and correction of programatic weaknesse The inspector reviewed selected records of radioactive liquid effluent sampling and analysis for 1988 and semiannual effluent reports for 1987 and through June 1988. The pathways sampled and the analyses perfomed

, appear to comply with technical specifications. In 1987, about 8.8E-01

curies of gross beta-gama activity (excluding tritium) and 1.09 curies i of tritium were released in liquid effluent from both units combined;

'

for the first six months of 1988, the gross beta-gama and tritium released were 10.38 and 1.3 curies, respectively. The increase in l

liquid activity releases is the result of significantly increased i

reactor availability. The licensee calculated whole bcdy and GI-LLI l

l

- _ _ - - _ _ _ _ _ _ _ _ _

_

'

. .

,

-

.

doses to an individual in 1987 beyond the site boundary were 3.5E-5 mrem and 1.5E-4 mrem, respectivel Liquid effluents are released on a batch basis from one of two tanks (following sampling and analysis) to a single release path which is a monitored (alarm and isolation functions) radwaste line. This line releases the efflhent through the cooling lake blowdown line to provide adequate dilution to assure that the effluent reaching the river is below NPC for the mixture of all nuclides release Analyses of batch liquid releases include counting a sample of the recirculated liquid using a GeLi system to identify and determine the concentration of gamma emitting nuclides in Technical Specification _

~

Table 4.11.1-1. For pure beta emitters, including strontium-89 and 90, iron-55 and hydrogen-3, concentrations are considered to be identical to the concentrations in the latest analysis of monthly composite samples of liquid batch releases. The composite samples are sent to a contractor for beta analyses. The concentrations of each nuclide, as well as the cooling lake blowdown flow rate are fed into a computer program which provides the MPC fraction for each nuclide, the sum of MPC fractions, the allowable radwaste discharge flow rate and the setpoint (above background) of the monitor on the dischange line which has alarm and isolation functions. Selective review of recent release records identified no problems with setpoint detenninations and setting During a selective review of recent release records, setpoint determinations and settings in the control room, a high background radiation level on the liquid radwaste effluent monitor was noted. The problem appears to be contamination of the detector chamber rather than elevated external background radiation. The chamber is routinely flushed with clean water after each discharge tank release, but flushing has been ineffective in reducing contamination levels. The configuration of the detector chamber tends to permit deposit of particles in the chamber and make flushing ineffective. Disassembly and decontamination of the monitor has become progressively less effective. The increased background has not reached the level where an adequate trip setpoint cannot be established but has reached the level where the internal check source had to be increased to adequately check operability. This matter was discussed at the exit interview and will be reviewed at a future inspectio (0 pen Item 373/88024-01; 374/88023-01)

Air Cleaning Systems (IP 84724,84750)

Two ventilation systems have HEPA filters and charcoal adsorbers subject to technical specification surveillance requirements. These systems are the two trains of the control room and auxiliary electric equipment room emergency filtration system and the two trains (common to both reactor units) of the standby gas treatment system. Inplace testing of HEPA filters and charcoal adsorbers have been performed on a timely basis and records show the efficiency to be greater than the 99.95 percent criteria for the latest tests of the systems described above. In addition, a laboratory analysis of a representative carbon sample from each train for methyl iodide removal has been performed with records showing the removal

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

. _ _ _ _ - - _ - _ _ _ _ - _ _ _ _ _ _ _ . _ -

!

,

  • e

.

p

I efficiency to be greater than the 90% criteria for the most recent test !

j results availabl l

~

No violations or deviations were identified, i 7. Calbrations and Surveillances of Gaseous and Liquid Process and Effluent

[

Kitors

The inspector reviewed records for seven monitors on the liquid system, '

j including the cormion radwaste discharge, the service water discharge

"

for each reactor unit and two RHR service water monitors for each unit j and several monitors on the gaseoue estem including, the SGTS and reactor 1 building vent exhaust, the pre- and pi st-offgas and fuel pool exhaust l

. lines monitors. Technical Specificatit 14.3.7.10 requires calibration !

of the liquid monitors at 18-month intervals and source check prior to ;

, each release. Technical Specification 4.3.7.11 requires calibration of (

the gaseous monitors described above at 18-month intervals and source ,

! checks at monthly intervals. The inspector reviewed selected calibration !

i records and selected source checks for the liquid and gaseous effluent l j monitors described above for the period July 1987 to June 1988. The t i review showed proper calibration !

i f l During a review of the offgas post-treatment calibration data it was j

- noted that the as-found alarm setpoints differed by as much as ten times i

! greater than the as-set alam setpoints for the upscale hi, and upscale ;

i hi-hi trip functions; a condition which permits tie alam to initiate in [

a non-conservative direction. Although the offgas post-treatment monitor j j will initiate an isolation of offgas only when the upscale hi-hi-hi ;
setpoint is exceeded (not the upscale hi or upscale hi-hi), such i j significant variations between the as-set and as-found readings should be

' investigated. The current procedure (LIS-0G-204) does not address this need for investigation. This matter was discussed at the exit meeting .

and will be reviewed at a future inspection. (0 pen Item 373/S8024-02; !

373/83023-02) + NRC Infomation Notice (IP 92701) {

i

No. 88-22: Disposal of Sludge from Onsite Sewage Treatment Facilities at i Nuclear Power Stations I

'

Currently, LaSalle Station stores sewage treatment slant sludge onsite [

in 55-gallon drums. The sludge is contaminated wit 1 very low levels of !

Co-58 and Co 6 The station holds an Illinois EPA pemit for onsite

land application of sludge, but due to the low level contamination, !
the station must also obtain the approval of the Illinois Department !

l of Nuclear Safety, since Illinois is an Agreement State, prior to ensite ;

i land application of sludge. LaSalle Station is proceeding in accordance !

I with NRC Infomation Notice No. 88-22, i i l I Review of Radiation Occurrence Report (ROR) 88-34. "Contaminated Haterial (

Found in an Uncontrolled Area" i l

During a survey conducted on August 5, 1988, of material designated for l

unconditional release and stored in an uncontrolled area, a piece of j contaminated wood was identified. The uncontrolled area was outside l

'

i 5  !

i

, L

/ .

.

.

the radiologically controlled area (RCA) but within the licensee's restricted area fence. As a result of this finding, extensive surveys outside the RCA were initiated, and between August 5-31, 1988, numerous l pieces of contaminated wood and 14 contaminated snubbers were found. The contamination levels on the wood ranged up to 10,000 dpm/100 cm2 smearable and 100,000 dpm/17 cm2 fixed. The levels on the snubbers ranged up to 5000 dpm/100 cm2 smearable and 25,000 dpm/17 cm2 fixe The contaminated articles were either disposed of as DAW or stored in designated area !

The licensee initiated an investigation to determine how the contaminated material, which should have been surveyed before leaving the RCA, was transferred to an uncontrolled area. The investigation was still in progress at the conclusion of this inspection on September 8,1988; no determination had been mad ;

During this inspection, the inspector reviewed this matter with the lead health physicist and plant management, and observed surveys in progress of material in those areas where the contaminated material was found. As a result of this review the inspector indicated that attention should be given to emphasizing and ensuring that a better survey program for 1 releasing material into uncontrolled areas be made, that the routine i uncontrolled area survey program be strengthened, and that a review I be made to ensure that material leaving the RCA is surveyed. The inspector also indicated that if the contaminated material found in the uncontrolled area was the result of a poor quality RCA survey program, then attention should also be given to ensure that the

, unconditional survey program quality is improved. These matters were discussed at the exit interview. The licensee's documented actions taken to prevent recurrence of incidents of this nature will be reviewed, at a future inspection. (Unresolved Item 373/88024-03; 374/88023-03)

Radiation Occurrence Report (ROR) 88-33 "Contamination of the MC

'

1 !

(Clean Demineralized hater) System in Radwaste" l

On July 27, 1988, thirteen station workers who had been mopping the 134'

elevation of the radwaste building we:e found to have contaminated shoes i at a whole body frisk booth upon completion of their work. The  !

contaminated shoes ranged from 2000 dpm/17cm2 to 25,000 dpm/17cm2 l direc !
!

l The licensee investigated this matter and found that water used to mop '

i the floor came from a contaminated MC tap. The spread of contamination

was limited to the 734' level and a stairwell in the radwaste building, i

! After discovery of the problem, the use of the MC system was suspended

to prevent further contamination, l

l The source of the contaminated water was the Unit-1 Floor Orain Evaporator '

l (1WF) which was connected to the MC system through a hose used for j flushing contaminated sludge from the line used to transfer the sludge

! from the IWF evaporator to a concentrator waste tank. The connection of l the hose to the MC system was the result of a temporary system change and

! has been routinely used for several years to flush the batchout line. A

'

i

l

[ -_ . - - . ..- .

_ - .

.. ,

t

. .: ?.i

~

'

l i

J t

pemanent flush line is scheduled to be installed in 198 In response ;

to IE Circular No. 80-14 concerning contamination of clean demineralized '

j water systems, the licensee issued instructions to close the valve and I

'

disconnect the temporary hosing after use; these instructions were i apparently not followe '

l'

During nomal operations, the pressure on the MC header is about 100 psi ,

and the pressure on the recycle pump on the evaporator recycle system is :

I about 20 psi. The difference between this pressure prevents the '

j contaminated sludge from entering the clean MC system when the evaporator 1 '

system is operating. This contamination event was caused when radwasto personnel operated the evaporator portion of the system when the MC !

portion of the system was- taken out of service for. valve repair. With l

, the MC system out of service, the pressure on the evaporator system i during operation was greater than that of the MC system, allowing the

'

contaminated sludge to enter the clean MC system.

L  :

-

As a result of the investigation, the licensee identified several i l' contributing causes for the incident and proposed several corrective actions to prevent recurrence. The inspector also reviewed the

circumstances surrounding the incident, reviewed the proposed corrective i actions, and discussed the matter at the exit meeting. The inspector !

I will review the licensee's corrective actions at a future inspection.

(Unresolved Item 373/88024-04;374/88023-04)

i

11. Exit Meeti,ng i The inspector met with licensee representatives (denoted in Section 1)

i at the cnnelusion of the onsite inspection on September 8, 1988. The l inspector summarized the scope and findings of the inspection. The i inspector also discussed the likely infomational content of the i inspection report with regard to documents and processes reviewed

!

'

by the inspector during the inspection. The licensee did not identify any such documents or processes as proprietary. The following matters were discussed specifically by the inspector:

' The apparent need to reduce radiation background levels for the l liquid radwaste discharge monitor. The license indicated they will investigate this matter (Section 5). The apparent need to revise the current "Post Treatment Monitor

, Calibration" procedure (LIS-0G-204) to ensure significant

{ discrepancies found between the as-set and as-found alarm

setpoints are 1 vestigate The licensee will investigate

!

this matter ($ection 7). The need to strengthen the control of contaminated material from the RCA into uncontrolled areas. The licensee is taFing c:rrective actions to prevent recurrence of this problem (Section 9). The need to strengthen controls for preventing contaminated water into the clean demineralized water system. The licensee is reviewing proposed corrective actions to prevent this type ;

of problem from recurring (Section 10). I 7