IR 05000373/1989015

From kanterella
Jump to navigation Jump to search
Insp Repts 50-373/89-15 & 50-374/89-15 on 890801-03. Weaknesses Noted Re Assembly/Accountability Drill.Major Areas Inspected:Annual Emergency Preparedness Exercise Including Observations of Key Functions & Locations
ML20246G314
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 08/17/1989
From: Patterson J, Snell W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20246G310 List:
References
50-373-89-15, 50-374-89-15, NUDOCS 8908310306
Download: ML20246G314 (16)


Text

{{#Wiki_filter:-- _ __ __ _ _ _. ,. , n h ' , , , . " ' ' ' _,.l-s , ._ . " O 'U.'S.

NUCLEAR REGULATORY COMMISSION: , , <' n ,

REGION III

< ,; < v

L-Reports'No. 50-373/89015(DRSS); 50-374/89615(DRSS) , , ' ,k' . <. . 50-373;'50-374 Licenses No. NPF-11; NPF-18 DocketfNos.

- " q > Licensee: Commonwealth Ediscn Company.~

' Post Office Box 767- ~ Chicago, IL J60690' Fac'lity,Name: LaSalle County Nuclear Generating Station, Units 1 and 2 i Inspection At: LaSalle Site, Marseilles, Illinois.

Inspection Conducted: ' August 1-3, 1989 '

- ~ 'atters [- f ?!99' Inspectors: P eam Leader Date/

' J. Hickman , M. Good' O.3 2 2 / / Afi'lliad Snell,.ChNf, f//'7/99 Approved By:,M radiological Controls and (, Date / Emergency Preparedness Section

,

' Inspection Summary Inspection on Auaust 1-3, 1989 (Reports No. 50-373/8901510RSS); - No. 50-374/89015(DRSS)) -] , Areas Inspected: Routine announced inspection of-the annual emergency - preparedness exercise (IP 82301) involving observations by three NRC . ' representatives of key functions and locations during the exercise.

Results: The licensee demonstrated a good respon3e to a simulated accident scenario involving tornado' damage to certain equipment on the plant site and a small release of liquid effluent. -All objectives were demonstrated , satisfactorily with the exception of the assembly / accountability drill.

An . Exer:ise Weakness was assessed for not meeting this objective.

j ' i , l' q l l 8900310306 890G21 i l PDR ADOCK 05000373 ' G PNU i

' , k, ' - ___________________________________..__________________________________________o

, . _ _, - - -. _ - .._; - _ - _ - - _ _._ . - _ - _ - -. __ , , ,, W.

+ . =,s m i ,.. b

.c ~ DETAILS' ! .

1.

Persons Contacted a, NRC Observers and Areas Observed J. Patterson, Control Room.(CR), Field Teams and: Emergency Operations Facility (EOF) J. Hickman, Technical Support Center.(TSC) and EOF M. Good,.CR & TSC b.

Licensee Representatives.

'G. Diederich, LaSalle Station Manager W.' Huntington, Technical Superintendent J. Walkington,. Services Director.- ' R. Shields, Technical Staff Engineer W. Kirchhoff, Operating Engineer T. Gilman, Corporate Emergency Planning Supervisor , T. Lechton, Corporate Emergency Pknning, Senior Administrator P. Vitalis, Corporate Emergency Planning Administrator D.' Waldscraidt, Security' Representative' - K. Klotz, Emergency Planning Coordinator - T. Hammerich, Regulatory Assurance Supervisor J. Gieseker, fechnical Staff Supervisor A.' Sheldon, Assistant Superintendent, Maintenance .T. Benoit, Quali.ty Assuranc'e Representative W. Friedmann,' Health Physicist-J. Lewis,.ALARA Coordinator R. Khemp, Radiation Protection Representative D.' Hieggalke, Health Physics Services Supervisor J. Thunstedt, Technical Staff Group Leader The above listed persons attended the August 3, 1989 exit interview.

2.

General i An exercise of the licensee's Generating Stations Emergency Plan (GSEP) was conducted at the LaSalle County station on August 2, 1989.

The exercise tested the licensee's capabilities to respond to an accident ! . scenario resulting in a simulated liquid release of radioactive material.

This was a utility only exercise without the participation of ) State and/or County agencies. Attachments'to this report describe the J exercise scope and objectives and narrative summary.

] 3.' General' Observations a.

Procedures

The exercise was conducted in accordance with 10 CFR Part 50, ! Appendix E requirements using the GSEP and associated implementing procedures.

2 j ,

= - _ - - -. - _ _ - _ _

_ _ - _ - - _ _ - - _ - _ _ _ _ _ _ _ _ _ _ _ _ _ , , B,. 7k,w

. ,3(y _ , ,, < - 1<, a s, M, n p.

' ,tY' b.

Coordination; " . 7.

, . , l; .The licensee's Lresponse was coordinated, orderli, and timely.

If

l scenario events had been real, the licensee's actions'would have L been' sufficient to allow State'and local officials to take - j appropriate actions to protect pub'lic health and safety.

C ' c.

Observers ticensee observers monitored and critiqued the' exercise along with three NRC observers.

L

' d.

Critiques d The licensee held facil.ity critiques following the exercise.

The;. , NRC evaluation team discussed the strengths and weaknesses identified-

during the exercise at the exit interview held on August 3, 1989 at ] the LaSalle Piant site.

Personnel kno attended the.NRC exit

interview are listed in Section 1.

i 4.

Specific Observations (IP 82301) a.

Control Room (CR) u The Shift Engineer, as the initial Station Director, demonstrated good-leadership and his crew responded well.

The CR staff handled the technical aspects of the scenario exceptionally'well.

The Shift-1 Control Room En0ineer, acting in the capacity of a Shift Technical ] Advisor (STA), raue valuable contributions in confirming Technical l4 Specifications, emergency classifications and procedural ' requirements.

Notifications to State,~1ocal agencies, and to the NRC were made l ' within ths required times for both the Unusual Event and the Alert.

However, the NRC observer noted a difference in the notification guidance between Procedure LZP-1310-1 and LZP-1110-1.

Procedure LZP-1310-1, which is used for notifications, states that the NRC will.be notified immediately after the State and local agencies have been notified.

Procedure LPZ-1110-1, which provides ! guidance for the Station Director's duties, includes checklists for l notification steps for all four emergency classifications.

Each of ! these. checklists states that the NRC is to be notified "as soon as ! possible, but within one hour of the declaration of the emergency" I following State and local notifications.

Procedures LZP-1310-1 and j LZP-1110-1 should be reviewed to ensure consistency between the

procedures as well as with 10 CFR 50.72(a)(3).

l l Announcements on the Public Address (PA) system couldn't be heard " in the Control Room.

The NRC observers were told that it was turned I down so as not to interfere with CR operations.

This condition gave j no real assurance that these PA announcements were being heard ' throughout the plant (without designated individuals within the various plant areas calling back to confirm that the message was heard).

!

,- _ _ _ _ _ _ . - - - - -

,, -

,.:.. g - , , [.m , -, . L '.y , . , 'a. > I , More use should have been made of the PA announcements; for example,. more ' frequent' updates' on the sev.ere weather anc' tornado conditions, 'j l.

leaking lake blowdown line, retreatment tank overflow, and other

I ' significant events that could af fect the' safety of thote in the plant - l' " as well ss emergency workers.

There was a PA announcement following-a report at 0855 that water was:found in a field north of the plant.

. The SE requested that a Rad / Chem team be dispatched to investigate i the condition.

However, continued severe weather conditions, ! followed later by the team.being secured in the OSC while assembly / 'l I > . accountability was being completed, prevented them from arriving on ] T n,, the scene antil 1120.

This is disassed further in Section 4.b.

s ' Objective briefings were held frequently by the SE, who briefed the

entire CR crew on each occasion.

Logs were maintained by the SE and -{ other key support staff. 8 0900 the.SE declared an Alert based oc ] the possibility of a rele)se due to the liquid leak reported earlier j north of the plant.

Before transfer of command and control to the l 'TSC took place, the SE provided a good, detailed status briefing to the incoming Station Director in the TSC.

Based on the above findings, this portion of the licensee's program-2 was acceptable; however, the following ' items thould be considered i for improvement: .]

some means should be found to assure that PA announcements are-being heard in the plant and other site support buildings.

, Also, the PA should be used more often to inform plant personnel- ) and e,nergency workers of significant events occurring during' an ] energency, in addition to emergency classification announcements.

  • Proccdure tZP-1110-1 and LZP-1301-1 should be reviewed to ensure there is consistency between procedures and with 10 CFR 50,72(a)(3).

j i I b.

Technical Support Center (TSC) ? At 0950, following a discussion between the SE and the TSC Station j Director (SD), a Site Area Emergency (SAE) was declared from the

Control Room based on tornado conditions with sustained winds greater than 90 miles per hour.

The TSC took over command and , control at 0955.

To assist the CR, the TSC agreed to complete the ' NARS Form #3 for the SAE.

The TSC was tsked to establish an open line on the ENS phone for communicating with the NRC by 1000.

The simulated NRC response cell had asked for this earlier at 0948.

! At 1002 there was a security briefing on the tornado damage.

Tnese activities were all well performed.

Briefings were held frequently by the SD, and they were satisfactory in content and delivery.

_ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ - - - _ _ - _ _ _ _ _ _ _ - - _ _ _ - __. - _ _ _.

. _ - _ - - . _ _. _.. _ -. _ _. - . - - g c %1 f1 . . , O

w

. - . y ' ' . Following the' announcement for a si'a assembly and accountability, the evacuation alarm was actuated at 1003.

At 1033'there were o l 30 people unaccounted for, seven of which were in a trailer and . deliberately did not report as part of the scenario.

There were . 16 in the Training Building who did not' hear the siren, and five who did not card in properly.

It was 1110 (or 67 minutes) before ,' all were accounted for.

A total of 350 people participated in the . accountability drill.

As a result, the licensee failed to l satisfactorily complete Exercise Objet.tive 5g which states,- l " Demonstrate the capability to assemble and account for all onsite personnel within 30 minutes of sounding the evacuation alarm." This drill resulted in an unsatisfactory performance for assembly /- ,. accountability, and an exercise weakness was assessed.

(0 pen Item f No. 373/89015-01 and 374/89015-01) Also related to this assembly / accountability drill'was'the detainment of a Rad / Chem team which was. earlier assigned to investigate the liquid.releasa near the Lake Blowdown Valve House.

This delay was still being (iiscussed in the TSC at 1059.

At 1140,

following the assembly /acco s tability drill, a simulated NRC Site ' ~ Team, being briefed in the TSC, remarked that they also'were detained by Security at the Main. Access Facility due to the drill.

TSese. incidents of emergency response personnel.being detained antil all phases of an assembly / accountability drill were completed '.s ' undesirable.

Procedure LZP-1170-1 should be reviewed and if appropriate, revised to give priority to the release of. emergency response personnel once they are accounted for so they can proceed with their. emergency response duties.

Status boards in the TSC were not always updated and on occasion j incorrect information was listed.. An example of incorrect

information was the Plant Status Board listing Unit 1 as being in

Mode 1 throughout the exercise.

At 1158, this board listed the last ' update as 0950.

The NARS Status Board was blank until the Site Area Emergency Declaration.

Most of this information was available in a message form and/or on computer terminal displays.

However, since l status boards are considered to be a vital part of the emergency j response effort they should be kept current.

Overall, the information ! flow in the TSC was very good between individuals, support groups to j the SD, and with the Control Room end EOF.

' Based on the above findings, this portion of the licensee's program was acceptable; however, the following' item should be considered for ) improvement: l A means should be found for a faster release of emergency

response workers after they have been accounted for during assembly / accountability so that they may pursue their emergency response functions without delay.

This may require a revision to Procedure LZP-1170-1.

- _ _ _ - _ _ _ _ _ - _ - - _

. _- - . - - __ ' ; c , . . ". , , . c.

' Field Teams At'0854 the initial. message relating to a' liquid release was received in the Control Room.

A' local ~ farmer walked into the Main ' ~ Access Facility and reported that water was comingiout:of the ground and flooding his corn field at the blacktop road straight' north of

the plant. At 0915, 15 minutes after the' Alert declaration; the SE:

requested a' Rad / Chem analysis of the discharge to'more specifically , p . identify the radioactive content of the water.

As previously ' discussed. the Rad / Chem Team was initially delayed by the strong ', .. winds and tornado ~ conditions.

Then there was another delay dne to

being sequested in the OSC until the assembly / accountability drill f was" reconciled.

It'was 1120 before the " Gold" team, consisting of u three members,' arrived at the blacktop rocd near the Blowdown Valve ! House.

. -Earlier, at 1018,:a Commonwealth Edison Division representative from the Streator Off. ice arrived.

If the scenario were on schedule h9 was to receive a briefing from the Gold Team.

Instead, an exercise' controller briefed him'on the downed electrical wire and the probable contaminated area near the' Blowdown Valve House.

The Division' representative, after surveying the conditions, described what he.would have'done with the overhead lines to restore power and remove the hanging wires.

He called his, findings into his office on his car phone and then'left. Thus, the goal to get input and coordination from a local-' division office through this participation l I was accomplished satisfactorily.

The Gold Team arriv'ed at'1120 and immediately put on double plastic l boots and gloves.

A desicjnated bag for contaminated gloves and l booties or.Other waste materials was made available immediately.

l When properly dressed and with radiation survey meter-in hand, three vegetation samples were taken.

Sample bags were pre-labeled.

A sample bottle for' liquid was provided but the-sample had to be simulated, since there was no real water standing on the ground.

- Surveys were made from the road to around the concrete block house 'or Blowdown Valve House.

Surveys'were made on the road at either l.

l~ end of the simulated water and smears ere taken from both lanes.

l This team demonstrated good radiation safety practices, avoided ' cross contamination of the samples, and labeled all samples adequately.

The third team member stayed with the vehicle as a radio operator, helped in preparation of sample taking, and storage of equipment / samples in the vehicle.

A second team arrived at 1142.

This team consisted of one Maintenance Operator and a Chemistry Technician (CT).

The CT had little to do since the Gold Team had done all the required sampling.

The l Maintenance Operator, with guidance of a Gold Team member, donned ' plastic boots and gloves and with a Rad / Chem Technician was led to the blowdown valve house.

His mission was to manually close the blowdown' valve to stop the release to the river and shut off the i , l

l

1 . _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ -

{A' ~ ~ ~ ~

~ > y< w ~ . , ' - i , - > o.

f I ' makeup line.

He accomplished this-m cessfully and the.n waited- , the 20-25 minutes it would actually have taken to do this, before i L informing the OSC that the task was completed.

He also brought thec L key along to open tae doorLto the blowdown' valve house. Without ~ the key the venture would have failed.

l In summary,.both field teams performed well and took what j preventative measures were necessary in performing field surveys, { posting an area and making protective' action recommendations for p personnel in controlling a contaminated spil'n < Based on the above findings,'this portion of the licensee's program l was acceptable.

cL Emergency Operations Facility (EOF) At 1047 the EOF took over command and control from the TSC in an orderly transfer.

The Site Area Emergency had been declared at 0950 by the SE,in the CR after discussion with the TSC.

Status boards in the EOF were well maintained.

The abnormal conditions status board-was used to track items being repaired and/or corrected.

Good , ' coordination'was demonstrated at the E0F with the' simulated NRC Site Team and the State representatives.

Briefings by the Manager of Emergency Operations (MEO) to'his support groups were meaningful

and objective.

The support groups worked well together to support the ME0 and clarify issues for his decision-making.

-l The E0F' Environs Group confirmed through calculations that 59 curies < had been released as liquid effluent on the ground adjacent to the blowdown valve house.

Good planning was demonstrated for control jf

and sampling'of the river should the release spread there.

The E0F ' management contacted the Illinois Radiological Control Team to assist by providing additional sampling'of river water in the area-and controlling river access.

These actions and others'made up the the content of the Protective Action Recommendations (PARS) for the public. The E0F staff did a good job of analyzing.the liquid y release and the potential dose to the public, both in milliroentgen

and in maximum permissible concentration (MPC).

Based on isotopic l concentration, the Protective Measures Group concluded that this

release exceeded the NRC allowable MPC and had the probability of resulting in a violation of NRC requirements.

The dose to the public, if all the release went to the river and was I taken in at the nearest water supply intake, was calculated to be 0.05 mR.

In a meeting with his support directors at 1312, the MEO got an update on the major events of the exercise.

A decision was made to go to Recovery when the tornado watch was lifted.

This I tornado watch was lifted at 1330.

Recovery discussions started at j ' that time.

i l

7 __ -_- -_ _ -

y, w , , !n 't: t > '. '

e ' '

l ' U* f ("

~' ' y , ' ' ' g j_ + 0 n[: ',c

' ' , , & . a% D a , %'$;.'4: 6 Recovery activities were discussed in' conjunction with the TSC by.

' . speaker phone.

The MEO followed closely the' recovery plan as-p specified it the GSEP.

He asked for input from his' support h directors and encouraged them'_to_make comments. 1Among other topics- ' ' discussed were the' disposition'onthe: fuel assembly, including repair '

for~the refueling bridge and a fix on' miscellaneous equipment, Selective staffing of the E0F and TSC for the~ recovery period was , addressed.. In general,-recovery activities were thorough, and ., J 1; concentrated on the key events and-related equipment which were oi

highi Qtted as action items by the MEO.

' , F Based on the above fin' dings this portion of the-licenseets program-c was acceptable.

15.

' Scenario ]

The exercise scope and objectives and the complete scenario packages were . < submittec' in:accordance with the established schedule..The licensee was L . responsive to the'one scenario related question regarding the liquid ! effluent release.

. . .

The participants were confronted with several challeoge.s throughout the ' scenario.

The worsening weather conditions culminated with a tornado damaging certain station equipment and'the Protective Area Security ~ i fence.

The lake blowdown air release and vent valve damage resulted in spraying water on the' ground which spread to a farmer's corn field.

The challenge to. confirm the extent of this contamination and cordon off the ! immediate' area to prevent spreading of contamination was perhaps the highest priority event in the scenario.

Loss of power to the refueling bridge crane was also a major concern since a fuel assembly was suspended ] , in the Fuel Transfer Chute. This refueling crane failure was.a chief concern in the TSC.

Spill of the Precoat Tank and loss of the Post LOCA 0xygen Monitor were two other events that required response in this l simulated emergency.

In summary, the challenges provided in the' scenario satisfactorily tested

the technical skills and coordinated efforts of plant management and j staff.

These scenario events kept the staff busy determining the best i corrective actions available.

6.

~ Exit Interview The inspection team met on August 31, 1989, with the licensee representatives denoted in Section 1 of this report.

The team leader ! discussed the scone and evaluation of the exercise, including preliminary inspection findings which identified one exercise weakness.

. This exercise weakness, which resulted in the failure of Exercise Objective 5.g., was the assembly / accountability drill.

This drill took approximately 67 minutes to accounte for all individuals onsite, with the i l goal being 30 minutes.

Related to the assembly / accountability drill was L the licensee's lack of a means to give priority to the release of any <

_--_- - _ __ _

y .,. ,w -- -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ,_ 'tj ~J.~ k ye . _, . I l ' i e . .n, 7g7, 'f.

. Y> , T.,. l ' emergency response personnel who were held up by the reconciliation'of H - Any emergency response individual.should be il . 'gthe drill's accountability.

iven priority for accountability in the particular assembly area and be-l , ,~ ' ' released to complete his.or her emergency related assignments as'soon as .; ' . possible.

The licensee agreed to consider the recommendations discussed by the NRC ] evaluation team at this meeting. The licensee indicated that none of'the ~ items discussed during the meeting were~ proprietary.

I .. < ." Attachments:

'1.

Exercise Scope ) and Objectives 2.

Narrative Summary , I l l J

i ! _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _. _ _ _ _ _ _ _ _ _ _ _ _ - _ _ -.. - - -. - - - -3

h[f ' . o =. MSA11E COUNTY NUCLEAR POWER STATION - - ' l .- 1989 GSIP EXERCISE ' l August 2, 1989 . OBJECTIVES [ HIfMRY OBJECIlyEl Demonstrate the capability to implement the Commonwealth Edison Generating Station Faergency Plan (CSEP) to protect the public in the event of a major accident at the LaSalle County Nuclear Power Station. Demonstrate this capability during the hours to qualify as a d>ytime Exercise in accordance with NRC guidelines.

SJTEORTING OBJECTIVES: . 1) Inc_ident_Ag_sessment and Classification a.

Demonstrate the capability to assess the accident conditions, to determine which Emergency Action Level (EAL) has been reached and to classify the accident lev el correctly in accordance with CSEP within 30 minutes of plant conditions warranting classification.

- (CR, G C) 2) BotJ ficat ion.And Coup _uqigating Demonstrate the capability to notify the applicable offsite a.

State and local organizations within fifteen (15) minutes of declaring an a::cident classification.

, (' - (CR, TSC) b.

Demonstrate the capability to notify the NEC as soon as possible and within one (1) hour of the initial incident.

- (CR) c.

Demonstrate the capability to contact pertinent organizations that would normally assist in an emergency, but are not participating in this Exercise (e.g., Murray and Trettel, General Electric, INPO, Ambulance Service, Hospital, etc.)

- (TSC, EOF) d.

Demonstrate the ability to provide follow-up infomation/ updates to the State and NRC within thirty (30) minutes of major plant condition changes or at least hourly.

- (TSC, EOF) e.

Demonstrate the ability to maintain an open-line of communication with the NRC upon request.

- (CR, TSC, EOF) f.

Demonstrate the ability of the ERP Communicators to accurately transmit information and provide timely response

to questions.

- (CR, TSC, EOF) 0108L/1/wjm LSCS '89 CSEP EX.

l ! ! - _ - - _ _ _ _ _ _.

- 7,q w ,

n

. ..

' . g.* I 3) Engiolorical AsaTTJ_ut , P a.- Demonstrate the ability to. collect, document and trend plant radiological'iurvey information and make ' appropriate . '

g recommendations concerning protective actions for personnel.

, a' - (OSC, TSC,. EOF.)- '

w H.- b.

Demonstrate the capability of'the Operations Support Center' (OSC) to implement proper Health Physics. practices and dosimetry issuance for OSC' personnel and Maintenance Teams dispatched to radiologically controlled areas in-plant.

- (OSC) Demonstrate the capability of.the Operations Support Center c.

(OSC) to ~ track and document personnel exposures for OSC ' personnel and Maintenance Teams dispatched from the OSC.

- (OSC) _ d.

Demonstrate the capability to caJcu2 ate offsite ' dose E projections.

' - (TSC, EOF) e.

Demonstrate the ability to make Protective Action-

.

Recommendations (PARS).

, - (CE, TSC, EOF) , f.

Demonstrate the ability of the Field Teams to collect and asa.ess environmental samples in accordance with procedures and proper contamination control techniques using sampling equipment and communication methods under the conditions of the scenario.

( - (TSC, OSC, EOF) Demonstrate the ability to share and compare survey results ! g.

from CECO and State Field Survey Teams.

- (EOF) h.

Demonstrate the ab'.11ty of plant personnel to perform field surveys, post ta area and make protective action recommendations for personnel controlling a contaminated spill.

- (CR, OSC, TSC) 4) Emere.ency Facilities ) I a.

Demonstrate the capability to activate and staff the ' on-site Emergency Response Facilities within sixty (60) minutes and in accordance with procedures.

- (CR, TSC, OSC) b.

Demonstrate the capability to activate and staff the Emergency Operations Facility in a timely manner.

- (EOF) Demonstrate the cepability to record and track major plant c.

status information relative to Exercise events using Plant Status Boards.

. .( - (TSC, OSC, EOF) ,e 0108L/2/wjm LSCS '89 CSEP EX.

l

Lmm____._____._______.____'____ ___ _ _ _ _. _. _ _ _ _ _. _ _ _ _ _ _ _ _ _ _... _ _ _ _ _ _. _ _ _. _

, -.

\\.

~ . . . L, .. ,. ,s d.' - ' Demonstrate - ths" capability to ' track and document, en status I boards : and logs, all' dispatchtd Optratians and Maint.cnanca Team activities and in-plant job statuses'. I ~ .. (CR, TSC, OSC), ((I

e.

D5monstrate the ' ability of the 2?ergency ' Response-Organization to interfat.e with Divisica personnel during a - CSEP event.

, -(TSC, EOF) 5) - E!pertency Direction and Control a.- Demonstrate the ability of the: individuals in.the GSEP Orge.nization. to - perform. their. assigned. duties and responsibilities. as specified in Generic GSEP and < position-specific procedures.

- (CR, TSC, OSC, EOF) . b.

Demonstrate the ability of the Managers ' and Directors to exert command and control in ' their respective facilities according to the duties and responsibilities - specified in Generic CSEP and position-specific procedures.

- (CR, TSC, OSC, EOF) c.

Demonstrate the ability of the Shift Engineer and the OSC "

Director to coordinate and prioritize Operations and Maintenance activities during abnormal and emergency.

situations.

- (CR, OSC) d.

Demonstrate the ability of the Shift Engineer to track .. operations and maintenance activities prior to TSC and OSC (' activation of the TSC and OSC.

- (CR) e.

Demonstrate the ability of the Shif t. Engineer to turnover operations and maintenance activities in progrecs upon activation of the TSC and OSC.

- (CE) f.

Demonstrate the ability to requisition, acquire and transport emergency equipment and supplies necessary to mitigate or control unsafe or abnormal plant conditions., - (CR, TSC, EOF) g.

Demonstrate the capability to assemble and account for all on-site personnel within thirty (30) minutes of sounding the evacuation alann.

- (TSC) h.

Demonstrate the ability of each Facility Director / Manager to conduct appropriate periodic briefings / updates covering plant status, event classification and plant activities in progress.

- (CR, TSC, OSC, EOF) Demonstrate the ability to provide access for and interface 1.

with the NRC Site Team.

- (TSC, EOF) ( 0108L/3/wjm LSCS '89 GSEP EX.

- - - - - .

m m,_ .. _ t t ' , . - ~ . ... r

~:.

.~'h J.

Dem:nstrate the r.bility of tha EOF Envirou:s Crcup to direct and track Environs Teams at monicor locations.

- (TSC, EOF) , [ ,6).

Recovegg-1 a.

-Demons'ttate the capability of the Emergency. Response ' Organization ~to identify the requirements, criteria and implementing procedures for recovery.

... - (TSC, EOF) b.

Demonstrate the capability to identify work priorities, procedures and programs which are required to return ' the . plant to a normal operating status.

- (TSC, EOF) ~. -r

- [h l < 0108L/4/wjn LSCS '89 GSEP EX.

f .s


. -. - - - _ - _. - - _ _ _ _ _.. _ - _ _. -. _. - _ _ _ _. _ _ _ _

_.

- _ ._ __.

_ - _ . _ _ _ - _ - _ _ - . - . - _ _ _ _ _ _ _ _ _ _ _ - - _ _ t.

... c , , A LASALLE COUNTY NUCLEAR POWER STATI0f(- . . 1989 CSEP EXERCISE- <v August 2, 1989- . '

r luenATIVE SUFMARI ()

INITIAL CONDITIONS - (0700 - 0730) UNIT 1 - Operating condition one for the last 195 days maintaining power at 1001 except for load following. B Reactor Eecirc Pump Seal #2 shows indication of a slow failure; pressure currently at 390 psig.

On one, the B Reactor Recire Flow Control 'talve (FCV) indicated shift A 24-hour servo error oscillations during performance of LOS-AA-W1.

timeclock for Tech. Spec. 3.6.6.2 was started at 0215 to inert the Dryvell p;r LOP-VQ-11 to reduce Oxygen concentration from 5.1% as noted during the surveillance.

Division II, Post LOCA Containment Oxygen Monitor, was determined to be inoperable during LOS-AA-VI which placed the Unit on a 7-day clock per Tech. Spec.

3.3.7.5 on order Action Statement.

(Per 1.M Department / Storeroom parts are to replace the Division II Orygen Pressure Regulator).

Inerting operations were started at 0500. The Reactor Core Isolation Cooling (RCIC) System is Out-of Service for scheduled lubrication.

OCS Cards were hung at 0530 with no work authorized or started.

UNIT 2 - Operational Condition Five in day 12 of a planned 15 week refueling Core unload is in progress with 509 assemblies transferred outage.

High Pressure Core Spray System and Diesel to spent fuel storage.

Generator are inoperable due to refueling maintenance and testing.

Six assemblies have been identified as leakers through sipping A operations. Suppression Pool cleanup put the outage schedule behind ( by two days due to higher than expected activities.

CO]giOB-At 0545, the SPS0 issued a Severe Storm Warning and Tornado Watch _ until 1400 today.

Winds are currently sustained at 30 to 40 mph gusting to 55 mph.

Both Units are in day 8 of a 30 day timeclock for inoperable Lake Blowdown Flow indication per Tech. Spec.

3.3.7.10.

Dilution Flow is being estimated every three hours by local valve position indication.

Radwaste has been discharging tanks for the last two weeks with the most recent discharge started at 0535.

UNUSUAL EVENT (0730 - 0900) l At 0730, the Unit 1 Rounds Equipment Attendant reports water spraying out of 1E22-F012 (High Pressure Core Spray Minimum flow Valve) packing gland.

At 0730, MCC 143-1 Cubicle 3B breaker indicated tripped. At 0800, Tornado Warnings came in af fect for the western portion of Illinois, southeastern Iowa and northeastern Missouri. Quad Cities Station is keeping both Units shutdown due to tornados in the area. At 0750, the Production Superintendent orders a power reduction per the Tech. Spec. as a precautionary measure in conjunction with the worsening weather conditions.

Indicated Drywell Oxygen concentration does not change due to instrument failure.

At 0815, an overflow of the Precoat Tank is reported by the Unit 1 EA.

( 0129L/1/wja LSCS '89 CSEP Ex.

N=_-_-__________________ _ _ _ _ _ _ _ _ __

- .. - - .__ -__ -__ - ______ --

I.

^.:

  • ~

, . . ? . M SUAL EVENT' ,X' (0720 .0900)~

' -(cont'd) . .. - ggg

ACTIONS: The Operating crew. will ~ determine the HPCS operability conditioh through Control Board indications and enter Tech Spec. 3.0.3.

This will' require commencing ' shutdown within one hour.. The Shift Engineer will send the Shif t Foreman to verify the '1E22-F012 valve .:. position closed per Tech. Spec.

3.6.3.

An Operator and EM crew will be dispatched to the MCC to investigate the tripped - breaker.

An Instrument Maintenance crew will he dispatched to investigate: the Oxygen Monitor when it is noticed that oxygen concentration. is not decreasing. The shutdown will commence at 0800 per orders and t.be Unusual Event classified per EAL #3A and #6A (Equipment described in Tech. Specs is degraded such that an Action Statement requires a shutdown- &HD power decrease for shutdown has commenced.)

The Unit 1 EA vill report the spill to the Control ~. Room and a team will be dispatched to control the area.

AL M (0900 - 0945) 0845, the Outside Rounds Equipmect Attendant reports that a Lake AtBlowdown air release and vent valve is spraying water onto 'the A farmer reports ground and also notes the high wind conditiona.

to Security at c.he Catehouse that water is flowing into his corn I field.

When the blowdown valve is checked, the P,A reports the position is the same as the last check but visual flow seems to-be less than ( expected. Flow is decreased due to corp sta.1ks and detris clogging the Blowdown inlet gate. The Radwaste Discharge P2K sample line is pit.gged with resin. The low sample flow alarm has not annunciated due to a failed time. delay relay. At 0900, it is discovered that the samples of the Esswaste Discharge Tanks were reversed.

At on Line 6102 and 0930, Transmission Substation 061 senses a - fault trips it off, deenergizing the 2iver Screen House. A static wire on the line breaks from a lightning strike and falls acros,s the ! l phases. of Line 6102.

A 12KV feeder is also shorted which ' deenergizes residential customers.

Wind speed increases' to sustained wind speed of 60 mph at 0930.

The Refuel Bridge Crane will stop moving (due to a f ailure to be determined) at the time when the decision is made to suspend fuel movement.

A fuel assembly will be suspended in the Transfer Chute.

EXPECTED ACTIONS: The EA vill investigate the air release and vent valve and the diminished dilution flow. When the sample tank calculation error is reported the release will be terminated.

Based on the calculations and ref erencing LZP-1200-4, Classification of Liquid will be classified per EAL #1L (Estimated liquid Release, an Alert release greater than pg equal to 40 Ci but less than 2000 C1 total in 24 hours).

Teams will be dispatched to collect samples and assess actual contamination in the environment.

0129L/2/wjm LSCS '89 CSEP Ex.

k ! l L _ - _ _ _ _ _ _ - _ _ _ _ _ _ - _ - _ _ - - _ _ _ _ _ - - _ _ - _ - _ _ _ _ - _ _ _ _ _ _ _ - _ _ _. . _ - _ _____

,,,, - -.,.,. - - - -.... - -. -. - - -.... - - , -,, - - -. - - - - - - - -. - - - - - - -. - - - -. ,.---..=---,-.---------------.------------------------------------,n-n,m . . ?,

. '. , , . ' )* EXPICIKD /.CTIONRI The Radwaste Diccharg2 PRM ~ will b1t inv33tig.ted ' icenlly to v2rify remote indication.- When power is Icst to the River Screen House, the blowdown valve will fail as is and sust be manually closed to.

( , stop the release. to the river. The Goritrol Room will notify the , Load Dispatcher of the loss of Line 6102 who will in turn notify ' the Streator Dispatcher.

Customers will call in to Streator-District and Southern Division to report the loss of power.

. SITE EMERCENCY ' (0945 - 1330) 0945, the sustained wind speed increases to greater than 90 mph At and a tornado touches down at the station.

Damage at the station includes a trailer,. the A Control Room Ventilation outside air intake structure is partially plugged cnd two Rad Monitors are damaged, one Met Tower guy -line is - snapped and a second is frayed, a fire hydrant is sheared off and hits the Demin. Regen. Solution ^ of' the Protective Area security fence and monitoring - Tank, and part system (camera and card reader) are damaged due to the flying ' debris.

The Unit SCRAMS due to Transformer I west differential lightning strike).- The overcurrent phase A to C (caused by a Refuel Bridge Crane will stop moving due to an elet.trical failure of the power cable connector at the time when the decision fr. made A fuel assembly will be suspended in the to suspend fuel movement.

. Transfer Chute until repairs or manual movement of the crane is: accomplished.

When the Assembly for personnel. accountability occurs, not all personnel will be accounted for.

EXPECTED .( ACTIONS: The Site Emergency will be declared vben sustained wind speed is than 90 mph per EAL #6X (Sustained winds of 90 mph with a - greater Unit not in Cold Shutdown or Refuel).

After the Assembly, crews to assess the damage to the Station ana to search for will be sent the unaccounted for personnel. After the initial damage assessment is made, crewa vill be assigned to begin restoration of priority areas and equipment. When the decision is made to suspend fuel movement, per LOA-AA-02, Operations during Tornado Warning, the Refuel Crane will be repaired or manually moved to place the assembly in safe storage.

EECOVERY (1330 - 1430) After 1330, plant conditions will need to be assessed for consideration of entry into a Recovery Phase. The TSC and EOF will prioritization plan for restoration of .the generate a failed / damaged equipment and systems. Conditions for Eecovery will be met.

EXPECTED The TSC and EOF will generate a pric,ritized plan for restoration of ACTIONS: the systems and equipment and enter into a Recovery Phase.

0129L/3/vjm LSCS '89 CSEP Ex.

\\ , " - - - - - - - - _. _.. _ _ _ _ _ _ _ _. _ _, _ _ . }}