IR 05000321/1980040
| ML20002B142 | |
| Person / Time | |
|---|---|
| Site: | Hatch |
| Issue date: | 10/17/1980 |
| From: | Herdt A, Zajac L NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML20002B140 | List: |
| References | |
| 50-321-80-40, 50-366-80-40, NUDOCS 8012090517 | |
| Download: ML20002B142 (4) | |
Text
'.,
- ' '
/* ""%
4[
I'
UNITED STATES A
7>
NUCLEAR REGULATORY COMMISSION N
t.
'j REGION ll
101 MARIETTA ST N.W., SulTE 3100 g
' ATLANTA, GEORGIA 30303
.....
Report Nos. 50-321/80-40 and 50-366/80-40 Licensee: Georgia Power Company 270 Peachtree Street Atlanta, GA 30303
.
Facility Name: Hatch Docket Nos. 50-321 and 50-366 License Nos. DPR-57 and NFP-5 Inspection at H s *te n ar.Baxley, GA Inspect 7:
(/ h M /7
_
/
L. D. Zaja'c Date figned
'[bd//
4db Approved by:
A. R. Heidt, Section Chief, RCES Branch Dite Signed SUMM'.RY Inspection on September 24-25, 1980 Area Inspected This routine unannounced inspection involved 12 inspector-hours onsite in the areas of:
Examination of containment liner penetration welds per Bulletin 80-08; followup of two noncompliances concerniag approval of the inservice inspection plan and certification of welding arJ NDE inspectors; and review of actions
,
taken on inspector followup items con;erning evaluation of a linear indication.
Results No items of noncompliance or deviations were identified.
,
80.noou 5/7
.
-
f.
N
'
,
l DETAILS 1. ' Persons Contacted Licensee Employees
- T. Greene, Assistant Plant Manager
- C. Belflower, QA Site Supervisor
- D. McCusker, QC Supervisor
- P. Fornel, Jr., Senior QA Field Representative
- S. Baxley, Superintendent of Operations Other licensee employees contacted included 4 technicians.
- Attended exit interview 2.
Exit Interview The inspection scope and findings were _ summarized on September 25, 1980, with those persons indicated in Paragraph I above.
3.
Licensee Action on Previous Inspection Findings (Closed) Deficiency (366/80-13-01) Failure to approve ISI plan. Georgia a.
Power letter PM-80-247 of March 19, 1980 indicates that the ISI plan for Unit 2 has been reviewed and approved. Therefore, this item is closed.
b.
(0 pen) Infraction (366/80-13-0?) Failure to certify welding and NDE inspectors. The inspector reviewed sample certification records for NDE personnel and found that certifications still do not comply with SNT-TC-1A as indicated below:
(1) NDE personnel are not given examinations based on the Georgia Power written NDE procedures. Refer to paragraphs 9.3 and 9.6.1 d of SNT-TC-1A.
This discrepancy applies to both NDE personnel employed by Georgia Power and NDE personnel employed by an outside contractor who perform NDE for Georgia Power.
Although contracted NDE personnel are qualified to other activities procedures, those procedures do not necessarily contain the same requirements as Georgia Power written procedures. Thus, certifi-cation to Georgia Power written procedures is required.
Georgia Power personnel are routinely trained and certified for NDE by an outside activity. Again this certification does not include examination based on Georgia Power written procedures.
(2) Georgia Power NDE personnel have been trained and certified by an outside activity, but Georgia Power has not audited this activity to ensure such services are performed in accordance with SNT-TC-1A. Refer to paragraph 9.5 of SNT-TC-1 h-
.
s
-, *.
-2-(3).. Personnel qualification records'do not include a description of-the test / specimen used for the practical examination. Refer to paragraph 9.6.1.f. of SNT-TC-1A.
,
(4) Georgia Power procedure HNP-823 Rev. 5,'" Qualification of Inspec-tion Personnel"-indicates that the testing program (para. D.I.b)
shall consist of written or oral ' examination. This is not in
.
. compliance with SNT-TC-1A which requires a written and practical'
examination.
c.
(Open). Unresolved Item (366/80-13-03). Review of licensee's final disposition of a linear indication. Several pieces of correspondence have been generated addressing this indication. A review of these reports and memorandum indicates that the indication was allowed to remain. Georgia Power memo PM-80-438 of April 22, 1980 specifies that the weld, adjacent to -the subject ' indication, be included as part of future inservice inspections. However, the ISI plan has not yet been revised to include this. weld (12BC/2B31-1RC-4AA) in future inservice inspections.
This item will remain open until the ISI plan includes the subject weld for inservice inspections and until NDE results of the weld are reviewed af ter th'e first inservice inspection.
4.
Unresolved Items
.
.
Unresolved items ' are matters about which more information is required to
.
determine whether they are acceptable or may involve noncompliance or deviations.
New unresolved items identified.during this inspection are discussed in paragraph S.
5.
Independent Inspection Effort During review of-the Georgia Power approval. for the Unit 2 ISI plan, the
inspector requested a copy of the approval lettes for Unit 1 ISI plan. The licensee stated that Unit I was approved, but could not locate documentation for such. The licensee agreed to locate documentation and to file appropri-
-ately. This is' Unresolved Item No.. 321/80-40-01, Lack of documented evidence for approval of Unit 1 ISI plan..
Within the area-inspected, no items of noncompliance or deviations were identified.
6.
Review of IE Bulletin No. 80-08, Examination of Containmer,t Liner Penetration -
IE Bulletin 80-08 was forwarded on April 7, 1980 and requested licensees to determine if their' facility. contained the flued head design for penetration connections, for other designs with containment boundary butt welds between
- the ' penetration sleeve and process piping.as illustrated in Figure NE 1120-1,- Winter.1975 addenda to the 1974 and later editions of the ASME
?
.
.
t
. 3-
,
Boiler & Pressure Vessel Code.
If the licensee's facility does contain this design then the licensee was requested to determine if welds were made
- with a backing ring and whether or_not volumetric examination was conducted by radiography. The Bulletin indicates that weld joints with a backing ring that have not been radiographed, are of ~particular interest as they are potentially defective.
In response to the Bulletin Georgia Power forwarded a letter dated August 5, 1980 which provides a partial listing of penetration welds. Fourteen (14)
welds of this list are the backing ring type and were not radiographed.
During the visit to Hatch site the inspector requested detailed informatfor.
for these 14 joints including diameter and wall thickness for the sleeve and process pipe, verification that a backing ring actually exists, and what, if any, obstructions exist that would preclude radiography of the weld.
After a lengthy search, the records for only_ one penetration (X-17)
could be located.
The detailed information for this penetration indicates that double wall radiography is feasible.
The licensee was requested to radiograph the flued head weld of penetration X-17, and to gather the same detailed information for the other penetrations having backing rings. If radiography is feasible, the other thirteen (13)
penetration welds should also be radiographed. The licensee should also complete the data collection requested by the Bulletin and submit to Region II for review and determination of any further work considered necessary.
Within the areas inspected, no items of noncompliance or deviations were identified.
NOTE:
During discussions if the Bulletin information required of the licensee to submit to NRC, a question was raised concerning which items of Figure NE-142^-1 were required to be researched. The inspector advised that all penetration welds described, except items (a), (b), and (f).
a
<