IR 05000321/2025001

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000321/2025001 and 05000366/2025001
ML25128A298
Person / Time
Site: Hatch  
Issue date: 05/13/2025
From: Alan Blamey
Division of Operating Reactors
To: Coleman J
Southern Nuclear Operating Co
References
IR 2025001
Download: ML25128A298 (25)


Text

SUBJECT:

EDWIN I. HATCH NUCLEAR PLANTS UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000321/2025001 AND 05000366/2025001

Dear Jamie Coleman:

On March 31, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Edwin I. Hatch Nuclear Plants, units 1 and 2. On April 17, 2025, the NRC inspectors discussed the results of this inspection with Matthew Busch, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. Two of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Edwin I. Hatch Nuclear Power Plants, units 1 and 2.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; and the NRC Resident Inspector at Edwin I. Hatch Nuclear Plants, unit 1 and 2.

May 13, 2025 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Alan J. Blamey, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000321 and 05000366 License Nos. DPR-57 and NPF-5

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000321 and 05000366

License Numbers:

DPR-57 and NPF-5

Report Numbers:

05000321/2025001 and 05000366/2025001

Enterprise Identifier: I-2025-001-0025

Licensee:

Southern Nuclear Operating Company, Inc.

Facility:

Edwin I. Hatch Nuclear Plants, Unit 1 and 2

Location:

Baxley, GA

Inspection Dates:

January 01, 2025 to March 31, 2025

Inspectors:

J. Bell, Senior Health Physicist

J. Diaz-Velez, Senior Health Physicist

R. Easter, Resident Inspector

P. Niebaum, Senior Resident Inspector

A. Nielsen, Senior Health Physicist

D. Restrepo, Health Physicist

D. Strickland, Senior Reactor Inspector

Approved By:

Alan J. Blamey, Chief

Reactor Projects Branch 3

Division of Operating Reactor Safety

Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Edwin I. Hatch Nuclear Plants, units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Unit 1 Reactor Core Isolation Cooling (RCIC) Rendered Inoperable Due to Human Error Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000321,05000366/2025001-01 Open/Closed

[H.12] - Avoid Complacency 71111.20 A Green self-revealed non-cited violation (NCV) of 10 CFR 50, Appendix B, Criterion XI, Test Control was identified when licensee personnel failed to follow test procedure 34SV-E51-010-2, RCIC Logic System Functional Test for unit 2. Specifically, licensee personnel installed electrical jumpers in a unit 1 panel instead of the unit 2 panel required by the procedure. As a result, on February 10, 2025, the unit 1 reactor core isolation cooling system was inadvertently isolated and rendered inoperable and unavailable for approximately 1.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.

Failure to properly calibrate effluent radiation monitors Cornerstone Significance Cross-Cutting Aspect Report Section Public Radiation Safety Green NCV 05000321,05000366/2025001-02 Open/Closed

[H.6] - Design Margins 71124.05 The NRC inspectors identified a Green finding and associated NCV of Technical Specification 5.5.1, for the failure to properly calibrate effluent radiation monitors 2D11K601 and 2D11K602, in accordance with the Offsite Dose Calculation Manual requirements.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at or near rated thermal power (RTP) and remained at or near RTP for the entire inspection reporting period.

Unit 2 began the inspection period at approximately 90 percent RTP due to the 10th and 12th stage 'A' feedwater heaters being out of service and the isolation of extraction steam to the 8th stage 'B' feedwater heater. Around January 10, the unit began a controlled coastdown in preparation for refueling outage 2R28. On February 8, a reactor shutdown was initiated from approximately 80 percent RTP, and the unit entered the refueling outage on February 9.

Following completion of the outage, a reactor startup commenced on March 14, and power ascension began. The main generator output breaker was closed on March 17, marking the end of the refueling outage. On March 19, the unit reached approximately 90 percent RTP.

Subsequently, on March 21, power was reduced to approximately 80 percent RTP due to removal of the 'B' condensate pump from service. The unit was shut down on March 26 for a maintenance outage to repair the pump. The unit was restarted on March 30, and power was raised in preparation for synchronizing to the grid, which occurred on April 1,

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to and during the onset of seasonal cold temperatures for the following systems during the week of January 6, 2025:

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather (i.e., tornado watch and warning)on March 16, 2025.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 2 'B' standby gas treatment (SBGT) system on January 7, 2025
(2) Common '1A' and '1B' main control room air conditioning subsystems on January 14, 2025
(3) Unit 2 high pressure coolant injection (HPCI) system on January 28, 2025
(4) Unit 1 'A' SBGT system on January 29, 2025
(5) Unit 2 'C' emergency diesel generator (EDG) on February 4, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 1 reactor building 228-foot elevation (refuel floor) on January 3, 2025
(2) Unit 2 reactor building 228-foot elevation (refuel floor) on January 3, 2025
(3) Unit 1 northeast diagonal and HPCI room on January 8, 2025
(4) Unit 2 low voltage switch yard on January 8, 2025

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Non-destructive Examination and Welding

Activities (IP Section 03.01)

The inspectors evaluated boiling water reactor non-destructive testing by reviewing the following examinations from February 17 - February 20, 2025:

(1)

1. Non-Destructive Examinations

Ultrasonic (UT) Exams

1. 2E11-1RHR-20-RS-5, valve-to-elbow, ASME Class 1

2. 2B31-1RCM-28AD-4, elbow to pipe, ASME Class 1

3. 2E51-1RCIC-4-D-16A, valve-to-penetration, ASME Class 1

Liquid Penetrant Exam

1. 2B11\2-26-03-1, pipe-to-pipe, ASME Class 1

Visual Exams

1. 2B11 I\H-121ID, perform EVT-1 of H5/V5 Weld in Cell Lane 46-43 from ID,

ASME Class 1

2. 2B11 I\M-8AB, VT-1 exam of middle core spray (CS) sparger bracket to

shroud (SB) at 60 deg, Weld 8, ASME Class 1 Welding Activities

1. SNC850244, replace residual heat removal (RHR) and CS Pump room cooler

cover bolts/cut and reweld piping to facilitate eddy current testing (ECT), ASME Class 3

2. SNC1804568, replace reactor building component cooling water piping to

accommodate new recirculation motor, ASME Class 2 Examinations with Relevant Indications Accepted for Continued Service

1. 2B11\2C-2-B, longitudinal weld on upper MID shell, UT exam, ASME

Class 1

2. 2B31-S32-H2, spring can, VT-3, ASME Class 1 Piping Support

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during the following:

1. Unit 2 train A CS pump in-service test (IST) on January 3, 2025

2. Unit 1 A cooling tower restoration on January 29, 2025

3. Unit 2 turbine building chiller swap on January 29, 2025

4. Unit 2 division 1 main steam line relay logic response time testing

on January 29, 2025

5. Unit 2 down power for refueling outage on February 8, 2025

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated just-in-time training prior to unit 2 down power for refueling outage on February 5 and February 6, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSC) remain capable of performing their intended function:

(1) Unit 1 analog transmitter trip system (ATTS) maintenance rule (10 CFR 50.65)(a)(1))

evaluation.

(2) SNC1797850, unit 2 B recirculation motor replacement and functional test reviewed on March 6, 2025.

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) Condition report (CR) 11130062, acceptance of the conditional release of nonconforming material for use on unit 1 'B' RHR pump.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)

(2) Unit 2, elevated risk due to A SBGT system outage on January 7, 2025 Unit 2, elevated risk due to reactor core isolation cooling (RCIC) system outage on
(3) January 28, 2025 Unit 1 and unit 2, elevated risk due to the 2A EDG system outage on February 4, 2025
(4) Unit 2, elevated risk (i.e., Yellow) for decay heat removal due to reactor pressure vessel head and piping not intact with cavity drained on March 3, 2025
(5) Unit 1, elevated risk due to PSW conditionally critical during 1A PSW breaker preventive maintenance and cubicle inspection on March 25, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (7 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) CR 11062086, unit 1 C safety relief valve (SRV), 1B21-F013C, 2nd stage temperature is erratic.
(2) CR 11079222, small leak identified on unit 1 RCIC drain trap, 1E51-D003.
(3) CRs 11121610 and 11125821, evaluate high energy line break (HELB) impacts from partially obstructed HELB grating in unit 1 reactor building.
(4) CR 11151026, PSW piping below minimal wall thickness.
(5) CR11158186, unit 2 reactor pressure vessel head closure bolt no. 33 not installed.
(6) CR 11152297, unit 2 snubber in torus bay identified to have a loose base bolt.
(7) CR 11158154, indication on reactor pressure vessel (RPV) flange stud hole 33.

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Design Change Package (DCP) SNC1580461, unit 2 RCIC turbine control system setpoint increase

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (2 Samples)

(1) The inspectors evaluated unit 2 refueling outage 2R28 activities from February 9 to March 17, 2025.
(2) The inspectors evaluated unit 2 maintenance outage activities to repair the B condensate pump from March 26 to March 31, 2025.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (IP Section 03.01) (6 Samples)

(1) SNC2270673, main control room air conditioner 1C run after relay replacement reviewed on January 21, 2025 (2)34SV-E51-002-2, unit 2 RCIC pump operability after high speed setpoint increase reviewed on January 29, 2025 (3)34SV-T46-003-2, unit 2 SBGT ventilation and operability after 'B' SBGT system outage on January 30, 2025 (4)34SV-C41-002-1, unit 1 standby liquid control (SBLC) pump operability test after A SBLC system outage on January 30, 2025 (5)34SV-R43-001-2, unit 2 A EDG monthly test after system outage on February 4, 2025 (6)52SV-B21-001-2, main steam isolation valve limit switch response and component inspection/repair on February 28, 2025

Surveillance Testing (IP Section 03.01) (4 Samples)

(1)34SV-E11-001-1, RHR pump operability for the unit 1 'B' and 'D' RHR pumps on January 13, 2025 (2)34SV-SUV-008-2, primary containment isolation valve operability for unit 2 reviewed on January 15, 2025 (3)34SV-E11-002-2, RHR valve operability for the unit 2 RHR loop B valves on January 21, 2025 (4)34SV-R43-020-2, Diesel Generator 2A loss of coolant accident LOCA/ loss of offsite power (LOSP) logic system functional test (LSFT) on February 13, 2025

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) Unit 2 'A' and 'C' RHR pump IST on January 8, 2025

Containment Isolation Valve (CIV) Testing (IP Section 03.01) (1 Sample)

(1)42SV-TET-001-2, primary containment periodic Type B and Type C leakage tests for penetration 26 on February 11 and 19,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1) Health physics personnel controlling material entering and exiting the radiologically controlled area (RCA) through an open vault door to the outside.
(2) Personnel exiting the drywell contaminated area during the unit 2 outage (2R28).

Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following radiological work:

(1) Unit 2 'B' recirculation motor removal and replacement.
(2) Unit 2 reactor vessel disassembly.
(3) Feed water and CS system nozzles 15-year inservice inspections.

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (4 Samples)

The inspectors evaluated licensee controls of the following high radiation areas and very high radiation areas (VHRAs):

(1) Reactor building east-west hallway posted VHRA.
(2) Reactor water cleanup heat exchanger, 'A' pump room, and 'B' pump room posted locked high radiation areas (LHRA).
(3) Unit 1 operating turbine enclosure LHRA.
(4) Unit 2 traversing in-core probe room LHRA.

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Permanent Ventilation Systems (IP Section 03.01) (1 Sample)

The inspectors evaluated the configuration of the following permanently installed ventilation systems:

(1) Main control room environmental control system filter testing in accordance with the ventilation filter testing program in 'A' and 'B' trains.

Temporary Ventilation Systems (IP Section 03.02) (1 Sample)

The inspectors evaluated the configuration of the following temporary ventilation systems:

(1) Portable high-efficiency particulate air (HEPA) unit, Serial #13, used Refuel Floor 2/10/2025.

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees use of respiratory protection devices.

Self-Contained Breathing Apparatus for Emergency Use (IP Section 03.04) (1 Sample)

(1) The inspectors evaluated the licensees use and maintenance of self-contained breathing apparatuses.

71124.04 - Occupational Dose Assessment

Source Term Characterization (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated licensee performance as it pertains to radioactive source term characterization.

External Dosimetry (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee processes, stores, and uses external dosimetry.

Internal Dosimetry (IP Section 03.03) (1 Sample)

The inspectors evaluated the following internal dose assessments:

(1) Tritium in-vitro bioassay results, torus diving, February 2024

Special Dosimetric Situations (IP Section 03.04) (1 Sample)

The inspectors evaluated the following special dosimetric situations:

(1) Declared pregnant worker dosimetry records, January 1, 2023 through February 12, 2025.

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (8 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1) Thermo Scientific, Small Article Monitor 12 at the main RCA exit (devices #289, and
  1. 286), and at the T-16 RCA exit (devices D21-N1929, and D21-N1927)
(2) Gem 5 portal monitors at the main RCA exit (devices D21-N1903, and D21-N1904),and at the T-16 RCA exit (device D21-N1842)
(3) Argos 5AB, personnel contamination monitors at the main RCA exit (devices D21-N1844, D21-N1900, D21-1901, and D21-N1902), and at the T-16 RCA exit (devices D21-N1853, and D21-N1848)
(4) Ludlum, Model 3, survey meters at the radiation protection (RP) office (devices D21-N1861, and D21-N1875)
(5) Telepole, survey meter at the RP office (device D21-1950)
(6) Alpha contamination friskers in use at various radiological protection checkpoints in the field, including Ludlum Model 3000 #25023061
(7) Ludlum Model 9-3, ion chamber survey meter at the unit 2 RP control point (drywell),

Serial Number (SN): 273437

(8) Eberline Model RM-25, at unit 2 refuel floor exit, SN: 690

Calibration and Testing Program (IP Section 03.02) (13 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) Unit 0, 1Z41N015A, Control Room Area Radiation Monitor, calibrated on August 3, 2023, and August 8, 2024
(2) Unit 0, 1Z41N015B, Control Room Area Radiation Monitor, calibrated on January 28, 2023, and January 24, 2024
(3) Mirion HNP-DO People Mover Whole-Body Counter, calibrated on July 30, 2024
(4) HIDEX Liquid Scintillator Counter, SN: 300SL 425-201, calibrated March 5, 22024
(5) Unit 2, 2D11-K621A, and 2D11-K621B, Drywell Wide-Range (Post LOCA) Radiation Monitors, calibrated on February 24, 2021 and February 17, 2023
(6) Unit 2, 64CI-OCB-006-2, Off-Gas Pre-Treatment Radiation Monitor, calibrated on February 13, 2023
(7) Unit 2, 64CI-OCB-007-0 Main Steam Line Radiation Monitor Channels A, B, C, and D, calibrated February 14, 2023
(8) Counting Room High Purity Germanium Detector 2, LVCC0 geometry, calibrated on April 30, 2019
(9) Counting Room High Purity Germanium Detector 3, LTBS geometry, calibrated on March 18, 2019
(10) Unit 2, 2D11-K622A, Drywell Post LOCA Radiation Monitor, calibrated January 26, 2021, and January 10, 2023
(11) Ludlum Model 3000 (Sn:25023080) with Alpha probe (Sn:PR403791), calibrated October 8, 2024
(12) Mirion, Telepole II, SN:232921-054, calibrated February 10, 2025
(13) Ludlum Model 9-3, Ion Chamber Survey Meter (SN: 358500), calibrated July 22, 2024 Effluent Monitoring Calibration and Testing Program Sample (IP Section 03.03) (3 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1) Unit 2, 2D11K604, Liquid Radwaste Radiation Monitor, calibrated on August 10, 2021, and July 21, 2023
(2) Unit 1, 1D11K600A, Plant Main Stack Radiation Monitoring, calibrated on May 30, 2024
(3) Unit 1, 1D11K600B, Plant Main Stack Radiation Monitoring, calibrated on May 30,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) Unit 1 (January 1 through December 31, 2024)
(2) Unit 2 (January 1 through December 31, 2024)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (2 Samples)

(1) Unit 1 (January 1 through December 31, 2024)
(2) Unit 2 (January 1 through December 31, 2024)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (2 Samples)

(1) Unit 1 (January 1 through December 31, 2024)
(2) Unit 2 (January 1 through December 31, 2024)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) February 10, 2024 through February 14, 2025 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) February 10, 2024 through February 14,

INSPECTION RESULTS

Unit 1 Reactor Core Isolation Cooling (RCIC) Rendered Inoperable Due to Human Error Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000321,05000366/2025001-01 Open/Closed

[H.12] - Avoid Complacency 71111.20 A Green self-revealed non-cited violation (NCV) of 10 CFR 50, Appendix B, Criterion XI, Test Control was identified when licensee personnel failed to follow test procedure 34SV-E51-010-2, RCIC Logic System Functional Test for unit 2. Specifically, licensee personnel installed electrical jumpers in a unit 1 panel instead of the unit 2 panel required by the procedure. As a result, on February 10, 2025, the unit 1 reactor core isolation cooling (RCIC)system was inadvertently isolated and rendered inoperable and unavailable for approximately 1.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.

Description:

On February 10, 2025, with unit 1 in Mode 1 at rated thermal power and unit 2 shutdown for a refueling outage, the licensee was performing a logic system functional test for the unit 2 RCIC system in accordance with test procedure 34SV-E51-010-2, RCIC Logic System Functional Test. Step 13 in Section 4.4, RCIC Auto-Isolation Logic B Test, requires installation of electrical jumpers in panel 2H11-P926 which is a unit 2 panel in the common main control room (MCR). This step simulates a steam line high differential pressure. During the test, electrical jumpers were incorrectly placed inside a unit 1 MCR panel instead of a unit 2 MCR panel as directed by the procedure. As a result, the unit 1 RCIC steam supply isolation valve (2E51-F007) went closed which isolated RCIC and rendered the system inoperable and unavailable. This was immediately recognized by the unit 1 operations staff through several MCR alarms. The licensee restored the unit 1 RCIC system after approximately 1.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. The licensee classified test procedure 34SV-E51-010-2 as a safety related procedure.

Corrective Actions: The licensee removed the electrical jumpers in the unit 1 panel and completed the unit 1 RCIC system standby alignment procedure which restored RCIC operability and availability.

Corrective Action References: Condition report (CR) 11150079 and corrective action report (CAR) 819309.

Performance Assessment:

Performance Deficiency: The failure to follow test procedure 34SV-E51-010-2 which required installation of electrical jumpers in a unit 2 MCR panel during testing of the unit 2 RCIC system was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Human Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, a unit 1 RCIC steam supply isolation valve went closed because of the performance deficiency which rendered the unit 1 RCIC system inoperable and unavailable for approximately 1.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors screened this finding using Exhibit 2, Mitigating Systems Screening Questions of IMC 0609, Appendix A. The finding screened to Green, very low safety significance, because all the screening questions were answered as No.

Cross-Cutting Aspect: H.12 - Avoid Complacency: Individuals recognize and plan for the possibility of mistakes, latent issues, and inherent risk, even while expecting successful outcomes. This includes the effective use of appropriate error-reduction tools. In this case, licensee personnel involved in the installation of electrical jumpers did not adequately apply such tools. Specifically, both the performer and the peer checker failed to identify that the jumpers were being installed in a unit 1 panel, rather than the unit 2 panel specified in the procedure.

Enforcement:

Violation: 10 CFR 50, Appendix B, Criterion XI, Test Control requires in part, a test program shall be established to assure that all testing required to demonstrate that structures, systems, and components will perform satisfactorily in service is identified and performed in accordance with written test procedures. Contrary to this requirement, on February 10, 2025, licensee personnel failed to perform a logic system functional test for the unit 2 RCIC system in accordance with test procedure 34SV-E51-010-2, RCIC Logic System Functional Test.

Specifically, licensee personnel installed electrical jumpers in a unit 1 panel instead of the unit 2 panel as required by the procedure which isolated unit 1 RCIC and rendered the system inoperable and unavailable for approximately 1.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. The licensee classified test procedure 34SV-E51-010-2 as a safety related procedure.

Enforcement Action: This violation is being treated as an NCVs, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to properly calibrate effluent radiation monitors Cornerstone Significance Cross-Cutting Aspect Report Section Public Radiation Safety Green NCV 05000321,05000366/2025001-02 Open/Closed

[H.6] - Design Margins 71124.05 The NRC inspectors identified a Green finding and associated non-cited violation (NCV) of Technical Specification (TS) 5.5.1, Offsite Dose Calculation Manual (ODCM), for the failure to properly calibrate effluent radiation monitors 2D11K601 and 2D11K602, in accordance with the ODCM requirements.

Description:

The ODCM identifies unit 2 pre-treatment radiation monitors 2D11K601 and 2D11K602 as effluent radiation monitors in Table 3-1. The ODCM defines channel calibration as the adjustment, as necessary, of the channel output, such that it responds within the necessary range and accuracy to known values of the parameter that the channel monitors.

NRC inspectors reviewed calibration records of radiation monitors 2D11K601, and 2D11K602 using procedure 64CI-OCB-006-2 Pre-treatment Radiation Monitoring, and determined 1) the wrong calibration source output data was used; 2) the calibration source-detector setup lacked an alignment jig or tool to ensure adequate exposure of the active volume of the detector; 3) a fixed source-detector distance setup methodology was not appropriately used to ensure exposure distance repeatability; and 4) instrument calibration acceptance criteria, required by Updated Final Safety Analysis Report (UFSAR) Section 11.4.4.2, was not kept within +/- 15 percent. Additionally, the main steam line radiation monitors, and the post-LOCA (loss of coolant accident) monitors, as well as the unit 1 pre-treatment radiation monitors, were found to have the same issues.

Corrective Actions: The licensee entered the issue in their corrective action program. The licensee conducted industry benchmarking, obtained vendor support, and pulled historical records for additional review. The licensee indicated that after the applicable procedures are revised, the monitors in question will have the calibrations re-performed (as soon as reasonably achievable) with any adjustments to electronics needed to bring their response within the revised calibration acceptance criterion.

The licensee attempted to re-calibrate unit 2 pre-treatment radiation monitors, 2D11K601 and 2D11K602, using a proposed new methodology, but the radiation monitors were found to be outside the +/- 15 percent acceptance criteria required.

Corrective Action References: Condition Report (CR) 11162134

Performance Assessment:

Performance Deficiency: The failure to properly calibrate effluent radiation monitors, 2D11K601 and 2D11K602, per the UFSAR Section 11.4.4.2 and in accordance with the ODCM as required by TS 5.5.1, was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Plant Facilities/Equipment and Instrumentation attribute of the Public Radiation Safety cornerstone and adversely affected the cornerstone objective to ensure adequate protection of public health and safety from exposure to radioactive materials released into the public domain as a result of routine civilian nuclear reactor operation.

Specifically, the as-found condition of the effluent radiation monitors was out of the UFSAR-described acceptance criteria tolerance.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix D, Public Radiation Safety SDP. Specifically, the finding is associated with the radioactive effluent release program but with no dose impact to a member of the public and did not exceed the dose values in Appendix I to 10 CFR Part 50 and/or 10 CFR 20.1301(e),resulting in a very low radiological significance, which the Significance Determination Process (SDP) classifies as Green.

Cross-Cutting Aspect: H.6 - Design Margins: The organization operates and maintains equipment within design margins. Margins are carefully guarded and changed only through a systematic and rigorous process. Special attention is placed on maintaining fission product barriers, defense-in-depth, and safety related equipment. Specifically, the procedures in use were inadequate to ensure that the radiation monitors responded within the necessary range and accuracy to a known radiation source.

Enforcement:

Violation: Technical Specification 5.5.1 Offsite Dose Calculation Manual (ODCM), requires in part that the ODCM be established, implemented, and maintained. The ODCM requires, in part, that each gaseous effluent monitoring instrumentation channel be demonstrated operable by performance of a channel calibration. The ODCM defines channel calibration as the adjustment, as necessary, of the channel output, such that it responds within the necessary range and accuracy to known values of the parameter that the channel monitors.

The ODCM identifies radiation monitors 2D11K601 and 2D11K602 as effluent radiation monitors in Table 3-1.

Contrary to the above, as of March 7, 2025, the licensee failed to perform calibrations on the pre-treatment gaseous effluent monitors such that they responded within the necessary range and accuracy to a known radiation source.

Enforcement Action: This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified that no proprietary information was retained or documented in this report.

  • On April 17, 2025, the inspectors presented the integrated inspection results to Matthew Busch, Site Vice President (SVP), and other members of the licensee staff.
  • On February 20, 2025, the inspectors presented the in-service inspection results to Matthew Busch, SVP, and other members of the licensee staff.
  • On February 14, 2025, the inspectors presented the RP inspection results to Matthew Busch, SVP, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

Condition Report

(CRs)

11090278, 11090700, 11090736

Corrective Action

Documents

Resulting from

Inspection

CRs

11140676, 11140693, 11140695, 11141146

Miscellaneous

1-DT-21-X41-

00100(2)

Danger Tagout for 1X41B005A, Intake Structure Room

Heater 1A

34AB-Y22-002-0

Naturally Occurring Phenomena

20.6

34SO-X41-002-0

Intake Structure Ventilation System

4.7

2PM-MEL-005-0

Cold Weather Checks

18.7

DI-OPS-36-0989

Cold Weather Checks

23.8

NMP-OS-017

Severe Weather

5.0

Procedures

NMP-OS-020

Hatch Station Response To Southern Company System

Alert Conditions

1.0

71111.01

Work Orders

SNC1235494

07/08/2024

CR 11146329

NRC resident concern

01/28/2025

Corrective Action

Documents

Resulting from

Inspection

CR 11146740

Valve restraint required tightening based on NRC resident

question

01/29/2025

34SO-E41-001-2

HPCI System

31.5

34SO-R43-001-2

Diesel Generator Standby AC System

30.11

34SO-T46-001-1

Standby Gas Treatment System

21.7

34SO-T46-001-2

Standby Gas Treatment System

15.3

71111.04

Procedures

34SO-Z41-001-1

Control Room Ventilation System

25.3

CR 11040584

Trouble Alarm on panel in PCR

01/18/2024

CR 11104855

2X43-P004 PCR Alarm In

08/24/2024

Corrective Action

Documents

CR 11108507

Fire Alarm Panel alarming in PCR Room

09/07/2024

Fire Plans

NMP-ES-035-

019-GL02-F12

U1 Reactor Building El. Below 130

1.0

71111.05

Fire Plans

NMP-ES-035-

019-GL02-F17

U1 Reactor Building El. 228

1.0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NMP-ES-035-

019-GL02-F34

U2 Reactor Building El. 228

1.0

NMP-ES-035-

019-GL02-F57

Unit 2 Main Power Transformer Yard El. 129

1.0

CR 10945502

FAC Component Alternate Calculation

2/03/2023

CR 10949041

SBLC ISI Pressure Test Equipment Issue

2/17/2023

Corrective Action

Documents

11020740

Eng Recommendation - Pipe Support Inspection

11/01/2023

71111.08G

Work Orders

SNC1857323

Repair Leak on 2E11-D002B

06/19/2024

Corrective Action

Documents

CR 11146794

Relay Logic Time Response Failures

01/29/2025

34GO-OPS-013-2

Normal Plant Shutdown

33.9

34SV-E21-001-2

Core Spray Pump Operability

24.11

57SV-MNT-005-2

Relay Logic Response Time Testing Channel A

5.0

Procedures

57SV-MNT-020-2

Relay Logic Response Time testing In Mode 1 Channel A

2.1

71111.11Q

Work Orders

SNC1011189

Relay Logic Response Time Testing

01/29/2025

CR 11129891

Unit 1 ATTS channel check UNSAT for 1E11-N655B/N656B

11/21/2024

CR 11130062

VP Approval is REQUIRED to accept/reject the conditional

release of nonconforming material

11/21/2024

CR 11136901

MRule CME criteria exceeded for A70-01

2/19/2024

Corrective Action

Documents

CR 11157186

H23355

Single Line Diagram 4160V Bus 2A & 2B

H26003

Recirculating System P & ID

Drawings

H27481

Reactor Recirc. Pump & ASD "A" System

EVAL-H-A70-

06730

ATTS (a)(1) review

01/14/2025

Engineering

Evaluations

TE 1167023

2SP-05-06-24-

RR-1-2

2B31-C001B Reactor Recirc Pump Motor Uncoupled Run

FT

2CM-B31-003-0

Reactor Recirculation System Recirculation Pump

Mechanical Seal Replacement

2PM-B31-005-0

Reactor Recirculation Pump Maintenance

Procedures

NMP-ES-027

Maintenance Rule Program

11.1

71111.12

Work Orders

SNC 1797850

2B Recirc Pump motor replacement

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SNC1455927

Repair/Replace ATTS card 1E11N694D

03/18/2023

SNC1564256

Replace ATTS card and calibrate per applicable

09/11/2023

SNC2162038

Unit 1 ATTS channel check UNSAT for 1E11-N655B/N656B

11/22/2024

Calculations

U2 Phoenix

model

U2 Phoenix model

2/04/2025

31GO-OPS-024-0

Outage Safety Assessment

03/03/2025

NMP-OS-010

Protected train/division and protected equipment program

71111.13

Procedures

NMP-OS-010-002

Hatch Protected Equipment Logs

2.6

Calculations

BH1-M-V005-0003

Reactor Building HELB Flow Model

11/11/2003

CRs

11070121, 11079222, 11090655, 11089513, 11081767,

11082238

CR 11151026

PSW piping below min wall thickness

2/13/2025

Corrective Action

Documents

CR 11152297

Snubber base bolt thread engagement

2/17/2025

009N7112

Hatch unit 2 RPV Closure Region Stress and Fatigue

Reconciliation to Address Bushing Modification

2/21/2025

FDDR 009N7732

Field Deviation Disposition Request Evaluation for

indications on RPV flange stud hole 33

03/06/2025

Engineering

Evaluations

Technical

Evaluations (TEs)

1153550, 1165673, 1170355

2GM-MME-004-2

Reactor Vessel Reassembly (RPV Stud Elongation

Readings)

25.0

ACMP

Adverse Condition Monitoring Plan - 1C SRV Leakage

04/18/2024

Miscellaneous

ODMI: 1-24-004

1C safety relief valve (SRV) 2nd stage leak

1.0

NDE Reports

S17H2U001

2017 RPV Stud UT Examination

2/23/2017

Procedures

34AB-B21-003-1

Failure of Safety/Relief Valves

10.5

SNC 1764525

2R28 - 2E11 - Snubber visual examination

2/13/2025

SNC 2327951

Replace snubber at location 2E11RHRR226A

2/24/2025

71111.15

Work Orders

SNC1811373

Repair steam leak at 1E51-D003 cover

07/10/2024

34SV-E51-002-2

RCIC Pump Operability

27.3

71111.18

Procedures

2SP-12-17-24-

RC-1-2

Alternate RCIC Turbine Speed Control Test

1.0

CR 11150238

PQ&S not validated/approved by end of shift

2/11/2025

71111.20

Corrective Action

Documents

CR 11152551

PQ&S not validated/approved by end of shift

2/18/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR 11153378

PQ&S not validated/approved by end of shift

2/19/2025

CR 11155830

Training Impact Review - Throttling for 2E11F048B

2/27/2025

CR 11155830

Training Impact Review - Throttling for 2E11F048B

2/27/2025

CR 11155997

Missing Pipe Cap on unit 2 Vent Valve in Drywell

2/27/2025

CR 11155998

Crack on transformer drawer on 2R22-S006 FR 6

2/27/2025

CR 11158511

Multiple T48 valve model 9200 thrust washers found missing

03/07/2025

CR 11158873

Damaged Insulation in the Drywell

03/09/2025

CR 11152406

Inaccurate Time To Boil in Outage Safety Assessment

CR 11153274

Questioned tag placement position of RHR valve

2E11F017A

CR 11157616

2R28 Torus proper walkdown with NRC

03/05/2026

CR 11158760

Items identified during drywell closeout.

03/09/2025

Corrective Action

Documents

Resulting from

Inspection

CR 11160314

Seismic and housekeeping concerns inside U2 Reactor

Building

03/13/2025

Drawings

H10167

Refueling Floor Heavy Load Paths

13.0

H2R28 Shutdown Safety Assessment

01/09/2025

Hatch unit 2 Core, Cycle 29 Final Core Map

2/27/2025

2-CA-25-2P41-

04000

Tagout

2/15/2025

2-DT-25-2E11-

00091

Tagout

2/16/2025

2SV-TET-001-2

Hatch Nuclear Plant Spring 2025 unit 2 Refueling Outage

Summarized LLRT Test Results Report

03/13/2025

Main Control Room Schedule Report

Feb. 2025

Maintenance Department Schedule Report

Feb. 2025

Miscellaneous

Fatigue

Management

Program

Documents

Operations A Team Schedule Report

Feb. 2025

34AB-E11-001-2

Loss of Shutdown Cooling

6.26

34GO-OPS-001-2

Plant Startup

51.16

34GO-OPS-003-2

Startup System Status Checklist

15.11

34GO-OPS-013-2

Normal Plant Shutdown

33.9

34GO-OPS-015-2

Maintaining Cold Shutdown or Refuel Condition

16.4

Procedures

34GO-OPS-028-2

Drywell Closeout

7.23

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

34GO-OPS-029-0

Torus and Torus Area Closeout

4.0

34SO-G71-001-0

Decay Heat Removal System

19.3

2SV-TET-001-0

LLRT Testing Methodology

13.1

57SV-B21-020-2

Reactor Wide Range Level Indication

4.4

NMP-AD-003

Equipment Clearance and Tagging

33.1

NMP-AD-016

Fatigue Management Program

11.2

NMP-OM-002

Shutdown Risk Management

6.11

NMP-OS-010-002

Hatch Protected Equipment Logs

2.7

NMP-RE-007

Core Verification

6.0

Work Orders

SNC1155459

Perform Channel Calibration of 2B21N027 and 2B21R605

2/09/2025

CAR 805135

Partially Completed Surveillance

01/14/2025

CAR 821174

2A EDG Trip

CR 11142216

Partially Completed Surveillance

01/14/2025

CR 11143415

C MCR air conditioner tripped after starting

01/17/2025

CR 11143417

main power relay is faulty

01/17/2025

CR 11146518

Unit 2 RCIC oil level is low following special purpose run

01/29/2025

CR 11146552

RCIC pump/turbine new reference data

01/29/2025

CR 11147164

2B SBGT Flow High

01/30/2025

CR 11147167

2B SBGT Heater Not Energized

01/30/2025

CR 11148513

2A EDG lube oil level low

2/05/2024

CR 11151270

2A EDG Trip

2/13/2025

CR 11151726

EDG Industry Best Maintenance Practices

2/14/2025

Corrective Action

Documents

TE 1168944

IRT for Partially Completed Surveillance

01/14/2025

Drawings

H-26084

Hatch Unit 2 Primary Containment Purge & Inerting System

P&ID

2SV-TET-001-0

Form ENG-0135

Volumetric Leak Rate Monitor Local Leak Rate Test Data

Sheets for Valves 2T48-F319 and F320, Drywell Vent

Isolation Valves

2/11/2025

MIS-16-005

Unit 1 Fifth 10-Year Interval Pump Inservice Testing Basis

Document

3.0

Unit 2 Control Log

Unit 2 Control Log

01/08/2025

Miscellaneous

Unit 2 Control Log

Unit 2 Control Log

11/26/2024

71111.24

Procedures

34SV-C41-002-1

Standby Liquid Control Pump Operability Test

01/30/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

34SV-E11-001-2

Residual Heat Removal Pump Operability

01/08/2025

34SV-E11-002-2

RHR Valve Operability

01/21/2025

34SV-E51-002-2

RCIC Pump Operability

01/29/2025

34SV-R43-001-2

Diesel Generator 2A Monthly Test

2/04/2025

34SV-R43-020-2

Diesel Generator 2A LOCA/LOSP LSFT

2/14/2025

34SV-SUV-008-2

Primary Containment Isolation Valve Operability

08/27/2024

34SV-SUV-008-2

Primary Containment Isolation Valve OOperability

01/14/2025

34SV-T46-003-2

Standby Gas Treatment Ventilation & Operability

01/30/2025

2SP-12-17-24-

RC-1-2

Alternate RCIC Turbine Speed Control Test

01/29/2025

SNC1129763

SBGT Filter Trains DOP Test

01/30/2025

SNC1150432

Unit 2 MCR Level Indicator for 2A Fuel Oil Tank

2/20/2021

SNC1155232,

1155253,

1155292,

1155293

Outboard Main Steam Isolation Valve 24-Month Preventive

Maintenance

SNC1579391

RCIC Turbine Control System Setpoint

01/29/2025

SNC1637229

Primary Containment Isolation Valve Operability

11/26/2024

SNC1681030

2C RHR Pump IST

01/08/2025

SNC1681045

2A RHR Pump IST

01/08/2025

SNC1695773

1A SBLC IST

01/30/2025

SNC1710586

2A EDG Monthly Test

2/04/2025

SNC2262873

Perform 34SV-SUV-008-2 Section 4.3

01/14/2025

SNC2270673

Replace relays on 1C main control room air conditioner

01/17/2025

SNC2319920

Replace Overspeed Trip Switch for 2R43S001A

2/14/2025

Work Orders

SNC456365

evaluate replacement relays for MCREC condenser unit

09/26/2013

Corrective Action

Documents

Resulting from

Inspection

CRs

11151237, 11151643, 11151875, 11151877, 11151881

NMP-HP-501

Radiological Respiratory Protection Program

2.0

71124.03

Procedures

NMP-HP-501-003

Inspection, Repair, and Storage of Non-SCBA Respiratory

Protection Equipment

1.2

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NMP-HP-501-005

Inspection, Repair and Storage of the MSA G1 SCBA

3.0

NMP-HP-504

Quantitative Fit Testing of Individuals for Respiratory Use

5.0

SNC1137783

Testing of Control Room Habitability Filter Trains

2/11/2024

SNC805890

Testing of Control Room Habitability Filter Trains

05/26/2021

SNC839149

Testing of Control Room Habitability Filter Trains

01/21/2021

SNC988760

Testing of Control Room Habitability Filter Trains

04/14/2023

Work Orders

SNC992454

Testing of Control Room Habitability Filter Trains

01/16/2023

NMP-HP-107

Individual Radiation Exposure Records and Reports

Version 4.0

NMP-HP-107-F02

Declaration of Pregnancy

Version 1.0

71124.04

Procedures

NMP-HP-108-001

Instruction for Issuing and Activating Dosimetry and

Updating Dose Records in HIS-20

Version 2.3

64CI-OCB-006-2

Unit 2, Pre-treatment Radiation Monitoring

2/13/2023

64CI-OCB-007-0

Main Steam Line Channel A

2/14/2023

64CI-OCB-007-0

Main Steam Line Channel B

2/14/2023

64CI-OCB-007-0

Main Steam Line Channel C

2/14/2023

64CI-OCB-007-0

Main Steam Line Channel D

2/14/2023

64CI-OCB-011-0

Calibration of Post-LOCA Monitors 2D11K622A

01/26/2021

64CI-OCB-011-0

Calibration of Post-LOCA Monitors 2D11K622A

01/10/2023

64CI-OCB-011-0

Calibration of Post-LOCA Monitors 2D11K622B

2/27/2021

64CI-OCB-011-0

Calibration of Post-LOLA Monitors 2D11K622B

2/27/2021

64CI-OCB-011-0

Calibration of Post-LOCA Monitors 2D11K622B

2/15/2023

64CI-OCB-011-0

Calibration of Post-LOCA Monitors 2D11K622C

2/27/2021

64CI-OCB-011-0

Calibration of Post-LOCA Monitors 2D11K622C

01/10/2023

64CI-OCB-011-0

Calibration of Post-LOCA Monitors 2D11K622D

01/26/2021

Calibration

Records

64CI-OCB-011-0

Calibration of Post-LOCA Monitors 2D11K622D

01/17/2023

71124.05

Corrective Action

Documents

CRs

10992832, 11033362, 10963536, 10964305, 10980185,

11002375, 11011800, 11020950, 11064846, 11093894

Miscellaneous

IRIS Report

585807

PI Report

03/11/2024

IRIS Report

588449

PI Report

03/19/2024

71151

IRIS Report

588450

PI Report

03/26/2024