IE Insp Repts 50-321/80-37 & 50-366/80-37 on 800916-17.No Noncompliance Noted.Major Areas Inspected:Followup on Items of Noncompliance Re Part 21 Evaluation & Reporting Matters
ML19345B227
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 10/03/1980
From: Brownlee V, Conlon T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19345B225 List:
References
50-321-80-37, 50-366-80-37, NUDOCS 8011260387
Download: ML19345B227 (2)


Text

[

_

.

.-

UNITED STATES

!"

h NUCLEAR REGULATORY COMMISSION

'$

I REGION 11

,

e, f

101 MARtETTA ST., N.W SdlTE 3100 b

%

o ATLANTA, CEORGIA 30303

.....

Report Nos. 50-321/80-37 and 50-366/80-37 Licensee: Georgia Power Company 270 Peachtree Street Atlanta, CA 30303 Facility Name: E.I. Hatch Docket Nos. 50-321 and 50-366 License Nos. DPR-57 and NPF-5 Inspection at E.I.

atch site near Baxley, Georgia

/0/3f6C inspector: { tw 1 sy s

'

V.'L.Obrownlee Datt Signed zur d>f u

/o /c-/1fo Approted by r T. E. Conlon, Section Chief, RCES Branch Dat( Signed i

SUMMARY (

Areas Inspected This special, unannounced management inspection involved 8 inspector-hours onsite in the area of followup on items of noncompliance relative to Part 21 evaluation and reporting matters.

Results Noncompliance 321/79-33-01 and 366/79-37-01, " Hatch Part 21 Procedures" are closed.

.

..

.

i

8 01126oJ{ff

__

_

. -_.

~

.

__

.

. _ _ _.

.

[

,

,

.

.

DETAILS 1.

Persons Contacted Licensee Employees

  • M. Manry, Plant Manager
  • T. V. Greene, Assistant Plant Manager
  • C. R. Miles, Jr., QA Field Supervisor
  • P. E. Farnel, Jr., Senior QA Field Representative
  • C. E. Belflower,QA Site Supervisor
  • G. U. Deyton, Cognizant Engineer for Part 21
  • D. A. McCusker,QC Supervisor
  • R. M. Bellamy, Engineering Supervisor
  • Attended exit interview 2.

Exit Interview The inspection scope and findings were summarized on September 17, 1980 with those persons indicated in Paragraph I above.

3.

Licensee Action on Previous Inspection Findings (Closed) Infraction 321/79-33-01 and 366/79-37-01,

"E. I. Ha tch Pa rt 21 Procedures".

The inspector reviewed GPC's letter of response dated December 20, 1979; reviewed IE Reports dated November 26, 1979, March 4, 198T and August 25, 1980; held discussions with responsible QA plant mana3ement and Plant Review Board personnel; and reviewed the following documents:

a.

KNP-152, Posting Procedure b.

HNP-829, Requisition Review for Quality Requirements c.

KNP-456, Revision 4,

September 4,1980, Reporting of Defects and Noncompliance.

The inspector concluded the following:

Responsible personnel are quite knowledgrable of Part 21 requirements.

a.

b.

Responsible personnel understand the company Part 21 procedures.

c.

The procedures are adequate.

The inspector has no further que stions regarding this matter.

4.

Unresolv(d Items Unresolved items were not identified during this inspection.