05000245/LER-1997-023, Forwards LER 97-023-00 Per 10CFR50.73(a)(2)(iv).Commitments Made by Util,Submitted

From kanterella
Jump to navigation Jump to search
Forwards LER 97-023-00 Per 10CFR50.73(a)(2)(iv).Commitments Made by Util,Submitted
ML20196G182
Person / Time
Site: Millstone Dominion icon.png
Issue date: 05/08/1997
From: Noll W
NORTHEAST NUCLEAR ENERGY CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20196G185 List:
References
B16337, NUDOCS 9705150074
Download: ML20196G182 (2)


LER-2097-023, Forwards LER 97-023-00 Per 10CFR50.73(a)(2)(iv).Commitments Made by Util,Submitted
Event date:
Report date:
2452097023R00 - NRC Website

text

- - , . . - - - . _ - . -. . - . . . - . - - . . . - . - - . . - - --

Northeast 1 7 saden stnet, Bem cm037 Utilities System sorthe..t utiiitie. service company P.o. Box 270 llartford, CT 06141-0270 (203) 665-5000 r May 8,1997 Docket No. 50-245 I B16337 .

Re: 10CFR50.73(a)(2)(iv)

U.S.' Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 This letter forwards Licensee Event Report (LER) 97-023-00, documenting an event that occurred at Millstone Nuclear Power Station, Unit No.1 on April 9,1997. This LER is submitted pursuant to 10CFR50.73(a)(2)(iv). j The following are Northeast Nuclear Energy Company's (NNECO's) commitments made within this letter. All other statements made within this letter are for information only. I

~ B 16337-1 NNECO commits to provide a briefing to instrumentation and control personnel  ;

on the roles, responsibilities, and behaviors required during testing including self l checking and dual verification by June 1,1997.

B16337-2 NNECO commits to perform a review of all instrumentation and control procedures that require step-by-step use to prevent immediate effects on nuclear safety and plant reliability to verify that these procedures include adequate instructions for dual verification activities by December 31,1997.

B16337-3 NNECO commits to add the review of this event and any similar events to the initial and continuing training programs for instrumentation and control personnel prior to startup for operating cycle 16, Very truly yours, 4

NORTHEAST NUCLEAR ENERGY COMPANY  !

For: P. D. Hinnenkamp

Director, Unit Operations 4 4

By: W. G. Noll 9705150074 970508 y anage , Operations PDR S ADOCK 05000245[ PDR b,

_ _ _ . _ _ _ . . _ . . _ _ _ _ _ _ _ _ _ _ _ _ . _ . _ _ _ _ . _ _ _ . . . _ - - ~ . - _ . _ -

U.S. Nuclear Regulatory Commission

?- , B16337\Page 2 of 2

]

i 3

i l-

Attachment:

LER 97-023-00

. cc: Dr. W. D. Travers, Director, Special Projects

H. J. Miller, Region I Administrator  !

). S. Dembek, NRC Project Manager, Millstone Unit No.1 l j T. A. Eastick, Senior Resident Inspector, Millstone Unit No. I f