Provides List of Commitments for LER 97-007-00 Re Event That Occurred on 970308
ML20137S104
Person / Time
Site: Millstone Dominion icon.png
Issue date: 04/04/1997
From: Price J
NORTHEAST NUCLEAR ENERGY CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20137S106 List:
References
B16346, NUDOCS 9704150032
Download: ML20137S104 (2)


LER-2097-007, Provides List of Commitments for LER 97-007-00 Re Event That Occurred on 970308
Event date:
Report date:
3362097007R00 - NRC Website

text

Ifr li"P' F"'Y I- ("" ' 56)' *"""'d 'If 6385 Noed Nuclear Energy uai,too,Noacar n,,,rst. tion Northeet Nudcar Energy Cornpany P.O. Ilos 128 Waterfuni, (TT 06385-0128 (B60) 447-179i Fax (860) 444 4277 The Northcaat Utihtica Systern April 4, 1997 Docket No. 50-336 B16346 Re: 10 CFR 50.73(a)(2)(i)(B)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 This letter forwards Licensee Event Report (LER) 97-007-00, documenting an event that occurred at Millstone Nuclear Power Station, Unit No. 2 on March 8,1997. This LER is being submitted pursuant to 10 CFR 50.73(a)(2)(i)(B).

The following are NNECO's commitments made within this letter.

B16346-01: The Surveillance Procedure, " Reactor Head and Pressurizer Vent Solenoid Valve Operability Test," will be revised to ensure that this surveillance requirement is fulfilled before entering Mode 4 from the current outage.

B16346-02: Technical Specification surveillance procedures will be reviewed to ensure compliance with Technical Specification surveillance requirements as part of the Millstone Unit No. 2 Operational Readiness Plan. The review will initially focus on Technical Specification surveillance procedures required for Mode 6 and defueled. Surveillance procedures required for subsequent mode changes will be reviewed prior to mode entry. (This commitment was previously sent to the NRC in the response to NOV 336/96-08-07, NNECO Commitment No.

B16076-2.)

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY 9704150032 970404 e

. Sw>

$DR ADOCK0500g6 J. A. Pri([e)"

Director (Alillstone Unit No. 2 cc: see page 2 i

(,am.s uv. n*

181,Hpiippp,Hp,ER

U. S. Nuclear Regulatory Commission Q16346/Page 2

Attachment:

LER 97-007-00 cc: W. D. Travers, Director of Special Projects H. J. Miller, Region 1 Administrator D. P. Beaulieu, Senior Resident Inspector, Millstone Unit No. 2 D. G. Mcdonald, Jr., NRC Senior Project Manager, Millstone Unit No. 2

.