MONTHYEARML18102B6911997-01-31031 January 1997 Monthly Operating Repts for Jan 1997 for Diablo Canyon Power Plant,Units 1 & 2.W/970218 Ltr ML16342C3091993-12-31031 December 1993 Monthly Operating Repts for Dec 1993 for Dcnpp Units 1 & 2 ML16342A3691993-08-31031 August 1993 Revised MOR for Aug 1993 for Dcnpp Unit 1 ML16342A3681993-07-31031 July 1993 Revised MOR for July 1993 for Dcnpp Unit 1 ML20059G6811993-06-30030 June 1993 Revised MOR for June 1993 for Dcnpp Unit 1 ML20045D1731993-05-31031 May 1993 Monthly Operating Repts for May 1993 for Diablo Canyon,Units 1 & 2 ML16342A3671993-05-31031 May 1993 Revised MOR for May 1993 for Dcnpp Unit 1 ML20065R8731990-11-30030 November 1990 Monthly Operating Repts for Diablo Canyon Units 1 & 2 for Nov 1990 ML20195G3301988-04-30030 April 1988 Corrected Monthly Operating Repts for Apr 1988 for Diablo Canyon ML20236R8541987-10-31031 October 1987 Monthly Operating Repts for Oct 1987 ML20236N6611987-09-30030 September 1987 Monthly Operating Repts for Sept 1987 ML20234B4981987-08-31031 August 1987 Monthly Operating Repts for Aug 1987 ML20237J4591987-07-31031 July 1987 Monthly Operating Repts for Jul 1987 ML20235N9921987-06-30030 June 1987 Monthly Operating Repts for June 1987 ML20215F8331987-05-31031 May 1987 Monthly Operating Repts for May 1987 ML20214J0191987-04-30030 April 1987 Monthly Operating Repts for Apr 1987 ML20206J5941987-03-31031 March 1987 Monthly Operating Rept for Mar 1987 ML20207S4501987-02-28028 February 1987 Monthly Operating Repts for Feb 1987 ML20211C7871987-01-31031 January 1987 Monthly Operating Repts for Jan 1987 ML20212G7121986-12-31031 December 1986 Monthly Operating Repts for Dec 1986 ML20211P3021986-11-30030 November 1986 Monthly Operating Repts for Nov 1986 ML20212M1041986-10-31031 October 1986 Monthly Operating Repts for Oct 1986 ML20207F7541986-09-30030 September 1986 Monthly Operating Repts for Sept 1986 ML20212C6691986-08-31031 August 1986 Monthly Operating Repts for Aug 1986 ML20215D8211986-07-31031 July 1986 Monthly Operating Rept for Jul 1986 ML20214L6491986-06-30030 June 1986 Monthly Operating Repts for June 1986 ML20205D4361986-05-31031 May 1986 Monthly Operating Rept for May 1986 ML20207C7661986-04-30030 April 1986 Monthly Operating Repts for Apr 1986 ML20211H0161986-03-31031 March 1986 Monthly Operating Repts for Mar 1986 ML20197D0671986-02-28028 February 1986 Monthly Operating Repts for Feb 1986 ML20141H3321986-01-31031 January 1986 Monthly Operating Repts for Jan 1986 ML20154S5711985-12-31031 December 1985 Monthly Operating Repts for Dec 1985 ML20137V4291985-11-30030 November 1985 Monthly Operating Repts for Nov 1985 ML20141F9121985-10-31031 October 1985 Monthly Operating Repts for Oct 1985 ML20138C1801985-09-30030 September 1985 Monthly Operating Rept for Sept 1985 ML20138R8321985-08-31031 August 1985 Monthly Operating Repts for Aug 1985 ML20132G7291985-07-31031 July 1985 Monthly Operating Repts for Jul 1985 ML20135C3351985-06-30030 June 1985 Monthly Operating Repts for June 1985 ML20133H2481985-05-31031 May 1985 Monthly Operating Repts for May 1985 ML20129F2421985-04-30030 April 1985 Monthly Operating Repts for Apr 1985 ML20129H2061985-03-31031 March 1985 Monthly Operating Rept for Mar 1985 ML20115C7021985-02-28028 February 1985 Monthly Operating Rept for Feb 1985 ML20111C2651985-01-31031 January 1985 Monthly Operating Rept for Jan 1985 ML20106J6531984-12-31031 December 1984 Monthly Operating Rept for Dec 1984 ML20113F3281984-11-30030 November 1984 Monthly Operating Rept for Nov 1984 ML20100B8341984-11-29029 November 1984 Responds to 841126 Telcon Re Observation Training for D Barkley.Remaining 4 Wks of Required 12-wk Observation Time Should Be Waived.Related Correspondence ML20100L5471984-10-31031 October 1984 Monthly Operating Rept for Oct 1984 ML20093L4681984-09-30030 September 1984 Monthly Operating Rept for Sept 1984 ML20093G8671984-08-31031 August 1984 Monthly Operating Rept for Aug 1984 ML20097A4291984-07-31031 July 1984 Monthly Operating Rept for Jul 1984 1997-01-31
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20211A9981999-07-12012 July 1999 Draft,Probabilistic Safety Assessment, Risk Info Matrix, Risk Ranking of Systems by Importance Measure DCL-99-045, 1998 Annual Financial Rept for PG&E Corp. with1998-12-31031 December 1998 1998 Annual Financial Rept for PG&E Corp. with ML20217G5151997-12-31031 December 1997 1997 PG&E Corp Annual Rept ML20205F5881997-07-24024 July 1997 Decommissioning Cost Estimate for Diablo Canyon Power Plant,Units 1 & 2 ML17264A9381997-07-10010 July 1997 Deficiency Rept Re Potential Safety Hazard Associated w/FM-Alco 251 Engin,High Pressure Fuel tube-catalog: 4401031-2 in Which Dual Failure Mode Exists.Caused by Incorrect Forming Process ML18102B6911997-01-31031 January 1997 Monthly Operating Repts for Jan 1997 for Diablo Canyon Power Plant,Units 1 & 2.W/970218 Ltr ML16342D5351997-01-31031 January 1997 WCAP-14826, Instrumentation Calibr & Drift Evaluation Process for Diablo Canyon Units 1 & 2,24 Month Fuel Cycle Evaluation. ML16343A4741997-01-31031 January 1997 WCAP-11595,Rev 2, W Improved Thermal Design Procedure Instrument Uncertainty Methodology Diablo Canyon Units 1 & 2 24 Month Fuel Cycle Evaluation. ML17083C6231997-01-31031 January 1997 Rev 4 to WCAP-13705, W Setpoint Methodology for Protection Sys Diablo Canyon Units 1 & 2,24 Month Fuel Cycle Evaluation. DCL-97-045, Pacific Gas & Electric Co 1996 Annual Rept1996-12-31031 December 1996 Pacific Gas & Electric Co 1996 Annual Rept ML16342D5541996-12-31031 December 1996 Non-proprietary Nrc/Util Meeting on Model 51 SG Tube Integrity & ARC Methodology. ML20129J4311996-10-18018 October 1996 Safety Evaluation Approving Corporate Restructuring & Establishment of Holding Company Under Temporary Name PG&E Parent Co.,Inc of Which PG&E Would Become Wholly Owned Subsidiary DCL-96-155, Revised Special Rept SR 95-05:on 950806,EDG 1-2 to Achieve Rated Output Frequency within TS Limits.Caused by Degraded Electronic Governor Performance.Replaced Electronic Governor Motor Operated Potentiometer & Electronic Governor1996-07-22022 July 1996 Revised Special Rept SR 95-05:on 950806,EDG 1-2 to Achieve Rated Output Frequency within TS Limits.Caused by Degraded Electronic Governor Performance.Replaced Electronic Governor Motor Operated Potentiometer & Electronic Governor ML20116B8491996-07-22022 July 1996 Revised Special Rept SR 95-03:on 950621,EDG 1-2 Failed to Load During Surveillance Testing.Caused by Loose Fuse Holder Contact Clip.Retensioned Loose Fuse Holder Contact Clip & Tightened Loose Wire Connection ML20116B8521996-07-22022 July 1996 Revised Special Rept SR 95-04:on 950718,EDG 1-2 Load Swings Occurred.Caused by Defective Electronic Governor Stability Potentiometer.Replaced Electronic Governor ML20236Q2611996-04-15015 April 1996 Rev 0 to DCP M-050284, Design Change Package for Installation of CCW Surge Tank Pressurization Sys for Unit 1 ML20094M6251995-11-21021 November 1995 Final Part 21 Rept of Investigation & Analysis of Suspect Fasteners Event 29257.B&G-Cardinal Discontinued Using Heat Treatment Equipment at Cardinal Facility Until Such Time That Satisfactory Mods Made to Hardware & Procedures ML18064A8631995-08-14014 August 1995 LER 95-004-00:on 950714,determined That Redundant DG Circuits Not Separated Per App R Due to Insufficient App R Program Documentation.Hourly Fire Tour Established in EDG 1-1 Room & Review of LERs for App R Completed ML18100B2981994-05-24024 May 1994 LER 94-014-00:on 940426,SG 1-2 Automatically Started When Two Indicating Light Sockets Shorted Together Due to Personnel Error.Description of Event & Lessons Learned Will Be Published in Operations Incident Summary.W/940524 Ltr ML16342C3091993-12-31031 December 1993 Monthly Operating Repts for Dec 1993 for Dcnpp Units 1 & 2 ML16342A3691993-08-31031 August 1993 Revised MOR for Aug 1993 for Dcnpp Unit 1 ML16342A3681993-07-31031 July 1993 Revised MOR for July 1993 for Dcnpp Unit 1 ML20046A6611993-07-21021 July 1993 Cycle 6 Startup Rept. ML20059G6811993-06-30030 June 1993 Revised MOR for June 1993 for Dcnpp Unit 1 ML16342A3671993-05-31031 May 1993 Revised MOR for May 1993 for Dcnpp Unit 1 ML20045D1731993-05-31031 May 1993 Monthly Operating Repts for May 1993 for Diablo Canyon,Units 1 & 2 ML20126J5961992-12-31031 December 1992 Part 21 Rept Re Potential Loss of RHR Cooling During Nozzle Dam Removal.Nozzle Dams May Create Trapped Air Column Behind Cold Leg Nozzle Dam.Mod to Nozzle Dams Currently Underway. Ltrs to Affected Utils Encl ML20141M0471991-12-31031 December 1991 Pge Annual Rept - 1991 ML20086T1001991-12-31031 December 1991 Adequacy of Seismic Margins Assuming Increase in Amplitude of Diablo Canyon Seismic Long-Term Program Horizontal & Vertical Ground Motions Described in Sser 34 ML16341G4871991-11-30030 November 1991 Nonproprietary Technical Justification for Eliminating Large Primary Loop Pipe Rupture as Structural Design Basis for Diablo Canyon Units 1 & 2 Nuclear Power Plants. ML20085D2951991-08-21021 August 1991 Field Exercise Scenario,Aug 1991 ML20070S7311990-12-31031 December 1990 Analysis of Capsule X from Diablo Canyon Unit 2 Reactor Vessel Radiation Surveillance Program ML20065R8731990-11-30030 November 1990 Monthly Operating Repts for Diablo Canyon Units 1 & 2 for Nov 1990 ML20058P5181990-05-11011 May 1990 Accident Sequence Precursor Program Event Analysis 323/87-005 R2, Loss of RHR Cooling Results in Reactor Vessel Bulk Boiling ML20058P5131990-04-0505 April 1990 Accident Sequence Precursor Program Event Analysis 424/PNO-IIT-90-02A, Loop,Diesel Generator Failure & 36 Min Interruption of SDC During Mid-Loop Operation ML20058P5221990-02-0303 February 1990 Accident Sequence Precursor Program Event Analysis Loss of Reactor Protection Sys Bus B Causes Loss of Shutdown Cooling ML20006E5441989-11-30030 November 1989 Review of Flow Peaking & Tube Fatique in Diablo Canyon Units 1 & 2 Steam Generators. ML20006C6681989-11-30030 November 1989 Nonproprietary WCAP-12416, Evaluation of Thermal Stratification for Diablo Canyon Units 1 & 2 Pressurizer Surge Line. ML20246E4891989-06-30030 June 1989 Quarterly Sys Status Rept,2nd Quarter 1989,Sys 65 120V Instrument AC Sys,Sys 66 120V Security UPS Sys & Sys 67 125/250VDC Sys ML20245G9881989-06-16016 June 1989 Has Been Canceled.Resolution of LERs Missing from Lertrk/Scss/Dcs Discussed DCL-89-117, Special Rept:On 890406,main Steam Line Radiation Monitor 1RM-71 Alarmed & Declared Inoperable.Caused by Failure of Detector Tube.Tube Replaced.Monitor Returned to Svc on 8904181989-04-27027 April 1989 Special Rept:On 890406,main Steam Line Radiation Monitor 1RM-71 Alarmed & Declared Inoperable.Caused by Failure of Detector Tube.Tube Replaced.Monitor Returned to Svc on 890418 ML20247M6281989-03-31031 March 1989 Nonproprietary Advanced Digital Feedwater Control Sys Median Signal Selector for Diablo Canyon Units 1 & 2 ML20246P4461989-03-23023 March 1989 Corrected Diablo Canyon Power Plant Unit 2 Second Refueling Outage Inservice Insp (ISI) Rept ML20236E0581988-12-31031 December 1988 Pacific Gas & Electric Co Annual Rept 1988 ML20247H0761988-11-30030 November 1988 Vol 1 to Bit Elimination Study for Diablo Canyon Units 1 & 2 ML20205S9071988-10-31031 October 1988 Steam Generator U-Bend Tube Fatigue Evaluation ML20153E5331988-08-29029 August 1988 Safety Evaluation Supporting Amends 31 & 30 to Licenses DPR-80 & DPR-82,respectively ML20206E7181988-05-30030 May 1988 Analysis of Capsule U from PG&E Diablo Canyon Unit 2 Reactor Vessel Radiation Surveillance Program ML20195G3301988-04-30030 April 1988 Corrected Monthly Operating Repts for Apr 1988 for Diablo Canyon ML20153B0411988-03-31031 March 1988 Comments on ACRS Subcommittee on Diablo Canyon Meeting on 880223-24 in Burlingham,Ca Re Status of Long Term Seismic Program of Plant 1999-07-12
[Table view] |
Text
.- __ _ ___ ________
MONTHLY NARRATIVE REPORT OF OPERATION AND MAJOR MAINTENANCE EXPERIENCE This report describes the operating and major maintenance experience for the month of February,1987. This narrative report was prepared by the plant staff and is submitted in accordance with Section 6.9.1.7 of the Units 1 and 2 Technical Specifications.
On February 1,1987 Unit 1 started the month at 100X.
Unit 2 started the month at 100%.
On February 15, 1987 Unit 2 reduced power to 80% due to hydrogen leaking into the generator stator cooling water system.
On February 16, 1987 Unit 2 returned to full power after investigating the hydrogen leak into the generator stator cooling water system.
On February 17, 1987 Unit 2 was removed from the PGandE system and entered Mode 2 to repair a hydrogen leak in the generator stator cooling system.
On February 22, 1987 Unit I declared an unusual event when the Solid State Protection System (SSPS) Train B was declared inoperable. Unit 1 connenced a power decrease in preparation for unit shutdown. The SSPS train B was repaired and declared operable, the shut down was terminated, and the unit was stabilized at 30%
reactor power. At 30% reactor power Unit 1 experienced a turbine trip and subsequent reactor trip due to a High-High Steam Generator Level signal from 1-4 Steam Generator.
Unit 2 was returned to Mode 1 and synchronized to the PGandE system. Unit 2 commenced a power increase to 100%.
On February 23, 1987 Unit 1 entered Mode 1, synchronized to the PGandE system and returned to 73% power. Power was curtailed at 73% due to problems with the Heater #2 Drip Pump seals. Followihg pump repairs Unit I was returned to full power. Unit 2 returned to full power.
On February 25, 1987 Unit 2 reduced power to 50% to search for leaking undenser tubes. Unit 2 was then returned to full power after plugging leaking condenser tubes.
8703190470 870228 PDR ADOCK 05000275 i R PDR
/
MO.RPT
On February 26, 1987 Unit 2 reduced power to 50% to search for leaking condenser tubes.
On February 27, 1987 Unit 2 returned to full power after plugging leaking condenser tubes.
On February 28, 1987 Unit 1 ended the month with power at 100%.
Unit 2 ended the month with power at 100%.
Unit 1 operated this month with a unit availability factor of 93.1% and a unit capacity factor of 91.0%. Unit I shutdown one time this month due to a reactor trip.
Unit 2 operated this month with a unit availability factor of 84.4% and a unit capacity factor of 78.8%. Unit 2 shutdown one time this month to repair a hydrogen leak into the generator stator cooling water system.
Unit 2 reduced power three times this month, once for a hydrogen leak into the generator stator cooling water system and two times to search for and plug leaking condenser tubes.
No challenges to the steam generator safety valves or pressurizer power operated relief valves were made.
Significant safety related maintenance consisted of repairs to the Solid State Protection System and to the Plant Vent Gaseous and Particulate Radiation Monitors.
j M0.RPT
OPERATING DATA REPORT ,
l DOCKET NO. 50-275 DATE 03/02/87 COMPLETED BY A.T. Keller TELEPHONE (805)S95-7351 OPERATING STATUS
- 1. Unit Name: Diablo Canyon Unit 1
- 2. Reporting Period: February 1987
- 3. Licensed Thermal Power (Et): 3338
-4. Nameplate Rating (Gross We): 1137
- 5. Design Electrical Rating (Net We): 1086
- 6. Maximum Dependable Capacity (Gross MWe): 1125
- 7. Maximum Dependable Capacity (Net MWe): 1073
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:
N/A
- 9. Power Level To Which Restricted If Any (Net MWe): N/A
- 10. Reasons For Restrictions, If Any: None This Month Yr-to-Date Cumulative *
- 11. Hours In Reporting Period 672.0 1416.0 15910.3
- 12. Number Of Hours Reactor Was Critical 636.0 1288.5 12554.2
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
- 14. Hours Generator On-Line 625.8 1243.3 12208.8
- 15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 16. Gross Thermal Energy Generated ( WH) 2028965 3169447 36711516
- 17. Gross Electrical Energy Generated (MWH) 689400 1050700 12184432
- 18. Net Electrical Energy Generated (MWH) 656084 982341 11510162
- 19. Unit Service Factor 93.1 87.8 76.7
- 20. Unit Availability Factor 93.1 87.8 76.7 l 21. Unit Capacity Factor (Using EC Net) 91.0 64.7 67.4
- 22. Unit Capacity Factor (Using DER Net) 89.9 63.9 66.6 i
- 23. Unit Forced Outage Rate 6.9 12.2 5.9
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
(
N/A
- 25. If Shut Down At End Of Report Period. Est. Date of Startup: N/A l'
- As of counmercial operation on 5-7-85 at 0243.
M0.RPT
OPERATING DATA REPORT DOCKET NO. 50-323 DATE 03/02/87 COMPLETED BY A.Y. Keller TELEPHONE (805)595-7351 OPERATING STATUS P
- 1. Unit Name: Diablo Canyon Unit 2
- 2. Reporting Period: February 1987
- 3. Licensed Themal Power (Wt): 3411
- 4. Nameplate Rating (Gross W e): 1164
- 5. Design Electrical Rating (Net W e): 1119
- 6. Maximum Dependable Capacity (Gross MWe): 1130 **
- 7. Maximus Dependable Capacity (Net MWe): 1079 **
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report.
Give Reasons:
N/A
- 9. Power Level To Which Restricted If Any (Net MWe): N/A
- 10. Reasons For Restrictions, If Any: None This Month Yr-to-Date Cumulative *
- 11. Hours In Reporting Period 672.0 1416.0 8469.0
- 12. Number Of Hours Reactor Was Critical 672.0 1416.0 8273.0
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
- 14. Hours Generator On-Line 566.9 1310.9 8041.3
- 15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 16. Gross Thermal Energy Generated (WH) 1834179 4218919 2529 % 37
! 17. Gross Electrical Energy Generated (MWH) 606900 1394600 8307099 l 18. Het Electrical Energy Generated (MWH) 571402 1318681 7866855 l
- 19. Unit Service Factor 84.4 92.6 94.9
- 20. Unit Availability Factor 84.4 92.6 94.9
- 21. Unit Capacity Factor (Using W C Net) 78.8 86J 86.1
- 22. Unit Capacity Factor (Using DER Net) 76.0 d3.2 83.0
- 23. Unit Forced Outage Rate 15.6 7.4 5.1
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
l l Refueling Outage, April 3, 1987, 84 days
- 25. If Shut Down At End Of Report Period, Est. Date of Startup: N/A l
- As of commercial operation on March 13,1%6 at 0300 PST.
- These values are predictions - actual values are to be determined by operating experience during the first year of commercial operation.
M0.RPT
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-275 UNIT Diablo Canyon Unit 1 DATE 03/02/87 COMPLETED BY A.T. Keller TELEPHONE (805)S95-7351 MONTH February 1987 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (We-Net) (We-Net) 1 1068 17 1094 2 1087 18 1087 3 1083 19 1077 4 1091 20 1091 5 1091 21 1092 6 1091 22 284 7 1096 23 -37 8 1075 24 360 9 1091 25 744 10 1087 26 1009 11 1092 27 1083 12 1079 28 1088 13 1083 14 1079 15 1079 16 1095 INSTRUCTIONS On this format, list the average daily unit power level in We-Met for each day in the reporting month. Compute to the nearest whole megawatt.
The Average Monthly Electrical Power Level for February, 1987 = 976.32 W e-Net.
MO.RPT
{
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-323 UNIT Diablo Canyon Unit 2 DATE 03/02/87 COMPLETED BY A.T. Keller TELEPHONE (805)S95-7351 MONTH February 1987 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (We-Net) (We-Net) 1 1046 17 836 2 1087 18 -43 3 1087 19 -46 4 1087 20 -48 5 1087 21 -48 6 1087 22 225 7 1047 23 1016 8 1088 24 1093 9 1087 25 798 10 1092 26 997 11 1080 27 878 12 1088 28 1058 13 1083 14 1062 15 1054 16 934 INSTRUCTIONS On this format, list the average daily unit power level in We-Net for each de in the reporting month. Compute to the nearest whole megawatt.
The Average Monthly Electrical Power Level for February, 1987 = 850.30 We-Met.
M0.RPT
UNIT SHUTDOWNS Page 1 of 1 DOCKET NO. 50-275 UNIT NAME Diablo Canyon Unit 1 DATE 03/03/87 COMPLETED BY M.T. HUG REPORT MONTH FEBRUARY 1987 TELEPHONE (805)S95-7351 Duration Method of y System Component Ac i 2 4 5 No. Date Type l (Hours) Reason Shutdown 3 Report i Code Code Prevent Recurrence 1 02/22/87 F 46.2 A- 3 87-002 SJ FCV During a return to full power
from 30%, plant operators were unable to control steam generator level due to equipment problems with
. feedwater control valve (FCV) 510. Due to feed flow -
exceeding steam flow, steam generator 1-4 rose to the High-High trip setpoint. FCV 510 tras recalibrated and returned to service.
s 9
1 2 3 4 F: Forced Reason: Method: Exhibit G - Instructions S: Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test s 2-Manual Scram Entry Sheets for Licensee C-Refueling '
31 Automatic Scram Event Report (LER) File D-Regulatory Rettriction 4-Continuation from (NUREG-1022)
E-Operator Training & License Examination previous montii F-Administrative 5-Power reduction 5 G-Operational Error (Explain) 6,7,8-N/A
~
Exhibit I - Same Source -
H-Other (Explain) 9-Other '
~ _
M0.RPT - -
s 1 _
.h S m , .
UNIT SHUTDOWNS Page 1 of 1 DOCKET NO. 50-323 i -
UNIT NAME Diablo Canyon Unit 2
<x
~"
DATE 03/03/87 w~ -
'CCMPLETED BY. M.T. HUG
- REPORT MONTH FEBRUARY 1987 r- TC fPMHE (805)S95-7351 - -c w
=
i MeM"E , System: *0hnhgpcme - t Action in- ,_x
'~
s s (Hours) N Reason2 j vcnh No. Dura} ion Dates ~ Type SNddown3 rkeport i Cradek ' -Code 5 Prevent Recurrance
~
1 02/17/87 F 105 d _s
~A I _ N/A TJ CCL' -
Unit 2 was removed fim the _,
'M PGandE system and enteica rade 2 l s .to repair'a hydrogen leak in the
' generator 7 stator cooling' system. _
the leakage source was Jdentified and repaired and the~ unit? returned
, +~-_ -
- % to service. '
2-f ,,
( _
"~
1 2 3 4 F: Forced Reason: Method: Exhibit G - Instructions S: Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER) File D-Regulatory Restriction 4-Continuation from (NUREG-1022)
E-Operator Training & License Examination previous month F-Administrative 5-Power reduction 5 G-Operational Error (Explain) 6,7,8-M/A Exhibit I - Same Source-H-Other (Explain) 9-Other M0.RPT
PAC I F'IC GAS AND ELECTR,IC C O M PANY DIABLO CANYON POWER PLANT Y PO. Box 56 Avila Beach, California 93424 - (805) 595-7351 lllllllll R C. THORNBERRY PLANT MANAGER March 13, 1987 U.S. Nuclear Regulatory Comission Attn: Document Control Desk Washington, DC 20555 RE: Docket No. 50-275 and 50-323 License No. DPR-80 and DPR-82 Monthly Operating Report for February,1987 Gentlemen:
Enclosed are the completed monthly operating report forms for Diablo Canyon Units 1 and 2 for February,1987. This report is submitted in accordance with Section 6.9.1.7 of the Units 1 and 2 Technical Specifications.
Sincerely,
, &0 ^
ROBERT C. THORNBERRY RCT:1m l
Enclosures
, cc Mr. John B. Martin, Regional Administrator l Region V - USNRC l
l M0.RPT