IR 05000413/2020005

From kanterella
Revision as of 09:43, 24 August 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (NRC Inspection Report 05000413/2020005 and 05000414/2020005)
ML20230A000
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 08/17/2020
From: Frank Ehrhardt
NRC/RGN-II/DRP/RPB1
To: Simril T
Duke Energy Carolinas
References
IR 2020005
Download: ML20230A000 (6)


Text

ust 17, 2020

SUBJECT:

UPDATED INSPECTION PLAN FOR CATAWBA NUCLEAR STATION UNITS 1 AND 2 (NRC INSPECTION REPORT 05000413/2020005 AND 05000414/2020005)

Dear Mr. Simril:

The enclosed inspection plan lists the inspections scheduled through June 30, 2022, for Catawba Nuclear Station. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the Reactor Oversight Process (ROP), including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant.

In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, determine how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the May 28, 2020 memo, Inspection Guidance During Transition From COVID-19 Mandatory Telework (ML20141L766). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here:

https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.

The NRC will also be performing baseline inspections of licensee cyber security programs. The specific schedule and procedure to be used for these inspections is being developed by the NRC staff. The staff expects to communicate the schedule for these inspections to each utility separately.

Additionally, during this period the NRC will schedule an additional inspection per a revised version Temporary Instruction (TI) 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerability in Electrical Power Systems (NRC Bulletin 2012-01) for any sites who elect to implement the guidance of the Industry Initiative on Open Phase Condition, Revision 3 (ML19163A176), which included an option for relying on annunciation and operator manual actions instead of automatic protective features to isolate a power supply affected by an open phase condition. Licensees will be individually notified when the NRC schedules these inspections In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 404-997-4611 with any questions you have regarding this letter.

Sincerely,

/RA/

Frank J. Ehrhardt, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos.: 50-413, 50-414 License Nos.: NPF-35, NPF-52 Enclosure:

Catawba Inspection Activity Plan (08/17/2020 - 06/30/2022)

cc: Distribution via ListServ SUBJECT: UPDATED INSPECTION PLAN FOR CATAWBA NUCLEAR STATION UNITS 1 AND 2 (NRC INSPECTION REPORT 05000413/2020005 AND 05000414/2020005)

Dated August 17, 2020 DISTRIBUTION:

M. Kowal, RII L. Gibson, RII OE Mail RIDSNRRDRO PUBLIC RidsNrrPMCatawba Resource ROP Assessment ROP Reports ADAMS Accession Number: ML20230A000 OFFICE RII:DRP RII:DRP NAME JWorosilo FEhrhardt DATE 8/13/2020 8/17/2020 OFFICIAL AGENCY RECORD

IP 22 Inspection Activity Plan Report Catawba 08/17/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count CATAWBA IP 92723 1 1, 2 08/24/2020 08/28/2020 IP 92723 000914 Follow Up Inspection for Three or More Severity Level IV Traditional Enforcement Violations in the S CATAWBA REQUAL INSPECTION 2 1, 2 08/31/2020 09/04/2020 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance RP OCCUPATIONAL RAD SAFETY BASELINE INSPECTION 3 1, 2 09/14/2020 09/18/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 09/14/2020 09/18/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 09/14/2020 09/18/2020 IP 71124.04 000728 Occupational Dose Assessment 1, 2 09/14/2020 09/18/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation SECURITY BASELINE INSPECTION 3 1, 2 10/19/2020 10/23/2020 IP 71130.02 000734 Access Control 1, 2 10/19/2020 10/23/2020 IP 71130.09 001656 Security Plan Changes 1, 2 10/19/2020 10/23/2020 IP 71151 001338 Performance Indicator Verification EMERGENCY PREPAREDNESS EXERCISE INSPECTION (RESCHEDULED) 5 1, 2 10/26/2020 10/30/2020 IP 71114.01 000716 Exercise Evaluation 1, 2 10/26/2020 10/30/2020 IP 71151 001397 Performance Indicator Verification PROBLEM IDENTIFICATION AND RESOLUTION 4 1, 2 11/02/2020 11/06/2020 IP 71152B 000747 Problem Identification and Resolution 1, 2 11/16/2020 11/20/2020 IP 71152B 000747 Problem Identification and Resolution SECURITY BASELINE INSPECTION 2 1, 2 02/08/2021 02/12/2021 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1, 2 02/08/2021 02/12/2021 IP 71130.07 000739 Security Training EMERGENCY PREPAREDNESS PROGRAM INSPECTION 2 1, 2 03/15/2021 03/19/2021 IP 71114.02 000717 Alert and Notification System Testing 1, 2 03/15/2021 03/19/2021 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1, 2 03/15/2021 03/19/2021 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1, 2 03/15/2021 03/19/2021 IP 71114.05 000720 Maintenance of Emergency Preparedness 1, 2 03/15/2021 03/19/2021 IP 71151 001397 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report Catawba 08/17/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count UNIT 2 POST-APPROVAL LR PHASE 1 2 2 03/29/2021 04/02/2021 IP 71003 000687 Post-Approval Site Inspection for License Renewal UNIT 2 IN-SERVICE INSPECTION +SG 2 2 03/29/2021 04/02/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP PUBLIC RAD SAFETY INSPECTION 3 1, 2 05/24/2021 05/28/2021 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 05/24/2021 05/28/2021 IP 71124.07 000731 Radiological Environmental Monitoring Program 1, 2 05/24/2021 05/28/2021 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &

Transportation 1, 2 05/24/2021 05/28/2021 IP 71151 000746 Performance Indicator Verification DESIGN BASES ASSURANCE INSPECTION (TEAMS) 6 1, 2 06/28/2021 07/02/2021 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)

1, 2 07/19/2021 07/23/2021 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)

MATERIAL CONTROL & ACCOUNTING 2 1, 2 08/16/2021 08/20/2021 IP 71130.11 000742 Material Control and Accounting (MC&A)

TARGET SET INSPECTION 2 1, 2 08/16/2021 08/20/2021 IP 71130.14 000743 Review of Power Reactor Target Sets CATAWBA INITIAL LICENSE EXAM 3 1, 2 08/16/2021 08/20/2021 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1, 2 09/20/2021 10/01/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

SECURITY BASELINE INSPECTION 3 1, 2 10/04/2021 10/08/2021 IP 71130.02 000734 Access Control 1, 2 10/04/2021 10/08/2021 IP 71130.05 000737 Protective Strategy Evaluation 1, 2 10/04/2021 10/08/2021 IP 71130.09 001656 Security Plan Changes 1, 2 10/04/2021 10/08/2021 IP 71151 001338 Performance Indicator Verification UNIT 1 POST-APPROVAL LR PHASE 1 2 1 10/18/2021 10/22/2021 IP 71003 000687 Post-Approval Site Inspection for License Renewal This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report Catawba 08/17/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count UNIT 1 IN-SERVICE INSPECTION +SG 2 1 10/18/2021 10/22/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP OCCUPATIONAL RAD SAFETY BASELINE INSPECTION 1 1, 2 10/18/2021 10/22/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 10/18/2021 10/22/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 10/18/2021 10/22/2021 IP 71151 000746 Performance Indicator Verification DUKE CORPORATE AA/FFD BASELINE SECURITY INSPECTION 2 1, 2 01/10/2022 01/14/2022 IP 71130.01 000733 Access Authorization 1, 2 01/10/2022 01/14/2022 IP 71130.08 000740 Fitness For Duty Program SECURITY BASELINE INSPECTION 1 1, 2 01/24/2022 01/28/2022 IP 71130.01 000733 Access Authorization 1, 2 01/24/2022 01/28/2022 IP 71130.08 000740 Fitness For Duty Program RP OCCUPATIONAL RAD SAFETY BASELINE INSPECTION 3 1, 2 03/21/2022 03/25/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 03/21/2022 03/25/2022 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 03/21/2022 03/25/2022 IP 71124.04 000728 Occupational Dose Assessment 1, 2 03/21/2022 03/25/2022 IP 71124.05 000729 Radiation Monitoring Instrumentation 1, 2 03/21/2022 03/25/2022 IP 71151 000746 Performance Indicator Verification 1, 2 04/10/2022 04/15/2022 IP 71151 000746 Performance Indicator Verification 1, 2 04/11/2022 04/15/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 04/11/2022 04/15/2022 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 04/11/2022 04/15/2022 IP 71124.04 000728 Occupational Dose Assessment 1, 2 04/11/2022 04/15/2022 IP 71124.05 000729 Radiation Monitoring Instrumentation DESIGN BASES ASSURANCE INSPECTION (PROGRAMS) 3 1, 2 05/23/2022 05/27/2022 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements 1, 2 06/06/2022 06/10/2022 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.