Inspection/Activity Plan, 03/01/12 - 06/30/2013, Report 22
ML12066A016
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 03/05/2012
From:
NRC/RGN-II
To:
Duke Energy Carolinas
References
IR-11-007
Download: ML12066A016 (2)


Text

Page 1 of 2 03/05/2012 08:34:19 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Catawba Inspection / Activity Plan 03/01/2012 - 06/30/2013 EB3 ISI

- UNIT 2 INSERVICE INSPECTION 1

2 IP Inservice Inspection Activities - PWR 7111108P 03/19/2012 03/23/2012 PSB1-RP

- OCCUPATIONAL RADIATION PROTECTION WK1 3

1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/19/2012 03/23/2012 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 03/19/2012 03/23/2012 1, 2 IP Occupational Dose Assessment 71124.04 03/19/2012 03/23/2012 1, 2 IP Performance Indicator Verification 71151 03/19/2012 03/23/2012 EB3SGISI

- UNIT 2 SG INSERVICE INSPECTION 2

2 IP Inservice Inspection Activities - PWR 7111108P 03/26/2012 03/30/2012 PSB1EP

- EMERGENCY PREPAREDNESS EXERCISE 4

1, 2 IP Exercise Evaluation 7111401 04/16/2012 04/20/2012 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 04/16/2012 04/20/2012 1, 2 IP Drill Evaluation 7111406 04/16/2012 04/20/2012 OL RQ

- REQUAL INSPECTION 2

1, 2 IP Licensed Operator Requalification Program 7111111B 07/23/2012 07/27/2012 CDBI

- COMPONENT DESIGN BASES INSPECTION 8

1, 2 IP Component Design Bases Inspection 7111121 07/23/2012 07/27/2012 1, 2 IP Component Design Bases Inspection 7111121 08/13/2012 08/17/2012 1, 2 IP Component Design Bases Inspection 7111121 08/27/2012 08/31/2012 1, 2 IP Component Design Bases Inspection 7111121 09/10/2012 09/14/2012 OL EXAM

- INITIAL EXAM PREP 3

1 CATAWBA/AUGUST 2012 EXAM AT POWER FACILITIES V23378 08/13/2012 08/17/2012 OL EXAM

- INITIAL EXAM - WEEK 1 3

1 CATAWBA/AUGUST 2012 EXAM AT POWER FACILITIES V23378 09/03/2012 09/07/2012 OL EXAM

- INITIAL EXAM - WEEK 2 3

1 CATAWBA/AUGUST 2012 EXAM AT POWER FACILITIES V23378 09/10/2012 09/14/2012 PI&R

- PROBLEM IDENTIFICATION AND RESOLUTION 4

1, 2 IP Problem Identification and Resolution 71152B 10/22/2012 10/26/2012 1, 2 IP Problem Identification and Resolution 71152B 11/05/2012 11/09/2012 PSB1-RP

- OCCUPATIONAL RADIATION PROTECTION WK2 2

1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 11/05/2012 11/09/2012 1, 2 IP Occupational ALARA Planning and Controls 71124.02 11/05/2012 11/09/2012 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 11/05/2012 11/09/2012 1, 2 IP Occupational Dose Assessment 71124.04 11/05/2012 11/09/2012 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 2 03/05/2012 08:34:19 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Catawba Inspection / Activity Plan 03/01/2012 - 06/30/2013 PSB1-RP

- OCCUPATIONAL RADIATION PROTECTION WK2 2

1, 2 IP Radiation Monitoring Instrumentation 71124.05 11/05/2012 11/09/2012 1, 2 IP Performance Indicator Verification 71151 11/05/2012 11/09/2012 EB3 ISI

- UNIT 1 INSERVICE INSPECTION & RPVH EXAMS 2

1 IP Inservice Inspection Activities - PWR 7111108P 12/03/2012 12/07/2012 HS

- TRIENNIAL HEAT SINK PERFORMANCE 1

1, 2 IP Heat Sink Performance 7111107T 01/14/2013 01/18/2013 TI-182

- TI-182 BURIED PIPING/TANK - PHASE 1 1

1, 2 IP Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 2515/182 04/01/2013 04/05/2013 CAT TFPI

- CAT - TRIENNIAL FIRE PROTECTION INSP 4

1, 2 IP Fire Protection [Triennial]

7111105T 04/09/2013 04/11/2013 1, 2 IP Fire Protection [Triennial]

7111105T 04/22/2013 04/26/2013 1, 2 IP Fire Protection [Triennial]

7111105T 05/06/2013 05/10/2013 PSB1-RP

- RP PUBLIC BASELINE 6

1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 06/03/2013 06/07/2013 1, 2 IP Radiological Environmental Monitoring Program 71124.07 06/03/2013 06/07/2013 1, 2 IP Performance Indicator Verification 71151 06/03/2013 06/07/2013 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.