Inspection / Activity Plan - Catawba - 09/01/2005 - 03/31/2007
ML052420542
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 08/29/2005
From: Ernstes M
NRC/RGN-II/DRP/RPB1
To: Jamil D
Duke Energy Corp
Shared Package
ML052420530 List:
References
Download: ML052420542 (2)


Text

Page 1 of 2 Catawba 08/29/2005 16:47:47 Inspection / Activity Plan Report 22 09/01/2005 - 03/31/2007 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB3-HS - HEAT SINK 2 1, 2 IP 7111107B Heat Sink Performance 10/17/2005 10/17/2005 Baseline Inspections EB1SSDPC - SAFETY SYSTEM DESIGN & PERF. CAPABILITY 6 1, 2 IP 7111121 Safety System Design and Performance Capability 09/19/2005 09/23/2005 Baseline Inspections 1, 2 IP 7111121 Safety System Design and Performance Capability 10/03/2005 10/07/2005 Baseline Inspections OL PREP - INITIAL PREP 3 1 V23229 CATAWBA/EXAMS AT POWER FACILITIES 11/14/2005 11/18/2005 Not Applicable OL EXAM - INITIAL EXAM 3 1 V23229 CATAWBA/EXAMS AT POWER FACILITIES 12/05/2005 12/09/2005 Not Applicable EB3-ISI - U2 INSERVICE INSPECTION 1 2 IP 7111108P Inservice Inspection Activities - PWR 03/27/2006 03/31/2006 Baseline Inspections EB3SGISI - U2 STEAM GENERATOR ISI 2 2 IP 7111108P Inservice Inspection Activities - PWR 04/03/2006 04/07/2006 Baseline Inspections EB1-MODS - MODIFICATIONS/10CFR50.59 3 1, 2 IP 7111102 Evaluation of Changes, Tests, or Experiments 04/17/2006 04/21/2006 Baseline Inspections 1, 2 IP 7111117B Permanent Plant Modifications 04/17/2006 04/21/2006 Baseline Inspections PS2-EP - EP EXERCISE 3 1, 2 IP 7111401 Exercise Evaluation 05/15/2006 05/19/2006 Baseline Inspections 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 05/15/2006 05/19/2006 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 05/15/2006 05/19/2006 Baseline Inspections OL RQ - REQUAL INSPECTION 2 1, 2 IP 7111111B Licensed Operator Requalification Program 07/24/2006 07/28/2006 Baseline Inspections PI&R - PI&R 4 1, 2 IP 71152B Identification and Resolution of Problems 08/07/2006 08/12/2006 Baseline Inspections 1, 2 IP 71152B Identification and Resolution of Problems 08/21/2006 08/25/2006 Baseline Inspections PSB1 RP - RP OCCUPATIONAL PRE-INSP VISIT 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 09/25/2006 09/27/2006 Baseline Inspections PS-RP - RP OCCUPATIONAL BASELINE - WEEK 1 3 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 11/06/2006 11/10/2006 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 11/06/2006 11/10/2006 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 11/06/2006 11/10/2006 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 11/06/2006 11/10/2006 Baseline Inspections EB3-ISI - U1 INSERVICE INSPECTION 1 1 IP 7111108P Inservice Inspection Activities - PWR 11/13/2006 11/17/2006 Baseline Inspections This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures.

Page 2 of 2 Catawba 08/29/2005 16:47:47 Inspection / Activity Plan Report 22 09/01/2005 - 03/31/2007 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB3TI160 - 2515/150 U-1: RPV & VHP NOZZLES 1 1 IP 2515/150 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC ORDER EA 11/13/2006 11/17/2006 Safety Issues OL PREP - INITIAL EXAM PREP 3 1 V23246 CATAWBA/EXAM AT POWER FACILITIES 11/13/2006 11/17/2006 Not Applicable EB3SGISI - U1 STEAM GENERATOR ISI 1 1 IP 7111108P Inservice Inspection Activities - PWR 11/20/2006 11/24/2006 Baseline Inspections PS1-RP - RP OCCPATIONAL BASELINE - WEEK 2 3 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 11/27/2006 12/01/2006 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 11/27/2006 12/01/2006 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 11/27/2006 12/01/2006 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 11/27/2006 12/01/2006 Baseline Inspections OL EXAM - INITIAL EXAM 3 1 V23246 CATAWBA/EXAM AT POWER FACILITIES 12/04/2006 12/15/2006 Not Applicable EB3-MR - MR EFFECTIVENESS 1 1, 2 IP 7111112B Maintenance Effectiveness 01/22/2007 01/26/2007 Baseline Inspections EB1SSDPC - SSDPC PRE- INSPECTION VISIT 1 1, 2 IP 7111121 Safety System Design and Performance Capability 02/26/2007 03/02/2007 Baseline Inspections PS2-EP - EP INSP 1 1, 2 IP 7111402 Alert and Notification System Testing 03/19/2007 03/23/2007 Baseline Inspections 1, 2 IP 7111403 Emergency Response Organization Augmentation Testing 03/19/2007 03/23/2007 Baseline Inspections 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 03/19/2007 03/23/2007 Baseline Inspections 1, 2 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 03/19/2007 03/23/2007 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 03/19/2007 03/23/2007 Baseline Inspections EB1SSDPC - SAFETY SYSTEM DESIGN & PERF. CAPABILITY 5 1, 2 IP 7111121 Safety System Design and Performance Capability 03/19/2007 03/23/2007 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.