UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 March 4, 2014 Mr. Kelvin Henderson Site Vice President Duke Energy Corporation Catawba Nuclear Station 4800 Concord Road York, SC 29745-9635
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR CATAWBA NUCLEAR STATION UNITS 1 AND 2 (NRC INSPECTION REPORT 05000413/2014001 AND 05000414/2014001)
Dear Mr. Henderson:
On February 11, 2014, the NRC completed its end-of-cycle performance review of Catawba Nuclear Station Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1 through December 31, 2013. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Catawba Units 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Catawba Unit 1 and Unit 2 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low safety significance (Green) and all PIs indicated performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct ROP baseline inspections at your facility.
As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised. All cross-cutting aspects identified during inspections conducted in calendar year 2014 will reflect this revision to Inspection Manual Chapter (IMC) 0310. The CY 2013 end-of-cycle assessments were conducted using the IMC 0310 guidance in effect in CY 2013 (dated October 28, 2011). Cross-cutting aspects identified in 2013 using the 2013 terminology will be converted to the latest revision in accordance with the cross-reference in IMC 0310 during the mid-cycle assessment review and evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305.
K. Henderson 2
The enclosed inspection plan lists the inspections scheduled through June 30, 2015. Routine inspections performed by resident inspectors are not included in the inspection plan. We will also be performing Temporary Instruction (TI) 189, Inspection to Determine Compliance of Dynamic Restraint (Snubber) Program with 10 CFR 50.55a, "Regulatory Requirements for Inservice Examination and Testing of Snubbers and reactor operator licensing examinations.
The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections which will be sent via separate, non-publicly available correspondence.
Additionally, an NRC audit of licensee efforts towards compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events is ongoing. This audit includes an onsite component in order for the NRC to evaluate mitigating strategies as described in licensee submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component NRC's documentation system (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Gerald McCoy at (404) 997-4551 with any questions you have regarding this letter.
Sincerely,
/RA/
Richard P. Croteau, Director Division of Reactor Projects Docket Nos.: 50-413, 50-414 License Nos.: NPF-35, NPF-52
Enclosure:
Catawba Inspection/Activity Plan (03/01/2014 - 06/30/2015) cc distribution via ListServ
X SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP RII:DRP RII:DRP SIGNATURE GJM /RA/
GJM /RA for/
RPC /RA/
NAME GMcCoy ARuh WJones RCroteau DATE 02/27/2014 02/27/2014 02/27/2014 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO
K. Henderson 3
Letter to Kelvin Henderson from Richard P. Croteau dated March 4, 2014
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR CATAWBA NUCLEAR STATION UNITS 1 AND 2 (NRC INSPECTION REPORT 05000413/2014001 AND 05000414/2014001)
Distribution w/encl:
C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC A. Adams, NRR RidsNrrPMCatawba Resource ROP Assessment Institute of Nuclear Power Operations (INPO)
Page 1 of 2 03/04/2014 08:39:32 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Catawba Inspection / Activity Plan 03/01/2014 - 06/30/2015 EP
- EP EXERCISE 3
1, 2 IP Exercise Evaluation - Scenario Review 7111408 02/01/2014 03/21/2014 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 03/17/2014 03/21/2014 1, 2 IP Exercise Evaluation - Hostile Action (HA) Event 7111407 03/17/2014 03/21/2014 1, 2 IP Performance Indicator Verification 71151 03/17/2014 03/21/2014 MODS
- PLANT MODIFICATION INSPECTION 3
1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 7111117T 03/24/2014 03/28/2014 1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 7111117T 04/07/2014 04/11/2014 OL EXAM
- INITIAL LICENSE EXAM PREP 2
1 CATAWBA/MAY 2014 INITIAL EXAM AT POWER FACILITIES V23422 04/14/2014 04/18/2014 ISI
- UNIT 1 IN-SERVICE INSPECTION 1
1 IP Inservice Inspection Activities - PWR 7111108P 05/12/2014 05/16/2014 OL EXAM
- INITIAL LICENSE EXAM WEEK 1 2
1 CATAWBA/MAY 2014 INITIAL EXAM AT POWER FACILITIES V23422 05/12/2014 05/16/2014 RP
- RP OCCUPATIONAL BASELINE 2
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 05/19/2014 05/23/2014 1, 2 IP Occupational ALARA Planning and Controls 71124.02 05/19/2014 05/23/2014 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 05/19/2014 05/23/2014 1, 2 IP Occupational Dose Assessment 71124.04 05/19/2014 05/23/2014 1, 2 IP Radiation Monitoring Instrumentation 71124.05 05/19/2014 05/23/2014 1, 2 IP Performance Indicator Verification 71151 05/19/2014 05/23/2014 SGISI
- UNIT 1 SG IN-SERVICE INSPECTION 1
1 IP Inservice Inspection Activities - PWR 7111108P 05/19/2014 05/23/2014 TI-189
- TI-189 DYNAMIC RESTRAINT PROGRAM 1
1, 2 IP Inspection to Determine Compliance of Dynamic Restraint (Snubber) Program with 10 CFR 50.55a 2515/189 05/19/2014 05/23/2014 OL EXAM
- INITIAL LICENSE EXAM WEEK 2 2
1 CATAWBA/MAY 2014 INITIAL EXAM AT POWER FACILITIES V23422 05/19/2014 05/23/2014 RP
- RP OCCUPATIONAL BASELINE WEEK2 3
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 06/02/2014 06/06/2014 1, 2 IP Occupational ALARA Planning and Controls 71124.02 06/02/2014 06/06/2014 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 06/02/2014 06/06/2014 1, 2 IP Occupational Dose Assessment 71124.04 06/02/2014 06/06/2014 1, 2 IP Radiation Monitoring Instrumentation 71124.05 06/02/2014 06/06/2014 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
Page 2 of 2 03/04/2014 08:39:32 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Catawba Inspection / Activity Plan 03/01/2014 - 06/30/2015 RP
- RP OCCUPATIONAL BASELINE WEEK2 3
1, 2 IP Performance Indicator Verification 71151 06/02/2014 06/06/2014 OL-RQ
- REQUAL INSP 2
1, 2 IP Licensed Operator Requalification Program 7111111B 08/11/2014 08/15/2014 PI&R
- PROBLEM IDENTIFICATION AND RESOLUTION 4
1, 2 IP Problem Identification and Resolution 71152B 10/06/2014 10/10/2014 1, 2 IP Problem Identification and Resolution 71152B 10/20/2014 10/24/2014 RP
- RP PUBLIC RADIAITON SAFETY 2
1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 01/26/2015 01/30/2015 1, 2 IP Radiological Environmental Monitoring Program 71124.07 01/26/2015 01/30/2015 1, 2 IP Performance Indicator Verification 71151 01/26/2015 01/30/2015 EP
- EP PROGRAM INSPECTION 1
1, 2 IP Alert and Notification System Testing 7111402 03/23/2015 03/27/2015 1, 2 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 03/23/2015 03/27/2015 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 03/23/2015 03/27/2015 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 03/23/2015 03/27/2015 1, 2 IP Performance Indicator Verification 71151 03/23/2015 03/27/2015 ISI
- UNIT 2 IN-SERVICE INSPECTION 1
2 IP Inservice Inspection Activities - PWR 7111108P 03/23/2015 03/27/2015 RP
- RAD HAZARDS ANALYSIS AND TRANSPORTATION 2
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/23/2015 03/27/2015 1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 03/23/2015 03/27/2015 1, 2 IP Performance Indicator Verification 71151 03/23/2015 03/27/2015 SGISI
- UNIT 2 SG IN-SERVICE INSPECTION 1
2 IP Inservice Inspection Activities - PWR 7111108P 03/30/2015 04/03/2015 TFPI
- TRIENNIAL FIRE PROTECTION INSPECTION 4
1, 2 IP Fire Protection - NFPA 805 (Triennial) 7111105x 06/01/2015 06/05/2015 1, 2 IP Fire Protection - NFPA 805 (Triennial) 7111105x 06/15/2015 06/19/2015 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure