MONTHYEARIR 05000458/20230052023-08-21021 August 2023 Updated Inspection Plan for River Bend Station (Report 05000458/2023005) - Mid Cycle Letter IR 05000458/20220062023-03-0101 March 2023 Annual Assessment Letter for River Bend Station Report 05000458/2022006 ML23059A2332023-03-0101 March 2023 Cyber Security Inspection Request for Information ML22235A1082022-08-19019 August 2022 RBS Emergency Preparedness (EP) Exercise Inspection October 2022 RFI ML22186A0762022-07-0505 July 2022 Information Request, Security IR 2022402 ML22175A0652022-06-30030 June 2022 Notification of Inspection (NRC Inspection Report 05000458/2022004) and Request for Information ML22180A0612022-06-29029 June 2022 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000458/2022010) and Request for Information IR 05000458/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000458/2021006) ML21253A2442021-09-13013 September 2021 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (5000458/2021004) and Request for Information ML21232A2272021-09-0101 September 2021 RBS Mid-Cycle Inspection Plan Transmittal Letter 2021 ML21099A0312021-03-30030 March 2021 Email 3-30-2021 - Request for Information_ RBS EP Exercise Inspection (Week of 5_10_2021) ML21063A2372021-03-0303 March 2021 RBS 2020 Annual Assessment Letter ML20350B8112020-12-11011 December 2020 2021 RBS PIR Request for Information ML20337A4452020-12-0202 December 2020 Riverbend Station Inservice Inspection Request for Information ML20328A1202020-11-23023 November 2020 Notification of Evaluations of Changes, Tests, and Experiments Inspection (Inspection Report 05000458/2021001) and Request for Information ML20255A1892020-09-0909 September 2020 Email 09Sept2020 - RFI for RBS EP Exercise Inspection IR 05000458/20200052020-09-0101 September 2020 Updated Inspection Plan for River Bend Station (Report 05000458/2020005) ML20162A1122020-06-10010 June 2020 Notification of Inspection (NRC Inspection Report 05000458/2020003) and Request for Information ML20105A3712020-04-14014 April 2020 Notification of NRC Design Bases - Assurance Inspection (Teams) (05000458/2020011) and Initial Request for Information ML20055E1572020-03-0303 March 2020 RBS2019006 Annual Assessment Letter IR 05000458/20190052019-08-30030 August 2019 Updated Inspection Plan for River Bend Station, Report 05000458/2019005 ML19128A1012019-05-0808 May 2019 Notification of NRC Design Bases Assurance Inspection (Programs) (05000458/2019012) and Initial Request for Information IR 05000458/20180062019-03-0404 March 2019 Annual Assessment Letter for River Bend Station (Report 05000458/2018006) IR 05000458/20180052018-08-31031 August 2018 Updated Inspection Plan for River Bend Station (Report 05000458/2018005) ML18166A2362018-06-15015 June 2018 Notification Inspection Report 05000458/2018003, and Request for Information IR 05000458/20170062018-03-0101 March 2018 Annual Assessment Letter for River Bend Station (Report 05000458/2017006) IR 05000458/20170052017-08-28028 August 2017 Updated Inspection Plan for River Bend Station(Report 05000458/2017005) IR 05000458/20160062017-03-0101 March 2017 Annual Assessment Letter for River Bend Station (Report (05000458/2016006) ML17053C0312017-02-22022 February 2017 Notification of NRC Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans(05000458/2017008) and RFI IR 05000458/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for River Bend Station (Report 05000458/2016005) IR 05000458/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for River Bend Station (NRC Physical Security Inspection Report Number 05000458/2016401) ML16242A3262016-08-31031 August 2016 Mid-Cycle Assessment Letter for River Bend Station (Report 05000458/2016005) IR 05000458/20150062016-03-0202 March 2016 Annual Assessment Letter for River Bend Station (Report 05000458/2015006) IR 05000458/20154012015-09-0101 September 2015 Non-Public Security Inspection Plan for River Bend Station (NRC Physical Security Inspection Report Number 05000458/2015401) IR 05000458/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for River Bend Station (05000458/2015005) ML15170A2332015-06-19019 June 2015 Notification of Evaluations of Changes, Tests, and Experiments, and Permanent Plant Modifications Inspection (05000458/2015007) and Request for Information IR 05000458/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for River Bend Station (Report 05000458/2014006) IR 05000458/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for River Bend Station (NRC Physical Security Inspection Report Number 05000458/2014402) IR 05000416/20130062013-09-0303 September 2013 Mid-Cycle Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2013006) IR 05000458/20130062013-09-0303 September 2013 Mid-Cycle Assessment Letter for River Bend Station (Report 05000458/2013006) IR 05000458/20128012013-03-0404 March 2013 Annual Assessment Letter for River Bend Station (Report 05000458-12-801) IR 05000458/20120062012-09-0404 September 2012 IR 05000458-12-006, on 08/15/2012, Mid-Cycle Assessment Letter for River Bend Station, Inspection Plan ML12229A5112012-08-16016 August 2012 IR 05000458-12-010, River Bend, Augmented Inspection Team Follow-Up Inspection Planning Letter ML12180A5012012-06-28028 June 2012 IR 05000458-12-004, on 08/06/2012 - 08/10/2012, River Bend Station - Notification of Inspection (NRC Inspection and Request for Information) IR 05000458/20120012012-03-0505 March 2012 Annual Assessment Letter for River Bend Station (Report 05000458/2012001) ML11250A0632011-09-0707 September 2011 IR 05000458-11-005, on 11/14/2011, River Bend Station - Notification of Inspection and Request for Information ML1124305932011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan - River Bend Station IR 05000458/20110012011-03-0404 March 2011 IR 05000458-11-001, 03/01/2011 - 06/30/2012, Annual Assessment Letter for River Bend Station ML1024305742010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - River Bend Station IR 05000458/20100012010-03-0303 March 2010 Annual Assessment Letter - River Bend Station (Report 05000458-10-001) 2023-08-21
[Table view] Category:Letter
MONTHYEARIR 05000458/20230402024-01-18018 January 2024 95001 Supplemental Inspection Supplemental Report 05000458/2023040 and Follow-Up Assessment Letter RBG-48271, Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk2024-01-12012 January 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and ML24011A1742024-01-11011 January 2024 Security Baseline Inspection Report (Cover Letter) ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection IR 05000458/20230102023-12-12012 December 2023 Biennial Problem Identification and Resolution Inspection Report 05000458/2023010 RBG-48267, Reply to a Notice of Violation, NRC Inspection Report 05000458/20230032023-12-0707 December 2023 Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1432023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23310A0322023-11-13013 November 2023 Integrated Inspection Report 05000458/2023003 IR 05000458/20230032023-11-13013 November 2023 Integrated Inspection Report 05000458/2023003 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23311A4322023-11-0909 November 2023 Notification of NRC Supplemental Inspection (95001) and Request for Information RBG-48264, Core Operating Limits Report (COLR) - Cycle 23, Revision 12023-11-0606 November 2023 Core Operating Limits Report (COLR) - Cycle 23, Revision 1 RBG-48260, Notification of Readiness for Supplemental Inspection2023-10-12012 October 2023 Notification of Readiness for Supplemental Inspection ML23278A2402023-10-0606 October 2023 Regulatory Audit Plan in Support of License Amendment Requests to Revise TSs to Adopt Risk-Informed Completion Times and Implement the Provisions of 10 CFR 50.69 RBG-48258, Notification of Readiness for Supplemental Inspection2023-10-0505 October 2023 Notification of Readiness for Supplemental Inspection RBG-48259, Revision to Reply to Notice of Violation; EA-23-0552023-10-0303 October 2023 Revision to Reply to Notice of Violation; EA-23-055 ML23270B9932023-09-29029 September 2023 Request to Update ASME Boiler & Pressure Vessel Code Relief Request SE with NRC-Approved Revision of Bwrip Guidelines (GG-ISI-020 & RBS-ISI-019) (EPID L-2022-LLR-0090) - Non-Proprietary ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000458/20234012023-09-26026 September 2023 Cyber Security Inspection Report 05000458/2023401 IR 05000458/20230012023-09-21021 September 2023 NRC Inspection Report 05000458/2023001, Disputed Non-Cited Violation Rescinded RBG-48254, Report of Changes and Errors to 10CFR50.462023-09-21021 September 2023 Report of Changes and Errors to 10CFR50.46 IR 05000458/20234032023-09-21021 September 2023 NRC Security Inspection Report 05000458/2023403 (Cover Letter) RBG-48249, Reply to a Notice of Violation, EA-23-0712023-09-14014 September 2023 Reply to a Notice of Violation, EA-23-071 RBG-48253, Submittal of Owner'S Activity Report Form for Cycle 222023-09-12012 September 2023 Submittal of Owner'S Activity Report Form for Cycle 22 IR 05000458/20230122023-09-0101 September 2023 Comprehensive Engineering Team Inspection Report 05000458/2023012 IR 05000458/20230052023-08-21021 August 2023 Updated Inspection Plan for River Bend Station (Report 05000458/2023005) - Mid Cycle Letter RBG-48247, Reply to Notice of Violation; EA-23-0552023-08-21021 August 2023 Reply to Notice of Violation; EA-23-055 IR 05000458/20230922023-08-15015 August 2023 Final Significance Determination of a White Finding, Notice of Violation, and Follow-Up Assessment Letter; NRC Inspection Report 05000458/2023092 IR 05000458/20230022023-08-0909 August 2023 Integrated Inspection Report 05000458/2023002 ML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23195A0692023-07-24024 July 2023 2023 River Bend Station Notification of Biennial Problem Identification and Resolution Inspection and Request for Information IR 05000458/20230912023-07-20020 July 2023 Final Significance Determination of a White Finding, Notice of Violation, and Follow-Up Assessment Letter; NRC Inspection Report 05000458/2023091 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23195A0222023-07-11011 July 2023 4-2022-012 Letter - OI Closure to Licensee IR 05000458/20234042023-07-11011 July 2023 NRC Security Inspection Report 05000458/2023404 (Cover Letter Only) IR 05000458/20230902023-06-26026 June 2023 NRC Inspection Report 05000458/2023090 and Preliminary White Finding ML23159A2302023-06-0808 June 2023 Response to Request for Additional Information Concerning Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined RBG-48226, Core Operating Limits Report (COLR) - Cycle 23, Revision 02023-05-31031 May 2023 Core Operating Limits Report (COLR) - Cycle 23, Revision 0 RBG-48237, Response to NRC Integrated Inspection Report 05000458/20230012023-05-25025 May 2023 Response to NRC Integrated Inspection Report 05000458/2023001 ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23116A2352023-05-0101 May 2023 Integrated Inspection Report 05000458/2023001 RBG-48220, Submittal of 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report 2024-01-18
[Table view] |
Text
rch 3, 2004
SUBJECT:
ANNUAL ASSESSMENT LETTER - RIVER BEND STATION (NRC REPORT 05000458/2004001)
Dear Mr. Hinnenkamp:
On February 4, 2004, the NRC staff completed its end-of-cycle plant performance assessment of River Bend Station. The end-of-cycle review for River Bend Station involved the participation of all technical divisions in evaluating performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2003. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility so that you will have an opportunity to prepare for these inspections and to inform us of any planned inspections that may conflict with your plant activities.
Overall, River Bend Station operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter was within the Regulatory Response Column of the NRCs Action Matrix, based on one finding of low to moderate safety significance (White) in the mitigating systems cornerstone.
The White finding involved a failure to properly secure a valve in the condensate system that resulted in a loss of feedwater flow following a reactor scram in September 2002. Corrective actions, including procedural changes and additional training, were implemented by your staff following the event. NRC staff conducted a special inspection following occurrence of the event in 2002, and we conducted a supplemental inspection in February 2004. On the basis of our reviews conducted to date, we have concluded that you have adequately addressed the root causes and have implemented appropriate corrective actions.
As you are aware, the NRC has issued several Orders and threat advisories to enhance security capabilities and improve guard force readiness since the terrorist attacks on September 11, 2001. We have conducted inspections to review your implementation of these requirements and have monitored your actions in response to changing threat conditions. For calendar year 2004, we plan to continue inspections of Order implementation combined with newly developed portions of the security baseline inspection program. The enclosed inspection plan details the inspections scheduled through September 30, 2005. In addition to the baseline
Entergy Operations, Inc. -2-inspections listed in the enclosure, NRC will conduct inspections on your independent spent fuel storage facility as work progresses and construction and operational milestones are achieved.
The inspection plan is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The inspections in the last 12 months of the inspection plan are tentative and may be revised at the midcycle review meeting.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact David N. Graves at 817/860-8141 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/ by MASatorius for Arthur T. Howell III, Director Division of Reactor Projects Docket: 50-458 License: NPF-47 Enclosure:
River Bend Station Inspection/Activity Plan cc w/enclosure:
Senior Vice President and Chief Operating Officer Entergy Operations, Inc.
P.O. Box 31995 Jackson, MS 39286-1995 Vice President Operations Support Entergy Operations, Inc.
P.O. Box 31995 Jackson, MS 39286-1995
Entergy Operations, Inc. -3-General Manager Plant Operations Entergy Operations, Inc.
River Bend Station 5485 US Highway 61N St. Francisville, LA 70775 Director - Nuclear Safety Entergy Operations, Inc.
River Bend Station 5485 US Highway 61N St. Francisville, LA 70775 Wise, Carter, Child & Caraway P.O. Box 651 Jackson, MS 39205 Mark J. Wetterhahn, Esq.
Winston & Strawn 1401 L Street, N.W.
Washington, DC 20005-3502 Manager - Licensing Entergy Operations, Inc.
River Bend Station 5485 US Highway 61N St. Francisville, LA 70775 The Honorable Charles C. Foti, Jr.
Attorney General Department of Justice State of Louisiana P.O. Box 94005 Baton Rouge, LA 70804-9005 H. Anne Plettinger 3456 Villa Rose Drive Baton Rouge, LA 70806 Burt Babers, President West Feliciana Parish Police Jury P.O. Box 1921 St. Francisville, LA 70775
Entergy Operations, Inc. -4-Michael E. Henry, State Liaison Officer Department of Environmental Quality Permits Division P.O. Box 4313 Baton Rouge, LA 70821-4313 Brian Almon Public Utility Commission William B. Travis Building P.O. Box 13326 1701 North Congress Avenue Austin, TX 78711-3326 Jimmy Bello, President Pointe Coupe Parish Police Jury P.O. Box 290 New Roads, LA 70760 James Hunt, President East Feliciana Parish Police Jury P.O. Box 427 Clinton, LA 70722 Riley Berthelot, Jr., Parish President West Baton Rouge Parish Counsel P.O. Box 757 Port Allen, LA 70767 Bobby Simpson, Mayor-President Office of the Mayor-President East Baton Rouge Parish P.O. Box 1471 Baton Rouge, LA 70821 Federal Emergency Management Agency ATTN: Ron Castleman, Regional Director Region VI, Federal Center 800 North Loop 288 Denton, TX 76201-3698 Jim Brewer Assistant Chief Administrative Officer Office of the Mayor/President East Baton Rouge Parish P.O. Box 1471 Baton Rouge, LA 70821
Entergy Operations, Inc. -5-Joanne Moreau, Director Office of Homeland Security and Emergency Preparedness East Baton Rouge Parish P.O. Box 1471 Baton Rouge, LA 70821 Charles LeBlanc, Director Office of Emergency Preparedness West Baton Rouge Parish P.O. Box 757 Port Allen, LA 70767 Don Ewing, Director Office of Emergency Preparedness Pointe Coupee Parish P.O. Box 248 New Roads, LA 70760 Col. Michael L. Brown, Assistant Director Military Department Louisiana Office of Emergency Preparedness P.O. Box 44217 7667 Independence Blvd.
Baton Rouge, LA 70806 Jesse Means, Jr., Director Office of Homeland Security and Emergency Preparedness West Feliciana Parish P.O. Box 1927 St. Francisville, LA 70775 T. W. Prewitt, Director Office of Homeland Security and Emergency Preparedness East Feliciana Parish P.O. Box 640 Jackson, LA 70748 The Honorable William D'Aquilla Mayor, Town of St. Francisville P.O. Box 400 St. Francisville, LA 70775 Institute of Nuclear Power Operations (INPO)
700 Galleria Parkway SE, Suite 100 Atlanta, GA 30339
Entergy Operations, Inc. -6-Electronic distribution by RIV:
Regional Administrator (BSM1)
DRP Director (ATH)
DRS Director (DDC)
Senior Resident Inspector (PJA)
Branch Chief, DRP/B (DNG)
Senior Project Engineer, DRP/B (RAK1)
Staff Chief, DRP/TSS (PHH)
RITS Coordinator (NBH)
RidsNrrDipmIipb V. Dricks, PAO (VLD)
W. A. Maier, RSLO (WAM)
C. J. Gordon (CJG)
DRS Branch Chiefs (LJS, TWP, ATG, CSM)
W. D. Travers, EDO (WDT)
S. A. Richards, Chief, NRR/DIPM/IIPB (SAR)
R. K. Frahm, PPR Program Manager, NRR/DIPM/IIPB (RKF)
J. W. Craig, Associate Dir. for Inspection and Programs (JWC1)
B. W. Sheron, Associate Dir. for Project Licensing and Technical Analysis (BWS)
T. A. Bergman, Chief, Regional Operations Staff, OEDO (TAB)
H. N. Berkow, NRR Project Director (HNB)
R. A. Gramm, Chief, Section 1, NRR/DLPM (RAG)
M. K. Webb, NRR Project Manager (MKW)
ADAMS: WYes G No Initials: __dng___
W Publicly Available G Non-Publicly Available G Sensitive W Non-Sensitive S:\DRP\DRPDIR\EOC for 03\Assessment Letters\RBS.wpd C:DRP/B D:DRS D:DRP DNGraves;df DDChamberlain ATHowell
/RA/ /RA/ MASatorius for 2/23/04 2/26/04 3/3/04 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
Page 1 of 2 River Bend 03/01/2004 15:34:17 Inspection / Activity Plan Report 22 03/01/2004 - 10/01/2005 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type ALARA1 - ALARA PLANNING AND CONTROLS 1 1 IP 7112102 ALARA Planning and Controls 03/22/2004 03/26/2004 Baseline Inspections PSB-S1 - AA-AC-PI-FFD 2 1 IP 7113001 Access Authorization 03/22/2004 03/26/2004 Baseline Inspections 1 IP 7113002 Access Control 03/22/2004 03/26/2004 Baseline Inspections 1 IP 7113008 Fitness For Duty Program 03/22/2004 03/26/2004 Baseline Inspections 1 IP 71151 Performance Indicator Verification 03/22/2004 03/26/2004 Baseline Inspections EB-21/02 - SSD&PCI AND 50.59 7 1 IP 7111102 Evaluation of Changes, Tests, or Experiments 05/03/2004 05/07/2004 Baseline Inspections 1 IP 7111121 Safety System Design and Performance Capability 05/03/2004 05/07/2004 Baseline Inspections 1 IP 7111121 Safety System Design and Performance Capability 05/17/2004 05/21/2004 Baseline Inspections OB-RQ - REQUALIFICATION EXAM 4 1 IP 7111111B Licensed Operator Requalification Program 06/21/2004 06/25/2004 Baseline Inspections OB-EP2 - EP EXERCISE 2 1 IP 7111401 Exercise Evaluation 06/07/2004 06/11/2004 Baseline Inspections 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 06/07/2004 06/11/2004 Baseline Inspections 1 IP 71151 Performance Indicator Verification 06/07/2004 06/11/2004 Baseline Inspections PEB-12B - MAINTENANCE EFFECTIVENESS 1 1 IP 7111112B Maintenance Effectiveness 06/14/2004 06/18/2004 Baseline Inspections OB-IN EX - OB - INITIAL EXAMINATION 7 1 X02267 RIVER BEND (09/04) INITIAL EXAM 09/06/2004 09/10/2004 Not Applicable 1 X02267 RIVER BEND (09/04) INITIAL EXAM 09/20/2004 09/24/2004 Not Applicable EB-08G - INSERVICE INSPECTION ACTIVITIES 1 1 IP 7111108G Inservice Inspection Activities - BWR 10/25/2004 10/29/2004 Baseline Inspections ACCESSPI - ACRSA/PIV 1 1 IP 7112101 Access Control to Radiologically Significant Areas 10/25/2004 10/29/2004 Baseline Inspections PEB-07B - HX & HEAT SINK PERFORMANCE TESTING 2 1 IP 7111107B Heat Sink Performance 11/29/2004 12/03/2004 Baseline Inspections ALARA2 - ALARA PLANNING AND CONTROLS 2 1 1 IP 7112102 ALARA Planning and Controls 01/10/2005 01/14/2005 Baseline Inspections EB17B - PERMANENT PLANT MODS 2 1 IP 7111117B Permanent Plant Modifications 03/07/2005 03/11/2005 Baseline Inspections PEB-52 - RBS PIR INSPECTION 2 1 IP 71152B Identification and Resolution of Problems 06/06/2005 06/10/2005 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 River Bend 03/01/2004 15:34:17 Inspection / Activity Plan Report 22 03/01/2004 - 10/01/2005 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type PEB-52 - RBS PIR INSPECTION 2 1 IP 71152B Identification and Resolution of Problems 06/20/2005 06/24/2005 Baseline Inspections OB-EP2 - EMERG PREPAREDNESS PROGRAM INSPECTION 1 1 IP 7111402 Alert and Notification System Testing 06/13/2005 06/17/2005 Baseline Inspections 1 IP 7111403 Emergency Response Organization Augmentation Testing 06/13/2005 06/17/2005 Baseline Inspections 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 06/13/2005 06/17/2005 Baseline Inspections 1 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 06/13/2005 06/17/2005 Baseline Inspections 1 IP 71151 Performance Indicator Verification 06/13/2005 06/17/2005 Baseline Inspections ACRSA - ACCESS CONTROL TO RAD SIGNIFICANT AREAS 1 1 IP 7112101 Access Control to Radiologically Significant Areas 06/20/2005 06/24/2005 Baseline Inspections ALARA3 - ALARA PLANNING AND CONTROLS 1 1 IP 7112102 ALARA Planning and Controls 09/26/2005 09/30/2005 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.