September 1, 2021 Mr. Kent Scott, Site Vice President Entergy Operations, Inc.

5485 U.S. Highway 61N St. Francisville, LA 70775

SUBJECT:

UPDATED INSPECTION PLAN FOR RIVER BEND STATION (REPORT 05000458/2021005)

Dear Mr. Scott:

The enclosed inspection plan lists the inspections scheduled through June 30, 2023, for River Bend Station. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

Inspection procedure (IP) 71111.21N.03 is included in the inspection plan as a placeholder for your next Design Basis Assurance Inspection (Programs). The NRC is still determining the specific technical area to replace the previously performed power-operated valves programs inspection, IP 71111.21N.02. Once the inspection area has been determined, an inspection procedure will be issued publicly at least six months prior to the start of this inspection.

In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the Reactor Oversight Process (ROP). Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, determine how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the February 1, 2021 memo, Calendar Year 2021 Inspection Guidance During COVID-19 Telework Restrictions (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21027A274). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other

K. Scott 2 changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.

On March 12, 2018, the NRC issued a Confirmatory Order (ADAMS Accession No. ML18072A191) (EA-17-132 and EA-17-153) to the Entergy fleet that included the River Bend Station. The Regional Administrator has approved the staffs plan to conduct follow-up inspection of Entergys implementation of actions required by the Confirmatory Order actions in accordance with Inspection Procedure 92702, Follow-up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, And Alternative Dispute Resolution Confirmatory Orders. The NRC will continue to coordinate with Entergy regarding this inspection, which is currently in progress.

The NRC will also be performing baseline inspections of licensee cyber security programs. The specific schedule and procedure to be used for these inspections is being developed by the NRC staff. The staff expects to communicate the schedule for these inspections to each utility separately.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 817-200-1144 with any questions you have regarding this letter.

Sincerely, Jason W. Digitally signed by Jason W. Kozal Kozal Date: 2021.09.01 07:22:10 -05'00' Jason W. Kozal, Chief Project Branch C Division of Reactor Projects Docket No. 05000458 License No. NPF-47

Enclosure:

Inspection Plan cc w/ encl: Distribution via LISTSERV

SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:

By: CYOUNG Yes No Publicly Available Sensitive NRC-002 OFFICE DRP DRP:BC NAME CYoung JKozal DATE 08/19/21 09/01/21 IP 22b Site Inspection Activity Plan 07200049 - River Bend (ISFSI) 07/01/2021 - 06/30/2023 Unit Start End Activity CAC Title Staff Count River Bend ISFSI Triennial Loading Inspection (1 week in July)(Part 72) 2 1 7/1/2022 7/29/2022 IP 60855 001001 Operation Of An ISFSI Prepared on 8/18/2021 1:59:45 PM 1 of 4

IP 22b Site Inspection Activity Plan River Bend 07/01/2021 - 06/30/2023 Unit Start End Activity CAC Title Staff Count RP 5,6,7,8 PS Team 4 1 8/9/2021 8/13/2021 IP 71124.05 000729 Radiation Monitoring Instrumentation 1 8/9/2021 8/13/2021 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1 8/9/2021 8/13/2021 IP 71124.07 000731 Radiological Environmental Monitoring Program 1 8/9/2021 8/13/2021 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Security Access Authorization .01 and Access Control .02 w/PIV 2 1 9/13/2021 9/17/2021 IP 71130.01 000733 Access Authorization 1 9/13/2021 9/17/2021 IP 71130.02 000734 Access Control 1 9/13/2021 9/17/2021 IP 71130.09 001656 Security Plan Changes 1 9/13/2021 9/17/2021 IP 71151 001338 Performance Indicator Verification Security FFD .08 1 1 10/25/2021 10/29/2021 IP 71130.08 000740 Fitness For Duty Program Heat Sink Performance 07T - River Bend Station 2 1 11/1/2021 11/5/2021 IP 71111.07T 000700 Heat Sink Performance RP 5,6,7,8 Onsite Aspects 2 1 11/15/2021 11/19/2021 IP 71124.05 000729 Radiation Monitoring Instrumentation 1 11/15/2021 11/19/2021 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1 11/15/2021 11/19/2021 IP 71124.07 000731 Radiological Environmental Monitoring Program 1 11/15/2021 11/19/2021 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation MCA - Material Control & Accounting 1 1 11/15/2021 11/19/2021 IP 71130.11 000742 Material Control and Accounting (MC&A)

RP 2,4 2 1 2/14/2022 2/18/2022 IP 71124.02 000726 Occupational ALARA Planning and Controls 1 2/14/2022 2/18/2022 IP 71124.04 000728 Occupational Dose Assessment FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - RB 6 1 2/28/2022 3/4/2022 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1 3/21/2022 3/25/2022 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Power-Operated Valves Inspection - 21N - River Bend Station 3 1 4/4/2022 4/22/2022 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements Security Access Control .02 1 1 4/25/2022 4/29/2022 IP 71130.02 000734 Access Control Prepared on 8/18/2021 1:59:45 PM 2 of 4

IP 22b Site Inspection Activity Plan 1 4/25/2022 4/29/2022 IP 71130.09 001656 Security Plan Changes 1 4/25/2022 4/29/2022 IP 71151 001338 Performance Indicator Verification River Bend ISFSI Triennial Loading Inspection (Part 50) Feeder for Residents 2 1 7/1/2022 7/2/2022 IP 60855 001001 Operation Of An ISFSI EP 2022 Exercise Scenario In-Office Review - RBS 4 1 8/14/2022 9/17/2022 IP 71114.08 000723 Exercise Evaluation  Scenario Review RBS 2022 BRQ 3 1 8/28/2022 9/3/2022 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Security Training/Equip Maint .07 and .04 2 1 8/29/2022 9/2/2022 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1 8/29/2022 9/2/2022 IP 71130.07 000739 Security Training Fire Protection Inspection - RBS 3 1 10/17/2022 10/21/2022 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI) 1 10/31/2022 11/4/2022 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

EP 2022 Biennial Exercise & PI Inspection - RBS 4 1 10/17/2022 10/21/2022 IP 71114.01 000716 Exercise Evaluation 1 10/17/2022 10/21/2022 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 10/17/2022 10/21/2022 IP 71151 001397 Performance Indicator Verification RP 1,3,PI 2 1 11/14/2022 11/18/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 11/14/2022 11/18/2022 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation RBS 2022 INITIAL EXAM 5 1 10/30/2022 11/5/2022 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV) 1 12/4/2022 12/10/2022 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)

Design Bases Assurance Inspection (Team) - 21M - River Bend Station 6 1 1/1/2023 6/30/2023 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)

Inservice Inspection RFO 22 - RBS 1 1 2/20/2023 3/3/2023 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

RP 1,2,PI 2 1 2/27/2023 3/3/2023 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 2/27/2023 3/3/2023 IP 71124.02 000726 Occupational ALARA Planning and Controls Security Protective Strategy .05 (Place Holder) 2 1 5/8/2023 5/12/2023 IP 71130.05 000737 Protective Strategy Evaluation Cyber Security Inspection - RBS 2 1 5/15/2023 5/19/2023 IP 71130.10P 000741 Cyber Security Prepared on 8/18/2021 1:59:45 PM 3 of 4

IP 22b Site Inspection Activity Plan Security Access Authorization .01 and Access Control .02 + PIV + Plan Change .09 2 1 6/19/2023 6/23/2023 IP 71130.01 000733 Access Authorization 1 6/19/2023 6/23/2023 IP 71130.02 000734 Access Control 1 6/19/2023 6/23/2023 IP 71130.09 001656 Security Plan Changes 1 6/19/2023 6/23/2023 IP 71151 001338 Performance Indicator Verification Prepared on 8/18/2021 1:59:45 PM 4 of 4