March 2, 2016

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR RIVER BEND STATION (REPORT 05000458/2015006)

Dear Mr. Maguire:

On February 17, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of the River Bend Station. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2015 through December 31, 2015. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined the performance at the River Bend Station during the most recent quarter was within the Regulatory Response Column (Column 2) of the NRCs Reactor Oversight Process (ROP) Action Matrix because of one or more greater-than-green Security Cornerstone inputs as described in Inspection Report 05000458/2014406 dated September 24, 2014, (ML14268A573), and one White input in the Mitigating Systems Cornerstone as described in our letter dated September 10, 2015, (ML15253A352).

On October 7, 2015, the NRC completed a supplemental inspection to review the actions taken to address the performance issues associated with the greater-than-green Security Cornerstone input(s) referenced above. Based on the results of this inspection, as described in Inspection Report 05000458/2015409 dated November 2, 2015, (ML15306A420), the greater-than-green Security Cornerstone input(s) are not considered as an Action Matrix input as of the end of the fourth quarter of 2015.

On February 1, 2016, your staff notified the NRC of your readiness for our office to conduct a supplemental inspection to review the actions taken to address the performance issues associated with the White Mitigating Systems Cornerstone finding referenced above. Therefore, in addition to ROP baseline inspections, the NRC plans to conduct a supplemental inspection in accordance with Inspection Procedure 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area, beginning on March 21, 2016. The supplemental inspection will provide assurance that the root causes and contributing causes of risk-significant performance issues are understood; the extent of condition and extent of cause of risk-significant performance issues are identified; and, the corrective actions for risk-significant performance issues are sufficient to address the root and contributing causes and prevent recurrence.

As discussed in previous assessment letters dated March 4, 2015, (ML15063A562), and September 1, 2015, (ML15243A564), the NRC also plans to conduct a supplemental inspection in accordance with Inspection Procedure 95001 to review the actions taken to address the performance issues associated with a White Unplanned Scrams with Complications PI, which was a White Action Matrix input from the fourth quarter of 2014 through the third quarter of 2015. The NRC has not yet received notification of your readiness for us to conduct this supplemental inspection.

The enclosed inspection plan lists the inspections scheduled through December 31, 2017.

Routine inspections performed by resident inspectors are not included in the inspection plan.

The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.

In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. This Order requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. This Order requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. This audit includes an onsite component in order for the NRC to evaluate licensee plans for complying with the Orders, as described in site-specific submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations. Following the audit, and after the NRC staff receives the Final Compliance letter for the site, the Final Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing Temporary Instruction 191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Greg Warnick at 817-200-1144 with any questions you have regarding this letter.

Sincerely,

/RA/

Troy Pruett, Director Division of Reactor Projects

Docket No:

50-458 License No:

NPF-47

Enclosure:

River Bend Station Inspection/

Activity Plan

ML16061A414 SUNSI Review By: CHY ADAMS:

Yes No Sensitive Non-Sensitive Non-Publicly Available Publicly Available Keyword NRC-002 OFFICE BC:DRP/C D:DRS D:DRP

NAME GWarnick AVegel TPruett

SIGNATURE

/RA/CYoung, for

/RA/

/RA/RLantz, for

DATE 3/1/16 3/1/16 2/26/16

Letter to William Maguire from Troy Pruett, dated March 2, 2016

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR RIVER BEND STATION (REPORT 05000458/2015006)

DISTRIBUTION:

Regional Administrator (Marc.Dapas@nrc.gov)

Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)

DRP Director (Troy.Pruett@nrc.gov)

DRP Deputy Director (Ryan.Lantz@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Senior Resident Inspector (Shiattin.Makor@nrc.gov)

Resident Inspector (Brian.Parks@nrc.gov)

RBS Administrative Assistant (Lisa.Day@nrc.gov)

Branch Chief, DRP/C (Greg.Warnick@nrc.gov)

Senior Project Engineer (Cale.Young@nrc.gov)

Project Engineer (Michael.Stafford@nrc.gov)

Project Engineer (Lindsay.Brandt@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Project Manager (Stephen.Koenick@nrc.gov)

Team Leader, DRS/TSS (Thomas.Hipschman@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)

RIV/ETA: OEDO (Raj.Iyengar@nrc.gov)

Director, DIRS, NRR (Scott.Morris@nrc.gov)

Deputy Director, DIRS, NRR (Clay.Johnson@nrc.gov)

Director, DORL, NRR (Anne.Boland@nrc.gov)

Deputy Director, DORL, NRR (George.Wilson@nrc.gov)

Director, DPR (Lawrence.Kokajko@nrc.gov)

Director, NSIR (Brian.Holian@nrc.gov)

DRP Branch Chiefs (R4DRPBC@nrc.gov)

DRS Branch Chiefs (R4DRSBC@nrc.gov)

ROPreports.Resource@nrc.gov ROPassessment.Resource@nrc.gov

Page 1 of 2 02/29/2016 15:46:49 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site River Bend Inspection / Activity Plan 04/01/2016 - 12/31/2017 EXAM

- INITIAL EXAM

1 INITIAL EXAM RIVER BEND STATION UNIT 1 (09/2016)

X02575 08/15/2016 08/19/2016

INITIAL EXAM RIVER BEND STATION UNIT 1 (09/2016)

X02575 09/12/2016 09/16/2016 EB2-05T

- TRIENNIAL FIRE PROTECTION INSPECTION

1 IP Fire Protection [Triennia ]

7111105T 04/11/2016 04/15/2016

IP Fire Protection [Triennia ]

7111105T 04/25/2016 04/29/2016 ISFSI

- ROUTINE ISFSI (ONE WEEK IN MONTH)

1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 05/09/2016 05/13/2016 RS 13 PI

- RADIATION SAFETY

1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 06/13/2016 06/17/2016

IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 06/13/2016 06/17/2016

IP Occupational Exposure Control Effectiveness 71151-OR01 06/13/2016 06/17/2016

IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 06/13/2016 06/17/2016 EP-2

- EP PERFORMANCE INDICATORS

1 IP Drill/Exercise Performance 71151-EP01 06/27/2016 07/01/2016

IP ERO Readiness 71151-EP02 06/27/2016 07/01/2016

IP Alert & Notification System Reliability 71151-EP03 06/27/2016 07/01/2016 EP-3

- BIENNIAL EXERCISE INSPECTION

1 IP Exercise Evaluation 7111401 06/27/2016 07/01/2016

IP Emergency Action Level and Emergency Plan Changes 7111404 06/27/2016 07/01/2016 INSP

- BIENNIAL REQUAL INSPECTION

1 IP Licensed Operator Requalification Program 7111111B 08/29/2016 09/02/2016 71111.08

- INSERVICE INSPECTION

1 IP Inservice Inspection Activities - BWR 7111108G 02/13/2017 02/17/2017 RS 12 PI

- RADIATION SAFETY

1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 02/13/2017 02/17/2017

IP Occupational ALARA Planning and Controls 71124.02 02/13/2017 02/17/2017

IP Occupational Exposure Control Effectiveness 71151-OR01 02/13/2017 02/17/2017

IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 02/13/2017 02/17/2017 EB1-21T

- RBS COMPONENT DESIGN BASIS INSPECTION

1 IP Component Design Bases Inspection 7111121 03/27/2017 04/28/2017 TSB 52B

- BIENNIAL PI&R

1 IP Problem Identification and Resolution 71152B 06/12/2017 06/16/2017 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 2 02/29/2016 15:46:49 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site River Bend Inspection / Activity Plan 04/01/2016 - 12/31/2017 TSB 52B

- BIENNIAL PI&R

1 IP Problem Identification and Resolution 71152B 06/26/2017 06/30/2017 EP-1

- BIENNIAL EP PROGRAM INSPECTION

1 IP Alert and Notification System Testing 7111402 07/24/2017 07/28/2017

IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 07/24/2017 07/28/2017

IP Emergency Action Level and Emergency Plan Changes 7111404 07/24/2017 07/28/2017

IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 07/24/2017 07/28/2017 EP-2

- EP PERFORMANCE INDICATOR VERIFICATION

1 IP Drill/Exercise Performance 71151-EP01 07/24/2017 07/28/2017

IP ERO Readiness 71151-EP02 07/24/2017 07/28/2017

IP Alert & Notification System Reliability 71151-EP03 07/24/2017 07/28/2017 RS 5678

- RS TEAM

1 IP Radiation Monitoring Instrumentation 71124.05 08/21/2017 08/25/2017

IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 08/21/2017 08/25/2017

IP Radiological Environmental Monitoring Program 71124.07 08/21/2017 08/25/2017

IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 08/21/2017 08/25/2017 EB1-07T

- RBS HEAT SINK PERFORMANCE

1 IP Heat Sink Performance 7111107T 09/18/2017 09/22/2017 EB2-02

- LICENSE RENEWAL INSPECTION

1 IP License Renewal Inspection 71002 11/27/2017 12/01/2017

IP License Renewal Inspection 71002 12/11/2017 12/15/2017 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.