MONTHYEARIR 05000458/20230052023-08-21021 August 2023 Updated Inspection Plan for River Bend Station (Report 05000458/2023005) - Mid Cycle Letter IR 05000458/20220062023-03-0101 March 2023 Annual Assessment Letter for River Bend Station Report 05000458/2022006 ML23059A2332023-03-0101 March 2023 Cyber Security Inspection Request for Information ML22235A1082022-08-19019 August 2022 RBS Emergency Preparedness (EP) Exercise Inspection October 2022 RFI ML22186A0762022-07-0505 July 2022 Information Request, Security IR 2022402 ML22175A0652022-06-30030 June 2022 Notification of Inspection (NRC Inspection Report 05000458/2022004) and Request for Information ML22180A0612022-06-29029 June 2022 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000458/2022010) and Request for Information IR 05000458/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000458/2021006) ML21253A2442021-09-13013 September 2021 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (5000458/2021004) and Request for Information ML21232A2272021-09-0101 September 2021 RBS Mid-Cycle Inspection Plan Transmittal Letter 2021 ML21099A0312021-03-30030 March 2021 Email 3-30-2021 - Request for Information_ RBS EP Exercise Inspection (Week of 5_10_2021) ML21063A2372021-03-0303 March 2021 RBS 2020 Annual Assessment Letter ML20350B8112020-12-11011 December 2020 2021 RBS PIR Request for Information ML20337A4452020-12-0202 December 2020 Riverbend Station Inservice Inspection Request for Information ML20328A1202020-11-23023 November 2020 Notification of Evaluations of Changes, Tests, and Experiments Inspection (Inspection Report 05000458/2021001) and Request for Information ML20255A1892020-09-0909 September 2020 Email 09Sept2020 - RFI for RBS EP Exercise Inspection IR 05000458/20200052020-09-0101 September 2020 Updated Inspection Plan for River Bend Station (Report 05000458/2020005) ML20162A1122020-06-10010 June 2020 Notification of Inspection (NRC Inspection Report 05000458/2020003) and Request for Information ML20105A3712020-04-14014 April 2020 Notification of NRC Design Bases - Assurance Inspection (Teams) (05000458/2020011) and Initial Request for Information ML20055E1572020-03-0303 March 2020 RBS2019006 Annual Assessment Letter IR 05000458/20190052019-08-30030 August 2019 Updated Inspection Plan for River Bend Station, Report 05000458/2019005 ML19128A1012019-05-0808 May 2019 Notification of NRC Design Bases Assurance Inspection (Programs) (05000458/2019012) and Initial Request for Information IR 05000458/20180062019-03-0404 March 2019 Annual Assessment Letter for River Bend Station (Report 05000458/2018006) IR 05000458/20180052018-08-31031 August 2018 Updated Inspection Plan for River Bend Station (Report 05000458/2018005) ML18166A2362018-06-15015 June 2018 Notification Inspection Report 05000458/2018003, and Request for Information IR 05000458/20170062018-03-0101 March 2018 Annual Assessment Letter for River Bend Station (Report 05000458/2017006) IR 05000458/20170052017-08-28028 August 2017 Updated Inspection Plan for River Bend Station(Report 05000458/2017005) IR 05000458/20160062017-03-0101 March 2017 Annual Assessment Letter for River Bend Station (Report (05000458/2016006) ML17053C0312017-02-22022 February 2017 Notification of NRC Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans(05000458/2017008) and RFI IR 05000458/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for River Bend Station (Report 05000458/2016005) IR 05000458/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for River Bend Station (NRC Physical Security Inspection Report Number 05000458/2016401) ML16242A3262016-08-31031 August 2016 Mid-Cycle Assessment Letter for River Bend Station (Report 05000458/2016005) IR 05000458/20150062016-03-0202 March 2016 Annual Assessment Letter for River Bend Station (Report 05000458/2015006) IR 05000458/20154012015-09-0101 September 2015 Non-Public Security Inspection Plan for River Bend Station (NRC Physical Security Inspection Report Number 05000458/2015401) IR 05000458/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for River Bend Station (05000458/2015005) ML15170A2332015-06-19019 June 2015 Notification of Evaluations of Changes, Tests, and Experiments, and Permanent Plant Modifications Inspection (05000458/2015007) and Request for Information IR 05000458/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for River Bend Station (Report 05000458/2014006) IR 05000458/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for River Bend Station (NRC Physical Security Inspection Report Number 05000458/2014402) IR 05000416/20130062013-09-0303 September 2013 Mid-Cycle Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2013006) IR 05000458/20130062013-09-0303 September 2013 Mid-Cycle Assessment Letter for River Bend Station (Report 05000458/2013006) IR 05000458/20128012013-03-0404 March 2013 Annual Assessment Letter for River Bend Station (Report 05000458-12-801) IR 05000458/20120062012-09-0404 September 2012 IR 05000458-12-006, on 08/15/2012, Mid-Cycle Assessment Letter for River Bend Station, Inspection Plan ML12229A5112012-08-16016 August 2012 IR 05000458-12-010, River Bend, Augmented Inspection Team Follow-Up Inspection Planning Letter ML12180A5012012-06-28028 June 2012 IR 05000458-12-004, on 08/06/2012 - 08/10/2012, River Bend Station - Notification of Inspection (NRC Inspection and Request for Information) IR 05000458/20120012012-03-0505 March 2012 Annual Assessment Letter for River Bend Station (Report 05000458/2012001) ML11250A0632011-09-0707 September 2011 IR 05000458-11-005, on 11/14/2011, River Bend Station - Notification of Inspection and Request for Information ML1124305932011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan - River Bend Station IR 05000458/20110012011-03-0404 March 2011 IR 05000458-11-001, 03/01/2011 - 06/30/2012, Annual Assessment Letter for River Bend Station ML1024305742010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - River Bend Station IR 05000458/20100012010-03-0303 March 2010 Annual Assessment Letter - River Bend Station (Report 05000458-10-001) 2023-08-21
[Table view] Category:Letter
MONTHYEARIR 05000458/20230402024-01-18018 January 2024 95001 Supplemental Inspection Supplemental Report 05000458/2023040 and Follow-Up Assessment Letter RBG-48271, Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk2024-01-12012 January 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and ML24011A1742024-01-11011 January 2024 Security Baseline Inspection Report (Cover Letter) ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection IR 05000458/20230102023-12-12012 December 2023 Biennial Problem Identification and Resolution Inspection Report 05000458/2023010 RBG-48267, Reply to a Notice of Violation, NRC Inspection Report 05000458/20230032023-12-0707 December 2023 Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1432023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23310A0322023-11-13013 November 2023 Integrated Inspection Report 05000458/2023003 IR 05000458/20230032023-11-13013 November 2023 Integrated Inspection Report 05000458/2023003 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23311A4322023-11-0909 November 2023 Notification of NRC Supplemental Inspection (95001) and Request for Information RBG-48264, Core Operating Limits Report (COLR) - Cycle 23, Revision 12023-11-0606 November 2023 Core Operating Limits Report (COLR) - Cycle 23, Revision 1 RBG-48260, Notification of Readiness for Supplemental Inspection2023-10-12012 October 2023 Notification of Readiness for Supplemental Inspection ML23278A2402023-10-0606 October 2023 Regulatory Audit Plan in Support of License Amendment Requests to Revise TSs to Adopt Risk-Informed Completion Times and Implement the Provisions of 10 CFR 50.69 RBG-48258, Notification of Readiness for Supplemental Inspection2023-10-0505 October 2023 Notification of Readiness for Supplemental Inspection RBG-48259, Revision to Reply to Notice of Violation; EA-23-0552023-10-0303 October 2023 Revision to Reply to Notice of Violation; EA-23-055 ML23270B9932023-09-29029 September 2023 Request to Update ASME Boiler & Pressure Vessel Code Relief Request SE with NRC-Approved Revision of Bwrip Guidelines (GG-ISI-020 & RBS-ISI-019) (EPID L-2022-LLR-0090) - Non-Proprietary ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000458/20234012023-09-26026 September 2023 Cyber Security Inspection Report 05000458/2023401 IR 05000458/20230012023-09-21021 September 2023 NRC Inspection Report 05000458/2023001, Disputed Non-Cited Violation Rescinded RBG-48254, Report of Changes and Errors to 10CFR50.462023-09-21021 September 2023 Report of Changes and Errors to 10CFR50.46 IR 05000458/20234032023-09-21021 September 2023 NRC Security Inspection Report 05000458/2023403 (Cover Letter) RBG-48249, Reply to a Notice of Violation, EA-23-0712023-09-14014 September 2023 Reply to a Notice of Violation, EA-23-071 RBG-48253, Submittal of Owner'S Activity Report Form for Cycle 222023-09-12012 September 2023 Submittal of Owner'S Activity Report Form for Cycle 22 IR 05000458/20230122023-09-0101 September 2023 Comprehensive Engineering Team Inspection Report 05000458/2023012 IR 05000458/20230052023-08-21021 August 2023 Updated Inspection Plan for River Bend Station (Report 05000458/2023005) - Mid Cycle Letter RBG-48247, Reply to Notice of Violation; EA-23-0552023-08-21021 August 2023 Reply to Notice of Violation; EA-23-055 IR 05000458/20230922023-08-15015 August 2023 Final Significance Determination of a White Finding, Notice of Violation, and Follow-Up Assessment Letter; NRC Inspection Report 05000458/2023092 IR 05000458/20230022023-08-0909 August 2023 Integrated Inspection Report 05000458/2023002 ML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23195A0692023-07-24024 July 2023 2023 River Bend Station Notification of Biennial Problem Identification and Resolution Inspection and Request for Information IR 05000458/20230912023-07-20020 July 2023 Final Significance Determination of a White Finding, Notice of Violation, and Follow-Up Assessment Letter; NRC Inspection Report 05000458/2023091 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23195A0222023-07-11011 July 2023 4-2022-012 Letter - OI Closure to Licensee IR 05000458/20234042023-07-11011 July 2023 NRC Security Inspection Report 05000458/2023404 (Cover Letter Only) IR 05000458/20230902023-06-26026 June 2023 NRC Inspection Report 05000458/2023090 and Preliminary White Finding ML23159A2302023-06-0808 June 2023 Response to Request for Additional Information Concerning Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined RBG-48226, Core Operating Limits Report (COLR) - Cycle 23, Revision 02023-05-31031 May 2023 Core Operating Limits Report (COLR) - Cycle 23, Revision 0 RBG-48237, Response to NRC Integrated Inspection Report 05000458/20230012023-05-25025 May 2023 Response to NRC Integrated Inspection Report 05000458/2023001 ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23116A2352023-05-0101 May 2023 Integrated Inspection Report 05000458/2023001 RBG-48220, Submittal of 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report 2024-01-18
[Table view] |
Text
tember 2, 2014
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR RIVER BEND STATION (REPORT 05000458/2014006)
Dear Mr. Olson:
On August 14, 2014, the NRC completed its mid-cycle performance review of the River Bend Station. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2013, through June 30, 2014. This letter informs you of the NRCs assessment of the River Bend Station during this period and its plans for future inspections at your facility.
The NRC determined that overall, the River Bend Station operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at the River Bend Station during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e. ,Green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
Although plant performance was within the Licensee Response Column, the NRC has not yet finalized the significance of Apparent Violation (AV)05000458/2014405-01. This finding is an input to the Securtiy Cornerstone and was communicated to your staff on June 20, 2014. The final safety significance determination may affect the NRCs assessment of plant performance and the enclosed inspection plan.
As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised. All cross-cutting aspects identified during inspections conducted in calendar year 2014 reflect this revision to Inspection Manual Chapter (IMC) 0310.
Cross-cutting aspects identified in 2013 using the 2013 terminology were converted to the latest revision in accordance with the cross-reference in IMC 0310 during the mid-cycle assessment review and evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305. In our 2011 Annual Assessment letter (ML120610414) dated March 5, 2012, the NRC identified a cross-cutting theme in the Safety Conscious Work Environment component of Environment for Raising Concerns. This theme resulted from the issuance of a Confirmatory Order dated August 24, 2011, that involved discrimination. The cross-cutting aspect was related to behavior and actions that encourage free flow of information related to raising nuclear safety issues such that personnel raise nuclear safety issues without fear of retaliation [S.1/S.1(a)]. At that time, the NRC determined that a substantive cross-cutting issue did not exist because the NRC did not have concerns with the actions you committed to take to address the theme.
By letter, dated August 23, 2012, Entergy notified the NRC of the actions that had been taken in response to the requirements imposed by the Confirmatory Order. Accordingly, during the week of April 29, 2013, NRC staff from the Office of Enforcement and Region IV performed an inspection at the River Bend Station to assess the specific actions identified in Entergy's response letter. NRC staff also verified implementation of the remaining actions required to satisfy the conditions set forth in the Confirmatory Order. Subsequent to this inspection, NRC staff continued to interact with Entergy regarding the adequacy of the corrective and preventive actions related to the underlying discriminatory issue. Based on these reviews, the NRC determined that Entergy properly implemented the conditions specified in the Confirmatory Order and the associated actions were adequately implemented. Therefore, the criteria for a cross-cutting theme in the Safety Conscious Work Environment component of Environment for Raising Concerns [S.1] are no longer met.
The enclosed inspection plan lists the inspections scheduled through December 31, 2015.
Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. This audit includes an onsite component in order for the NRC to evaluate licensee plans for complying with the Orders, as described in site-specific submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations. In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (817) 200-1144 with any questions you have regarding this letter.
Sincerely,
/RA/
Donald B. Allen, Chief Project Branch C Docket No.: 50-458 License No.: NPF-47
ML14239A413 SUNSI Review ADAMS Publicly Available Non-Sensitive By: DAllen Yes No Non-Publicly Available Sensitive OFFICE RIV/BC/DRP RIV/D/DRS RIV/D/DRP NAME DAllen/dll AVegel TPruett SIGNATURE /RA/ /RA/VGaddy /RA/
for DATE 8/22/14 8/25/14 8/22/14
Letter to Eric from Troy Pruett dated September 2, 2014 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR RIVER BEND STATION (REPORT 05000458/2014006)
DISTRIBUTION:
Regional Administrator (Marc.Dapas@nrc.gov)
Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)
Acting DRP Director (Troy.Pruett@nrc.gov)
Acting DRP Deputy Director (Michael.Hay@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Deputy Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (Jeffrey.Sowa@nrc.gov)
Resident Inspector (Andy.Barrett@nrc.gov)
Administrative Assistant (Lisa.Day@nrc.gov)
Branch Chief (Don.Allen@nrc.gov)
Senior Project Engineer (Ray.Azua@nrc.gov)
Project Engineer (Paul.Nizov@nrc.gov)
Project Engineer (Michael.Langelier@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
RIV State Liaison Officer (Bill.Maier@nrc.gov)
Project Manager (Alan.Wang@nrc.gov)
Branch Chief, DRS/TSB (Geoffrey.Miller@nrc.gov)
R4DRPBC@nrc.gov R4DRSBC@nrc.gov Director, DIRS, NRR (Scott.Morris@nrc.gov)
Deputy Director, DIRS, NRR (Allen.Howe@nrc.gov)
Acting Director, DORL, NRR (Louise.Lund@nrc.gov)
Acting Deputy Director, DORL (Michael.Markley@nrc.gov)
Director, NSIR/DPR (Rob.Lewis@nrc.gov)
Chief, PLB IV, DORL, NRR (Eric.Oesterle@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV/ETA: OEDO (Anthony.Bowers@nrc.gov)
ROPassessment Resource@nrc.gov ROPreports@nrc.gov OEMail Resource@nrc.gov Distribution via Listserv for River Bend Station
Page 1 of 1 River Bend 08/22/2014 14:02:11 Inspection / Activity Plan Report 22 09/01/2014 - 12/31/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EXAM - INITIAL OPERATOR EXAM 4 1 11/03/2014 11/07/2014 X02534 INITIAL EXAM- RIVER BEND (4/1/15)
1 12/08/2014 12/12/2014 X02534 INITIAL EXAM- RIVER BEND (4/1/15)
INSP - BIENNIAL REQUAL INSPECTION 3 1 09/15/2014 09/19/2014 IP 7111111B Licensed Operator Requalification Program EB1-07T - TRIENNIAL HEAT SINK INSPECTION 1 1 11/17/2014 11/21/2014 IP 7111107T Heat Sink Performance 71111.08 - INSERVICE INSPECTION 1 1 02/23/2015 03/06/2015 IP 7111108G Inservice Inspection Activities - BWR RS 12 PI - RADIATION SAFETY 2 1 03/02/2015 03/06/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 03/02/2015 03/06/2015 IP 71124.02 Occupational ALARA Planning and Controls 1 03/02/2015 03/06/2015 IP 71151-OR01 1 03/02/2015 03/06/2015 IP 71151-PR01 TSB 52B - BIENNIAL PI&R INSPECTION 4 1 06/01/2015 06/05/2015 IP 71152B Problem Identification and Resolution 1 06/15/2015 06/19/2015 IP 71152B Problem Identification and Resolution EP-1 - BIENNAIL EP PROGRAM INSPECTION 1 1 08/17/2015 08/21/2015 IP 7111402 Alert and Notification System Testing 1 08/17/2015 08/21/2015 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 08/17/2015 08/21/2015 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 08/17/2015 08/21/2015 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies EP-2 - EP PERFORMANCE INDICATORS 1 1 08/17/2015 08/21/2015 IP 71151-EP01 1 08/17/2015 08/21/2015 IP 71151-EP02 1 08/17/2015 08/21/2015 IP 71151-EP03 EB1-17T - RBS PERMANENT PLANT MODS & 50.59 3 1 09/28/2015 10/09/2015 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications RS 5678 - RADIATION SAFETY - TEAM 4 1 11/30/2015 12/04/2015 IP 71124.05 Radiation Monitoring Instrumentation 1 11/30/2015 12/04/2015 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 11/30/2015 12/04/2015 IP 71124.07 Radiological Environmental Monitoring Program 1 11/30/2015 12/04/2015 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.