ML19254B348

From kanterella
Revision as of 00:22, 2 February 2020 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Responds to NRC 790711 Ltr Re Violations Noted in IE Insp Repts 50-413/79-12 & 50-414/79-12.Corrective Actions:Qa Personnel Reinstructed in Proper Handling of Document Approval & QA Procedure P-1 Revised
ML19254B348
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 08/06/1979
From: Dail L
DUKE POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19254B347 List:
References
NUDOCS 7909270349
Download: ML19254B348 (2)


Text

~ ~

. . DUKEEDOTVER . COMPANY ELECT 1 tic CENTElt, HOX 33189, CII AltLOTTE. N. C. 2M242 All 00 odSb'35'h6 l9 IUC 10 August 6,1979

^

Mr. J. P. O'Reilly, Director U.S. Nuclear Regulatory Commission 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303 Re: Catawba Nuclear Station RII: RJH Inspection Reports: 50-413/79-11 and 50-414/79-12 Duke File: CN-1412.ll-1

Dear Mr. O'Reilly:

In the referenced inspection reports, certain items of non-compliance were identified. Duke Power's response to these items is enclosed.

Duke Power does not consider any of the information contained in these reports to be proprietary.

Very truly yours, l_. C. Dail, Vice-President Desis, Engineering EKM/ cam Attachment 7909270349 1046 237-49dM6c

Duke Res nse to Infraction 50-417/f9-12-02 and 50-414/79-12-02-QAP Procedure-P1

./

/

Mr. Hardwick identified one deficiency with two uamples where the instructions of QA Procedure P-1 were not followed. Below is Duke's response to each example.

1. In the example involving " Vendor Quality Assurance Certification,"

the corrected documentation was received from the vendor on 8/1/79.

QA personnel workit.g in this area of responsibility have been re-instructed in the proper handling of documentation approval, full compliance was achieved by 8/1/79.

2. In the example involving signature deficiencies on Form P-1 A, explanatory notes have been added to the form to clarify the concerns identified by the inspector. QA personnel working in this area of responsibility have been instructed in the proper handling of documentation approval . Additionally, QA Procedure P-1 is being revised to clarify site release of items. Full com-pliance will be achieved by 9/1/79.

1046 238

..