EOC Report 22
ML120650240
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 03/05/2012
From:
NRC/RGN-II
To:
Shared Package
ML120650215 List:
References
Download: ML120650240 (2)


Text

Inspection / Activity Plan Page 1 of 2 03/05/2012 07:49:48 Report 22 03/01/2012

-06/30/2013 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Saint Lucie EPU INSP-EXTENDED POWER UPRATE INSPECTION 2 1 IP Power Uprate 71004 01/01/2012 03/15/2012 PI&R-PROBLEM IDENTIFICATION AND RESOLUTION 6 1, 2 IP Problem Identification and Resolution 71152B 04/02/2012 04/06/2012 1, 2 IP Problem Identification and Resolution 71152B 04/16/2012 04/20/2012 TI-182-TI-182 BURIED PIPING/TANK - PHASE 1 1 1, 2 IP Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 2515/182 06/04/2012 06/08/2012 PSB1EP-EMERGENCY PREPAREDNESS EXERCISE 4 1, 2 IP Exercise Evaluation 7111401 06/11/2012 06/15/2012 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 06/11/2012 06/15/2012 1, 2 IP Performance Indicator Verification 71151 06/11/2012 06/15/2012 EPU INSP-EXTENDED POWER UPRATE INSPECTION 3 2 IP Power Uprate 71004 06/27/2012 09/30/2012 1, 2 IP Power Uprate 71004 07/09/2012 07/13/2012 EB3 ISI-UNIT 2 INSERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR 7111108P 08/13/2012 08/17/2012 EB3SGISI-UNIT 2 SG INSERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR 7111108P 08/20/2012 08/24/2012 CDBI-COMPONENT DESIGN BASES 6 1, 2 IP Component Design Bases Inspection 7111121 10/01/2012 10/05/2012 1, 2 IP Component Design Bases Inspection 7111121 10/22/2012 10/26/2012 1, 2 IP Component Design Bases Inspection 7111121 11/05/2012 11/09/2012 1, 2 IP Component Design Bases Inspection 7111121 11/26/2012 11/30/2012 PSB1-RP-RADIOLOGICAL HAZARD ASSESSMENT 2 1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 10/15/2012 10/19/2012 1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 10/15/2012 10/19/2012 1, 2 IP Performance Indicator Verification 71151 10/15/2012 10/19/2012 PSB1-RP-PUBLIC RADIATION SAFETY BASELINE 3 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 10/15/2012 10/19/2012 1, 2 IP Radiological Environmental Monitoring Program 71124.07 10/15/2012 10/19/2012 1, 2 IP Performance Indicator Verification 71151 10/15/2012 10/19/2012 OL EXAM-INITIAL EXAM PREP 3 1 ST LUCIE/DECEMBER 2012 INITIAL EXAM AT POWER FACILITIES V23390 11/05/2012 11/09/2012 OL EXAM-INITIAL EXAM - WEEK 1 3 1 ST LUCIE/DECEMBER 2012 INITIAL EXAM AT POWER FACILITIES V23390 12/03/2012 12/07/2012 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Inspection / Activity Plan Page 2 of 2 03/05/2012 07:49:48 Report 22 03/01/2012

-06/30/2013 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Saint Lucie OL EXAM-INITIAL EXAM - WEEK 2 3 1 ST LUCIE/DECEMBER 2012 INITIAL EXAM AT POWER FACILITIES V23390 12/10/2012 12/14/2012 STL TFPI-STL - TRIENNIAL FIRE PROTECTION INSP 4 1, 2 IP Fire Protection [Triennial]

7111105T 02/19/2013 02/21/2013 1, 2 IP Fire Protection [Triennial]

7111105T 03/11/2013 03/15/2013 1, 2 IP Fire Protection [Triennial]

7111105T 03/25/2013 03/29/2013 RESBASE-RES BASELINE 2 2 1, 2 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 04/01/2013 06/30/2013 1, 2 IP A dverse Weather Protection 7111101 04/01/2013 06/30/2013 1, 2 IP Equipment Alignment (Quarterly) 7111104 04/01/2013 06/30/2013 1, 2 IP Equipment Alignment 7111104S 04/01/2013 06/30/2013 1, 2 IP Fire Protection - Annual 7111105A 04/01/2013 06/30/2013 1, 2 IP Fire Protection - Quarterly 7111105Q 04/01/2013 06/30/2013 1, 2 IP Flood Protection Measures 7111106 04/01/2013 06/30/2013 1, 2 IP Heat Sink Performance 7111107A 04/01/2013 06/30/2013 1, 2 IP Licensed Operator Requalification Program 7111111Q 04/01/2013 06/30/2013 1, 2 IP Maintenance Effectiveness 7111112Q 04/01/2013 06/30/2013 1, 2 IP Maintenance Risk Assessments and Emergent Work Control 7111113 04/01/2013 06/30/2013 1, 2 IP Operability Determinations and Functionality Assessments 7111115 04/01/2013 06/30/2013 1, 2 IP Plant Modifications 7111118 04/01/2013 06/30/2013 1, 2 IP Post Maintenance Testing 7111119 04/01/2013 06/30/2013 1, 2 IP Refueling and Other Outage Activities 7111120 04/01/2013 06/30/2013 1, 2 IP Surveillance Testing 7111122 04/01/2013 06/30/2013 1, 2 IP Performance Indicator Verification 71151 04/01/2013 06/30/2013 1, 2 IP Problem Identification and Resolution 71152 04/01/2013 06/30/2013 1 IP Followup of Events and Notices of Enforcement Discretion 71153 04/01/2013 06/30/2013 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.