ML090630486

From kanterella
Jump to navigation Jump to search
EOC Report. 22, Inspection Plan
ML090630486
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 03/04/2009
From:
NRC/RGN-II
To:
Shared Package
ML090630480 List:
References
Download: ML090630486 (2)


Text

Inspection / Activity Plan Page 1 of 2 03/04/2009 07:25:22 Report 22 03/01/2009 - 06/30/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Saint Lucie PSB1-RP

- RP OCCUPATIONAL INSPECTION WK1 (OUTAGE) 2 1, 2 IP Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 2515/173 04/27/2009 05/01/2009 1, 2 IP Access Control to Radiologically Significant Areas 7112101 04/27/2009 05/01/2009 1, 2 IP ALARA Planning and Controls 7112102 04/27/2009 05/01/2009 1, 2 IP Radioactive Material Processing and Transportation 7112202 04/27/2009 05/01/2009 1, 2 IP Performance Indicator Verification 71151 04/27/2009 05/01/2009 EB3ISI

- UNIT 2 INSERVICE INSPECTION 1

2 IP Inservice Inspection Activities - PWR 7111108P 05/04/2009 05/08/2009 EB3TI172

- TI-172 RCS DM BUTT WELDS 1

2 IP Reactor Coolant System Dissimiliar Metal Butt Welds 2515/172 05/04/2009 05/08/2009 PSB1-RP

- RP OCCUPATIONAL INSPECTION WK2 (OUTAGE) 3 1, 2 IP Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 2515/173 05/11/2009 05/15/2009 1, 2 IP Access Control to Radiologically Significant Areas 7112101 05/11/2009 05/15/2009 1, 2 IP ALARA Planning and Controls 7112102 05/11/2009 05/15/2009 1, 2 IP Radioactive Material Processing and Transportation 7112202 05/11/2009 05/15/2009 INSP

- COMPONENT DESIGN BASIS INSPECTION (CDBI) 7 1, 2 IP Component Design Bases Inspection 7111121 07/13/2009 07/17/2009 1, 2 IP Component Design Bases Inspection 7111121 08/03/2009 08/07/2009 1, 2 IP Component Design Bases Inspection 7111121 08/10/2009 08/14/2009 1, 2 IP Component Design Bases Inspection 7111121 08/31/2009 09/04/2009 OL EXAM

- INITIAL EXAM PREP 4

1 ST LUCIE/OCTOBER 2009 EXAM AT POWER FACILITIES V23309 09/14/2009 09/18/2009 OL EXAM

- INITIAL EXAM WEEK 1 3

1 ST LUCIE/OCTOBER 2009 EXAM AT POWER FACILITIES V23309 09/28/2009 10/01/2009 OL EXAM

- INITIAL EXAM - WEEK 2 3

1 ST LUCIE/OCTOBER 2009 EXAM AT POWER FACILITIES V23309 10/05/2009 10/09/2009 OL EXAM

- INITIAL EXAM - WEEK 3 3

1 ST LUCIE/OCTOBER 2009 EXAM AT POWER FACILITIES V23309 10/19/2009 10/23/2009 OL RQ

- REQUAL INSPECTION 2

1, 2 IP Licensed Operator Requalification Program 7111111B 11/16/2009 11/20/2009 PSB1EP

- EMERGENCY PREPAREDNESS EXERCISE 3

1, 2 IP Exercise Evaluation 7111401 02/22/2010 02/26/2010 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 02/22/2010 02/26/2010 1, 2 IP Performance Indicator Verification 71151 02/22/2010 02/26/2010 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Inspection / Activity Plan Page 2 of 2 03/04/2009 07:25:22 Report 22 03/01/2009 - 06/30/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Saint Lucie ISFSI

- ISFSI ROUTING LOADING 2

1, 2 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 04/01/2010 06/30/2010 EB3ISI

- UNIT 1 INSERVICE INSPECTION 1

1 IP Inservice Inspection Activities - PWR 7111108P 05/10/2010 05/14/2010 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure