Notification of Licensed Operator Retake Initial Examination 05000335/2019302 and 05000389/2019302
ML19205A014
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 07/23/2019
From: Eugene Guthrie
Division of Reactor Safety II
To: Nazar M
Florida Power & Light Co
Reeder D
References
IR 2019302
Download: ML19205A014 (4)


Text

July 23, 2019

SUBJECT:

ST. LUCIE NUCLEAR PLANT - NOTIFICATION OF LICENSED OPERATOR

RETAKE INITIAL EXAMINATION 05000335/2019302 AND 05000389/2019302

Dear Mr. Nazar:

During a telephone conversation on June 24, 2019, between Mr. Travis Ouret, Lead NRC Exam Author and Mr. Andreas Goldau, Operations Engineer, arrangements were made for the administration of a retake licensing examination at the St. Lucie Nuclear Plant. The on-site preparation and administration of the JPM portion of the operating test are scheduled for the week of August 26, 2019.

As agreed during the telephone conversation, your staff will prepare the JPM portion of the operating test based on the guidelines in Revision 11 of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The U.S. Nuclear Regulatory Commission (NRC)

regional office will discuss with your staff any changes that might be necessary before the examination is administered. Your staff has also agreed to make copies of all examination materials that are necessary for administering the examination.

To meet the above schedule, it will be necessary for your staff to furnish the JPM outlines by July 15, 2019. The JPM portion of the operating test and the supporting reference materials identified in Attachment 3 to ES-201 will be due by August 5, 2019. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized representative of the facility licensee shall approve the outline, examination, and test before they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use.

We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Any delay in receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled. In order to conduct the requested operating test, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels)

generated during the dynamic operating tests until the NRC takes licensing action on all the applications and any adjudicatory actions on any hearing demands are complete.

Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the operating tests are being administered.

To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator waiver and/or excusal requests (Office of Management and Budget (OMB) approval number 3150-0090) at least 60 days before the first examination date (if possible). Contact Mr. Goldau to determine the method for submission of the waiver or excusal requests. Preliminary reactor operator and senior reactor operator license applications (OMB approval number 3150-0090) and medical certifications (OMB approval number 3150-0024)

should be submitted at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary.

Final signed applications certifying that all training has been completed and requesting any waivers or excusals, as applicable, should be submitted at least 14 days before the first examination date.

Although the guidelines for receiving waiver or excusal requests call for at least 30 days before the first examination date (preliminary) and 14 days before the first examination date (final), the requests should be submitted as early as possible in the process (see the 60-day guideline above). Resolutions resulting from verbal inquiries by the licensee to the NRC are not binding.

Submittals addressing waivers or excusals, or both, should be in writing (i.e., using NRC Form 398, Personal Qualifications StatementLicensee, or as directed by Mr. Goldau when contacting him to determine the method for submission). The NRC will document its final decision on whether to grant a waiver or excusal on the final (not preliminary) NRC Form 398 submitted for the applicant. The NRC will not provide its decision until the final application is submitted to the agency.

Paperwork Reduction Act Statement

This letter contains information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018.

The burden to the public for these mandatory information collections is estimated to average 2,250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> per examination, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collections. You may submit comments on any aspect of the information collections, including suggestions for reducing the burden, to FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by electronic mail to infocollects.resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503. Public Protection Notification

The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information, unless the document requesting or requiring the collection displays a currently valid OMB control number.

In accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding, of the agencys Rules of Practice, a copy of this letter and its enclosures will be available electronically for public inspection through the Agency wide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html.

Thank you for your cooperation in this matter. Mr. Ouret has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Goldau at (404) 997-4528, (Internet E-mail:

Andreas.Goldau@nrc.gov), or me at (404) 997-4662, (Internet E-mail:

Eugene.Guthrie@nrc.gov).

Sincerely,

/RA/

Eugene F. Guthrie, Chief

Operations Branch 2

Division of Reactor Safety

Docket Nos.: 50-335 and 50-389 License Nos.: DPR-67 and NPF-16

cc: Distribution via ListServ

ML19205A014 OFFICE RII:DRS RII:DRS

NAME A.GOLDAU E.GURTHRIE

DATE 07/22/2019 07/23/2019