Page 1 of 2 Saint Lucie 03/05/2012 07:49:48 Inspection / Activity Plan Report 22 03/01/2012 - 06/30/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EPU INSP - EXTENDED POWER UPRATE INSPECTION 2 1 01/01/2012 03/15/2012 IP 71004 Power Uprate PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 6 1, 2 04/02/2012 04/06/2012 IP 71152B Problem Identification and Resolution 1, 2 04/16/2012 04/20/2012 IP 71152B Problem Identification and Resolution TI-182 - TI-182 BURIED PIPING/TANK - PHASE 1 1 1, 2 06/04/2012 06/08/2012 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping PSB1EP - EMERGENCY PREPAREDNESS EXERCISE 4 1, 2 06/11/2012 06/15/2012 IP 7111401 Exercise Evaluation 1, 2 06/11/2012 06/15/2012 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 06/11/2012 06/15/2012 IP 71151 Performance Indicator Verification EPU INSP - EXTENDED POWER UPRATE INSPECTION 3 2 06/27/2012 09/30/2012 IP 71004 Power Uprate 1, 2 07/09/2012 07/13/2012 IP 71004 Power Uprate EB3 ISI - UNIT 2 INSERVICE INSPECTION 1 2 08/13/2012 08/17/2012 IP 7111108P Inservice Inspection Activities - PWR EB3SGISI - UNIT 2 SG INSERVICE INSPECTION 1 2 08/20/2012 08/24/2012 IP 7111108P Inservice Inspection Activities - PWR CDBI - COMPONENT DESIGN BASES 6 1, 2 10/01/2012 10/05/2012 IP 7111121 Component Design Bases Inspection 1, 2 10/22/2012 10/26/2012 IP 7111121 Component Design Bases Inspection 1, 2 11/05/2012 11/09/2012 IP 7111121 Component Design Bases Inspection 1, 2 11/26/2012 11/30/2012 IP 7111121 Component Design Bases Inspection PSB1-RP - RADIOLOGICAL HAZARD ASSESSMENT 2 1, 2 10/15/2012 10/19/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 10/15/2012 10/19/2012 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 1, 2 10/15/2012 10/19/2012 IP 71151 Performance Indicator Verification PSB1-RP - PUBLIC RADIATION SAFETY BASELINE 3 1, 2 10/15/2012 10/19/2012 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 10/15/2012 10/19/2012 IP 71124.07 Radiological Environmental Monitoring Program 1, 2 10/15/2012 10/19/2012 IP 71151 Performance Indicator Verification OL EXAM - INITIAL EXAM PREP 3 1 11/05/2012 11/09/2012 V23390 ST LUCIE/DECEMBER 2012 INITIAL EXAM AT POWER FACILITIES OL EXAM - INITIAL EXAM - WEEK 1 3 1 12/03/2012 12/07/2012 V23390 ST LUCIE/DECEMBER 2012 INITIAL EXAM AT POWER FACILITIES This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure

Page 2 of 2 Saint Lucie 03/05/2012 07:49:48 Inspection / Activity Plan Report 22 03/01/2012 - 06/30/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site OL EXAM - INITIAL EXAM - WEEK 2 3 1 12/10/2012 12/14/2012 V23390 ST LUCIE/DECEMBER 2012 INITIAL EXAM AT POWER FACILITIES STL TFPI - STL - TRIENNIAL FIRE PROTECTION INSP 4 1, 2 02/19/2013 02/21/2013 IP 7111105T Fire Protection [Triennial]

1, 2 03/11/2013 03/15/2013 IP 7111105T Fire Protection [Triennial]

1, 2 03/25/2013 03/29/2013 IP 7111105T Fire Protection [Triennial]

RESBASE - RES BASELINE 2 2 1, 2 04/01/2013 06/30/2013 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 1, 2 04/01/2013 06/30/2013 IP 7111101 Adverse Weather Protection 1, 2 04/01/2013 06/30/2013 IP 7111104 Equipment Alignment (Quarterly) 1, 2 04/01/2013 06/30/2013 IP 7111104S Equipment Alignment 1, 2 04/01/2013 06/30/2013 IP 7111105A Fire Protection - Annual 1, 2 04/01/2013 06/30/2013 IP 7111105Q Fire Protection - Quarterly 1, 2 04/01/2013 06/30/2013 IP 7111106 Flood Protection Measures 1, 2 04/01/2013 06/30/2013 IP 7111107A Heat Sink Performance 1, 2 04/01/2013 06/30/2013 IP 7111111Q Licensed Operator Requalification Program 1, 2 04/01/2013 06/30/2013 IP 7111112Q Maintenance Effectiveness 1, 2 04/01/2013 06/30/2013 IP 7111113 Maintenance Risk Assessments and Emergent Work Control 1, 2 04/01/2013 06/30/2013 IP 7111115 Operability Determinations and Functionality Assessments 1, 2 04/01/2013 06/30/2013 IP 7111118 Plant Modifications 1, 2 04/01/2013 06/30/2013 IP 7111119 Post Maintenance Testing 1, 2 04/01/2013 06/30/2013 IP 7111120 Refueling and Other Outage Activities 1, 2 04/01/2013 06/30/2013 IP 7111122 Surveillance Testing 1, 2 04/01/2013 06/30/2013 IP 71151 Performance Indicator Verification 1, 2 04/01/2013 06/30/2013 IP 71152 Problem Identification and Resolution 1 04/01/2013 06/30/2013 IP 71153 Followup of Events and Notices of Enforcement Discretion This report does not include INPO and OUTAGE activities.