IR 05000335/2022010

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Programs) Inspection Report 05000335/2022010 and 05000389/2022010
ML22117A104
Person / Time
Site: Saint Lucie  
Issue date: 04/27/2022
From: James Baptist
Division of Reactor Safety II
To: Coffey B
Florida Power & Light Co
References
IR 2022010
Download: ML22117A104 (14)


Text

SUBJECT:

ST. LUCIE PLANT UNITS 1 AND 2 - DESIGN BASIS ASSURANCE INSPECTION (PROGRAMS) INSPECTION REPORT 05000335/2022010 AND 05000389/2022010

Dear Mr. Coffey:

On March 18, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at St. Lucie Plant Units 1 and 2. On April 1, 2022, the NRC inspectors discussed the results of this inspection with Mr. Dan DeBoer, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at St. Lucie Plant Units 1 and 2.

April 27, 2022 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety Docket Nos. 05000335 and 05000389 License Nos. DPR-67 and NPF-16

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000335 and 05000389

License Numbers:

DPR-67 and NPF-16

Report Numbers:

05000335/2022010 and 05000389/2022010

Enterprise Identifier:

I-2022-010-0022

Licensee:

Florida Power and Light Company

Facility:

St. Lucie Plant Units 1 and 2

Location:

Jensen Beach, FL

Inspection Dates:

February 28-March 18, 2022

Inspectors:

G. Ottenberg, Senior Reactor Inspector

K. Kirchbaum, Operations Engineer

B. Smith, Nuclear Systems Engineer

M. Yeminy, Contractor

Approved By:

James B. Baptist, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (programs) inspection at St. Lucie Plant Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Consider Maximum Transmitted Torque in Motor Operated Valve Structural Evaluation Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000335,05000389/2022010-01 Open/Closed None (NPP)71111.21N.02 The inspectors identified a Green finding and associated non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, subsection 55a(b)(3)(ii), when the licensee did not establish a motor operated valve (MOV) program that ensured the butterfly valves within the program continued to be capable of performing their function. Specifically, the licensee did not appropriately include and consider the Electric Power Research Institute (EPRI) Performance Prediction Methodology (PPM) calculated maximum transmitted torque in their MOV program instructions for evaluating the acceptability of the structural limitations of the butterfly valve weak link and the actuator ratings.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection, unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met, consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.02 - Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements POV Review (IP Section 03)

The inspectors:

a.

Evaluated whether the sampled POVs are being tested and maintained in accordance with NRC regulations along with the licensees commitments and/or licensing bases.

Specific Guidance b.

Evaluated whether the sampled POVs are capable of performing their design-basis functions.

c.

Evaluated whether testing of the sampled POVs is adequate to demonstrate the capability of the POVs to perform their safety functions under design-basis conditions.

d.

Evaluated maintenance activities, including a walkdown of the sampled POVs (if accessible).

(1)2-MV-07-2A, Safety Injection Pump Containment Sump Suction Valve (2)1-HCV-3625, 1A1 Low Pressure Safety Injection Cold Leg Injection Isolation Valve (3)2-MV-08-19B, Main Steamline Atmospheric Dump Valve (4)1-2515, Primary Isolation Valve (Penetration P-26) for Reactor Coolant Loop 1B1 Letdown (5)2-MV-08-12, Auxiliary Feedwater Pump Turbine Steam Supply Valve (6)2-MV-09-12, 2C Auxiliary Feedwater Flow Control Valve (7)1-HCV-08-1A, 1A Main Steam Isolation Valve (8)2-HCV-09-2A, Main Feedwater Isolation Valve B Train at Penetration P-4

INSPECTION RESULTS

Failure to Consider Maximum Transmitted Torque in Motor Operated Valve Structural Evaluation Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000335,05000389/2022010-01 Open/Closed None (NPP)71111.21N.02 The inspectors identified a Green finding and associated non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, subsection 55a(b)(3)(ii), when the licensee did not establish a motor operated valve (MOV) program that ensured the butterfly valves within the program continued to be capable of performing their function. Specifically, the licensee did not appropriately include and consider the Electric Power Research Institute (EPRI) Performance Prediction Methodology (PPM) calculated maximum transmitted torque in their MOV program instructions for evaluating the acceptability of the structural limitations of the butterfly valve weak link and the actuator ratings.

Description:

The inspectors reviewed the safety injection pump containment sump suction valve, 2-MV-07-2A, to evaluate its ability to open and close according to its design requirements. The valve has safety functions to open to allow flow from the containment sump to the suction of the safety injection and containment spray pumps, and to close to isolate a limited leakage passive failure that is postulated to occur downstream of the valve. To determine the torque required to open and close the valve, the licensee utilized the EPRI PPM which involves the use of computer software to perform the calculation. The EPRI PPM software also calculates the maximum transmitted torque, which is the maximum valve stem torque predicted by the model, and its magnitude is equal to the larger of the required actuation torque and the peak hydrodynamic torque. This torque is used to determine if the torque rating of the actuator will be exceeded and to evaluate the structural adequacy of the valve stem and its connections to the actuator and to the disk. The program described in TR-103237, EPRI MOV Performance Prediction Program, details that the maximum transmitted torque is the additional torque calculated by the model for use in structural evaluation of MOV components.

The inspectors identified that the valve structural limits for the 2-MV-07-2A valve were determined in evaluations, 1331762-DD-1, Weaklink Analysis for 24-Model NMKII Butterfly Valve with Limitorque H3BC / SMB-00-10 Operator Tag #: Unit 1-MV-07-2A & MV-07-2B, and in DD-99, Engineering Analysis of Torque Requirements for Nuclear Butterfly Valves-FPL P.O. #C9293491253, and that the Limitorque actuator ratings were contained in Limitorque sizing and selection documents (SELs). The inspectors determined the licensee had not compared the valve structural limits determined in 1331762-DD-1 and DD-99 and the actuator structural limits in the SELs to the maximum transmitted torque value calculated by the EPRI PPM and instead inappropriately only compared the structural limits to the less limiting calculated value of required torque. Further, the inspectors determined that the maximum transmitted torque value calculated by the EPRI PPM when evaluating the close stroke direction exceeded the calculated valve weak link torque values and the published actuator rated torque values.

Upon review of the licensees failure to compare the maximum transmitted torque to the valve weak link and the actuator ratings, the inspectors determined that STD-M-003, Engineering Guidelines for Sizing and Evaluation of Limitorque Motor Operators, did not provide guidance describing the need to compare the valve structural limitations and actuator ratings to the maximum transmitted torque, and only provided guidance to compare the valve structural limits and actuator ratings to the calculated required torque. Once it was discovered the comparison of the structural limits to the maximum transmitted torque was never completed, the licensee entered the issue into their corrective action program for evaluation.

Corrective Actions: Florida Power and Light personnel entered the issue into their corrective action program for further evaluation. During the week of March 21, 2022, the licensee re-evaluated the valve closure scenario and determined the original calculation contained system parameters (differential pressure and flow) that were overly conservative and not required by the valves design basis. The licensee reduced the assumption for expected flow in the system and re-ran the PPM software and obtained results that supported that the valve and actuator structural components would not be over-stressed. The licensee plans to complete calculations that are more reflective of the actual valve requirements and incorporate more specific instructions into their MOV program guidance to address the maximum transmitted torque for quarter turn valves.

Corrective Action References: AR 2422566

Performance Assessment:

Performance Deficiency: The licensee failed to appropriately include and consider the EPRI PPM calculated maximum transmitted torque in their MOV program instructions for evaluating the acceptability of the structural limitations of the butterfly valve weak link and the actuator ratings. The licensee should have been aware that this potentially more limiting torque value had the potential to overload valve and actuator components through their use of the EPRI PPM.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the licensee failed to verify the capability of the valve and actuator sub-components to withstand the applied forces that would be present during and following design basis events.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The finding screened as of very low safety significance (Green) because it was a deficiency affecting the design or qualification of a mitigating SSC, and the SSC maintained its operability or PRA functionality.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: 10 CFR 50.55a(b)(3)(ii) required, in part, OM condition: Motor-Operated Valve (MOV) testing. Licensees must comply with the provisions for testing MOVs in ASME OM Code, and must establish a program to ensure that MOVs continue to be capable of performing their design basis safety functions. Contrary to the above, the licensee did not establish a program that ensured the butterfly valves within the program continued to be capable of performing their function. Specifically, butterfly valves may experience applied torques higher than those calculated for the required torque for the valve, and the associated higher stress applied to the valve and actuator sub-components was not required to be evaluated by the MOV program instructions.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On March 18, 2022, the inspectors presented the onsite inspection results to Mr. Carlos Santos and other members of the licensee staff.

On April 1, 2022, the inspectors presented the design basis assurance inspection (programs) inspection results to Mr. Dan DeBoer, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DC-025

Required Thrust and Weak Link Calculations-required

thrust and maximum thrust calculations

DD-99

Engineering Analysis of Torque Requirements for

Nuclear Butterfly Valves-FPL P.O. #C9293491253

01/07/1993

JPN-PSL-SEMP-

93-036

Pressure Locking and Thermal Binding of Motor

Operated Gate Valves

L-MECH-CALC-017

Evaluation of the Calculations Made by Florida Power

and Light for the Minimum and Maximum Torque

Requirements of the Butterfly Motor Operated Valves in

the Generic Letter 89-10 Program at St. Lucie Unit 2

& 17

MA-23698

Actuator Calculation Criteria and Capability Margins

E

PSL-1-FJE-90-002

GL 89-10 MOV Cable Voltage Drop, St. Lucie Unit 1

PSL-1FJM-91-011

NRC Generic Letter 89-10 MOV Design Basis

Differential Pressure Determination

PSL-1FJM-91-017

NRC Generic Letter 89-10 Gate/Globe Valve Motor-

Operator Evaluations

PSL-2-J-E-90-003

GL 89-10 MOV Cable Voltage Drop, St. Lucie Unit 2

PSL-2FJE-94-003

GL 89-10 125 VDC Motor Operated Valve Cable Voltage

Drop, St. Lucie Unit 2

PSL-2FJM-91-046

St. Lucie Unit 2 Generic Letter 89-10 Design Basis

Differential Pressures for Motor Operated Valves

PSL-2FJM-91-048

St. Lucie Unit 2 Generic Letter 89-10 Gate and Globe

Valve Required Stem Thrust and Actuator Torque

Switch Setting Evaluation

Calculations

PSL-2FJM-93-002

GL 89-10 Differential Pressure Calculation for St. Lucie

Unit 2 HPSI and AFW Motor Operated Valves

& 6

Corrective Action

Documents

ARs 02268907,

298807,

2150607,

2396453,

2006410

71111.21N.02

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 2420540

22 POV Insp-NOP Guidance for MOV Jogging

Inadequate

03/04/2022

AR 2421591

22 POV Insp-MV-07-2A Motor Insulation

Documentation Documentation Only Issue with EQ Doc

Pac 2998-A-451-3.1

03/15/2022

AR 2421767

NRC ISFSI MOV Inspection - MOV T-Drain Painted

Over

03/17/2022

AR 2421778

U1 ECCS FATHOM Hydraulic Model Error, HCV-3625

K-Factor

03/17/2022

AR 2421835

Calculation PSL-1FJM-91-01 Valve Thrust Discrepancy

03/17/2022

AR 2421869

22 POV Insp-Eval Effects of MOV Jogging / Throttling

03/18/2022

AR 2421874

22 POV Insp-Use of PPM When Classifying MOVs

03/18/2022

AR 2422240

2-MV-07-2A MTR Torque Derate Not Evaluated,

Limitorque 93-03

03/22/2022

Corrective Action

Documents

Resulting from

Inspection

AR 2422566

2-MV-07-2A MOV PPM Calc Max Torque Exceeds

Weak Link Torque

03/24/2022

2998-1871

600# MO Valves Tag # I-MV-09-11&12

2998-19252

4-600 Weld Ends Carbon Steel Double Disk Gate Valve

for SMP-00-10 (D.C.) Limitorque Actuator

2998-19745

4-600 Weld Ends Carbon Steel Model 70-28-2 Globe

Control Valve W/SMP-000-5 Limitorque Actuator

2998-2236

24in M/O BFLY VL No. 1-2-MV-07-2A & 2B 8770-3820

2998-2237

Cross Section Dwg for I-MV-07-1A, 1B, 2A

2998-3847

Mot. Op. for Valve I-MV-07-2A & 2B

2998-9695

Schematic for Anchor Darling Self Contained Hydraulic

Actuator Non-Redundant

2998-B-327 Sheet

299

Control Wiring Diagram Reactor Sump Valve MV-07-2A

2998-B-327 Sheet

Control Wiring Diagram General Notes

2998-G-078 Sheet

130B

Flow Diagram Safety Injection System

Drawings

2998-G-088 Sheet

Flow Diagram Containment Spray and Refueling Water

Systems

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2998-G-125 Sheet

SI-N-I

Large Bore Piping Isometric Safety Injection

8770-1375

SI Motor Valve HCV-3615, 3625, 3635, 3645

8770-1574

Limitorque Valve Control

8770-B-327 Sheet

260

Low Press Safety Inject Flow Cont Valve HCV-3625

8770-G-078 Sheet

130A

Flow Diagram Safety Injection System

8770-G-078 Sheet

130B

Flow Diagram Safety Injection System

8770-G-078 Sheet

131B

Flow Diagram Safety Injection System

8770-G-078, Sheet

131A

Flow Diagram Safety Injection System

EC 209138

Replaced Motor on Limitorque Actuator on MV-07-2A

with Equivalent Motor Per IEE 76263.

10/30/2006

Engineering

Changes

PCM 200-283-16

Main Feedwater Isolation Valves Relief Orifice

Modification

1331762-00-1

WEAKLINK ANALYSIS for 24"- Model NMKII Butterfly

Valve With Limitorque H3BC / SMB-00-10 Operator Tag

  1. Unit 1-MV-07-2A & MV-07-2B

Document No.

2576C

St. Lucie MOV Periodic Verification Classification

JPN-PSL-SEMP-

93-031

Substantial Safety Hazard Evaluation of Limitorque

Valve Actuators with AC Motors

JPN-PSL-SEMS-

96-070

Evaluation of EPRI MOV Performance Prediction

Program Results-MPR Report 1759

MPR Report 1759,

Part 16

Evaluation of Stem Thrust Requirements for MV-07-2A

and MV-07-2B Using the EPRI MOV Globe Valve

Performance Prediction Methodology

06/17/1996

PSL-ENG-SEMS-

19-002

Evaluation of Conditions/Limitations in the NRC Safety

Evaluation Report on the EPRI MOV PPM

Engineering

Evaluations

PSL-ENG-SEMS-

97-062

GL 89-10 MOV Program Load Sensitive Behavior

Engineering Evaluation

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

01855973

Root Cause Evaluation for Unit 1 Automatic Reactor Trip

due to Failure of 1B Main Steam Isolation Valve

04/23/2013

2998-4508

Henry Pratt Butterfly Valves

3332C

Kalsi Report for St. Lucie Unit 1 MSIV Redesign for EPU

Conditions Post March 2013 Event

8770-6271

VELAN VALVES AND MAINTENANCE

INSTRUCTIONS (Pl-1184-N)

CN-SEE-II-09-4

St. Lucie Unit 1 Emergency Core Cooling System

(ECCS) Delivery and Surveillance Test Requirements

DBD-CS-2

Containment Spray System

DBD-SDC-1

Low Pressure Safety Injection and Shutdown Cooling

System

EQUIPMENT

QUALIFICATION

DOCUMENTATION

PACKAGE 2998-A-

451-3.1

Limitorque Corporation Motor Operators

ER-AA-113

Inservice Testing (IST) Program

ER-AA-116

Motor Operated Valve Program

SPEC-M-188

Specification for Main Steam Isolation Valve

Replacement Actuator

Miscellaneous

STD-M-003

Engineering Guidelines for Sizing and Evaluation of

Limitorque Motor Operators

2-OSP-09.01C

2C Auxiliary Feedwater Pump Code Run

ADM-03.04

Motor Operated Valve Trending and Monitoring

ADM-29.01A

Inservice Testing (IST) Program for Pumps and Valves

ER-AA-113-1000

Inservice Testing Procedure

ER-AA-113-1007-

10000

Preconditioning of Structures, Systems and Components

ER-AA-116

Motor Operated Valve Program

MA-AA-100-1014

Limitorque Motor Operated Valve Testing and Actuator

Inspections

Procedures

MA-AA-100-1020

Limitorque Motor Operated Valve Stem Lube and Full

Actuator Inspection

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

WO 40696460-01,

40765714-01,

37013972-01,

40568241-01,

40554564-01,

40717669-01,

40774350-01,

40641408-01,

40641408-07,

40605121-01,

40758776-01,

40773331-01,

40696151-01,

40718324-04