Mid-Cycle Assessment Letter
ML13246A054
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 09/03/2013
From: Gregory Kolcum
Division Reactor Projects II
To: Nazar M
Florida Power & Light Co
References
IR-13-006
Download: ML13246A054 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 3, 2013 Mr. Mano Nazar Executive Vice President and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420

SUBJECT:

MID-CYCLE ASSESSMENT LETTER FOR ST. LUCIE PLANT UNIT 1 AND UNIT 2 (REPORT 05000335/2013006 AND 05000389/2013006)

Dear Mr. Nazar:

On August 14, 2013, the NRC completed its mid-cycle performance review of St. Lucie Plant Unit 1 and Unit 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2012, through June 30, 2013. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined the performance at St. Lucie Unit 1 and Unit 2 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2014.

Routine inspections performed by resident inspectors are not included in the inspection plan.

The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.

We also plan on conducting one non-ROP inspection; Temporary Instruction (TI) 2515/182, Review of Implementation of the Industry Initiative to Control Degradation of Underground Piping - Phase 2.

M. Nazar 2 In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (404) 997-4533 with any questions you may have regarding this letter.

Sincerely,

/RA/

Gregory J. Kolcum, Acting Chief Reactor Projects Branch 3 Division of Reactor Projects Docket Nos.: 50-335, 50-389 License Nos.: DPR-67, NPF-16

Enclosure:

St. Lucie Inspection/Activity Plan (09/01/2013 - 12/31/2014) cc: Distribution via Listserv

_________________________ X SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP SIGNATURE SRS /RA/ GJK /RA/

NAME SSandal GKolcum DATE 08/26/2013 08/29/2013 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO M. Nazar 3 Letter to Mano Nazar from Gregory J. Kolcum dated September 3, 2013

SUBJECT:

MID-CYCLE ASSESSMENT LETTER FOR ST. LUCIE PLANT UNIT 1 AND UNIT 2 (REPORT 05000335/2013006 AND 05000389/2013006)

Distribution w/encl:

C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMStLucie Resource ROP Assessment Institute of Nuclear Power Operations (INPO)

Page 1 of 2 Saint Lucie 09/03/2013 08:08:19 Inspection / Activity Plan Report 22 09/01/2013 - 12/31/2014 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site TI-182 - TI-182 BURIED PIPING/TANK - PHASE 2 1 1, 2 09/16/2013 09/18/2013 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping RP - RP OCCUPATIONAL BASELINE 3 1, 2 09/16/2013 09/20/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 09/16/2013 09/20/2013 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 09/16/2013 09/20/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 09/16/2013 09/20/2013 IP 71124.04 Occupational Dose Assessment 1, 2 09/16/2013 09/20/2013 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 09/16/2013 09/20/2013 IP 71151 Performance Indicator Verification RP - RP OCCUPATIONAL BASELINE WEEK2 3 1, 2 09/30/2013 10/04/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 09/30/2013 10/04/2013 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 09/30/2013 10/04/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 09/30/2013 10/04/2013 IP 71124.04 Occupational Dose Assessment 1, 2 09/30/2013 10/04/2013 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 09/30/2013 10/04/2013 IP 71151 Performance Indicator Verification ISI - UNIT 1 INSERVICE INSPECTION 1 1 10/07/2013 10/11/2013 IP 7111108P Inservice Inspection Activities - PWR SGISI - UNIT 1 SG INSERVICE INSPECTION 1 1 10/14/2013 10/18/2013 IP 7111108P Inservice Inspection Activities - PWR EP - EP EXERCISE 1 1, 2 02/17/2014 02/21/2014 IP 7111407 Exercise Evaluation - Hostile Action (HA) Event 1, 2 02/17/2014 02/21/2014 IP 71151 Performance Indicator Verification PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 4 1, 2 01/13/2014 01/17/2014 IP 71152B Problem Identification and Resolution 1, 2 01/27/2014 01/31/2014 IP 71152B Problem Identification and Resolution RP - RP PUBLIC RADIATION BASELINE 2 1, 2 02/03/2014 02/07/2014 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 02/03/2014 02/07/2014 IP 71124.07 Radiological Environmental Monitoring Program 1, 2 02/03/2014 02/07/2014 IP 71151 Performance Indicator Verification ISI - UNIT 2 IN-SERVICE INSPECTION 1 2 03/10/2014 03/14/2014 IP 7111108P Inservice Inspection Activities - PWR This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure

Page 2 of 2 Saint Lucie 09/03/2013 08:08:19 Inspection / Activity Plan Report 22 09/01/2013 - 12/31/2014 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site SGISI - UNIT 2 SG IN-SERVICE INSPECTION 1 2 03/17/2014 03/21/2014 IP 7111108P Inservice Inspection Activities - PWR RP - RADIOLOGICAL HAZARDS AND TRANSPORTATION 2 1, 2 03/24/2014 03/28/2014 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 03/24/2014 03/28/2014 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 1, 2 03/24/2014 03/28/2014 IP 71151 Performance Indicator Verification Comments:

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure