U.S. NUCLEAR REGULATORY COMMISSION (NRC)

OFFICE OF NUCLEAR SECURITY AND INCIDENT RESPONSE (NSIR)

INSPECTION REPORT Docket Numbers: 05000335 and 05000389 License Numbers: DPR-67 and NPF-16 Report Number: 05000335/2020420 and 05000389/2020420 Enterprise Identifier: I-2020-420-0016 Licensee: Florida Power & Light Company Facility: St. Lucie Nuclear Power Plant, Units 1 and 2 Location: Jensen Beach, Florida Inspection Dates: September 28, 2020 to October 02, 2020 Inspectors: T. Barry, Security Specialist D. Bradfield, Team Leader R. Patterson, Senior Physical Security Inspector R. Stone, Security Specialist A. Woyansky, Security Specialist Approved By: Dante C. Johnson, Chief Security Performance Evaluation Br Division of Security Operations Enclosure

SUMMARY

The NRC continued monitoring the licensees performance by conducting a security inspection at St. Lucie Nuclear Power Plant, Units 1 and 2, in accordance with Inspection Manual Chapter (IMC) 2201, Appendix C, Generic, Special, and Infrequent Inspections. IMC 2201 Appendix C inspections for the security inspection program are designed to support the NRC goals of maintaining safety, enhancing public confidence, improving the effectiveness, efficiency and realism of the regulatory process, reducing unnecessary regulatory burden, and promoting the common defense and security.

List of Findings and Violations No findings or violations of more than minor significance were identified.

Additional Tracking Items None.

2

INSPECTION SCOPES Unless otherwise noted, security inspections were conducted in accordance with the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. Publicly available IPs are located at:

http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

OTHER ACTIVITIES - TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL 92707 - Security Inspection of Facilities Impacted by a Local, State, or Federal Emergency Where the NRCs Ability to Conduct Triennial Force On-Force Exercises is Limited (1 Sample)

(1) The NRC inspectors completed this inspection by gathering sufficient information to develop a scenario that can be segmented into limited scope tactical response drills that allows for a limited assessment of the ability of licensees physical security systems and security organization to meet the general performance objective of Title 10 of the Code of Federal Regulations (10 CFR) 73.55(b) and to ensure changes made to the physical protection program in response to a local, State, or Federal emergency (e.g., state of emergency, disaster, or public health emergency) have not adversely impacted the licensees implementation of their protective strategy.

REPORT ATTACHMENTS Supplemental Information for the report is considered Safeguards Information and is located separately within the NRCs Safeguards Information Local Area Network and Electronic Safe database (SLES), under NS125678.

INSPECTION RESULTS No findings were identified.

EXIT MEETINGS AND DEBRIEFS The inspectors verified no proprietary information was retained or documented in this report.

  • On October 7, 2020, the inspectors presented the security inspection results to Mr. Dan DeBoer and other members of the licensee staff.

3

DOCUMENTS REVIEWED Inspection Type Designation Description or Title Revision or Procedure Date 92707 Corrective AR02370421 Action Documents Resulting from Inspection Miscellaneous FPL St. Lucie St. Lucie Physical Security Revision 21 PSP Plan SFI 2415 St. Lucie Plant Target Sets Revision 13, Dated 03/11/2020 4